Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in M0 Mechanical Equipment × clear
Code
Activity
Start
Finish
Flt
%
CO01BM0130
01B Tank Erection 2001-FA (Water Storage Tank)
28-Dec-26
21-Apr-27
9.0d
0%
CO01BM0140
01B Tank Erection 2001-FB (Water Storage Tank)
28-Dec-26
25-Mar-27
32.0d
0%
WT010M0100
010 Tank Erection
28-Dec-26
21-Apr-27
9.0d
0%
30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr Data Date
CO01BM0130 — 01B Tank Erection 2001-FA (Water Storage Tank) | 28-Dec-26 → 21-Apr-27 | Not Started 0% | float 9.0d CO01BM0130 CO01BM0140 — 01B Tank Erection 2001-FB (Water Storage Tank) | 28-Dec-26 → 25-Mar-27 | Not Started 0% | float 32.0d CO01BM0140 WT010M0100 — 010 Tank Erection | 28-Dec-26 → 21-Apr-27 | Not Started 0% | float 9.0d WT010M0100