Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 652 activities in 00 Common × clear
Code
Activity
Start
Finish
Flt
%
EK000CK085
Establish bank account in Egypt
02-Jul-24
24-Jan-26
100%
EK000SY005
Systems Work Plan & Project Setup
21-Jan-25
25-Mar-25
100%
EK000YA002
Start Project
22-Jan-25
22-Jan-25
100%
EK000PR025
Pressure Profile
22-Jan-25
01-Feb-25
100%
EK000PR050
Electrical Load Summary - Initial
22-Jan-25
01-Feb-25
100%
EK000MD005
Attend Alignment & strategy meetings
22-Jan-25
09-Feb-25
100%
EK000PR015
Process Configuration
22-Jan-25
13-Feb-25
100%
EK000PR030
Stream Summary
22-Jan-25
13-Feb-25
100%
EK000PR035
Process Flow Diagrams PFD's - EOR
22-Jan-25
13-Feb-25
100%
EK000PR040
Steam Balance Diagram - EOR
22-Jan-25
13-Feb-25
100%
EK000GE005
Estimate Escalation Check - Info to Estimating
22-Jan-25
14-Feb-25
100%
EK000PR045
Cooling Water Balance - EOR
22-Jan-25
15-Feb-25
100%
EK000PE025
Document Management Plan - Issue for Review
22-Jan-25
16-Feb-25
100%
EK000SY010
MEC Convert prelim P&ID's to Smart Plant P&ID's
22-Jan-25
16-Feb-25
100%
EK000MD015
Conversion of drawings to metric units
22-Jan-25
19-Feb-25
100%
EK000PM015
Project Coordination Procedure - IFA
22-Jan-25
23-Feb-25
100%
EK000PR020
Heat & Material Balances (SOR & EOR)
22-Jan-25
23-Feb-25
100%
EK000PE085
Participate in Escalation confirmation effort
22-Jan-25
01-Mar-25
100%
EK000IM030
Project Portal & Dashboard
22-Jan-25
06-Mar-25
100%
EK000IC030
Develop & Issue FieldBus Main Instr Vendor ERW
22-Jan-25
08-Mar-25
100%
EK000PR055
Feed & Fuel Summary
22-Jan-25
09-Mar-25
100%
EK000IM020
IM Strategy plan
22-Jan-25
12-Mar-25
100%
EK000IM025
IM Execution plan
22-Jan-25
12-Mar-25
100%
EK000PR010
Process Work Plan
22-Jan-25
23-Mar-25
100%
EK000AR020
Gather Bldg Requirements & Coordinate w/ Constr
22-Jan-25
12-Apr-25
100%
EK000IM010
Object Engineering set-up & procedures
22-Jan-25
13-Apr-25
100%
EK000CV005
Identify scope / Project set-up
23-Jan-25
23-Feb-25
100%
EK000PE125
Preliminary Issue - Equipment List
29-Jan-25
12-Feb-25
100%
EK000CV020
Review FMCL documents - Specs & Drawings
29-Jan-25
16-Feb-25
100%
EK000IM040
Establish Citrix for Test of PDS (HOC-MEC)
29-Jan-25
23-Feb-25
100%
EK000PI080
Develop Split of work
29-Jan-25
23-Feb-25
100%
EK000IM005
Equipment List (MEL) Definition
29-Jan-25
30-Mar-25
100%
EK000PE050
Confirm of Split of Work for MEC
02-Feb-25
23-Feb-25
100%
EK000IC35A
DCS - Engr ERW Issued
04-Feb-25
12-Feb-25
100%
EK000IM035
Establish Documentum
05-Feb-25
16-Feb-25
100%
EK000PE010
Publish Unit conversion standard
05-Feb-25
16-Feb-25
100%
EK000PE040
Devlop & Issue List of Project Specs & Standards
05-Feb-25
16-Feb-25
100%
EK000CV025
Review SEGAS Wind & Earthquake Specs
05-Feb-25
19-Feb-25
100%
EK000PI120
Identify priority pipe classes
05-Feb-25
20-Feb-25
100%
EK000PS015
Issue 90 Day look ahead schedule
05-Feb-25
21-Feb-25
100%
EK000MJ005
Prepare Machinery Specs (Motors, Pkg Equipment)
05-Feb-25
25-Feb-25
100%
EK000IC015
Modify Package Equipment Spec for IEC basis
05-Feb-25
05-Mar-25
100%
EK000PE110
Issue Draft Project Design Data
05-Feb-25
06-Mar-25
100%
EK000MC010
Develop & Issue Exchanger Work Plan
05-Feb-25
09-Mar-25
100%
EK000PI115
Develop Piping Class Index (IOPMC)
05-Feb-25
13-Mar-25
100%
EK000SY015
Develop Utility & offsite block flow diagrams
05-Feb-25
16-Mar-25
100%
EK000PI132
Develop Early Tech P-Class specs for Procurement
05-Feb-25
22-Mar-25
100%
EK000SY065
Complete Utility Flow Diagrams
05-Feb-25
03-Apr-25
100%
EK000CV010
HOC / MEC split of Work
07-Feb-25
16-Feb-25
100%
EK000CV030
Prepare EBIC Wind & EarthquakeSpecs
07-Feb-25
26-Feb-25
100%
EK000QM010
Training - Export Compliance
08-Feb-25
08-Feb-25
100%
EK000ELZE0
Area Classification
11-Feb-25
30-Dec-25
100%
EK000MD31C
Prepare & Issue Prelim. RFQ - MD301 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD32C
Prepare & Issue Prelim. RFQ - MD302 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD34C
Prepare & Issue Prelim. RFQ - MD304 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD51C
Prepare & Issue Prelim. RFQ - MD501 to Proc.
12-Feb-25
16-Feb-25
100%
EK000CV040
Prepare Topo Survey S/C Pkg
12-Feb-25
23-Feb-25
100%
EK000PE090
Develop & Issue Engineering Plan
12-Feb-25
02-Mar-25
100%
EK000EL005
Electrical Work Plans
12-Feb-25
09-Mar-25
100%
EK000PI040
Prepare technology work plan - Piping Engr.
12-Feb-25
09-Mar-25
100%
EK000PI060
Prepare Other Project Documentation
12-Feb-25
09-Mar-25
100%
EK000PI051
Prepare P/Mech Support Details
12-Feb-25
15-Mar-25
100%
EK000CV015
Civil work Plan & Safety check list
12-Feb-25
16-Mar-25
100%
EK000CV050
Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis
12-Feb-25
16-Mar-25
100%
EK000MB005
Develop & Issue Furnance Job Plan
12-Feb-25
16-Mar-25
100%
EK000MJ31C
Prepare & Issue Prelim. RFQ - MJ301 to Proc.
13-Feb-25
13-Feb-25
100%
EK000MJ32C
Prepare & Issue Prelim. RFQ - MJ302 to Proc.
13-Feb-25
13-Feb-25
100%
EK000MB33A
101-B Develop & Issue Load Sheet
14-Feb-25
16-Feb-25
100%
EK000MD33A
Develop & Issue Load Sheets for ERW - MD303
14-Feb-25
16-Feb-25
100%
EK000MJ22A
Develop & Issue Load Sheets for ERW - MJ201
14-Feb-25
16-Feb-25
100%
EK000MJ21A
Develop & Issue Load Sheets for ERW - MJ202
14-Feb-25
21-Feb-25
100%
EK000PI110
Locate FMCL Documents
14-Feb-25
23-Feb-25
100%
EK000PR060
Process Load Sheets
14-Feb-25
22-Mar-25
100%
EK000PC005
Prepare Estimate for Escalation Check
15-Feb-25
23-Feb-25
100%
EK000PE015
MSD (From Metallurgy) - ISBL
15-Feb-25
27-Feb-25
100%
EK000MC31C
Prepare & Issue Prelim. RFQ - MC310 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MC61C
Prepare & Issue Prelim. RFQ - MC610 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MBP1C
101-B Prepare & Issue Prelim. Shop Fab to Proc.
16-Feb-25
20-Feb-25
100%
EK000QM015
Develop & Issue Quality Plan
16-Feb-25
16-Mar-25
100%
EK000MC32C
Issue Prelim. RFQ - MC311
19-Feb-25
19-Feb-25
100%
EK000MJ22C
Prepare & Issue Prelim. RFQ - MJ201 to Proc.
19-Feb-25
19-Feb-25
100%
EK020MC31A
MC312 - (120,121-C) - Issue Prelim. RFQ
19-Feb-25
19-Feb-25
100%
EK000MD21A
Develop & Issue Load Sheets for ERW - MD201
19-Feb-25
20-Feb-25
100%
EK000MD41C
Prepare & Issue Prelim. RFQ - MD401 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD43C
Prepare & Issue Prelim. RFQ - MD403 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD43A
Develop & Issue Load Sheets for ERW - MD403
19-Feb-25
21-Feb-25
100%
EK000MJ31A
Develop & Issue Load Sheets for ERW - MJ301
19-Feb-25
21-Feb-25
100%
EK000MD33C
Prepare & Issue Prelim. RFQ - MD303 to Proc.
19-Feb-25
22-Feb-25
100%
EK000EL020
Define bulk material requirements
19-Feb-25
23-Feb-25
100%
EK000MJ22B
Develop & Issue Design Data for ERW - MJ201
19-Feb-25
23-Feb-25
100%
EK000ML31C
Prepare & Issue Prelim. RFQ - ML313 to Proc.
19-Feb-25
23-Feb-25
100%
EK000PR115
Issue Prelim Load Sht for Air Cooling Study
19-Feb-25
23-Feb-25
100%
EK000MC210
Cooling Water Balance Review
19-Feb-25
26-Feb-25
100%
EK000IM045
Establish IPMS
19-Feb-25
01-Mar-25
100%
EK000IC005
Develop Typical SIL Values Worksheet
19-Feb-25
02-Mar-25
100%
EK000MJ35C
Prepare & Issue Prelim. RFQ - MJ305 to Proc.
19-Feb-25
02-Mar-25
100%
EK000MJ36C
Prepare & Issue Prelim. RFQ - MJ306 to Proc.
19-Feb-25
02-Mar-25
100%
EK000PK030
Provide Job Specific SDR2 Priorities to Purch.
19-Feb-25
02-Mar-25
100%
EK000PI160
P&ID Area Break Mark-up
19-Feb-25
08-Mar-25
100%
EK000MJ39C
Prepare & Issue Prelim. RFQ - MJ391 to Proc.
19-Feb-25
09-Mar-25
100%
EK000PR076
Identify Risk of Equipment Changes
19-Feb-25
09-Mar-25
100%
EK000PE035
Rvw Lesson Learn w/Prj. Team&Develop Action List
19-Feb-25
16-Mar-25
100%
EK000EV005
Conceptual Design of Wastewater Systems
19-Feb-25
23-Mar-25
100%
EK000PR145
Eng. Studies - Ammonia Product Line U/G vs. A/G
19-Feb-25
29-Mar-25
100%
EK000MB010
101-B Furnance Analytical - Convection Design
19-Feb-25
30-Mar-25
100%
EK000CV070
Validate Concrete & Steel by Planning Areas
19-Feb-25
15-Apr-25
100%
EK000MD33P
Develop Analytical Sketches for ERW - MD303
19-Feb-25
04-May-25
100%
EK000PM055
Complete EPC Insurance Forms
19-Feb-25
04-May-25
100%
EK000PI020
Develop Piping Specs (Paper)
19-Feb-25
28-May-25
100%
EK000MJ21C
Prepare & Issue Prelim. RFQ - MJ202 to Proc.
20-Feb-25
20-Feb-25
100%
EK000ML50C
Prepare & Issue Prelim. RFQ - ML500 to Proc.
20-Feb-25
26-Feb-25
100%
EK000MD44A
Develop & Issue Load Sheets for ERW - MD404
20-Feb-25
20-Mar-25
100%
EK000MB61C
Prepare & Issue Prelim. RFQ - MB610 to Proc.
21-Feb-25
23-Feb-25
100%
EK000MB62C
Prepare & Issue Prelim. RFQ - MB621 to Proc.
21-Feb-25
23-Feb-25
100%
EK000MD34A
Develop & Issue Load Sheets for ERW - MD304
21-Feb-25
26-Feb-25
100%
EK000MJ21B
Develop & Issue Design Data for ERW - MJ202
22-Feb-25
07-Mar-25
100%
EK000MD21P
Develop Prelim Analytical Sktch for ERW - MD201
22-Feb-25
22-Mar-25
100%
EK000MD21Q
Develop Final Analytical Sktch for ERW - MD201
22-Feb-25
26-Apr-25
100%
EK000YA804
(EP-05) Issue Heat and Material Balance for Process Release
22-Feb-25
22-Feb-25
100%
EK000YA805
(EP-06) Issue Equipment List for review
22-Feb-25
22-Feb-25
100%
EK000YA807
(EP-08) Issue Utility Balances for Initial Release
22-Feb-25
22-Feb-25
100%
EK000FP025
FP Gas Detection Location Plans - Not Required
22-Feb-25
23-Aug-25
100%
EK000MC32A
Develop & Issue Load Sheets for ERW - MC311
23-Feb-25
28-Feb-25
100%
EK000CK080
Expedite legal issues associated w/ KBRII
23-Feb-25
28-Feb-26
100%
EK000MB060
101-B General Arrangement Drawing
25-Feb-25
08-Mar-25
100%
EK000MF31A
Develop & Issue Load Sheets for ERW - MF301
26-Feb-25
26-Feb-25
100%
EK000MB41C
Prepare & Issue Prelim. RFQ - MB410 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC21C
Prepare & Issue Prelim. RFQ - MC210 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC23C
Prepare & Issue Prelim. RFQ - MC230 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MD31A
Develop & Issue Load Sheets for ERW - MD301
26-Feb-25
27-Feb-25
100%
EK000MD32A
Develop & Issue Load Sheets for ERW - MD302
26-Feb-25
27-Feb-25
100%
EK000MD41A
Develop & Issue Load Sheets for ERW - MD401
26-Feb-25
27-Feb-25
100%
EK000EL015
Split of work with MEC and Other Discipline
26-Feb-25
28-Feb-25
100%
EK000MB63C
Prepare & Issue Prelim. RFQ - MB630 to Proc.
26-Feb-25
28-Feb-25
100%
EK000MBP4C
Prepare & Issue Prelim. RFQ Cast Material
26-Feb-25
28-Feb-25
100%
EK000PE060
Define Task Force Area in MEC
26-Feb-25
28-Feb-25
100%
EK000PE075
MEC Organization Chart
26-Feb-25
28-Feb-25
100%
EK000PM030
Estimate Escalation Check - IRC Approvals
26-Feb-25
01-Mar-25
100%
EK000PR095
Steam Balance - Startup, 103-J, Etc
26-Feb-25
02-Mar-25
100%
EK000MBP3C
Prepare & Issue Prelim. RFQ Pressure Parts
26-Feb-25
05-Mar-25
100%
EK000MD33B
Develop & Issue Design Data for ERW - MD303
26-Feb-25
08-Mar-25
100%
EK000EV025
Develop & Issue Enviromental Work Plan
26-Feb-25
09-Mar-25
100%
EK000IC020
Establlish data warehouse - Intools Basic Setup
26-Feb-25
09-Mar-25
100%
EK000IC025
Review Instr. & Installation Details - ID Change
26-Feb-25
09-Mar-25
100%
EK000MJ22F
Update/Issue Formal Inquiry for ERW - MJ201
26-Feb-25
09-Mar-25
100%
EK000PK010
Issue critical req'n submittal sched to Procmnt
26-Feb-25
09-Mar-25
100%
EK000GE010
Eng. Studies - Air Coolers vs. Cooling Water
26-Feb-25
12-Mar-25
100%
EK000CV060
Civil project highlights
26-Feb-25
16-Mar-25
100%
EK000PI005
Locate Permanent Tie in pnts Gas, Wtr, Storm wtr
26-Feb-25
16-Mar-25
100%
EK000PE065
Develop & Issue HOC - MEC Coordination Plan
26-Feb-25
23-Mar-25
100%
EK000PI133
Dvlp/Issue V-class specs & Standads for Procurmt
26-Feb-25
09-Apr-25
100%
EK000MB085
101-B Radiant Detail Drawings - IFF
26-Feb-25
12-Apr-25
100%
EK000MB090
101-B Convection Detail Drawings - IFF
26-Feb-25
12-Apr-25
100%
EK000CV035
Prepare Geotech S/C Pkgs
26-Feb-25
27-Apr-25
100%
EK000EL025
Develop installation details
26-Feb-25
07-May-25
100%
EK000IC045
Develop & Issue CSE Work Plan
26-Feb-25
08-May-25
100%
EK000PM045
Issue Execution Strategy /Project Execution Plan
26-Feb-25
24-May-25
100%
EK000MC31A
Develop & Issue Load Sheets for ERW - MC310
27-Feb-25
01-Mar-25
100%
EK000ML50B
Develop/Issue Load Sht & Design Data ERW - ML500
27-Feb-25
05-Mar-25
100%
EK000MD42A
Develop & Issue Load Sheets for ERW - MD402
28-Feb-25
01-Mar-25
100%
EK000MD51A
Develop & Issue Load Sheets for ERW - MD501
28-Feb-25
05-Mar-25
100%
EK000MJ35A
Develop & Issue Load Sheets for ERW - MJ305
28-Feb-25
23-Mar-25
100%
EK000YA808
(EP-09) Issue Engineering Plan
01-Mar-25
01-Mar-25
100%
EK000MD060
Prepare Vessel work plan & other quality documents
02-Mar-25
02-Mar-25
100%
EK000MC31B
Develop & Issue Design Data for ERW - MC310
02-Mar-25
13-Mar-25
100%
EK000MC31F
Finalize Equip. Data Sheets for ERW - MC310
02-Mar-25
12-Apr-25
100%
EK000PI125
Validate new plot layout (impacts on pipe stress
02-Mar-25
21-May-25
100%
EK000MJ21D
Technical Evaluation - MJ202
05-Mar-25
05-Mar-25
100%
EK000MJ75A
Develop & Issue Load Sheets for ERW - MJ750
05-Mar-25
05-Mar-25
100%
EK000ML31A
Develop & Issue Load Sheets for ERW - ML313
05-Mar-25
05-Mar-25
100%
EK000MB51C
Prepare & Issue Prelim. RFQ - MB511 to Proc.
05-Mar-25
07-Mar-25
100%
EK000CV075
Egyptian Professional Engineer - Define Reqmnts
05-Mar-25
08-Mar-25
100%
EK000MC21A
Develop & Issue Load Sheets for ERW - MC210
05-Mar-25
08-Mar-25
100%
EK000EL035
Voltage drop table
05-Mar-25
09-Mar-25
100%
EK000ML42C
Prepare & Issue Prelim. RFQ - ML420 to Proc.
05-Mar-25
09-Mar-25
100%
EK000MU33C
Prepare & Issue Prelim. RFQ - MU330 to Proc.
05-Mar-25
09-Mar-25
100%
EK000CS030
Start-up Schedule (Prelim for 1st Planner)
05-Mar-25
14-Mar-25
100%
EK000MC32B
Develop & Issue Design Data for ERW - MC311
05-Mar-25
19-Mar-25
100%
EK000MC23A
Develop & Issue Load Sheets for ERW - MC230
05-Mar-25
22-Mar-25
100%
EK000MC32F
Finalize Equip. Data Sheets for ERW - MC311
05-Mar-25
24-May-25
100%
EK000MD22A
Develop & Issue Load Sheets for ERW - MD202
06-Mar-25
06-Mar-25
100%
EK000MBP1D
101-B Technical Bid Evaluation Shop Fab
06-Mar-25
09-Mar-25
100%
EK000MJ37A
Develop & Issue Load Sheets for ERW - MJ340
06-Mar-25
09-Mar-25
100%
EK000ML31B
Develop & Issue Design Data for ERW - ML313
06-Mar-25
15-Mar-25
100%
EK000MD42P
Confirm Analytical Design for ERW - MD402
06-Mar-25
21-Mar-25
100%
EK000ML50F
Update/Issue Formal Inquiry for ERW - ML500
06-Mar-25
27-Apr-25
100%
EK000PE020
WMS Setup & Development
07-Mar-25
15-Mar-25
100%
EK000CV080
Egyptian Professional Eng. - Issue P.O/Subc. Pkg
08-Mar-25
09-Mar-25
100%
EK000MJ21F
Update/Issue Formal Inquiry for ERW - MJ202
08-Mar-25
13-Mar-25
100%
EK000MC21B
Develop & Issue Design Data for ERW - MC210
08-Mar-25
01-Apr-25
100%
EK000MJ31B
Develop & Issue Design Data for ERW - MJ301
08-Mar-25
12-Apr-25
100%
EK000PI055
Prepare Object Engineering Work Instruction
08-Mar-25
15-Mar-25
100%
EK000PC010
Estimate Turnover to Project Team
09-Mar-25
15-Mar-25
100%
EK000PI085
Estimate/Schedule Review
09-Mar-25
15-Mar-25
100%
EK000MD34R
Develop Final Analytical Sktch for ERW - MD304
09-Mar-25
16-Mar-25
100%
EK000MD43P
Confirm Analytical Design for ERW - MD403
09-Mar-25
16-Mar-25
100%
EK000MC61A
Develop & Issue Load Sheets for ERW - MC610
09-Mar-25
20-Mar-25
100%
EK000PC015
Estimate Recast & Develop Project Control Budget
09-Mar-25
23-Apr-25
100%
EK000PI105
Performance Test of Citrix for PDS w/MEC
12-Mar-25
12-Mar-25
100%
EK000MU41F
Develop & Issue Inquiry for ERW - MU410
12-Mar-25
16-Mar-25
100%
EK000MD34P
Confirm Analytical Design for ERW - MD304
12-Mar-25
20-Mar-25
100%
EK000MU41A
Develop & Issue Load Sheets for ERW - MU410
12-Mar-25
20-Mar-25
100%
EK000MD31P
Confirm Analytical Design for ERW - MD301
12-Mar-25
29-Mar-25
100%
EK000MD32P
Confirm Analytical Design for ERW - MD302
12-Mar-25
02-Apr-25
100%
EK000PI100
Critical Line List
12-Mar-25
06-Apr-25
100%
EK000EV020
Develop Preliminary noise model
12-Mar-25
20-Apr-25
100%
EK000MC21F
Finalize Equip. Data Sheets for ERW - MC210
12-Mar-25
13-Jun-25
100%
EK000MD020
Equipment Modeling for Vessel - MEC
13-Mar-25
25-Mar-26
100%
EK000MB61D
Technical Evaluation - MB610
14-Mar-25
20-Mar-25
100%
EK000PR080
Input to Process Guarantees
14-Mar-25
03-May-25
100%
EK000IC35D
DCS - Tech Evaluation
14-Mar-25
14-May-25
100%
EK000MJ32A
Develop & Issue Load Sheets for ERW - MJ302
15-Mar-25
20-Mar-25
100%
EK000ML31F
Update/Issue Formal Inquiry for ERW - ML313
16-Mar-25
16-Mar-25
100%
EK000MD31B
Develop & Issue Design Data for ERW - MD301
16-Mar-25
19-Mar-25
100%
EK000MD32B
Develop & Issue Design Data for ERW - MD302
16-Mar-25
19-Mar-25
100%
EK000MD34B
Develop & Issue Design Data for ERW - MD304
16-Mar-25
19-Mar-25
100%
EK000MJ22D
Technical Evaluation - MJ201
16-Mar-25
19-Mar-25
100%
EK000MD45A
Develop & Issue Load Sheets for ERW - MD405
16-Mar-25
20-Mar-25
100%
EK000ML43A
Develop & Issue Load Sheets for ERW - ML430
16-Mar-25
20-Mar-25
100%
EK000ML44A
Develop & Issue Load Sheets for ERW - ML440
16-Mar-25
20-Mar-25
100%
EK000PE095
Disciplines Load WMS with Budgets & Deliverables
16-Mar-25
20-Apr-25
100%
EK000MD34D
Technical Evaluation - MD304
16-Mar-25
23-Apr-25
100%
EK000MD41D
Technical Evaluation - MD401
16-Mar-25
23-Apr-25
100%
EK000ML42A
Develop & Issue Load Sheets for ERW - ML420
19-Mar-25
20-Mar-25
100%
EK000MU35A
Develop & Issue Load Sheets for ERW - MU350
19-Mar-25
20-Mar-25
100%
EK000MU41B
Develop & Issue Design Data for ERW - MU410
19-Mar-25
21-Mar-25
100%
EK000MU30F
Develop & Issue Inquiry for ERW - MU300
19-Mar-25
26-Mar-25
100%
EK000MF33B
Develop/Issue Load Sht & Design Data ERW - MF311
19-Mar-25
26-Mar-25
100%
EK000MF32B
Develop/Issue Load Sht & Design Data ERW - MF302
19-Mar-25
06-Apr-25
100%
EK000MD21B
Develop & Issue Design Data for ERW - MD201
19-Mar-25
08-May-25
100%
EK000ML42F
Update/Issue Formal Inquiry for ERW - ML420
19-Mar-25
24-Apr-25
100%
EK000MC63A
Develop & Issue Load Sheets for ERW - MC630
20-Mar-25
22-Mar-25
100%
EK000MU61F
Develop & Issue Inquiry for ERW - MU611
20-Mar-25
25-Mar-25
100%
EK000I210D
000 Control Valves - Technical Evaluation
20-Mar-25
23-May-25
100%
EK000MU35F
Update/Issue Formal Inquiry for ERW - MU350
21-Mar-25
22-Mar-25
100%
EK000MD47A
Develop & Issue Load Sheets for ERW - MD406
21-Mar-25
23-Mar-25
100%
EK000MD51B
Develop & Issue Design Data for ERW - MD501
21-Mar-25
28-Mar-25
100%
EK000MC61D
Technical Evaluation - MC610
21-Mar-25
01-Apr-25
100%
EK000MC61F
Finalize Equip. Data Sheets for ERW - MC610
21-Mar-25
10-Apr-25
100%
EK000MJ32B
Develop & Issue Design Data for ERW - MJ302
21-Mar-25
13-Apr-25
100%
EK000MD34F
Update/Issue Formal Inquiry for ERW - MD304
21-Mar-25
20-Apr-25
100%
EK000EV010
Develop design basis for evaporation pond
22-Mar-25
11-May-25
100%
EK000YA802
(EP-03) Issue Process Plan
22-Mar-25
22-Mar-25
100%
EK000MB51F
Prepare & Issue Purchase ERW - MB511
23-Mar-25
17-Apr-25
100%
EK000MJ39B
Develop/Issue Load Sht & Design Data ERW - MJ391
25-Mar-25
29-Mar-25
100%
EK000ML50D
Technical Evaluation - ML500
25-Mar-25
27-Apr-25
100%
EK000MD025
Prepare job quality drawings for ERW
25-Mar-25
28-May-25
100%
EK000ML44B
Develop & Issue Design Data for ERW - ML440
26-Mar-25
27-Mar-25
100%
EK000MF31P
Confirm Analytical Design for ERW - MF301
26-Mar-25
29-Mar-25
100%
EK000PR070
Effluent Summary
26-Mar-25
30-Mar-25
100%
EK000MD51D
Technical Evaluation - MD501
26-Mar-25
03-Apr-25
100%
EK000MU33F
Update/Issue Formal Inquiry for ERW - MU330
26-Mar-25
04-Apr-25
100%
EK000MD33F
Update/Issue Formal Inquiry for ERW - MD303
26-Mar-25
11-May-25
100%
EK000MF32F
Develop & Issue Design Data for Tank Subcontract - MF302
26-Mar-25
08-Apr-25
100%
EK000I131D
Technical Evaluation - Transmitters
26-Mar-25
23-May-25
100%
EK000MJ35D
Technical Evaluation - MJ305
27-Mar-25
02-Apr-25
100%
EK000MJ36D
Technical Evaluation - MJ306
27-Mar-25
02-Apr-25
100%
EK000MF33F
Develop & Issue Design Data for Tank Subcontract - MF311
27-Mar-25
09-Apr-25
100%
EK000CVK35
OSBL Rough Grading/Road
27-Mar-25
23-May-25
100%
EK000MD51F
Update/Issue Formal Inquiry for ERW - MD501
29-Mar-25
08-Apr-25
100%
EK000MD45P
Confirm Analytical Design for ERW - MD405
29-Mar-25
25-Apr-25
100%
EK000MB62D
Technical Evaluation - MB621
30-Mar-25
18-Apr-25
100%
EK000MB63D
Technical Evaluation - MB630
30-Mar-25
24-Jun-25
100%
EK000MF31B
Develop & Issue Design Data for Tank Subcontrac - MF301
01-Apr-25
08-Apr-25
100%
EK000MJ34B
Develop/Issue Load Sht & Design Data ERW - MJ304
01-Apr-25
08-Apr-25
100%
EK000PR065
Catalyst and Chemical Specs
01-Apr-25
09-Apr-25
100%
EK000MB070
101-B Foundation Loads
01-Apr-25
19-Apr-25
100%
EK000PR075
Process Description
01-Apr-25
25-Apr-25
100%
EK000MJ39F
Update/Issue Formal Inquiry for ERW - MJ391
01-Apr-25
27-Apr-25
100%
EK000QM020
Develop/ Issue/ Approval of QA/QC Manual (EBIC/EXIM Verification)
01-Apr-25
31-Oct-25
100%
EK000MD44P
Confirm Analytical Design for ERW - MD404
02-Apr-25
03-Apr-25
100%
EK000MD31F
Update/Issue Formal Inquiry for ERW - MD301
02-Apr-25
16-Apr-25
100%
EK000MU61B
Develop/Issue Load Sht & Design Data ERW - MU611
02-Apr-25
14-May-25
100%
EK000MB51D
Technical Evaluation - MB511
02-Apr-25
16-Apr-25
100%
EK000MD32F
Update/Issue Formal Inquiry for ERW - MD302
02-Apr-25
20-Apr-25
100%
EK000MD43D
Technical Evaluation - MD403
02-Apr-25
25-Apr-25
100%
EK000MC61B
Develop & Issue Design Data for ERW - MC610
04-Apr-25
20-Apr-25
100%
EK000MJ35B
Develop & Issue Design Data for ERW - MJ305
05-Apr-25
09-May-25
100%
EK000MB080
101-B Convection Coil Design
05-Apr-25
12-Apr-25
100%
EK000ML31D
Technical Evaluation - ML313
05-Apr-25
19-Apr-25
100%
EK000MB050
101-B Radiant coil design
06-Apr-25
12-Apr-25
100%
EK000MD22P
Confirm Analytical Design for ERW - MD202
06-Apr-25
15-Apr-25
100%
EK000MB33F
MB333 - Develop & Issue Purchase ERW 101-B
06-Apr-25
23-Apr-25
100%
EK000MBP4D
Technical Evaluation - 101-B Cast Material
06-Apr-25
01-May-25
100%
EK000PI131
Devlop Balance Tech P-Class specs for Procuremnt
06-Apr-25
25-May-25
100%
EK000FP050
FP Overall Firewater P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK000MD43B
Develop & Issue Design Data for ERW - MD403
08-Apr-25
12-Apr-25
100%
EK000MU35D
Technical Evaluation - MU350
08-Apr-25
19-Apr-25
100%
EK000MC21D
Technical Evaluation - MC210
08-Apr-25
23-Apr-25
100%
EK000MC23D
Technical Evaluation - MC230
08-Apr-25
23-Apr-25
100%
EK000MD45B
Develop & Issue Design Data for ERW - MD405
08-Apr-25
08-May-25
100%
EK000MC23B
Develop & Issue Design Data for ERW - MC230
09-Apr-25
13-Apr-25
100%
EK000MD42B
Develop & Issue Design Data for ERW - MD402
09-Apr-25
13-Apr-25
100%
EK000MD41B
Develop & Issue Design Data for ERW - MD401
09-Apr-25
18-Apr-25
100%
EK000MU30B
Develop/Issue Load Sht & Design Data ERW - MU300
09-Apr-25
25-Apr-25
100%
EK000PS010
Level III CPM Schedule / First Planner
09-Apr-25
24-May-25
100%
EK000ML42D
Technical Evaluation - ML420
09-Apr-25
19-Apr-25
100%
EK000MJ34F
Update/Issue Formal Inquiry for ERW - MJ304
09-Apr-25
26-Apr-25
100%
EK000MB41D
Technical Evaluation - MB410
10-Apr-25
01-May-25
100%
EK000MJ33B
Develop/Issue Load Sht & Design Data ERW - MJ303
11-Apr-25
23-May-25
100%
EK000MJ32D
Technical Evaluation - MJ302
12-Apr-25
19-Apr-25
100%
EK000MJ31D
Technical Evaluation - MJ301
12-Apr-25
25-Apr-25
100%
EK000MB055
101-B Radiant coil BOM
15-Apr-25
19-Apr-25
100%
EK000MB075
101-B Convection Coil BOM
15-Apr-25
19-Apr-25
100%
EK000ML51B
Develop/Issue Load Sht & Design Data ERW - ML512
15-Apr-25
19-Apr-25
100%
EK000MC63B
Develop & Issue Design Data for ERW - MC630
15-Apr-25
20-Apr-25
100%
EK000MB61E
Prepare & Issue Purchase ERW - MB610
15-Apr-25
22-Apr-25
100%
EK000MD43F
Update/Issue Formal Inquiry for ERW - MD403
15-Apr-25
25-Apr-25
100%
EK000MD32D
Technical Evaluation - MD302
15-Apr-25
04-May-25
100%
EK000IC36D
DCS (MIV) - Tech Evaluation
15-Apr-25
17-May-25
100%
EK000MC31P
Develop & Issue Setting Plans for ERW - MC310
15-Apr-25
28-May-25
100%
EK000MC21P
Develop & Issue Setting Plans for ERW - MC210
15-Apr-25
20-Jun-25
100%
EK000CS025
Turnover System Definition for ISBL
15-Apr-25
31-Jan-26
100%
EK000MD42F
Update/Issue Formal Inquiry for ERW - MD402
16-Apr-25
19-Apr-25
100%
EK000ML42B
Develop & Issue Design Data for ERW - ML420
16-Apr-25
20-Apr-25
100%
EK000MD31D
Technical Evaluation - MD301
16-Apr-25
25-Apr-25
100%
EK000ML33B
Develop/Issue Load Sht & Design Data ERW - ML330
16-Apr-25
25-Apr-25
100%
EK000MD33D
Technical Evaluation - MD303
16-Apr-25
04-May-25
100%
EK000MBP3D
Technical Evaluation - 101-B Pressure Parts
16-Apr-25
10-May-25
100%
EK000MD21F
Develop & Issue Inquiry ERW - MD201
17-Apr-25
17-Jun-25
100%
EK000PR140
Formal Issue of Process Release
18-Apr-25
08-May-25
100%
EK000MD47P
Confirm Analytical Design for ERW - MD406
18-Apr-25
22-Apr-25
100%
EK000MJ37B
Develop & Issue Design Data for ERW - MJ340
19-Apr-25
09-May-25
100%
EK000MD41F
Update/Issue Formal Inquiry for ERW - MD401
20-Apr-25
26-Apr-25
100%
EK000MD44Q
Develop Analytical Sketches for ERW - MD404
20-Apr-25
27-Apr-25
100%
EK000MJ73B
Develop/Issue Load Sht & Design Data ERW - MJ730
20-Apr-25
30-Apr-25
100%
EK000EV015
Issue load sheets for wastewater systems
20-Apr-25
31-May-25
100%
EK000MD44B
Develop & Issue Design Data for ERW - MD404
22-Apr-25
25-Apr-25
100%
EK000MD47B
Develop & Issue Design Data for ERW - MD406
22-Apr-25
25-Apr-25
100%
EK000MD46B
Develop/Issue Load Sht & Design Data ERW - MD411
22-Apr-25
03-May-25
100%
EK000MU11B
05B MU311 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU25B
02G MU225 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU32B
01D MU322 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MD22B
Develop & Issue Design Data for ERW - MD202
23-Apr-25
01-May-25
100%
EK000MU31B
Develop/Issue Load Sht & Design Data ERW - MU310
23-Apr-25
16-May-25
100%
EK000MC23F
Finalize Equip. Data Sheets for ERW - MC230
23-Apr-25
13-Jun-25
100%
EK000CV036
Issue Geotech S/C PKG
26-Apr-25
02-May-25
100%
EK000CV140
Issue Site Survey S/C PKG
26-Apr-25
14-May-25
100%
EK000CV145
Issue Site Leveling PKG
26-Apr-25
16-May-25
100%
EK000MD44F
Update/Issue Formal Inquiry for ERW - MD404
27-Apr-25
01-May-25
100%
EK000ML51F
Develop & Issue Inquiry for ERW - ML512
27-Apr-25
01-May-25
100%
EK000MJ31F
Update/Issue Formal Inquiry for ERW - MJ301
27-Apr-25
08-May-25
100%
EK000MBP1E
Prepare & Issue Purchase ERW 101-B Shop Fab
27-Apr-25
10-May-25
100%
EK000ML33F
Develop & Issue Inquiry for ERW - ML330
27-Apr-25
13-May-25
100%
EK000MJ32F
Update/Issue Formal Inquiry for ERW - MJ302
27-Apr-25
29-May-25
100%
EK000MB63F
Prepare & Issue Purchase ERW - MB630
27-Apr-25
29-May-25
100%
EK000MJ36B
Develop/Issue Load Sht & Design Data ERW - MJ306
27-Apr-25
08-Jun-25
100%
EK000MU35B
Develop & Issue Design Data for ERW - MU350
01-May-25
14-May-25
100%
EK000IC010
Make decision of FF vs. Traditional DCS system
01-May-25
17-May-25
100%
EK000MJ75B
Develop & Issue Design Data for ERW - MJ750
01-May-25
20-May-25
100%
EK000CV136
Issue Rough Grade (Ammonia) S/C PKG
01-May-25
27-May-25
100%
EK000MJ73F
Develop & Issue Inquiry for ERW - MJ730
01-May-25
12-Jun-25
100%
EK000MD22F
Update/Issue Formal Inquiry for ERW - MD202
01-May-25
17-May-25
100%
EK000MC23P
Develop & Issue Setting Plans for ERW - MC230
01-May-25
21-Jun-25
100%
EK000MU11O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU25O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU310
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU32O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MD46P
Confirm Analytical Design for ERW - MD411
02-May-25
11-May-25
100%
EK000MJ34D
Technical Evaluation - MJ304
02-May-25
03-May-25
100%
EK000MC32P
Develop & Issue Setting Plans for ERW - MC311
02-May-25
20-Jun-25
100%
EK000MU41D
Technical Evaluation - MU410
03-May-25
28-Jun-25
100%
EK000MD31E
Prepare & Issue Purchase ERW - MD301
04-May-25
11-May-25
100%
EK000MD34E
Prepare & Issue Purchase ERW - MD304
04-May-25
11-May-25
100%
EK000MBP4E
Prepare & Issue Purchase ERW 101-B Cast Material
04-May-25
17-May-25
100%
EK000PC020
Load PCMS & Issue First Cost Report
04-May-25
18-May-25
100%
EK000MB41E
Prepare & Issue Purchase ERW - MB410
04-May-25
20-May-25
100%
EK000MD32E
Prepare & Issue Purchase ERW - MD302
06-May-25
10-May-25
100%
EK000MD43E
Prepare & Issue Purchase ERW - MD403
06-May-25
11-May-25
100%
EK000MU33B
Develop/Issue Load Sht & Design Data ERW - MU330
07-May-25
20-May-25
100%
EK000MC31D
Technical Evaluation - MC310
07-May-25
24-May-25
100%
EK000MC32D
Technical Evaluation - MC311
07-May-25
24-May-25
100%
EK020MC31D
MC312 - (120,121-C) - Technical Evaluation
07-May-25
24-May-25
100%
EK000MU61D
Technical Evaluation - MU611
07-May-25
20-Jun-25
100%
PK000PIA1C
Bulk Piping A/G & U/G - Tech Evaluation
07-May-25
21-Jun-25
100%
EK000MU21B
Develop/Issue Load Sht & Design Data ERW - MU221
08-May-25
10-May-25
100%
EK000MU22B
Develop/Issue Load Sht & Design Data ERW - MU222
08-May-25
20-May-25
100%
EK000MU29B
Develop/Issue Load Sht & Design Data ERW - MU292
08-May-25
20-May-25
100%
EK000YA005
Process Release
08-May-25
08-May-25
100%
EK000YA811
(EP-12) Issue Process Release
08-May-25
08-May-25
100%
EK000MD51E
Prepare & Issue Purchase ERW - MD501
09-May-25
11-May-25
100%
EK000MJ37F
Develop & Issue Inquiry for ERW - MJ340
09-May-25
05-Jun-25
100%
EK000MJ35F
Update/Issue Formal Inquiry for ERW - MJ305
10-May-25
24-May-25
100%
EK000MBP3E
Prepare & Issue Purchase ERW 101-B Pressure Part
13-May-25
16-May-25
100%
EK000I220A
Issue Preliminary ERW Pkg - MOV Valves
13-May-25
31-May-25
100%
EK000MD45F
Update/Issue Formal Inquiry for ERW - MD405
13-May-25
31-May-25
100%
EK000I354A
ITCC - Engr ERW Issued
13-May-25
23-Jul-25
100%
EK000MU30D
Technical Evaluation - MU300
13-May-25
27-Sep-25
100%
EK000MD46F
Update/Issue Formal Inquiry for ERW - MD411
14-May-25
31-May-25
100%
EK000MB62F
Prepare & Issue Purchase ERW - MB621
14-May-25
05-Jun-25
100%
EK000MB045
Catalyst Vac data sheets
20-May-25
28-May-25
100%
EK000CV065
Review Perimeter Wall Design - IFC (by OCI)
20-May-25
14-Jun-25
100%
EK000MJ75F
Develop & Issue Inquiry for ERW - MJ750
21-May-25
28-May-25
100%
EK000YA806
(EP-07) Issue Project Plan
24-May-25
24-May-25
100%
EK000MBG10
General & Administrative
28-May-25
27-Dec-26
57%
EK000I110D
Technical Evaluation - Orific Plates
28-May-25
10-Jun-25
100%
EK000I115D
Technical Evaluation - Annubars
28-May-25
10-Jun-25
100%
EK000I116D
Technical Evaluation - Wedge Flow Meters
28-May-25
10-Jun-25
100%
EK000I121D
Technical Evaluation - Vortex Meters
28-May-25
10-Jun-25
100%
EK000I122D
Technical Evaluation - Coriolis Meters
28-May-25
10-Jun-25
100%
EK000I124D
Technical Evaluation - Rotameters
28-May-25
10-Jun-25
100%
EK000I611D
Technical Evaluation - Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I612D
Technical Evaluation - Differential Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I616D
Technical Evaluation - Steam Drum Lvl Gauges
28-May-25
10-Jun-25
100%
EK000I617D
Technical Evaluation - Magnetic Lvl Gauges
28-May-25
10-Jun-25
100%
EK000MJ33F
Develop & Issue Inquiry for ERW - MJ303
28-May-25
18-Jun-25
100%
EK000MJ36F
Update/Issue Formal Inquiry for ERW - MJ306
28-May-25
19-Jun-25
100%
EK000I127D
Magnetic Flow Meters - Technical Evaluation
28-May-25
26-Jun-25
100%
EK000MB33D
MB333 - Technical Evaluation 101-B
28-May-25
01-Jul-25
100%
EK000YA801
(EP-02) Issue 30 day Look Ahead Schedule
28-May-25
28-May-25
100%
EK000MJ75D
Technical Evaluation - MJ750
29-May-25
30-May-25
100%
EK000ML43F
Develop & Issue Inquiry for ERW - ML430
31-May-25
06-Jun-25
100%
EK000MB69F
Prepare & IssuePurchase ERW - MB691
03-Jun-25
17-Jun-25
100%
EK000MU33D
Technical Evaluation - MU330
04-Jun-25
01-Jul-25
100%
EK000QM025
Training - Management System
05-Jun-25
05-Jun-25
100%
EK000I230A
Issue Preliminary ERW Pkg - On/Off Valves
05-Jun-25
15-Jun-25
100%
EK000PS040
Incorporate Comments / Issue Baseline Schedule
05-Jun-25
15-Jun-25
100%
EK000MU22F
Develop & Issue Inquiry for ERW - MU222
05-Jun-25
26-Jun-25
100%
EK000MB65F
Develop & Issue Purchase ERW - MB622
06-Jun-25
17-Jun-25
100%
PK000PIA4C
Product Line Piping - Tech Evaluation
07-Jun-25
04-Jul-25
100%
EK000I112D
Technical Evaluation - Venturis
10-Jun-25
14-Jun-25
100%
EK000PS030
Schedule Risk Analysis
10-Jun-25
20-Jun-25
100%
EK000MB66F
Prepare & IssuePurchase ERW - MB660
10-Jun-25
21-Jun-25
100%
EK000MU34B
Develop/Issue Load Sht & Design Data ERW - Chlorination Unit
11-Jun-25
15-Jun-25
100%
EK000MB68F
Prepare & Issue Purchase ERW - MB692
13-Jun-25
26-Jun-25
100%
EK000MB21F
Prepare & Issue Purchase ERW - MB212
17-Jun-25
25-Jun-25
100%
EK000MB42F
Prepare & Issue Purchase ERW - MB420
17-Jun-25
26-Jun-25
100%
EK000FP055
FP Overall Firewater P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK000MB34F
Prepare & Issue Purchase ERW - MB340
20-Jun-25
21-Jun-25
100%
EK000I221D
000 Everest Control Valves - Technical Evaluation
25-Jun-25
10-Jul-25
100%
EK000YA809
(EP-10) Locate Utility Tie-Ins
26-Jun-25
26-Jun-25
100%
EK000MU21F
Develop & Issue Inquiry for ERW - MU221
26-Jun-25
03-Jul-25
100%
EK000MD33E
Prepare & Issue Purchase ERW - MD303
01-Jul-25
04-Jul-25
100%
EK000MD41E
Prepare & Issue Purchase ERW - MD401
01-Jul-25
04-Jul-25
100%
EK000MB64F
Prepare & Issue Purchase ERW - MB640
02-Jul-25
11-Jul-25
100%
EK000ML33D
Technical Evaluation - ML330
10-Jul-25
23-Aug-25
100%
EK000ML43D
Technical Evaluation - ML430
10-Jul-25
06-Sep-25
100%
EK000I220D
Technical Evaluation - MOV's
16-Jul-25
23-Jul-25
100%
EK000MD21D
Technical Evaluation - MD201
16-Jul-25
10-Aug-25
100%
EK000I230D
Technical Evaluation - On/Off Valves
17-Jul-25
24-Jul-25
100%
EK000MB65D
Technical Evaluation - MB622
19-Jul-25
02-Aug-25
100%
EK000I618D
Technical Evaluation - Temperature Gauges
22-Jul-25
26-Jul-25
100%
EK000I621D
Technical Evaluation - Temperature Elements
22-Jul-25
26-Jul-25
100%
EK000I623D
Technical Evaluation - Multi-Point Thermocouples
22-Jul-25
26-Jul-25
100%
EK000I352A
SIS - Engr ERW Issued
22-Jul-25
02-Aug-25
100%
EK000MB69D
Technical Evaluation - MB691
22-Jul-25
07-Aug-25
100%
EK000MU22D
Technical Evaluation - MU222
22-Jul-25
06-Sep-25
100%
EK000MJ37D
Technical Evaluation - MJ340
24-Jul-25
28-Aug-25
100%
EK000MJ39D
Technical Evaluation - MJ391
25-Jul-25
21-Dec-25
100%
EK000MJ31X
Technical Evaluation - MJ301
25-Jul-25
10-Aug-25
100%
PK000MJ32X
Technical Evaluation - MJ302
25-Jul-25
10-Aug-25
100%
EK000MU11L
05B MU311 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MU25L
02G MU225 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MU32L
01D MU322 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MB68D
Technical Evaluation - MB692
29-Jul-25
30-Aug-25
100%
EK000MU31L
Define Chemical Treatment Requirements - MU310
30-Jul-25
10-Aug-25
100%
EK000MB66D
Technical Evaluation - MB660
30-Jul-25
13-Aug-25
100%
EK000MB34D
Technical Evaluation - MB340
30-Jul-25
13-Aug-25
100%
EK000ML51D
Technical Evaluation - ML512
30-Jul-25
19-Aug-25
100%
EK000MU21D
Technical Evaluation - MU221
30-Jul-25
14-Sep-25
100%
EK000MU35E
Prepare & Issue Purchase ERW - MU350
01-Aug-25
13-Aug-25
100%
EK000YA810
(EP-11) Issue Level 3 CPM Schedule
03-Aug-25
03-Aug-25
100%
EK000QM005
Training - Object Engineering
06-Aug-25
13-Aug-25
100%
EK000I444A
Develop & Issue Inquiry ERW - Analyzer Shelter
06-Aug-25
17-Aug-25
100%
EK000MJ73D
Technical Evaluation - MJ730
06-Aug-25
16-Sep-25
100%
EK000CV165
Issue ISBL Rough Grade Design Pkg.
09-Aug-25
04-Oct-25
100%
PK000MJ21N
Recv. Planning V. Data MJ202
09-Aug-25
30-Aug-25
100%
PK000MJ75N
Recv. Planning V. Data MJ750
09-Aug-25
30-Aug-25
100%
PK000MD31N
Recv. Planning V. Data MD301
09-Aug-25
09-Sep-25
100%
PK000ML31N
Recv. Planning V. Data ML313
09-Aug-25
12-Sep-25
100%
PK000MD41N
Recv. Planning V. Data MD401
09-Aug-25
17-Sep-25
100%
PK000MD33N
Recv. Planning V. Data MD303
09-Aug-25
25-Sep-25
100%
PK000MD43N
Recv. Planning V. Data MD403
09-Aug-25
14-Oct-25
100%
EK000MB64D
Technical Evaluation - MB640
09-Aug-25
17-Oct-25
100%
EK000EB015
Notice to Proceed (Eng. & Procurement Only)
10-Aug-25
10-Aug-25
100%
EK000I221A
000 Everest Control Valves - Issue Inquiry Req
12-Aug-25
16-Aug-25
100%
EK000MJ21E
Prepare & Issue Purchase ERW - MJ202
12-Aug-25
30-Aug-25
100%
PK000MU35N
Recv. Planning V. Data MU350
12-Aug-25
27-Sep-25
100%
EK000IC350
DCS - Develop Design Basis
12-Aug-25
04-Oct-25
100%
EK000MU61E
Prepare & Issue Purchase ERW - MU611
13-Aug-25
16-Aug-25
100%
PK000PTA0F
Engineered Pipe Supports - Planning V. Data
14-Aug-25
24-Jan-26
100%
PK000MD32N
Recv. Planning V. Data MD302
16-Aug-25
02-Oct-25
100%
PK000MD34N
Recv. Planning V. Data MD304
16-Aug-25
12-Nov-25
100%
EK000MJ75E
Prepare & Issue Purchase ERW - MJ750
19-Aug-25
28-Sep-25
100%
EK000PE070
Kick-off meeting at MEC
22-Aug-25
23-Aug-25
100%
PK000MJ35N
Recv. Planning V. Data MJ305
23-Aug-25
27-Sep-25
100%
PK000MJ36N
Recv. Planning V. Data MJ306
23-Aug-25
27-Sep-25
100%
EK000MD21E
Prepare & Issue Purchase ERW - MD201
27-Aug-25
29-Aug-25
100%
PK000MD51N
Recv. Planning V. Data MD501
27-Aug-25
01-Nov-25
100%
EK000MB21D
Technical Evaluation - MB212
29-Aug-25
01-Nov-25
100%
EK000MJ33D
Technical Evaluation - MJ303
30-Aug-25
19-Dec-25
100%
PK000MU21N
Recv. Planning V. Data MU221
01-Sep-25
27-Sep-25
100%
PK000ML42N
Recv. Planning V. Data ML420
02-Sep-25
26-Sep-25
100%
PK000MJ32N
Recv. Planning V. Data MJ302
02-Sep-25
27-Sep-25
100%
PK000MJ34N
Recv. Planning V. Data MJ304
02-Sep-25
27-Sep-25
100%
PK000MJ37N
Recv. Planning V. Data MJ340
02-Sep-25
27-Sep-25
100%
PK000MJ39N
Recv. Planning V. Data MJ391
02-Sep-25
27-Sep-25
100%
PK000MJ73N
Recv. Planning V. Data MJ730
02-Sep-25
27-Sep-25
100%
PK000MU22N
Recv. Planning V. Data MU222
02-Sep-25
27-Sep-25
100%
EK000MB095
101-B Ducting Detail Drawings - IFF
02-Sep-25
05-Apr-26
100%
EK000MD055
Pre-qualification trip to vendors shop (105-D)
03-Sep-25
05-Sep-25
100%
EK000MU41E
Prepare & Issue Purchase ERW - MU410
03-Sep-25
05-Sep-25
100%
PK000MU61N
Recv. Planning V. Data MU611
03-Sep-25
26-Sep-25
100%
PK000MJ22N
Recv. Planning V. Data MJ201
05-Sep-25
27-Sep-25
100%
PK000MJ31N
Recv. Planning V. Data MJ301
06-Sep-25
27-Sep-25
100%
PK000MC61N
Recv. Planning V. Data MC610
10-Sep-25
03-Dec-25
100%
EK000CV137
Issue OSBL Rough Grade Design Pkg.
11-Sep-25
26-Nov-25
100%
EK000ML51E
Prepare & Issue Purchase ERW - ML512
11-Sep-25
25-Sep-25
100%
PK000ML51N
Recv. Planning V. Data ML512
11-Sep-25
27-Sep-25
100%
EK000MJ36E
Prepare & Issue Purchase ERW - MJ306
13-Sep-25
25-Sep-25
100%
EK000MJ35E
Prepare & Issue Purchase ERW - MJ305
13-Sep-25
25-Sep-25
100%
EK000MJ22E
Prepare & Issue Purchase ERW - MJ201
13-Sep-25
13-Nov-25
100%
EK000I444D
Technical Evaluation - Analyzer Shelter
16-Sep-25
11-Dec-25
100%
EK000ML33E
Prepare & Issue Purchase ERW - ML330
17-Sep-25
25-Sep-25
100%
PK000MU41N
Recv. Planning V. Data MU410
17-Sep-25
27-Sep-25
100%
EK020PR20D
PR201 KAAP Catalyst - Technical Evaluation
17-Sep-25
01-Nov-25
100%
EK000MC61E
Prepare & Issue Purchase ERW - MC610
18-Sep-25
25-Sep-25
100%
EK000MJ32E
Prepare & Issue Purchase ERW - MJ302
20-Sep-25
13-Nov-25
100%
PK000ML33N
Recv. Planning V. Data ML330
20-Sep-25
27-Sep-25
100%
PK000ML43N
Recv. Planning V. Data ML430
20-Sep-25
01-Nov-25
100%
EK000MJ34E
Prepare & Issue Final Data Shts - MJ304
21-Sep-25
08-Nov-25
100%
EK000MU33E
Prepare & Issue Purchase ERW - MU330
21-Sep-25
26-Sep-25
100%
EK020MC31C
MC312 - (120,121-C) - Prepare & Issue Purchase ERW
23-Sep-25
27-Sep-25
100%
PK020MC31F
MC312 - (120,121-C) - Planning V. Data (Setting Plans)
23-Sep-25
08-Oct-25
100%
EK000MU31D
Technical Evaluation - MU310
24-Sep-25
30-Sep-25
100%
EK000MC23E
Prepare & Issue Purchase ERW - MC230
30-Sep-25
15-Oct-25
100%
EK000I352D
SIS - Tech Evaluation
30-Sep-25
07-Nov-25
100%
EK000MC21E
Prepare & Issue Purchase ERW - MC210
30-Sep-25
07-Nov-25
100%
EK000MU30E
Prepare & Issue Purchase ERW - MU300
01-Oct-25
14-Oct-25
100%
EK000ML42E
Prepare & Issue Purchase ERW - ML420
01-Oct-25
10-Oct-25
100%
EK000MJ37E
Prepare & Issue Purchase ERW - MJ340
01-Oct-25
16-Oct-25
100%
EK000MU31E
Prepare & Issue Purchase ERW - MU310
04-Oct-25
08-Oct-25
100%
EK000IC351
DCS - Develop Purchase T-Req
05-Oct-25
07-Nov-25
100%
EK000PR600
MD305 Merc. Removal Bed - Develop & Issue Load Sheets for ERW
08-Oct-25
09-Oct-25
100%
EK000MJ31E
Prepare & Issue Purchase ERW - MJ301
08-Oct-25
13-Nov-25
100%
PK000MJ33N
Recv. Planning V. Data MJ303
08-Oct-25
26-Dec-25
100%
EK000ML31E
Prepare & Issue Purchase ERW - ML313
08-Oct-25
09-Jan-26
100%
EK020ELEG2
Cathodic Protection - Subcontract Consultant ERW Package
09-Oct-25
01-Mar-26
100%
EK000MC32E
Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4)
10-Oct-25
15-Nov-25
100%
EK000MD103
MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW
10-Oct-25
26-Nov-25
100%
EK000PR610
MD305 Merc. Removal Bed - Analytical Design
10-Oct-25
26-Nov-25
100%
EK000YA813
(EP-14) Issue Plot Plans for Client Approval
11-Oct-25
11-Oct-25
100%
EK000I354D
ITCC - Tech Evaluation
15-Oct-25
12-Dec-25
100%
EK000MB42D
Technical Evaluation - MB420
16-Oct-25
30-Oct-25
100%
PK000IC35J
DCS - Planning V. Data
17-Oct-25
27-Dec-26
43%
PK000MU33N
03E MU330 2001-U - Piping Conceptual V. Data
30-Oct-25
02-Feb-26
100%
EK000ML43E
Prepare & Issue Purchase ERW - ML430
01-Nov-25
07-Nov-25
100%
EK000MJ37R
Develop & Issue Load Sheets for ERW - MJ307
04-Nov-25
08-Nov-25
100%
EK000MJ38R
Develop & Issue Load Sheets for ERW - MJ308
04-Nov-25
08-Nov-25
100%
EK000MU21E
Prepare & Issue Purchase ERW - MU221
05-Nov-25
22-Nov-25
100%
EK000MU22E
Prepare & Issue Purchase ERW - MU222
05-Nov-25
22-Nov-25
100%
EK000MU29F
Develop & Issue Inquiry for ERW - MU292
05-Nov-25
23-Nov-25
100%
EK000MJ37S
Develop & Issue Design Data for ERW - MJ307
11-Nov-25
15-Nov-25
100%
EK000MJ38S
Develop & Issue Design Data for ERW - MJ308
11-Nov-25
15-Nov-25
100%
EK000IC352
DCS - Final Tech Evaluation for Purchase
13-Nov-25
15-Nov-25
100%
EK000MJ37T
Update/Issue Formal Inquiry for ERW - MJ307
18-Nov-25
26-Nov-25
100%
EK000MJ73E
Prepare & Issue Purchase ERW - MJ730
19-Nov-25
05-Dec-25
100%
EK000FA005
Issue First Invoice to EBIC
19-Nov-25
19-Nov-25
100%
PK000MU30N
Recv. Planning V. Data MU300 - EDR Unit
19-Nov-25
10-Jan-26
100%
EK000E001A
Sub Stations - Issue ERW
22-Nov-25
31-Dec-25
100%
EK000MD102
MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur.
26-Nov-25
05-Dec-25
100%
EK000ML50Z
Technical Evaluation - ML500
10-Dec-25
31-Dec-25
100%
EK000E002A
Transformer - Issue ERW
18-Dec-25
30-Dec-25
100%
EK000MJ33E
Prepare & Issue Purchase ERW - MJ303
19-Dec-25
27-Dec-25
100%
PK000PSA8C
000 Relief Valves - Technical Evaluation
23-Dec-25
27-Dec-25
100%
EK000MU32D
01D MU322 Technical Evaluation
23-Dec-25
31-Jan-26
100%
EK000ELEJ1
Lighting, Installation Details
28-Dec-25
31-Dec-25
100%
EK000ELEK1
A/G Power & Control, Details
28-Dec-25
31-Dec-25
100%
EK000GE025
First Check Estimate
30-Dec-25
27-Feb-26
100%
EK000MU11D
05B MU311 Technical Evaluation
03-Jan-26
01-Feb-26
100%
EK000MC31E
Prepare & Issue Purchase ERW - MC310
03-Jan-26
12-Feb-26
100%
EK000MD104
MD305 Merc. Removal Bed - Technical Evaluation
13-Jan-26
29-Jan-26
100%
EK000IC353
DCS - Software Programming by KBR
15-Jan-26
27-Dec-26
29%
EK000CV045
Prepare Foundation Design Criteria
16-Jan-26
14-Mar-26
100%
EK000MJ37C
Prepare & Issue Purchase ERW - MJ307
17-Jan-26
20-Jan-26
100%
EK000MU29D
Technical Evaluation - MU292
20-Jan-26
03-Mar-26
100%
PK000PTA0H
Engineered Pipe Supports - Production V. Data
24-Jan-26
29-Jan-26
100%
EK000SY095
010 P&ID's - Tech Review
28-Jan-26
29-Jan-26
100%
EK000I3540
ITCC - Develop Final Design Basis
28-Jan-26
04-Mar-26
100%
EK000I3520
SIS - Develop Final Design Basis
28-Jan-26
12-Mar-26
100%
EK000MU25D
02G MU225 Technical Evaluation
28-Jan-26
21-Feb-26
100%
EK000MD105
MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW
29-Jan-26
01-Feb-26
100%
PK000ML50N
Recv. Planning V. Data ML500
29-Jan-26
24-Feb-26
100%
EK010E008A
540-SB Admin. Area Pwr Supply - ERW Package
01-Feb-26
14-Feb-26
100%
EK00012210
000 Everest Control Valves - D/S,Sizing,Tech Eval
03-Feb-26
05-Mar-26
100%
EK000YA822
(EP-22) Issue for Planning (IPL) >90% OSBL P&ID's
09-Feb-26
09-Feb-26
100%
EK000YA824
(EP-23) Issue For Planning (IPL) >90% ISBL P&ID's
09-Feb-26
09-Feb-26
100%
EK000MU11E
05B MU311 Prepare & Issue Purchase ERW
11-Feb-26
13-Feb-26
100%
EK000PS00C
000 SP Items - Technical Evaluation
11-Feb-26
01-Mar-26
100%
PK000MU11N
05B MU311 Recv. Planning V. Data
13-Feb-26
28-Feb-26
100%
EK000I444B
Develop Final Design Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000I444M
Develop Final Deign Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000E004A
UPS System - Issue ERW
17-Feb-26
28-Mar-26
100%
EK000E001D
Sub Stations - Tech Evaluation
19-Feb-26
27-Dec-26
21%
EK000CS027
Turnover System Definition for OSBL
25-Feb-26
27-Dec-26
19%
EK000I444F
Planning V. Data - Shelters/ Analyzers
25-Feb-26
27-Dec-26
19%
PK000I352J
SIS - Planning V. Data
25-Feb-26
27-Dec-26
19%
PK000I354J
ITCC - Planning V. Data
25-Feb-26
27-Dec-26
19%
EK000MJ38T
Update/Issue Formal Inquiry for ERW - MJ308
25-Feb-26
03-Mar-26
100%
EK000ML50E
Prepare & Issue Purchase ERW - ML500
25-Feb-26
08-Mar-26
100%
EK000YA831
(EP-26) Complete Hazard Review Meeting on >90% ISBL P&ID's
25-Feb-26
25-Feb-26
100%
EK000MJ39E
Prepare & Issue Purchase ERW - MJ391
27-Feb-26
09-Apr-26
100%
EK000I3541
ITCC - Develop Purchase T-Req
27-Feb-26
05-Mar-26
100%
EK000E002D
Transformer - Tech Evaluation
04-Mar-26
27-Dec-26
17%
EK000YA826
(EP-27) Begin Issuing Area Line Installation Details (IDF Files)
04-Mar-26
04-Mar-26
100%
EK000I221F
000 Everest Control Valves - Purchase ERW
11-Mar-26
27-Dec-26
15%
PK000MU29N
Recv. Planning V. Data MU292
19-Mar-26
09-Apr-26
100%
EK000MU29E
Prepare & Issue Purchase ERW - MU292
24-Mar-26
27-Mar-26
100%
EK000MU32E
01D MU322 Prepare & Issue Purchase ERW
31-Mar-26
31-Mar-26
100%
EK000I3521
SIS - Develop Purchase T-Req
31-Mar-26
03-Apr-26
100%
EK000MU25E
02G MU225 Prepare & Issue Purchase ERW
01-Apr-26
27-Dec-26
9%
EK000I3542
ITCC - Final Tech Evaluation for Purchase
01-Apr-26
03-Apr-26
100%
EK000I444C
Develop / Issue T-Req - Shelters/ Analyzers
01-Apr-26
03-Apr-26
100%
EK010E008D
540-SB Admin. Area Pwr Supply - Tech Evaluation
03-Apr-26
27-Dec-26
8%
EK000I3523
SIS - Software Programming by KBR
18-Apr-26
27-Dec-26
5%
EK000MJ38C
Prepare & Issue Purchase ERW - MJ308
23-Apr-26
27-Dec-26
5%
EK000E004D
UPS System - Tech Evaluation
27-Dec-26
27-Dec-26
0%
EK000ELEG0
Electrical Heat Tracing - ERW Package
27-Dec-26
27-Dec-26
0%
EK000FP060
FP Overall Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
0%
EK000FP065
FP Overall Firewater P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
0%
EK000GE030
Production Check Estimate
27-Dec-26
27-Dec-26
0%
EK000I3522
SIS - Final Tech Evaluation for Purchase
27-Dec-26
27-Dec-26
0%
EK000I352M
SIS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I354M
ITCC - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I444E
Final Tech Evaluation - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
EK000I444G
Review / Approve V. Data - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
EK000YA832
(EP-32) Issue OSBL (Units01/03) found./UG pipe work package
27-Dec-26
27-Dec-26
0%
EK000YA833
(EP-33) Issue > 90% ISBL Civil Foundations
27-Dec-26
27-Dec-26
0%
EK000YA839
(EP-35) Issue >90% OSBL P&ID's For Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA841
(EP-29) Issue OSBL Plot Plan for Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA848
(EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA888
(TLA-02) Second TLA Payment
27-Dec-26
27-Dec-26
0%
EK020ELEG5
Cathodic Protection - Design & Specs Package (By Consultant)
27-Dec-26
27-Dec-26
0%
PK000E001J
Sub Stations - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E002J
Transformer - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E004J
UPS System - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000IC35M
DCS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
PK010E008J
540-SG Admin. Area Pwr Supply - Planning V. Data
27-Dec-26
27-Dec-26
0%
EK000YA500
Issue ISBL Paint & Insulation Work Package
28-Dec-26
08-Mar-27
750.0d
0%
EK000ELEGP
Electrical Heat Tracing - Design & BOM by Consultant
30-Dec-26
30-Jan-27
91.0d
0%
EK000ELEN1
01,03,04 LV Wiring Diagrams - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN2
01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN3
01,03, Equipment Interconnection Diagrams - IFC
30-Dec-26
30-Jan-27
511.0d
0%
EK020ELEG6
Cathodic Protection - Material Supply (By Consultant)
30-Dec-26
02-May-27
6.0d
0%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
0%
EK000YA838
(EP-34) Issue >90% ISBL P&ID's For Construction (IFC)
03-Jan-27
03-Jan-27
0%
EK000YA030
Last PDS Planning Release
24-Jan-27
24-Jan-27
515.0d
0%
EK000YA040
Engineering 95% Complete
30-Jan-27
30-Jan-27
0%
PK000E001Z
Sub Stations - FAT
17-Feb-27
28-Feb-27
62.0d
0%
EK000YA835
(EP-36) Issue >90% Area Line Installation Details
21-Feb-27
21-Feb-27
0%
EK000YA847
(EP-39) Issue >90% OSBL Electrical Design Drawings
21-Feb-27
21-Feb-27
0%
EK000YA889
(TLA-03) Complete > TLA Payments
03-May-27
03-May-27
623.0d
0%
Q3 2024 Q4 2024 Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Q2 2027 Data Date
EK000CK085 — Establish bank account in Egypt | 02-Jul-24 → 24-Jan-26 | Complete 100% | float — EK000CK085 EK000SY005 — Systems Work Plan & Project Setup | 21-Jan-25 → 25-Mar-25 | Complete 100% | float — EK000SY005 EK000YA002 — Start Project | 22-Jan-25 | Complete EK000PR025 — Pressure Profile | 22-Jan-25 → 01-Feb-25 | Complete 100% | float — EK000PR050 — Electrical Load Summary - Initial | 22-Jan-25 → 01-Feb-25 | Complete 100% | float — EK000MD005 — Attend Alignment & strategy meetings | 22-Jan-25 → 09-Feb-25 | Complete 100% | float — EK000PR015 — Process Configuration | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR030 — Stream Summary | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR035 — Process Flow Diagrams PFD's - EOR | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR040 — Steam Balance Diagram - EOR | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000GE005 — Estimate Escalation Check - Info to Estimating | 22-Jan-25 → 14-Feb-25 | Complete 100% | float — EK000PR045 — Cooling Water Balance - EOR | 22-Jan-25 → 15-Feb-25 | Complete 100% | float — EK000PE025 — Document Management Plan - Issue for Review | 22-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000SY010 — MEC Convert prelim P&ID's to Smart Plant P&ID's | 22-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000MD015 — Conversion of drawings to metric units | 22-Jan-25 → 19-Feb-25 | Complete 100% | float — EK000PM015 — Project Coordination Procedure - IFA | 22-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PR020 — Heat & Material Balances (SOR & EOR) | 22-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PE085 — Participate in Escalation confirmation effort | 22-Jan-25 → 01-Mar-25 | Complete 100% | float — EK000PE085 EK000IM030 — Project Portal & Dashboard | 22-Jan-25 → 06-Mar-25 | Complete 100% | float — EK000IM030 EK000IC030 — Develop & Issue FieldBus Main Instr Vendor ERW | 22-Jan-25 → 08-Mar-25 | Complete 100% | float — EK000IC030 EK000PR055 — Feed & Fuel Summary | 22-Jan-25 → 09-Mar-25 | Complete 100% | float — EK000PR055 EK000IM020 — IM Strategy plan | 22-Jan-25 → 12-Mar-25 | Complete 100% | float — EK000IM020 EK000IM025 — IM Execution plan | 22-Jan-25 → 12-Mar-25 | Complete 100% | float — EK000IM025 EK000PR010 — Process Work Plan | 22-Jan-25 → 23-Mar-25 | Complete 100% | float — EK000PR010 EK000AR020 — Gather Bldg Requirements & Coordinate w/ Constr | 22-Jan-25 → 12-Apr-25 | Complete 100% | float — EK000AR020 EK000IM010 — Object Engineering set-up & procedures | 22-Jan-25 → 13-Apr-25 | Complete 100% | float — EK000IM010 EK000CV005 — Identify scope / Project set-up | 23-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PE125 — Preliminary Issue - Equipment List | 29-Jan-25 → 12-Feb-25 | Complete 100% | float — EK000CV020 — Review FMCL documents - Specs & Drawings | 29-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000IM040 — Establish Citrix for Test of PDS (HOC-MEC) | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PI080 — Develop Split of work | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000IM005 — Equipment List (MEL) Definition | 29-Jan-25 → 30-Mar-25 | Complete 100% | float — EK000IM005 EK000PE050 — Confirm of Split of Work for MEC | 02-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000IC35A — DCS - Engr ERW Issued | 04-Feb-25 → 12-Feb-25 | Complete 100% | float — EK000IM035 — Establish Documentum | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE010 — Publish Unit conversion standard | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE040 — Devlop & Issue List of Project Specs & Standards | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV025 — Review SEGAS Wind & Earthquake Specs | 05-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000PI120 — Identify priority pipe classes | 05-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000PS015 — Issue 90 Day look ahead schedule | 05-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MJ005 — Prepare Machinery Specs (Motors, Pkg Equipment) | 05-Feb-25 → 25-Feb-25 | Complete 100% | float — EK000IC015 — Modify Package Equipment Spec for IEC basis | 05-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000PE110 — Issue Draft Project Design Data | 05-Feb-25 → 06-Mar-25 | Complete 100% | float — EK000MC010 — Develop & Issue Exchanger Work Plan | 05-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI115 — Develop Piping Class Index (IOPMC) | 05-Feb-25 → 13-Mar-25 | Complete 100% | float — EK000SY015 — Develop Utility & offsite block flow diagrams | 05-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000SY015 EK000PI132 — Develop Early Tech P-Class specs for Procurement | 05-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PI132 EK000SY065 — Complete Utility Flow Diagrams | 05-Feb-25 → 03-Apr-25 | Complete 100% | float — EK000SY065 EK000CV010 — HOC / MEC split of Work | 07-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV030 — Prepare EBIC Wind & EarthquakeSpecs | 07-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000QM010 — Training - Export Compliance | 08-Feb-25 → 08-Feb-25 | Complete 100% | float — EK000ELZE0 — Area Classification | 11-Feb-25 → 30-Dec-25 | Complete 100% | float — EK000ELZE0 EK000MD31C — Prepare & Issue Prelim. RFQ - MD301 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD32C — Prepare & Issue Prelim. RFQ - MD302 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD34C — Prepare & Issue Prelim. RFQ - MD304 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD51C — Prepare & Issue Prelim. RFQ - MD501 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV040 — Prepare Topo Survey S/C Pkg | 12-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PE090 — Develop & Issue Engineering Plan | 12-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000EL005 — Electrical Work Plans | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI040 — Prepare technology work plan - Piping Engr. | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI060 — Prepare Other Project Documentation | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI051 — Prepare P/Mech Support Details | 12-Feb-25 → 15-Mar-25 | Complete 100% | float — EK000CV015 — Civil work Plan & Safety check list | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV050 — Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000MB005 — Develop & Issue Furnance Job Plan | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000MJ31C — Prepare & Issue Prelim. RFQ - MJ301 to Proc. | 13-Feb-25 → 13-Feb-25 | Complete 100% | float — EK000MJ32C — Prepare & Issue Prelim. RFQ - MJ302 to Proc. | 13-Feb-25 → 13-Feb-25 | Complete 100% | float — EK000MB33A — 101-B Develop & Issue Load Sheet | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD33A — Develop & Issue Load Sheets for ERW - MD303 | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MJ22A — Develop & Issue Load Sheets for ERW - MJ201 | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MJ21A — Develop & Issue Load Sheets for ERW - MJ202 | 14-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000PI110 — Locate FMCL Documents | 14-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PR060 — Process Load Sheets | 14-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PC005 — Prepare Estimate for Escalation Check | 15-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PE015 — MSD (From Metallurgy) - ISBL | 15-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC31C — Prepare & Issue Prelim. RFQ - MC310 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MC61C — Prepare & Issue Prelim. RFQ - MC610 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MBP1C — 101-B Prepare & Issue Prelim. Shop Fab to Proc. | 16-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000QM015 — Develop & Issue Quality Plan | 16-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000MC32C — Issue Prelim. RFQ - MC311 | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000MJ22C — Prepare & Issue Prelim. RFQ - MJ201 to Proc. | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK020MC31A — MC312 - (120,121-C) - Issue Prelim. RFQ | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000MD21A — Develop & Issue Load Sheets for ERW - MD201 | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD41C — Prepare & Issue Prelim. RFQ - MD401 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD43C — Prepare & Issue Prelim. RFQ - MD403 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD43A — Develop & Issue Load Sheets for ERW - MD403 | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MJ31A — Develop & Issue Load Sheets for ERW - MJ301 | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MD33C — Prepare & Issue Prelim. RFQ - MD303 to Proc. | 19-Feb-25 → 22-Feb-25 | Complete 100% | float — EK000EL020 — Define bulk material requirements | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MJ22B — Develop & Issue Design Data for ERW - MJ201 | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000ML31C — Prepare & Issue Prelim. RFQ - ML313 to Proc. | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PR115 — Issue Prelim Load Sht for Air Cooling Study | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MC210 — Cooling Water Balance Review | 19-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000IM045 — Establish IPMS | 19-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000IC005 — Develop Typical SIL Values Worksheet | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MJ35C — Prepare & Issue Prelim. RFQ - MJ305 to Proc. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MJ36C — Prepare & Issue Prelim. RFQ - MJ306 to Proc. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PK030 — Provide Job Specific SDR2 Priorities to Purch. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PI160 — P&ID Area Break Mark-up | 19-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000MJ39C — Prepare & Issue Prelim. RFQ - MJ391 to Proc. | 19-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PR076 — Identify Risk of Equipment Changes | 19-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PE035 — Rvw Lesson Learn w/Prj. Team&Develop Action List | 19-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000EV005 — Conceptual Design of Wastewater Systems | 19-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000PR145 — Eng. Studies - Ammonia Product Line U/G vs. A/G | 19-Feb-25 → 29-Mar-25 | Complete 100% | float — EK000PR145 EK000MB010 — 101-B Furnance Analytical - Convection Design | 19-Feb-25 → 30-Mar-25 | Complete 100% | float — EK000MB010 EK000CV070 — Validate Concrete & Steel by Planning Areas | 19-Feb-25 → 15-Apr-25 | Complete 100% | float — EK000CV070 EK000MD33P — Develop Analytical Sketches for ERW - MD303 | 19-Feb-25 → 04-May-25 | Complete 100% | float — EK000MD33P EK000PM055 — Complete EPC Insurance Forms | 19-Feb-25 → 04-May-25 | Complete 100% | float — EK000PM055 EK000PI020 — Develop Piping Specs (Paper) | 19-Feb-25 → 28-May-25 | Complete 100% | float — EK000PI020 EK000MJ21C — Prepare & Issue Prelim. RFQ - MJ202 to Proc. | 20-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000ML50C — Prepare & Issue Prelim. RFQ - ML500 to Proc. | 20-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MD44A — Develop & Issue Load Sheets for ERW - MD404 | 20-Feb-25 → 20-Mar-25 | Complete 100% | float — EK000MB61C — Prepare & Issue Prelim. RFQ - MB610 to Proc. | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MB62C — Prepare & Issue Prelim. RFQ - MB621 to Proc. | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MD34A — Develop & Issue Load Sheets for ERW - MD304 | 21-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MJ21B — Develop & Issue Design Data for ERW - MJ202 | 22-Feb-25 → 07-Mar-25 | Complete 100% | float — EK000MD21P — Develop Prelim Analytical Sktch for ERW - MD201 | 22-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000MD21Q — Develop Final Analytical Sktch for ERW - MD201 | 22-Feb-25 → 26-Apr-25 | Complete 100% | float — EK000MD21Q EK000YA804 — (EP-05) Issue Heat and Material Balance for Process Release | 22-Feb-25 | Complete EK000YA805 — (EP-06) Issue Equipment List for review | 22-Feb-25 | Complete EK000YA807 — (EP-08) Issue Utility Balances for Initial Release | 22-Feb-25 | Complete EK000FP025 — FP Gas Detection Location Plans - Not Required | 22-Feb-25 → 23-Aug-25 | Complete 100% | float — EK000FP025 EK000MC32A — Develop & Issue Load Sheets for ERW - MC311 | 23-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000CK080 — Expedite legal issues associated w/ KBRII | 23-Feb-25 → 28-Feb-26 | Complete 100% | float — EK000CK080 EK000MB060 — 101-B General Arrangement Drawing | 25-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000MF31A — Develop & Issue Load Sheets for ERW - MF301 | 26-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MB41C — Prepare & Issue Prelim. RFQ - MB410 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC21C — Prepare & Issue Prelim. RFQ - MC210 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC23C — Prepare & Issue Prelim. RFQ - MC230 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD31A — Develop & Issue Load Sheets for ERW - MD301 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD32A — Develop & Issue Load Sheets for ERW - MD302 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD41A — Develop & Issue Load Sheets for ERW - MD401 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000EL015 — Split of work with MEC and Other Discipline | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MB63C — Prepare & Issue Prelim. RFQ - MB630 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MBP4C — Prepare & Issue Prelim. RFQ Cast Material | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE060 — Define Task Force Area in MEC | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE075 — MEC Organization Chart | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PM030 — Estimate Escalation Check - IRC Approvals | 26-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000PR095 — Steam Balance - Startup, 103-J, Etc | 26-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MBP3C — Prepare & Issue Prelim. RFQ Pressure Parts | 26-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000MD33B — Develop & Issue Design Data for ERW - MD303 | 26-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000EV025 — Develop & Issue Enviromental Work Plan | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC020 — Establlish data warehouse - Intools Basic Setup | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC025 — Review Instr. & Installation Details - ID Change | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000MJ22F — Update/Issue Formal Inquiry for ERW - MJ201 | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PK010 — Issue critical req'n submittal sched to Procmnt | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000GE010 — Eng. Studies - Air Coolers vs. Cooling Water | 26-Feb-25 → 12-Mar-25 | Complete 100% | float — EK000CV060 — Civil project highlights | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000PI005 — Locate Permanent Tie in pnts Gas, Wtr, Storm wtr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000PE065 — Develop & Issue HOC - MEC Coordination Plan | 26-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000PI133 — Dvlp/Issue V-class specs & Standads for Procurmt | 26-Feb-25 → 09-Apr-25 | Complete 100% | float — EK000PI133 EK000MB085 — 101-B Radiant Detail Drawings - IFF | 26-Feb-25 → 12-Apr-25 | Complete 100% | float — EK000MB085 EK000MB090 — 101-B Convection Detail Drawings - IFF | 26-Feb-25 → 12-Apr-25 | Complete 100% | float — EK000MB090 EK000CV035 — Prepare Geotech S/C Pkgs | 26-Feb-25 → 27-Apr-25 | Complete 100% | float — EK000CV035 EK000EL025 — Develop installation details | 26-Feb-25 → 07-May-25 | Complete 100% | float — EK000EL025 EK000IC045 — Develop & Issue CSE Work Plan | 26-Feb-25 → 08-May-25 | Complete 100% | float — EK000IC045 EK000PM045 — Issue Execution Strategy /Project Execution Plan | 26-Feb-25 → 24-May-25 | Complete 100% | float — EK000PM045 EK000MC31A — Develop & Issue Load Sheets for ERW - MC310 | 27-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000ML50B — Develop/Issue Load Sht & Design Data ERW - ML500 | 27-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000MD42A — Develop & Issue Load Sheets for ERW - MD402 | 28-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000MD51A — Develop & Issue Load Sheets for ERW - MD501 | 28-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000MJ35A — Develop & Issue Load Sheets for ERW - MJ305 | 28-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000YA808 — (EP-09) Issue Engineering Plan | 01-Mar-25 | Complete EK000MD060 — Prepare Vessel work plan & other quality documents | 02-Mar-25 → 02-Mar-25 | Complete 100% | float — EK000MC31B — Develop & Issue Design Data for ERW - MC310 | 02-Mar-25 → 13-Mar-25 | Complete 100% | float — EK000MC31F — Finalize Equip. Data Sheets for ERW - MC310 | 02-Mar-25 → 12-Apr-25 | Complete 100% | float — EK000MC31F EK000PI125 — Validate new plot layout (impacts on pipe stress | 02-Mar-25 → 21-May-25 | Complete 100% | float — EK000PI125 EK000MJ21D — Technical Evaluation - MJ202 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000MJ75A — Develop & Issue Load Sheets for ERW - MJ750 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000ML31A — Develop & Issue Load Sheets for ERW - ML313 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000MB51C — Prepare & Issue Prelim. RFQ - MB511 to Proc. | 05-Mar-25 → 07-Mar-25 | Complete 100% | float — EK000CV075 — Egyptian Professional Engineer - Define Reqmnts | 05-Mar-25 → 08-Mar-25 | Complete 100% | float — EK000MC21A — Develop & Issue Load Sheets for ERW - MC210 | 05-Mar-25 → 08-Mar-25 | Complete 100% | float — EK000EL035 — Voltage drop table | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000ML42C — Prepare & Issue Prelim. RFQ - ML420 to Proc. | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MU33C — Prepare & Issue Prelim. RFQ - MU330 to Proc. | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000CS030 — Start-up Schedule (Prelim for 1st Planner) | 05-Mar-25 → 14-Mar-25 | Complete 100% | float — EK000MC32B — Develop & Issue Design Data for ERW - MC311 | 05-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MC23A — Develop & Issue Load Sheets for ERW - MC230 | 05-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MC32F — Finalize Equip. Data Sheets for ERW - MC311 | 05-Mar-25 → 24-May-25 | Complete 100% | float — EK000MC32F EK000MD22A — Develop & Issue Load Sheets for ERW - MD202 | 06-Mar-25 → 06-Mar-25 | Complete 100% | float — EK000MBP1D — 101-B Technical Bid Evaluation Shop Fab | 06-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MJ37A — Develop & Issue Load Sheets for ERW - MJ340 | 06-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000ML31B — Develop & Issue Design Data for ERW - ML313 | 06-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000MD42P — Confirm Analytical Design for ERW - MD402 | 06-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000ML50F — Update/Issue Formal Inquiry for ERW - ML500 | 06-Mar-25 → 27-Apr-25 | Complete 100% | float — EK000ML50F EK000PE020 — WMS Setup & Development | 07-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000CV080 — Egyptian Professional Eng. - Issue P.O/Subc. Pkg | 08-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MJ21F — Update/Issue Formal Inquiry for ERW - MJ202 | 08-Mar-25 → 13-Mar-25 | Complete 100% | float — EK000MC21B — Develop & Issue Design Data for ERW - MC210 | 08-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MJ31B — Develop & Issue Design Data for ERW - MJ301 | 08-Mar-25 → 12-Apr-25 | Complete 100% | float — EK000PI055 — Prepare Object Engineering Work Instruction | 08-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PC010 — Estimate Turnover to Project Team | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI085 — Estimate/Schedule Review | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000MD34R — Develop Final Analytical Sktch for ERW - MD304 | 09-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD43P — Confirm Analytical Design for ERW - MD403 | 09-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MC61A — Develop & Issue Load Sheets for ERW - MC610 | 09-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000PC015 — Estimate Recast & Develop Project Control Budget | 09-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000PC015 EK000PI105 — Performance Test of Citrix for PDS w/MEC | 12-Mar-25 → 12-Mar-25 | Complete 100% | float — EK000MU41F — Develop & Issue Inquiry for ERW - MU410 | 12-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD34P — Confirm Analytical Design for ERW - MD304 | 12-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU41A — Develop & Issue Load Sheets for ERW - MU410 | 12-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MD31P — Confirm Analytical Design for ERW - MD301 | 12-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000MD32P — Confirm Analytical Design for ERW - MD302 | 12-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000PI100 — Critical Line List | 12-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000EV020 — Develop Preliminary noise model | 12-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000EV020 EK000MC21F — Finalize Equip. Data Sheets for ERW - MC210 | 12-Mar-25 → 13-Jun-25 | Complete 100% | float — EK000MC21F EK000MD020 — Equipment Modeling for Vessel - MEC | 13-Mar-25 → 25-Mar-26 | Complete 100% | float — EK000MD020 EK000MB61D — Technical Evaluation - MB610 | 14-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000PR080 — Input to Process Guarantees | 14-Mar-25 → 03-May-25 | Complete 100% | float — EK000PR080 EK000IC35D — DCS - Tech Evaluation | 14-Mar-25 → 14-May-25 | Complete 100% | float — EK000IC35D EK000MJ32A — Develop & Issue Load Sheets for ERW - MJ302 | 15-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML31F — Update/Issue Formal Inquiry for ERW - ML313 | 16-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD31B — Develop & Issue Design Data for ERW - MD301 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD32B — Develop & Issue Design Data for ERW - MD302 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD34B — Develop & Issue Design Data for ERW - MD304 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MJ22D — Technical Evaluation - MJ201 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD45A — Develop & Issue Load Sheets for ERW - MD405 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML43A — Develop & Issue Load Sheets for ERW - ML430 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML44A — Develop & Issue Load Sheets for ERW - ML440 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000PE095 — Disciplines Load WMS with Budgets & Deliverables | 16-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000MD34D — Technical Evaluation - MD304 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD34D EK000MD41D — Technical Evaluation - MD401 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD41D EK000ML42A — Develop & Issue Load Sheets for ERW - ML420 | 19-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU35A — Develop & Issue Load Sheets for ERW - MU350 | 19-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU41B — Develop & Issue Design Data for ERW - MU410 | 19-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MU30F — Develop & Issue Inquiry for ERW - MU300 | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MF33B — Develop/Issue Load Sht & Design Data ERW - MF311 | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MF32B — Develop/Issue Load Sht & Design Data ERW - MF302 | 19-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000MD21B — Develop & Issue Design Data for ERW - MD201 | 19-Mar-25 → 08-May-25 | Complete 100% | float — EK000MD21B EK000ML42F — Update/Issue Formal Inquiry for ERW - ML420 | 19-Mar-25 → 24-Apr-25 | Complete 100% | float — EK000MC63A — Develop & Issue Load Sheets for ERW - MC630 | 20-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MU61F — Develop & Issue Inquiry for ERW - MU611 | 20-Mar-25 → 25-Mar-25 | Complete 100% | float — EK000I210D — 000 Control Valves - Technical Evaluation | 20-Mar-25 → 23-May-25 | Complete 100% | float — EK000I210D EK000MU35F — Update/Issue Formal Inquiry for ERW - MU350 | 21-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MD47A — Develop & Issue Load Sheets for ERW - MD406 | 21-Mar-25 → 23-Mar-25 | Complete 100% | float — EK000MD51B — Develop & Issue Design Data for ERW - MD501 | 21-Mar-25 → 28-Mar-25 | Complete 100% | float — EK000MC61D — Technical Evaluation - MC610 | 21-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MC61F — Finalize Equip. Data Sheets for ERW - MC610 | 21-Mar-25 → 10-Apr-25 | Complete 100% | float — EK000MJ32B — Develop & Issue Design Data for ERW - MJ302 | 21-Mar-25 → 13-Apr-25 | Complete 100% | float — EK000MD34F — Update/Issue Formal Inquiry for ERW - MD304 | 21-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000EV010 — Develop design basis for evaporation pond | 22-Mar-25 → 11-May-25 | Complete 100% | float — EK000EV010 EK000YA802 — (EP-03) Issue Process Plan | 22-Mar-25 | Complete EK000MB51F — Prepare & Issue Purchase ERW - MB511 | 23-Mar-25 → 17-Apr-25 | Complete 100% | float — EK000MJ39B — Develop/Issue Load Sht & Design Data ERW - MJ391 | 25-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000ML50D — Technical Evaluation - ML500 | 25-Mar-25 → 27-Apr-25 | Complete 100% | float — EK000MD025 — Prepare job quality drawings for ERW | 25-Mar-25 → 28-May-25 | Complete 100% | float — EK000MD025 EK000ML44B — Develop & Issue Design Data for ERW - ML440 | 26-Mar-25 → 27-Mar-25 | Complete 100% | float — EK000MF31P — Confirm Analytical Design for ERW - MF301 | 26-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000PR070 — Effluent Summary | 26-Mar-25 → 30-Mar-25 | Complete 100% | float — EK000MD51D — Technical Evaluation - MD501 | 26-Mar-25 → 03-Apr-25 | Complete 100% | float — EK000MU33F — Update/Issue Formal Inquiry for ERW - MU330 | 26-Mar-25 → 04-Apr-25 | Complete 100% | float — EK000MD33F — Update/Issue Formal Inquiry for ERW - MD303 | 26-Mar-25 → 11-May-25 | Complete 100% | float — EK000MD33F EK000MF32F — Develop & Issue Design Data for Tank Subcontract - MF302 | 26-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000I131D — Technical Evaluation - Transmitters | 26-Mar-25 → 23-May-25 | Complete 100% | float — EK000I131D EK000MJ35D — Technical Evaluation - MJ305 | 27-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MJ36D — Technical Evaluation - MJ306 | 27-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MF33F — Develop & Issue Design Data for Tank Subcontract - MF311 | 27-Mar-25 → 09-Apr-25 | Complete 100% | float — EK000CVK35 — OSBL Rough Grading/Road | 27-Mar-25 → 23-May-25 | Complete 100% | float — EK000CVK35 EK000MD51F — Update/Issue Formal Inquiry for ERW - MD501 | 29-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000MD45P — Confirm Analytical Design for ERW - MD405 | 29-Mar-25 → 25-Apr-25 | Complete 100% | float — EK000MB62D — Technical Evaluation - MB621 | 30-Mar-25 → 18-Apr-25 | Complete 100% | float — EK000MB63D — Technical Evaluation - MB630 | 30-Mar-25 → 24-Jun-25 | Complete 100% | float — EK000MB63D EK000MF31B — Develop & Issue Design Data for Tank Subcontrac - MF301 | 01-Apr-25 → 08-Apr-25 | Complete 100% | float — EK000MJ34B — Develop/Issue Load Sht & Design Data ERW - MJ304 | 01-Apr-25 → 08-Apr-25 | Complete 100% | float — EK000PR065 — Catalyst and Chemical Specs | 01-Apr-25 → 09-Apr-25 | Complete 100% | float — EK000MB070 — 101-B Foundation Loads | 01-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000PR075 — Process Description | 01-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MJ39F — Update/Issue Formal Inquiry for ERW - MJ391 | 01-Apr-25 → 27-Apr-25 | Complete 100% | float — EK000QM020 — Develop/ Issue/ Approval of QA/QC Manual (EBIC/EXIM Verification) | 01-Apr-25 → 31-Oct-25 | Complete 100% | float — EK000QM020 EK000MD44P — Confirm Analytical Design for ERW - MD404 | 02-Apr-25 → 03-Apr-25 | Complete 100% | float — EK000MD31F — Update/Issue Formal Inquiry for ERW - MD301 | 02-Apr-25 → 16-Apr-25 | Complete 100% | float — EK000MU61B — Develop/Issue Load Sht & Design Data ERW - MU611 | 02-Apr-25 → 14-May-25 | Complete 100% | float — EK000MU61B EK000MB51D — Technical Evaluation - MB511 | 02-Apr-25 → 16-Apr-25 | Complete 100% | float — EK000MD32F — Update/Issue Formal Inquiry for ERW - MD302 | 02-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MD43D — Technical Evaluation - MD403 | 02-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MC61B — Develop & Issue Design Data for ERW - MC610 | 04-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MJ35B — Develop & Issue Design Data for ERW - MJ305 | 05-Apr-25 → 09-May-25 | Complete 100% | float — EK000MB080 — 101-B Convection Coil Design | 05-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000ML31D — Technical Evaluation - ML313 | 05-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MB050 — 101-B Radiant coil design | 06-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MD22P — Confirm Analytical Design for ERW - MD202 | 06-Apr-25 → 15-Apr-25 | Complete 100% | float — EK000MB33F — MB333 - Develop & Issue Purchase ERW 101-B | 06-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MBP4D — Technical Evaluation - 101-B Cast Material | 06-Apr-25 → 01-May-25 | Complete 100% | float — EK000PI131 — Devlop Balance Tech P-Class specs for Procuremnt | 06-Apr-25 → 25-May-25 | Complete 100% | float — EK000PI131 EK000FP050 — FP Overall Firewater P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK000FP050 EK000MD43B — Develop & Issue Design Data for ERW - MD403 | 08-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MU35D — Technical Evaluation - MU350 | 08-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MC21D — Technical Evaluation - MC210 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MC23D — Technical Evaluation - MC230 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MD45B — Develop & Issue Design Data for ERW - MD405 | 08-Apr-25 → 08-May-25 | Complete 100% | float — EK000MC23B — Develop & Issue Design Data for ERW - MC230 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MD42B — Develop & Issue Design Data for ERW - MD402 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MD41B — Develop & Issue Design Data for ERW - MD401 | 09-Apr-25 → 18-Apr-25 | Complete 100% | float — EK000MU30B — Develop/Issue Load Sht & Design Data ERW - MU300 | 09-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000PS010 — Level III CPM Schedule / First Planner | 09-Apr-25 → 24-May-25 | Complete 100% | float — EK000PS010 EK000ML42D — Technical Evaluation - ML420 | 09-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MJ34F — Update/Issue Formal Inquiry for ERW - MJ304 | 09-Apr-25 → 26-Apr-25 | Complete 100% | float — EK000MB41D — Technical Evaluation - MB410 | 10-Apr-25 → 01-May-25 | Complete 100% | float — EK000MJ33B — Develop/Issue Load Sht & Design Data ERW - MJ303 | 11-Apr-25 → 23-May-25 | Complete 100% | float — EK000MJ33B EK000MJ32D — Technical Evaluation - MJ302 | 12-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MJ31D — Technical Evaluation - MJ301 | 12-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MB055 — 101-B Radiant coil BOM | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MB075 — 101-B Convection Coil BOM | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML51B — Develop/Issue Load Sht & Design Data ERW - ML512 | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MC63B — Develop & Issue Design Data for ERW - MC630 | 15-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MB61E — Prepare & Issue Purchase ERW - MB610 | 15-Apr-25 → 22-Apr-25 | Complete 100% | float — EK000MD43F — Update/Issue Formal Inquiry for ERW - MD403 | 15-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD32D — Technical Evaluation - MD302 | 15-Apr-25 → 04-May-25 | Complete 100% | float — EK000IC36D — DCS (MIV) - Tech Evaluation | 15-Apr-25 → 17-May-25 | Complete 100% | float — EK000MC31P — Develop & Issue Setting Plans for ERW - MC310 | 15-Apr-25 → 28-May-25 | Complete 100% | float — EK000MC31P EK000MC21P — Develop & Issue Setting Plans for ERW - MC210 | 15-Apr-25 → 20-Jun-25 | Complete 100% | float — EK000MC21P EK000CS025 — Turnover System Definition for ISBL | 15-Apr-25 → 31-Jan-26 | Complete 100% | float — EK000CS025 EK000MD42F — Update/Issue Formal Inquiry for ERW - MD402 | 16-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML42B — Develop & Issue Design Data for ERW - ML420 | 16-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MD31D — Technical Evaluation - MD301 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000ML33B — Develop/Issue Load Sht & Design Data ERW - ML330 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD33D — Technical Evaluation - MD303 | 16-Apr-25 → 04-May-25 | Complete 100% | float — EK000MBP3D — Technical Evaluation - 101-B Pressure Parts | 16-Apr-25 → 10-May-25 | Complete 100% | float — EK000MD21F — Develop & Issue Inquiry ERW - MD201 | 17-Apr-25 → 17-Jun-25 | Complete 100% | float — EK000MD21F EK000PR140 — Formal Issue of Process Release | 18-Apr-25 → 08-May-25 | Complete 100% | float — EK000MD47P — Confirm Analytical Design for ERW - MD406 | 18-Apr-25 → 22-Apr-25 | Complete 100% | float — EK000MJ37B — Develop & Issue Design Data for ERW - MJ340 | 19-Apr-25 → 09-May-25 | Complete 100% | float — EK000MD41F — Update/Issue Formal Inquiry for ERW - MD401 | 20-Apr-25 → 26-Apr-25 | Complete 100% | float — EK000MD44Q — Develop Analytical Sketches for ERW - MD404 | 20-Apr-25 → 27-Apr-25 | Complete 100% | float — EK000MJ73B — Develop/Issue Load Sht & Design Data ERW - MJ730 | 20-Apr-25 → 30-Apr-25 | Complete 100% | float — EK000EV015 — Issue load sheets for wastewater systems | 20-Apr-25 → 31-May-25 | Complete 100% | float — EK000EV015 EK000MD44B — Develop & Issue Design Data for ERW - MD404 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD47B — Develop & Issue Design Data for ERW - MD406 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD46B — Develop/Issue Load Sht & Design Data ERW - MD411 | 22-Apr-25 → 03-May-25 | Complete 100% | float — EK000MU11B — 05B MU311 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU25B — 02G MU225 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU32B — 01D MU322 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MD22B — Develop & Issue Design Data for ERW - MD202 | 23-Apr-25 → 01-May-25 | Complete 100% | float — EK000MU31B — Develop/Issue Load Sht & Design Data ERW - MU310 | 23-Apr-25 → 16-May-25 | Complete 100% | float — EK000MC23F — Finalize Equip. Data Sheets for ERW - MC230 | 23-Apr-25 → 13-Jun-25 | Complete 100% | float — EK000MC23F EK000CV036 — Issue Geotech S/C PKG | 26-Apr-25 → 02-May-25 | Complete 100% | float — EK000CV140 — Issue Site Survey S/C PKG | 26-Apr-25 → 14-May-25 | Complete 100% | float — EK000CV145 — Issue Site Leveling PKG | 26-Apr-25 → 16-May-25 | Complete 100% | float — EK000MD44F — Update/Issue Formal Inquiry for ERW - MD404 | 27-Apr-25 → 01-May-25 | Complete 100% | float — EK000ML51F — Develop & Issue Inquiry for ERW - ML512 | 27-Apr-25 → 01-May-25 | Complete 100% | float — EK000MJ31F — Update/Issue Formal Inquiry for ERW - MJ301 | 27-Apr-25 → 08-May-25 | Complete 100% | float — EK000MBP1E — Prepare & Issue Purchase ERW 101-B Shop Fab | 27-Apr-25 → 10-May-25 | Complete 100% | float — EK000ML33F — Develop & Issue Inquiry for ERW - ML330 | 27-Apr-25 → 13-May-25 | Complete 100% | float — EK000MJ32F — Update/Issue Formal Inquiry for ERW - MJ302 | 27-Apr-25 → 29-May-25 | Complete 100% | float — EK000MB63F — Prepare & Issue Purchase ERW - MB630 | 27-Apr-25 → 29-May-25 | Complete 100% | float — EK000MJ36B — Develop/Issue Load Sht & Design Data ERW - MJ306 | 27-Apr-25 → 08-Jun-25 | Complete 100% | float — EK000MJ36B EK000MU35B — Develop & Issue Design Data for ERW - MU350 | 01-May-25 → 14-May-25 | Complete 100% | float — EK000IC010 — Make decision of FF vs. Traditional DCS system | 01-May-25 → 17-May-25 | Complete 100% | float — EK000MJ75B — Develop & Issue Design Data for ERW - MJ750 | 01-May-25 → 20-May-25 | Complete 100% | float — EK000CV136 — Issue Rough Grade (Ammonia) S/C PKG | 01-May-25 → 27-May-25 | Complete 100% | float — EK000MJ73F — Develop & Issue Inquiry for ERW - MJ730 | 01-May-25 → 12-Jun-25 | Complete 100% | float — EK000MJ73F EK000MD22F — Update/Issue Formal Inquiry for ERW - MD202 | 01-May-25 → 17-May-25 | Complete 100% | float — EK000MC23P — Develop & Issue Setting Plans for ERW - MC230 | 01-May-25 → 21-Jun-25 | Complete 100% | float — EK000MC23P EK000MU11O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU11O EK000MU25O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU25O EK000MU310 — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU310 EK000MU32O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU32O EK000MD46P — Confirm Analytical Design for ERW - MD411 | 02-May-25 → 11-May-25 | Complete 100% | float — EK000MJ34D — Technical Evaluation - MJ304 | 02-May-25 → 03-May-25 | Complete 100% | float — EK000MC32P — Develop & Issue Setting Plans for ERW - MC311 | 02-May-25 → 20-Jun-25 | Complete 100% | float — EK000MC32P EK000MU41D — Technical Evaluation - MU410 | 03-May-25 → 28-Jun-25 | Complete 100% | float — EK000MU41D EK000MD31E — Prepare & Issue Purchase ERW - MD301 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MD34E — Prepare & Issue Purchase ERW - MD304 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MBP4E — Prepare & Issue Purchase ERW 101-B Cast Material | 04-May-25 → 17-May-25 | Complete 100% | float — EK000PC020 — Load PCMS & Issue First Cost Report | 04-May-25 → 18-May-25 | Complete 100% | float — EK000MB41E — Prepare & Issue Purchase ERW - MB410 | 04-May-25 → 20-May-25 | Complete 100% | float — EK000MD32E — Prepare & Issue Purchase ERW - MD302 | 06-May-25 → 10-May-25 | Complete 100% | float — EK000MD43E — Prepare & Issue Purchase ERW - MD403 | 06-May-25 → 11-May-25 | Complete 100% | float — EK000MU33B — Develop/Issue Load Sht & Design Data ERW - MU330 | 07-May-25 → 20-May-25 | Complete 100% | float — EK000MC31D — Technical Evaluation - MC310 | 07-May-25 → 24-May-25 | Complete 100% | float — EK000MC32D — Technical Evaluation - MC311 | 07-May-25 → 24-May-25 | Complete 100% | float — EK020MC31D — MC312 - (120,121-C) - Technical Evaluation | 07-May-25 → 24-May-25 | Complete 100% | float — EK000MU61D — Technical Evaluation - MU611 | 07-May-25 → 20-Jun-25 | Complete 100% | float — EK000MU61D PK000PIA1C — Bulk Piping A/G & U/G - Tech Evaluation | 07-May-25 → 21-Jun-25 | Complete 100% | float — PK000PIA1C EK000MU21B — Develop/Issue Load Sht & Design Data ERW - MU221 | 08-May-25 → 10-May-25 | Complete 100% | float — EK000MU22B — Develop/Issue Load Sht & Design Data ERW - MU222 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000MU29B — Develop/Issue Load Sht & Design Data ERW - MU292 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000YA005 — Process Release | 08-May-25 | Complete EK000YA811 — (EP-12) Issue Process Release | 08-May-25 | Complete EK000MD51E — Prepare & Issue Purchase ERW - MD501 | 09-May-25 → 11-May-25 | Complete 100% | float — EK000MJ37F — Develop & Issue Inquiry for ERW - MJ340 | 09-May-25 → 05-Jun-25 | Complete 100% | float — EK000MJ35F — Update/Issue Formal Inquiry for ERW - MJ305 | 10-May-25 → 24-May-25 | Complete 100% | float — EK000MBP3E — Prepare & Issue Purchase ERW 101-B Pressure Part | 13-May-25 → 16-May-25 | Complete 100% | float — EK000I220A — Issue Preliminary ERW Pkg - MOV Valves | 13-May-25 → 31-May-25 | Complete 100% | float — EK000MD45F — Update/Issue Formal Inquiry for ERW - MD405 | 13-May-25 → 31-May-25 | Complete 100% | float — EK000I354A — ITCC - Engr ERW Issued | 13-May-25 → 23-Jul-25 | Complete 100% | float — EK000I354A EK000MU30D — Technical Evaluation - MU300 | 13-May-25 → 27-Sep-25 | Complete 100% | float — EK000MU30D EK000MD46F — Update/Issue Formal Inquiry for ERW - MD411 | 14-May-25 → 31-May-25 | Complete 100% | float — EK000MB62F — Prepare & Issue Purchase ERW - MB621 | 14-May-25 → 05-Jun-25 | Complete 100% | float — EK000MB045 — Catalyst Vac data sheets | 20-May-25 → 28-May-25 | Complete 100% | float — EK000CV065 — Review Perimeter Wall Design - IFC (by OCI) | 20-May-25 → 14-Jun-25 | Complete 100% | float — EK000MJ75F — Develop & Issue Inquiry for ERW - MJ750 | 21-May-25 → 28-May-25 | Complete 100% | float — EK000YA806 — (EP-07) Issue Project Plan | 24-May-25 | Complete EK000MBG10 — General & Administrative | 28-May-25 → 27-Dec-26 | In Progress 57% | float — EK000MBG10 EK000I110D — Technical Evaluation - Orific Plates | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I115D — Technical Evaluation - Annubars | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I116D — Technical Evaluation - Wedge Flow Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I121D — Technical Evaluation - Vortex Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I122D — Technical Evaluation - Coriolis Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I124D — Technical Evaluation - Rotameters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I611D — Technical Evaluation - Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I612D — Technical Evaluation - Differential Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I616D — Technical Evaluation - Steam Drum Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I617D — Technical Evaluation - Magnetic Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000MJ33F — Develop & Issue Inquiry for ERW - MJ303 | 28-May-25 → 18-Jun-25 | Complete 100% | float — EK000MJ36F — Update/Issue Formal Inquiry for ERW - MJ306 | 28-May-25 → 19-Jun-25 | Complete 100% | float — EK000I127D — Magnetic Flow Meters - Technical Evaluation | 28-May-25 → 26-Jun-25 | Complete 100% | float — EK000MB33D — MB333 - Technical Evaluation 101-B | 28-May-25 → 01-Jul-25 | Complete 100% | float — EK000YA801 — (EP-02) Issue 30 day Look Ahead Schedule | 28-May-25 | Complete EK000MJ75D — Technical Evaluation - MJ750 | 29-May-25 → 30-May-25 | Complete 100% | float — EK000ML43F — Develop & Issue Inquiry for ERW - ML430 | 31-May-25 → 06-Jun-25 | Complete 100% | float — EK000MB69F — Prepare & IssuePurchase ERW - MB691 | 03-Jun-25 → 17-Jun-25 | Complete 100% | float — EK000MU33D — Technical Evaluation - MU330 | 04-Jun-25 → 01-Jul-25 | Complete 100% | float — EK000QM025 — Training - Management System | 05-Jun-25 → 05-Jun-25 | Complete 100% | float — EK000I230A — Issue Preliminary ERW Pkg - On/Off Valves | 05-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000PS040 — Incorporate Comments / Issue Baseline Schedule | 05-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000MU22F — Develop & Issue Inquiry for ERW - MU222 | 05-Jun-25 → 26-Jun-25 | Complete 100% | float — EK000MB65F — Develop & Issue Purchase ERW - MB622 | 06-Jun-25 → 17-Jun-25 | Complete 100% | float — PK000PIA4C — Product Line Piping - Tech Evaluation | 07-Jun-25 → 04-Jul-25 | Complete 100% | float — EK000I112D — Technical Evaluation - Venturis | 10-Jun-25 → 14-Jun-25 | Complete 100% | float — EK000PS030 — Schedule Risk Analysis | 10-Jun-25 → 20-Jun-25 | Complete 100% | float — EK000MB66F — Prepare & IssuePurchase ERW - MB660 | 10-Jun-25 → 21-Jun-25 | Complete 100% | float — EK000MU34B — Develop/Issue Load Sht & Design Data ERW - Chlorination Unit | 11-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000MB68F — Prepare & Issue Purchase ERW - MB692 | 13-Jun-25 → 26-Jun-25 | Complete 100% | float — EK000MB21F — Prepare & Issue Purchase ERW - MB212 | 17-Jun-25 → 25-Jun-25 | Complete 100% | float — EK000MB42F — Prepare & Issue Purchase ERW - MB420 | 17-Jun-25 → 26-Jun-25 | Complete 100% | float — EK000FP055 — FP Overall Firewater P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK000FP055 EK000MB34F — Prepare & Issue Purchase ERW - MB340 | 20-Jun-25 → 21-Jun-25 | Complete 100% | float — EK000I221D — 000 Everest Control Valves - Technical Evaluation | 25-Jun-25 → 10-Jul-25 | Complete 100% | float — EK000YA809 — (EP-10) Locate Utility Tie-Ins | 26-Jun-25 | Complete EK000MU21F — Develop & Issue Inquiry for ERW - MU221 | 26-Jun-25 → 03-Jul-25 | Complete 100% | float — EK000MD33E — Prepare & Issue Purchase ERW - MD303 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — EK000MD41E — Prepare & Issue Purchase ERW - MD401 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — EK000MB64F — Prepare & Issue Purchase ERW - MB640 | 02-Jul-25 → 11-Jul-25 | Complete 100% | float — EK000ML33D — Technical Evaluation - ML330 | 10-Jul-25 → 23-Aug-25 | Complete 100% | float — EK000ML33D EK000ML43D — Technical Evaluation - ML430 | 10-Jul-25 → 06-Sep-25 | Complete 100% | float — EK000ML43D EK000I220D — Technical Evaluation - MOV's | 16-Jul-25 → 23-Jul-25 | Complete 100% | float — EK000MD21D — Technical Evaluation - MD201 | 16-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000I230D — Technical Evaluation - On/Off Valves | 17-Jul-25 → 24-Jul-25 | Complete 100% | float — EK000MB65D — Technical Evaluation - MB622 | 19-Jul-25 → 02-Aug-25 | Complete 100% | float — EK000I618D — Technical Evaluation - Temperature Gauges | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I621D — Technical Evaluation - Temperature Elements | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I623D — Technical Evaluation - Multi-Point Thermocouples | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I352A — SIS - Engr ERW Issued | 22-Jul-25 → 02-Aug-25 | Complete 100% | float — EK000MB69D — Technical Evaluation - MB691 | 22-Jul-25 → 07-Aug-25 | Complete 100% | float — EK000MU22D — Technical Evaluation - MU222 | 22-Jul-25 → 06-Sep-25 | Complete 100% | float — EK000MU22D EK000MJ37D — Technical Evaluation - MJ340 | 24-Jul-25 → 28-Aug-25 | Complete 100% | float — EK000MJ39D — Technical Evaluation - MJ391 | 25-Jul-25 → 21-Dec-25 | Complete 100% | float — EK000MJ39D EK000MJ31X — Technical Evaluation - MJ301 | 25-Jul-25 → 10-Aug-25 | Complete 100% | float — PK000MJ32X — Technical Evaluation - MJ302 | 25-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000MU11L — 05B MU311 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU25L — 02G MU225 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU32L — 01D MU322 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MB68D — Technical Evaluation - MB692 | 29-Jul-25 → 30-Aug-25 | Complete 100% | float — EK000MU31L — Define Chemical Treatment Requirements - MU310 | 30-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000MB66D — Technical Evaluation - MB660 | 30-Jul-25 → 13-Aug-25 | Complete 100% | float — EK000MB34D — Technical Evaluation - MB340 | 30-Jul-25 → 13-Aug-25 | Complete 100% | float — EK000ML51D — Technical Evaluation - ML512 | 30-Jul-25 → 19-Aug-25 | Complete 100% | float — EK000MU21D — Technical Evaluation - MU221 | 30-Jul-25 → 14-Sep-25 | Complete 100% | float — EK000MU21D EK000MU35E — Prepare & Issue Purchase ERW - MU350 | 01-Aug-25 → 13-Aug-25 | Complete 100% | float — EK000YA810 — (EP-11) Issue Level 3 CPM Schedule | 03-Aug-25 | Complete EK000QM005 — Training - Object Engineering | 06-Aug-25 → 13-Aug-25 | Complete 100% | float — EK000I444A — Develop & Issue Inquiry ERW - Analyzer Shelter | 06-Aug-25 → 17-Aug-25 | Complete 100% | float — EK000MJ73D — Technical Evaluation - MJ730 | 06-Aug-25 → 16-Sep-25 | Complete 100% | float — EK000MJ73D EK000CV165 — Issue ISBL Rough Grade Design Pkg. | 09-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000CV165 PK000MJ21N — Recv. Planning V. Data MJ202 | 09-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000MJ75N — Recv. Planning V. Data MJ750 | 09-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000MD31N — Recv. Planning V. Data MD301 | 09-Aug-25 → 09-Sep-25 | Complete 100% | float — PK000ML31N — Recv. Planning V. Data ML313 | 09-Aug-25 → 12-Sep-25 | Complete 100% | float — PK000MD41N — Recv. Planning V. Data MD401 | 09-Aug-25 → 17-Sep-25 | Complete 100% | float — PK000MD41N PK000MD33N — Recv. Planning V. Data MD303 | 09-Aug-25 → 25-Sep-25 | Complete 100% | float — PK000MD33N PK000MD43N — Recv. Planning V. Data MD403 | 09-Aug-25 → 14-Oct-25 | Complete 100% | float — PK000MD43N EK000MB64D — Technical Evaluation - MB640 | 09-Aug-25 → 17-Oct-25 | Complete 100% | float — EK000MB64D EK000EB015 — Notice to Proceed (Eng. & Procurement Only) | 10-Aug-25 | Complete EK000I221A — 000 Everest Control Valves - Issue Inquiry Req | 12-Aug-25 → 16-Aug-25 | Complete 100% | float — EK000MJ21E — Prepare & Issue Purchase ERW - MJ202 | 12-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000MU35N — Recv. Planning V. Data MU350 | 12-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MU35N EK000IC350 — DCS - Develop Design Basis | 12-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000IC350 EK000MU61E — Prepare & Issue Purchase ERW - MU611 | 13-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000PTA0F — Engineered Pipe Supports - Planning V. Data | 14-Aug-25 → 24-Jan-26 | Complete 100% | float — PK000PTA0F PK000MD32N — Recv. Planning V. Data MD302 | 16-Aug-25 → 02-Oct-25 | Complete 100% | float — PK000MD32N PK000MD34N — Recv. Planning V. Data MD304 | 16-Aug-25 → 12-Nov-25 | Complete 100% | float — PK000MD34N EK000MJ75E — Prepare & Issue Purchase ERW - MJ750 | 19-Aug-25 → 28-Sep-25 | Complete 100% | float — EK000MJ75E EK000PE070 — Kick-off meeting at MEC | 22-Aug-25 → 23-Aug-25 | Complete 100% | float — PK000MJ35N — Recv. Planning V. Data MJ305 | 23-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MJ36N — Recv. Planning V. Data MJ306 | 23-Aug-25 → 27-Sep-25 | Complete 100% | float — EK000MD21E — Prepare & Issue Purchase ERW - MD201 | 27-Aug-25 → 29-Aug-25 | Complete 100% | float — PK000MD51N — Recv. Planning V. Data MD501 | 27-Aug-25 → 01-Nov-25 | Complete 100% | float — PK000MD51N EK000MB21D — Technical Evaluation - MB212 | 29-Aug-25 → 01-Nov-25 | Complete 100% | float — EK000MB21D EK000MJ33D — Technical Evaluation - MJ303 | 30-Aug-25 → 19-Dec-25 | Complete 100% | float — EK000MJ33D PK000MU21N — Recv. Planning V. Data MU221 | 01-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000ML42N — Recv. Planning V. Data ML420 | 02-Sep-25 → 26-Sep-25 | Complete 100% | float — PK000MJ32N — Recv. Planning V. Data MJ302 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ34N — Recv. Planning V. Data MJ304 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ37N — Recv. Planning V. Data MJ340 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ39N — Recv. Planning V. Data MJ391 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ73N — Recv. Planning V. Data MJ730 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MU22N — Recv. Planning V. Data MU222 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — EK000MB095 — 101-B Ducting Detail Drawings - IFF | 02-Sep-25 → 05-Apr-26 | Complete 100% | float — EK000MB095 EK000MD055 — Pre-qualification trip to vendors shop (105-D) | 03-Sep-25 → 05-Sep-25 | Complete 100% | float — EK000MU41E — Prepare & Issue Purchase ERW - MU410 | 03-Sep-25 → 05-Sep-25 | Complete 100% | float — PK000MU61N — Recv. Planning V. Data MU611 | 03-Sep-25 → 26-Sep-25 | Complete 100% | float — PK000MJ22N — Recv. Planning V. Data MJ201 | 05-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ31N — Recv. Planning V. Data MJ301 | 06-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MC61N — Recv. Planning V. Data MC610 | 10-Sep-25 → 03-Dec-25 | Complete 100% | float — PK000MC61N EK000CV137 — Issue OSBL Rough Grade Design Pkg. | 11-Sep-25 → 26-Nov-25 | Complete 100% | float — EK000CV137 EK000ML51E — Prepare & Issue Purchase ERW - ML512 | 11-Sep-25 → 25-Sep-25 | Complete 100% | float — PK000ML51N — Recv. Planning V. Data ML512 | 11-Sep-25 → 27-Sep-25 | Complete 100% | float — EK000MJ36E — Prepare & Issue Purchase ERW - MJ306 | 13-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000MJ35E — Prepare & Issue Purchase ERW - MJ305 | 13-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000MJ22E — Prepare & Issue Purchase ERW - MJ201 | 13-Sep-25 → 13-Nov-25 | Complete 100% | float — EK000MJ22E EK000I444D — Technical Evaluation - Analyzer Shelter | 16-Sep-25 → 11-Dec-25 | Complete 100% | float — EK000I444D EK000ML33E — Prepare & Issue Purchase ERW - ML330 | 17-Sep-25 → 25-Sep-25 | Complete 100% | float — PK000MU41N — Recv. Planning V. Data MU410 | 17-Sep-25 → 27-Sep-25 | Complete 100% | float — EK020PR20D — PR201 KAAP Catalyst - Technical Evaluation | 17-Sep-25 → 01-Nov-25 | Complete 100% | float — EK020PR20D EK000MC61E — Prepare & Issue Purchase ERW - MC610 | 18-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000MJ32E — Prepare & Issue Purchase ERW - MJ302 | 20-Sep-25 → 13-Nov-25 | Complete 100% | float — EK000MJ32E PK000ML33N — Recv. Planning V. Data ML330 | 20-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000ML43N — Recv. Planning V. Data ML430 | 20-Sep-25 → 01-Nov-25 | Complete 100% | float — PK000ML43N EK000MJ34E — Prepare & Issue Final Data Shts - MJ304 | 21-Sep-25 → 08-Nov-25 | Complete 100% | float — EK000MJ34E EK000MU33E — Prepare & Issue Purchase ERW - MU330 | 21-Sep-25 → 26-Sep-25 | Complete 100% | float — EK020MC31C — MC312 - (120,121-C) - Prepare & Issue Purchase ERW | 23-Sep-25 → 27-Sep-25 | Complete 100% | float — PK020MC31F — MC312 - (120,121-C) - Planning V. Data (Setting Plans) | 23-Sep-25 → 08-Oct-25 | Complete 100% | float — EK000MU31D — Technical Evaluation - MU310 | 24-Sep-25 → 30-Sep-25 | Complete 100% | float — EK000MC23E — Prepare & Issue Purchase ERW - MC230 | 30-Sep-25 → 15-Oct-25 | Complete 100% | float — EK000I352D — SIS - Tech Evaluation | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000I352D EK000MC21E — Prepare & Issue Purchase ERW - MC210 | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000MC21E EK000MU30E — Prepare & Issue Purchase ERW - MU300 | 01-Oct-25 → 14-Oct-25 | Complete 100% | float — EK000ML42E — Prepare & Issue Purchase ERW - ML420 | 01-Oct-25 → 10-Oct-25 | Complete 100% | float — EK000MJ37E — Prepare & Issue Purchase ERW - MJ340 | 01-Oct-25 → 16-Oct-25 | Complete 100% | float — EK000MU31E — Prepare & Issue Purchase ERW - MU310 | 04-Oct-25 → 08-Oct-25 | Complete 100% | float — EK000IC351 — DCS - Develop Purchase T-Req | 05-Oct-25 → 07-Nov-25 | Complete 100% | float — EK000PR600 — MD305 Merc. Removal Bed - Develop & Issue Load Sheets for ERW | 08-Oct-25 → 09-Oct-25 | Complete 100% | float — EK000MJ31E — Prepare & Issue Purchase ERW - MJ301 | 08-Oct-25 → 13-Nov-25 | Complete 100% | float — PK000MJ33N — Recv. Planning V. Data MJ303 | 08-Oct-25 → 26-Dec-25 | Complete 100% | float — PK000MJ33N EK000ML31E — Prepare & Issue Purchase ERW - ML313 | 08-Oct-25 → 09-Jan-26 | Complete 100% | float — EK000ML31E EK020ELEG2 — Cathodic Protection - Subcontract Consultant ERW Package | 09-Oct-25 → 01-Mar-26 | Complete 100% | float — EK020ELEG2 EK000MC32E — Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4) | 10-Oct-25 → 15-Nov-25 | Complete 100% | float — EK000MD103 — MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW | 10-Oct-25 → 26-Nov-25 | Complete 100% | float — EK000MD103 EK000PR610 — MD305 Merc. Removal Bed - Analytical Design | 10-Oct-25 → 26-Nov-25 | Complete 100% | float — EK000PR610 EK000YA813 — (EP-14) Issue Plot Plans for Client Approval | 11-Oct-25 | Complete EK000I354D — ITCC - Tech Evaluation | 15-Oct-25 → 12-Dec-25 | Complete 100% | float — EK000I354D EK000MB42D — Technical Evaluation - MB420 | 16-Oct-25 → 30-Oct-25 | Complete 100% | float — PK000IC35J — DCS - Planning V. Data | 17-Oct-25 → 27-Dec-26 | In Progress 43% | float — PK000IC35J PK000MU33N — 03E MU330 2001-U - Piping Conceptual V. Data | 30-Oct-25 → 02-Feb-26 | Complete 100% | float — PK000MU33N EK000ML43E — Prepare & Issue Purchase ERW - ML430 | 01-Nov-25 → 07-Nov-25 | Complete 100% | float — EK000MJ37R — Develop & Issue Load Sheets for ERW - MJ307 | 04-Nov-25 → 08-Nov-25 | Complete 100% | float — EK000MJ38R — Develop & Issue Load Sheets for ERW - MJ308 | 04-Nov-25 → 08-Nov-25 | Complete 100% | float — EK000MU21E — Prepare & Issue Purchase ERW - MU221 | 05-Nov-25 → 22-Nov-25 | Complete 100% | float — EK000MU22E — Prepare & Issue Purchase ERW - MU222 | 05-Nov-25 → 22-Nov-25 | Complete 100% | float — EK000MU29F — Develop & Issue Inquiry for ERW - MU292 | 05-Nov-25 → 23-Nov-25 | Complete 100% | float — EK000MJ37S — Develop & Issue Design Data for ERW - MJ307 | 11-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000MJ38S — Develop & Issue Design Data for ERW - MJ308 | 11-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000IC352 — DCS - Final Tech Evaluation for Purchase | 13-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000MJ37T — Update/Issue Formal Inquiry for ERW - MJ307 | 18-Nov-25 → 26-Nov-25 | Complete 100% | float — EK000MJ73E — Prepare & Issue Purchase ERW - MJ730 | 19-Nov-25 → 05-Dec-25 | Complete 100% | float — EK000FA005 — Issue First Invoice to EBIC | 19-Nov-25 | Complete PK000MU30N — Recv. Planning V. Data MU300 - EDR Unit | 19-Nov-25 → 10-Jan-26 | Complete 100% | float — PK000MU30N EK000E001A — Sub Stations - Issue ERW | 22-Nov-25 → 31-Dec-25 | Complete 100% | float — EK000E001A EK000MD102 — MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur. | 26-Nov-25 → 05-Dec-25 | Complete 100% | float — EK000ML50Z — Technical Evaluation - ML500 | 10-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000E002A — Transformer - Issue ERW | 18-Dec-25 → 30-Dec-25 | Complete 100% | float — EK000MJ33E — Prepare & Issue Purchase ERW - MJ303 | 19-Dec-25 → 27-Dec-25 | Complete 100% | float — PK000PSA8C — 000 Relief Valves - Technical Evaluation | 23-Dec-25 → 27-Dec-25 | Complete 100% | float — EK000MU32D — 01D MU322 Technical Evaluation | 23-Dec-25 → 31-Jan-26 | Complete 100% | float — EK000MU32D EK000ELEJ1 — Lighting, Installation Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000ELEK1 — A/G Power & Control, Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000GE025 — First Check Estimate | 30-Dec-25 → 27-Feb-26 | Complete 100% | float — EK000GE025 EK000MU11D — 05B MU311 Technical Evaluation | 03-Jan-26 → 01-Feb-26 | Complete 100% | float — EK000MC31E — Prepare & Issue Purchase ERW - MC310 | 03-Jan-26 → 12-Feb-26 | Complete 100% | float — EK000MC31E EK000MD104 — MD305 Merc. Removal Bed - Technical Evaluation | 13-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000IC353 — DCS - Software Programming by KBR | 15-Jan-26 → 27-Dec-26 | In Progress 29% | float — EK000IC353 EK000CV045 — Prepare Foundation Design Criteria | 16-Jan-26 → 14-Mar-26 | Complete 100% | float — EK000CV045 EK000MJ37C — Prepare & Issue Purchase ERW - MJ307 | 17-Jan-26 → 20-Jan-26 | Complete 100% | float — EK000MU29D — Technical Evaluation - MU292 | 20-Jan-26 → 03-Mar-26 | Complete 100% | float — EK000MU29D PK000PTA0H — Engineered Pipe Supports - Production V. Data | 24-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000SY095 — 010 P&ID's - Tech Review | 28-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000I3540 — ITCC - Develop Final Design Basis | 28-Jan-26 → 04-Mar-26 | Complete 100% | float — EK000I3520 — SIS - Develop Final Design Basis | 28-Jan-26 → 12-Mar-26 | Complete 100% | float — EK000I3520 EK000MU25D — 02G MU225 Technical Evaluation | 28-Jan-26 → 21-Feb-26 | Complete 100% | float — EK000MD105 — MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW | 29-Jan-26 → 01-Feb-26 | Complete 100% | float — PK000ML50N — Recv. Planning V. Data ML500 | 29-Jan-26 → 24-Feb-26 | Complete 100% | float — EK010E008A — 540-SB Admin. Area Pwr Supply - ERW Package | 01-Feb-26 → 14-Feb-26 | Complete 100% | float — EK00012210 — 000 Everest Control Valves - D/S,Sizing,Tech Eval | 03-Feb-26 → 05-Mar-26 | Complete 100% | float — EK000YA822 — (EP-22) Issue for Planning (IPL) >90% OSBL P&ID's | 09-Feb-26 | Complete EK000YA824 — (EP-23) Issue For Planning (IPL) >90% ISBL P&ID's | 09-Feb-26 | Complete EK000MU11E — 05B MU311 Prepare & Issue Purchase ERW | 11-Feb-26 → 13-Feb-26 | Complete 100% | float — EK000PS00C — 000 SP Items - Technical Evaluation | 11-Feb-26 → 01-Mar-26 | Complete 100% | float — PK000MU11N — 05B MU311 Recv. Planning V. Data | 13-Feb-26 → 28-Feb-26 | Complete 100% | float — EK000I444B — Develop Final Design Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000I444M — Develop Final Deign Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000E004A — UPS System - Issue ERW | 17-Feb-26 → 28-Mar-26 | Complete 100% | float — EK000E004A EK000E001D — Sub Stations - Tech Evaluation | 19-Feb-26 → 27-Dec-26 | In Progress 21% | float — EK000E001D EK000CS027 — Turnover System Definition for OSBL | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000CS027 EK000I444F — Planning V. Data - Shelters/ Analyzers | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000I444F PK000I352J — SIS - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I352J PK000I354J — ITCC - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I354J EK000MJ38T — Update/Issue Formal Inquiry for ERW - MJ308 | 25-Feb-26 → 03-Mar-26 | Complete 100% | float — EK000ML50E — Prepare & Issue Purchase ERW - ML500 | 25-Feb-26 → 08-Mar-26 | Complete 100% | float — EK000YA831 — (EP-26) Complete Hazard Review Meeting on >90% ISBL P&ID's | 25-Feb-26 | Complete EK000MJ39E — Prepare & Issue Purchase ERW - MJ391 | 27-Feb-26 → 09-Apr-26 | Complete 100% | float — EK000MJ39E EK000I3541 — ITCC - Develop Purchase T-Req | 27-Feb-26 → 05-Mar-26 | Complete 100% | float — EK000E002D — Transformer - Tech Evaluation | 04-Mar-26 → 27-Dec-26 | In Progress 17% | float — EK000E002D EK000YA826 — (EP-27) Begin Issuing Area Line Installation Details (IDF Files) | 04-Mar-26 | Complete EK000I221F — 000 Everest Control Valves - Purchase ERW | 11-Mar-26 → 27-Dec-26 | In Progress 15% | float — EK000I221F PK000MU29N — Recv. Planning V. Data MU292 | 19-Mar-26 → 09-Apr-26 | Complete 100% | float — EK000MU29E — Prepare & Issue Purchase ERW - MU292 | 24-Mar-26 → 27-Mar-26 | Complete 100% | float — EK000MU32E — 01D MU322 Prepare & Issue Purchase ERW | 31-Mar-26 → 31-Mar-26 | Complete 100% | float — EK000I3521 — SIS - Develop Purchase T-Req | 31-Mar-26 → 03-Apr-26 | Complete 100% | float — EK000MU25E — 02G MU225 Prepare & Issue Purchase ERW | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EK000MU25E EK000I3542 — ITCC - Final Tech Evaluation for Purchase | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK000I444C — Develop / Issue T-Req - Shelters/ Analyzers | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK010E008D — 540-SB Admin. Area Pwr Supply - Tech Evaluation | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — EK010E008D EK000I3523 — SIS - Software Programming by KBR | 18-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK000I3523 EK000MJ38C — Prepare & Issue Purchase ERW - MJ308 | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK000MJ38C EK000E004D — UPS System - Tech Evaluation | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000ELEG0 — Electrical Heat Tracing - ERW Package | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP060 — FP Overall Firewater P&IDs - Development & Issue IFD | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP065 — FP Overall Firewater P&IDs - Development & Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000GE030 — Production Check Estimate | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I3522 — SIS - Final Tech Evaluation for Purchase | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I352M — SIS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I354M — ITCC - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444E — Final Tech Evaluation - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444G — Review / Approve V. Data - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000YA832 — (EP-32) Issue OSBL (Units01/03) found./UG pipe work package | 27-Dec-26 | Not Started EK000YA833 — (EP-33) Issue > 90% ISBL Civil Foundations | 27-Dec-26 | Not Started EK000YA839 — (EP-35) Issue >90% OSBL P&ID's For Construction (IFC) | 27-Dec-26 | Not Started EK000YA841 — (EP-29) Issue OSBL Plot Plan for Construction (IFC) | 27-Dec-26 | Not Started EK000YA848 — (EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC) | 27-Dec-26 | Not Started EK000YA888 — (TLA-02) Second TLA Payment | 27-Dec-26 | Not Started EK020ELEG5 — Cathodic Protection - Design & Specs Package (By Consultant) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001J — Sub Stations - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002J — Transformer - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004J — UPS System - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000IC35M — DCS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008J — 540-SG Admin. Area Pwr Supply - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000YA500 — Issue ISBL Paint & Insulation Work Package | 28-Dec-26 → 08-Mar-27 | Not Started 0% | float 750.0d EK000YA500 EK000ELEGP — Electrical Heat Tracing - Design & BOM by Consultant | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 91.0d EK000ELEN1 — 01,03,04 LV Wiring Diagrams - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN2 — 01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN3 — 01,03, Equipment Interconnection Diagrams - IFC | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EK020ELEG6 — Cathodic Protection - Material Supply (By Consultant) | 30-Dec-26 → 02-May-27 | Not Started 0% | float 6.0d EK020ELEG6 EK000PI200 — Final Delta Piping Bulk Quanities for Purchase | 03-Jan-27 | Not Started EK000YA838 — (EP-34) Issue >90% ISBL P&ID's For Construction (IFC) | 03-Jan-27 | Not Started EK000YA030 — Last PDS Planning Release | 24-Jan-27 | Not Started EK000YA040 — Engineering 95% Complete | 30-Jan-27 | Not Started PK000E001Z — Sub Stations - FAT | 17-Feb-27 → 28-Feb-27 | Not Started 0% | float 62.0d EK000YA835 — (EP-36) Issue >90% Area Line Installation Details | 21-Feb-27 | Not Started EK000YA847 — (EP-39) Issue >90% OSBL Electrical Design Drawings | 21-Feb-27 | Not Started EK000YA889 — (TLA-03) Complete > TLA Payments | 03-May-27 | Not Started