Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in M0 Mechanical Equipment × clear
Code
Activity
Start
Finish
Flt
%
CO01BM0130
01B Tank Erection 2001-FA (Water Storage Tank)
28-Dec-26
21-Apr-27
9.0d
0%
CO01BM0140
01B Tank Erection 2001-FB (Water Storage Tank)
28-Dec-26
25-Mar-27
32.0d
0%
WT010M0100
010 Tank Erection
28-Dec-26
21-Apr-27
9.0d
0%
Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 Data Date
CO01BM0130 — 01B Tank Erection 2001-FA (Water Storage Tank) | 28-Dec-26 → 21-Apr-27 | Not Started 0% | float 9.0d CO01BM0130 CO01BM0140 — 01B Tank Erection 2001-FB (Water Storage Tank) | 28-Dec-26 → 25-Mar-27 | Not Started 0% | float 32.0d CO01BM0140 WT010M0100 — 010 Tank Erection | 28-Dec-26 → 21-Apr-27 | Not Started 0% | float 9.0d WT010M0100