EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 31
activities
in P0 A/G Piping
× clear
Code
Activity
Start
Finish
Flt
%
CK01AP0110
01A A/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK01DP0110
01D A/G Pipe Spool Fabrication
28-Dec-26
22-Mar-27
104.0d
0%
CK01YP0110
01Y A/G Pipe Spool Fabrication
28-Dec-26
29-Jan-27
117.0d
0%
CK02BP0110
02B A/G Pipe Spool Fabrication
28-Dec-26
24-May-27
55.0d
0%
CK02DP0110
02D A/G Pipe Spool Fabrication
28-Dec-26
30-Apr-27
75.0d
0%
CK02EP0110
02E A/G Pipe Spool Fabrication
28-Dec-26
25-Feb-27
130.0d
0%
CK02FP0110
02F A/G Pipe Spool Fabrication
28-Dec-26
20-Apr-27
84.0d
0%
CK02NP0110
02N A/G Pipe Spool Fabrication
28-Dec-26
27-Mar-27
104.0d
0%
CK02PP0110
02P A/G Pipe Spool Fabrication
28-Dec-26
21-Apr-27
83.0d
0%
CK02YP0110
02Y A/G Pipe Spool Fabrication
28-Dec-26
29-Jan-27
27.0d
0%
CK03CP0110
03C A/G Pipe Spool Fabrication
28-Dec-26
17-Feb-27
137.0d
0%
CK03YP0110
03Y A/G Pipe Spool Fabrication
28-Dec-26
06-Feb-27
80.0d
0%
WK000P0100
000 A/G Pipe Spool Fabrication
28-Dec-26
31-May-27
49.0d
0%
CK01BP0110
01B A/G Pipe Spool Fabrication
31-Dec-26
23-Mar-27
101.0d
0%
CK02QP0110
02Q A/G Pipe Spool Fabrication
11-Jan-27
13-Apr-27
90.0d
0%
CK02CP0110
02C A/G Pipe Spool Fabrication
25-Jan-27
20-Feb-27
134.0d
0%
CK02GP0110
02G A/G Pipe Spool Fabrication
09-Feb-27
15-Mar-27
115.0d
0%
CK03EP0110
03E A/G Pipe Spool Fabrication
12-Feb-27
02-Mar-27
126.0d
0%
CK03FP0110
03F A/G Pipe Spool Fabrication
12-Feb-27
23-Feb-27
132.0d
0%
CK03AP0110
03A A/G Pipe Spool Fabrication
20-Feb-27
03-Mar-27
125.0d
0%
CK02JP0110
02J A/G Pipe Spool Fabrication
23-Feb-27
20-Mar-27
111.0d
0%
CK03DP0110
03D A/G Pipe Spool Fabrication
27-Feb-27
04-Mar-27
124.0d
0%
CK01CP0110
01C A/G Pipe Spool Fabrication
27-Feb-27
06-Mar-27
123.0d
0%
CK02MP0110
02M A/G Pipe Spool Fabrication
22-Mar-27
07-Apr-27
95.0d
0%
CK03BP0110
03B A/G Pipe Spool Fabrication
29-Mar-27
08-Apr-27
94.0d
0%
CK02LP0110
02L A/G Pipe Spool Fabrication
02-Apr-27
22-May-27
32.0d
0%
CK02KP0110
02K A/G Pipe Spool Fabrication
03-Apr-27
27-Apr-27
78.0d
0%
CK02HP0110
02H A/G Pipe Spool Fabrication
19-Apr-27
29-May-27
51.0d
0%
CK05AP0110
05A A/G Pipe Spool Fabrication
28-Apr-27
31-May-27
49.0d
0%
CK02AP0110
02A A/G Pipe Spool Fabrication
05-May-27
26-May-27
53.0d
0%
CK05BP0110
05B A/G Pipe Spool Fabrication
22-May-27
31-May-27
49.0d
0%