Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 652 activities in 00 Common × clear
Code
Activity
Start
Finish
Flt
%
EK000CK085
Establish bank account in Egypt
02-Jul-24
24-Jan-26
100%
EK000SY005
Systems Work Plan & Project Setup
21-Jan-25
25-Mar-25
100%
EK000YA002
Start Project
22-Jan-25
22-Jan-25
100%
EK000PR025
Pressure Profile
22-Jan-25
01-Feb-25
100%
EK000PR050
Electrical Load Summary - Initial
22-Jan-25
01-Feb-25
100%
EK000MD005
Attend Alignment & strategy meetings
22-Jan-25
09-Feb-25
100%
EK000PR015
Process Configuration
22-Jan-25
13-Feb-25
100%
EK000PR030
Stream Summary
22-Jan-25
13-Feb-25
100%
EK000PR035
Process Flow Diagrams PFD's - EOR
22-Jan-25
13-Feb-25
100%
EK000PR040
Steam Balance Diagram - EOR
22-Jan-25
13-Feb-25
100%
EK000GE005
Estimate Escalation Check - Info to Estimating
22-Jan-25
14-Feb-25
100%
EK000PR045
Cooling Water Balance - EOR
22-Jan-25
15-Feb-25
100%
EK000PE025
Document Management Plan - Issue for Review
22-Jan-25
16-Feb-25
100%
EK000SY010
MEC Convert prelim P&ID's to Smart Plant P&ID's
22-Jan-25
16-Feb-25
100%
EK000MD015
Conversion of drawings to metric units
22-Jan-25
19-Feb-25
100%
EK000PM015
Project Coordination Procedure - IFA
22-Jan-25
23-Feb-25
100%
EK000PR020
Heat & Material Balances (SOR & EOR)
22-Jan-25
23-Feb-25
100%
EK000PE085
Participate in Escalation confirmation effort
22-Jan-25
01-Mar-25
100%
EK000IM030
Project Portal & Dashboard
22-Jan-25
06-Mar-25
100%
EK000IC030
Develop & Issue FieldBus Main Instr Vendor ERW
22-Jan-25
08-Mar-25
100%
EK000PR055
Feed & Fuel Summary
22-Jan-25
09-Mar-25
100%
EK000IM020
IM Strategy plan
22-Jan-25
12-Mar-25
100%
EK000IM025
IM Execution plan
22-Jan-25
12-Mar-25
100%
EK000PR010
Process Work Plan
22-Jan-25
23-Mar-25
100%
EK000AR020
Gather Bldg Requirements & Coordinate w/ Constr
22-Jan-25
12-Apr-25
100%
EK000IM010
Object Engineering set-up & procedures
22-Jan-25
13-Apr-25
100%
EK000CV005
Identify scope / Project set-up
23-Jan-25
23-Feb-25
100%
EK000PE125
Preliminary Issue - Equipment List
29-Jan-25
12-Feb-25
100%
EK000CV020
Review FMCL documents - Specs & Drawings
29-Jan-25
16-Feb-25
100%
EK000IM040
Establish Citrix for Test of PDS (HOC-MEC)
29-Jan-25
23-Feb-25
100%
EK000PI080
Develop Split of work
29-Jan-25
23-Feb-25
100%
EK000IM005
Equipment List (MEL) Definition
29-Jan-25
30-Mar-25
100%
EK000PE050
Confirm of Split of Work for MEC
02-Feb-25
23-Feb-25
100%
EK000IC35A
DCS - Engr ERW Issued
04-Feb-25
12-Feb-25
100%
EK000IM035
Establish Documentum
05-Feb-25
16-Feb-25
100%
EK000PE010
Publish Unit conversion standard
05-Feb-25
16-Feb-25
100%
EK000PE040
Devlop & Issue List of Project Specs & Standards
05-Feb-25
16-Feb-25
100%
EK000CV025
Review SEGAS Wind & Earthquake Specs
05-Feb-25
19-Feb-25
100%
EK000PI120
Identify priority pipe classes
05-Feb-25
20-Feb-25
100%
EK000PS015
Issue 90 Day look ahead schedule
05-Feb-25
21-Feb-25
100%
EK000MJ005
Prepare Machinery Specs (Motors, Pkg Equipment)
05-Feb-25
25-Feb-25
100%
EK000IC015
Modify Package Equipment Spec for IEC basis
05-Feb-25
05-Mar-25
100%
EK000PE110
Issue Draft Project Design Data
05-Feb-25
06-Mar-25
100%
EK000MC010
Develop & Issue Exchanger Work Plan
05-Feb-25
09-Mar-25
100%
EK000PI115
Develop Piping Class Index (IOPMC)
05-Feb-25
13-Mar-25
100%
EK000SY015
Develop Utility & offsite block flow diagrams
05-Feb-25
16-Mar-25
100%
EK000PI132
Develop Early Tech P-Class specs for Procurement
05-Feb-25
22-Mar-25
100%
EK000SY065
Complete Utility Flow Diagrams
05-Feb-25
03-Apr-25
100%
EK000CV010
HOC / MEC split of Work
07-Feb-25
16-Feb-25
100%
EK000CV030
Prepare EBIC Wind & EarthquakeSpecs
07-Feb-25
26-Feb-25
100%
EK000QM010
Training - Export Compliance
08-Feb-25
08-Feb-25
100%
EK000ELZE0
Area Classification
11-Feb-25
30-Dec-25
100%
EK000MD31C
Prepare & Issue Prelim. RFQ - MD301 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD32C
Prepare & Issue Prelim. RFQ - MD302 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD34C
Prepare & Issue Prelim. RFQ - MD304 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD51C
Prepare & Issue Prelim. RFQ - MD501 to Proc.
12-Feb-25
16-Feb-25
100%
EK000CV040
Prepare Topo Survey S/C Pkg
12-Feb-25
23-Feb-25
100%
EK000PE090
Develop & Issue Engineering Plan
12-Feb-25
02-Mar-25
100%
EK000EL005
Electrical Work Plans
12-Feb-25
09-Mar-25
100%
EK000PI040
Prepare technology work plan - Piping Engr.
12-Feb-25
09-Mar-25
100%
EK000PI060
Prepare Other Project Documentation
12-Feb-25
09-Mar-25
100%
EK000PI051
Prepare P/Mech Support Details
12-Feb-25
15-Mar-25
100%
EK000CV015
Civil work Plan & Safety check list
12-Feb-25
16-Mar-25
100%
EK000CV050
Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis
12-Feb-25
16-Mar-25
100%
EK000MB005
Develop & Issue Furnance Job Plan
12-Feb-25
16-Mar-25
100%
EK000MJ31C
Prepare & Issue Prelim. RFQ - MJ301 to Proc.
13-Feb-25
13-Feb-25
100%
EK000MJ32C
Prepare & Issue Prelim. RFQ - MJ302 to Proc.
13-Feb-25
13-Feb-25
100%
EK000MB33A
101-B Develop & Issue Load Sheet
14-Feb-25
16-Feb-25
100%
EK000MD33A
Develop & Issue Load Sheets for ERW - MD303
14-Feb-25
16-Feb-25
100%
EK000MJ22A
Develop & Issue Load Sheets for ERW - MJ201
14-Feb-25
16-Feb-25
100%
EK000MJ21A
Develop & Issue Load Sheets for ERW - MJ202
14-Feb-25
21-Feb-25
100%
EK000PI110
Locate FMCL Documents
14-Feb-25
23-Feb-25
100%
EK000PR060
Process Load Sheets
14-Feb-25
22-Mar-25
100%
EK000PC005
Prepare Estimate for Escalation Check
15-Feb-25
23-Feb-25
100%
EK000PE015
MSD (From Metallurgy) - ISBL
15-Feb-25
27-Feb-25
100%
EK000MC31C
Prepare & Issue Prelim. RFQ - MC310 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MC61C
Prepare & Issue Prelim. RFQ - MC610 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MBP1C
101-B Prepare & Issue Prelim. Shop Fab to Proc.
16-Feb-25
20-Feb-25
100%
EK000QM015
Develop & Issue Quality Plan
16-Feb-25
16-Mar-25
100%
EK000MC32C
Issue Prelim. RFQ - MC311
19-Feb-25
19-Feb-25
100%
EK000MJ22C
Prepare & Issue Prelim. RFQ - MJ201 to Proc.
19-Feb-25
19-Feb-25
100%
EK020MC31A
MC312 - (120,121-C) - Issue Prelim. RFQ
19-Feb-25
19-Feb-25
100%
EK000MD21A
Develop & Issue Load Sheets for ERW - MD201
19-Feb-25
20-Feb-25
100%
EK000MD41C
Prepare & Issue Prelim. RFQ - MD401 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD43C
Prepare & Issue Prelim. RFQ - MD403 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD43A
Develop & Issue Load Sheets for ERW - MD403
19-Feb-25
21-Feb-25
100%
EK000MJ31A
Develop & Issue Load Sheets for ERW - MJ301
19-Feb-25
21-Feb-25
100%
EK000MD33C
Prepare & Issue Prelim. RFQ - MD303 to Proc.
19-Feb-25
22-Feb-25
100%
EK000EL020
Define bulk material requirements
19-Feb-25
23-Feb-25
100%
EK000MJ22B
Develop & Issue Design Data for ERW - MJ201
19-Feb-25
23-Feb-25
100%
EK000ML31C
Prepare & Issue Prelim. RFQ - ML313 to Proc.
19-Feb-25
23-Feb-25
100%
EK000PR115
Issue Prelim Load Sht for Air Cooling Study
19-Feb-25
23-Feb-25
100%
EK000MC210
Cooling Water Balance Review
19-Feb-25
26-Feb-25
100%
EK000IM045
Establish IPMS
19-Feb-25
01-Mar-25
100%
EK000IC005
Develop Typical SIL Values Worksheet
19-Feb-25
02-Mar-25
100%
EK000MJ35C
Prepare & Issue Prelim. RFQ - MJ305 to Proc.
19-Feb-25
02-Mar-25
100%
EK000MJ36C
Prepare & Issue Prelim. RFQ - MJ306 to Proc.
19-Feb-25
02-Mar-25
100%
EK000PK030
Provide Job Specific SDR2 Priorities to Purch.
19-Feb-25
02-Mar-25
100%
EK000PI160
P&ID Area Break Mark-up
19-Feb-25
08-Mar-25
100%
EK000MJ39C
Prepare & Issue Prelim. RFQ - MJ391 to Proc.
19-Feb-25
09-Mar-25
100%
EK000PR076
Identify Risk of Equipment Changes
19-Feb-25
09-Mar-25
100%
EK000PE035
Rvw Lesson Learn w/Prj. Team&Develop Action List
19-Feb-25
16-Mar-25
100%
EK000EV005
Conceptual Design of Wastewater Systems
19-Feb-25
23-Mar-25
100%
EK000PR145
Eng. Studies - Ammonia Product Line U/G vs. A/G
19-Feb-25
29-Mar-25
100%
EK000MB010
101-B Furnance Analytical - Convection Design
19-Feb-25
30-Mar-25
100%
EK000CV070
Validate Concrete & Steel by Planning Areas
19-Feb-25
15-Apr-25
100%
EK000MD33P
Develop Analytical Sketches for ERW - MD303
19-Feb-25
04-May-25
100%
EK000PM055
Complete EPC Insurance Forms
19-Feb-25
04-May-25
100%
EK000PI020
Develop Piping Specs (Paper)
19-Feb-25
28-May-25
100%
EK000MJ21C
Prepare & Issue Prelim. RFQ - MJ202 to Proc.
20-Feb-25
20-Feb-25
100%
EK000ML50C
Prepare & Issue Prelim. RFQ - ML500 to Proc.
20-Feb-25
26-Feb-25
100%
EK000MD44A
Develop & Issue Load Sheets for ERW - MD404
20-Feb-25
20-Mar-25
100%
EK000MB61C
Prepare & Issue Prelim. RFQ - MB610 to Proc.
21-Feb-25
23-Feb-25
100%
EK000MB62C
Prepare & Issue Prelim. RFQ - MB621 to Proc.
21-Feb-25
23-Feb-25
100%
EK000MD34A
Develop & Issue Load Sheets for ERW - MD304
21-Feb-25
26-Feb-25
100%
EK000MJ21B
Develop & Issue Design Data for ERW - MJ202
22-Feb-25
07-Mar-25
100%
EK000MD21P
Develop Prelim Analytical Sktch for ERW - MD201
22-Feb-25
22-Mar-25
100%
EK000MD21Q
Develop Final Analytical Sktch for ERW - MD201
22-Feb-25
26-Apr-25
100%
EK000YA804
(EP-05) Issue Heat and Material Balance for Process Release
22-Feb-25
22-Feb-25
100%
EK000YA805
(EP-06) Issue Equipment List for review
22-Feb-25
22-Feb-25
100%
EK000YA807
(EP-08) Issue Utility Balances for Initial Release
22-Feb-25
22-Feb-25
100%
EK000FP025
FP Gas Detection Location Plans - Not Required
22-Feb-25
23-Aug-25
100%
EK000MC32A
Develop & Issue Load Sheets for ERW - MC311
23-Feb-25
28-Feb-25
100%
EK000CK080
Expedite legal issues associated w/ KBRII
23-Feb-25
28-Feb-26
100%
EK000MB060
101-B General Arrangement Drawing
25-Feb-25
08-Mar-25
100%
EK000MF31A
Develop & Issue Load Sheets for ERW - MF301
26-Feb-25
26-Feb-25
100%
EK000MB41C
Prepare & Issue Prelim. RFQ - MB410 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC21C
Prepare & Issue Prelim. RFQ - MC210 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC23C
Prepare & Issue Prelim. RFQ - MC230 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MD31A
Develop & Issue Load Sheets for ERW - MD301
26-Feb-25
27-Feb-25
100%
EK000MD32A
Develop & Issue Load Sheets for ERW - MD302
26-Feb-25
27-Feb-25
100%
EK000MD41A
Develop & Issue Load Sheets for ERW - MD401
26-Feb-25
27-Feb-25
100%
EK000EL015
Split of work with MEC and Other Discipline
26-Feb-25
28-Feb-25
100%
EK000MB63C
Prepare & Issue Prelim. RFQ - MB630 to Proc.
26-Feb-25
28-Feb-25
100%
EK000MBP4C
Prepare & Issue Prelim. RFQ Cast Material
26-Feb-25
28-Feb-25
100%
EK000PE060
Define Task Force Area in MEC
26-Feb-25
28-Feb-25
100%
EK000PE075
MEC Organization Chart
26-Feb-25
28-Feb-25
100%
EK000PM030
Estimate Escalation Check - IRC Approvals
26-Feb-25
01-Mar-25
100%
EK000PR095
Steam Balance - Startup, 103-J, Etc
26-Feb-25
02-Mar-25
100%
EK000MBP3C
Prepare & Issue Prelim. RFQ Pressure Parts
26-Feb-25
05-Mar-25
100%
EK000MD33B
Develop & Issue Design Data for ERW - MD303
26-Feb-25
08-Mar-25
100%
EK000EV025
Develop & Issue Enviromental Work Plan
26-Feb-25
09-Mar-25
100%
EK000IC020
Establlish data warehouse - Intools Basic Setup
26-Feb-25
09-Mar-25
100%
EK000IC025
Review Instr. & Installation Details - ID Change
26-Feb-25
09-Mar-25
100%
EK000MJ22F
Update/Issue Formal Inquiry for ERW - MJ201
26-Feb-25
09-Mar-25
100%
EK000PK010
Issue critical req'n submittal sched to Procmnt
26-Feb-25
09-Mar-25
100%
EK000GE010
Eng. Studies - Air Coolers vs. Cooling Water
26-Feb-25
12-Mar-25
100%
EK000CV060
Civil project highlights
26-Feb-25
16-Mar-25
100%
EK000PI005
Locate Permanent Tie in pnts Gas, Wtr, Storm wtr
26-Feb-25
16-Mar-25
100%
EK000PE065
Develop & Issue HOC - MEC Coordination Plan
26-Feb-25
23-Mar-25
100%
EK000PI133
Dvlp/Issue V-class specs & Standads for Procurmt
26-Feb-25
09-Apr-25
100%
EK000MB085
101-B Radiant Detail Drawings - IFF
26-Feb-25
12-Apr-25
100%
EK000MB090
101-B Convection Detail Drawings - IFF
26-Feb-25
12-Apr-25
100%
EK000CV035
Prepare Geotech S/C Pkgs
26-Feb-25
27-Apr-25
100%
EK000EL025
Develop installation details
26-Feb-25
07-May-25
100%
EK000IC045
Develop & Issue CSE Work Plan
26-Feb-25
08-May-25
100%
EK000PM045
Issue Execution Strategy /Project Execution Plan
26-Feb-25
24-May-25
100%
EK000MC31A
Develop & Issue Load Sheets for ERW - MC310
27-Feb-25
01-Mar-25
100%
EK000ML50B
Develop/Issue Load Sht & Design Data ERW - ML500
27-Feb-25
05-Mar-25
100%
EK000MD42A
Develop & Issue Load Sheets for ERW - MD402
28-Feb-25
01-Mar-25
100%
EK000MD51A
Develop & Issue Load Sheets for ERW - MD501
28-Feb-25
05-Mar-25
100%
EK000MJ35A
Develop & Issue Load Sheets for ERW - MJ305
28-Feb-25
23-Mar-25
100%
EK000YA808
(EP-09) Issue Engineering Plan
01-Mar-25
01-Mar-25
100%
EK000MD060
Prepare Vessel work plan & other quality documents
02-Mar-25
02-Mar-25
100%
EK000MC31B
Develop & Issue Design Data for ERW - MC310
02-Mar-25
13-Mar-25
100%
EK000MC31F
Finalize Equip. Data Sheets for ERW - MC310
02-Mar-25
12-Apr-25
100%
EK000PI125
Validate new plot layout (impacts on pipe stress
02-Mar-25
21-May-25
100%
EK000MJ21D
Technical Evaluation - MJ202
05-Mar-25
05-Mar-25
100%
EK000MJ75A
Develop & Issue Load Sheets for ERW - MJ750
05-Mar-25
05-Mar-25
100%
EK000ML31A
Develop & Issue Load Sheets for ERW - ML313
05-Mar-25
05-Mar-25
100%
EK000MB51C
Prepare & Issue Prelim. RFQ - MB511 to Proc.
05-Mar-25
07-Mar-25
100%
EK000CV075
Egyptian Professional Engineer - Define Reqmnts
05-Mar-25
08-Mar-25
100%
EK000MC21A
Develop & Issue Load Sheets for ERW - MC210
05-Mar-25
08-Mar-25
100%
EK000EL035
Voltage drop table
05-Mar-25
09-Mar-25
100%
EK000ML42C
Prepare & Issue Prelim. RFQ - ML420 to Proc.
05-Mar-25
09-Mar-25
100%
EK000MU33C
Prepare & Issue Prelim. RFQ - MU330 to Proc.
05-Mar-25
09-Mar-25
100%
EK000CS030
Start-up Schedule (Prelim for 1st Planner)
05-Mar-25
14-Mar-25
100%
EK000MC32B
Develop & Issue Design Data for ERW - MC311
05-Mar-25
19-Mar-25
100%
EK000MC23A
Develop & Issue Load Sheets for ERW - MC230
05-Mar-25
22-Mar-25
100%
EK000MC32F
Finalize Equip. Data Sheets for ERW - MC311
05-Mar-25
24-May-25
100%
EK000MD22A
Develop & Issue Load Sheets for ERW - MD202
06-Mar-25
06-Mar-25
100%
EK000MBP1D
101-B Technical Bid Evaluation Shop Fab
06-Mar-25
09-Mar-25
100%
EK000MJ37A
Develop & Issue Load Sheets for ERW - MJ340
06-Mar-25
09-Mar-25
100%
EK000ML31B
Develop & Issue Design Data for ERW - ML313
06-Mar-25
15-Mar-25
100%
EK000MD42P
Confirm Analytical Design for ERW - MD402
06-Mar-25
21-Mar-25
100%
EK000ML50F
Update/Issue Formal Inquiry for ERW - ML500
06-Mar-25
27-Apr-25
100%
EK000PE020
WMS Setup & Development
07-Mar-25
15-Mar-25
100%
EK000CV080
Egyptian Professional Eng. - Issue P.O/Subc. Pkg
08-Mar-25
09-Mar-25
100%
EK000MJ21F
Update/Issue Formal Inquiry for ERW - MJ202
08-Mar-25
13-Mar-25
100%
EK000MC21B
Develop & Issue Design Data for ERW - MC210
08-Mar-25
01-Apr-25
100%
EK000MJ31B
Develop & Issue Design Data for ERW - MJ301
08-Mar-25
12-Apr-25
100%
EK000PI055
Prepare Object Engineering Work Instruction
08-Mar-25
15-Mar-25
100%
EK000PC010
Estimate Turnover to Project Team
09-Mar-25
15-Mar-25
100%
EK000PI085
Estimate/Schedule Review
09-Mar-25
15-Mar-25
100%
EK000MD34R
Develop Final Analytical Sktch for ERW - MD304
09-Mar-25
16-Mar-25
100%
EK000MD43P
Confirm Analytical Design for ERW - MD403
09-Mar-25
16-Mar-25
100%
EK000MC61A
Develop & Issue Load Sheets for ERW - MC610
09-Mar-25
20-Mar-25
100%
EK000PC015
Estimate Recast & Develop Project Control Budget
09-Mar-25
23-Apr-25
100%
EK000PI105
Performance Test of Citrix for PDS w/MEC
12-Mar-25
12-Mar-25
100%
EK000MU41F
Develop & Issue Inquiry for ERW - MU410
12-Mar-25
16-Mar-25
100%
EK000MD34P
Confirm Analytical Design for ERW - MD304
12-Mar-25
20-Mar-25
100%
EK000MU41A
Develop & Issue Load Sheets for ERW - MU410
12-Mar-25
20-Mar-25
100%
EK000MD31P
Confirm Analytical Design for ERW - MD301
12-Mar-25
29-Mar-25
100%
EK000MD32P
Confirm Analytical Design for ERW - MD302
12-Mar-25
02-Apr-25
100%
EK000PI100
Critical Line List
12-Mar-25
06-Apr-25
100%
EK000EV020
Develop Preliminary noise model
12-Mar-25
20-Apr-25
100%
EK000MC21F
Finalize Equip. Data Sheets for ERW - MC210
12-Mar-25
13-Jun-25
100%
EK000MD020
Equipment Modeling for Vessel - MEC
13-Mar-25
25-Mar-26
100%
EK000MB61D
Technical Evaluation - MB610
14-Mar-25
20-Mar-25
100%
EK000PR080
Input to Process Guarantees
14-Mar-25
03-May-25
100%
EK000IC35D
DCS - Tech Evaluation
14-Mar-25
14-May-25
100%
EK000MJ32A
Develop & Issue Load Sheets for ERW - MJ302
15-Mar-25
20-Mar-25
100%
EK000ML31F
Update/Issue Formal Inquiry for ERW - ML313
16-Mar-25
16-Mar-25
100%
EK000MD31B
Develop & Issue Design Data for ERW - MD301
16-Mar-25
19-Mar-25
100%
EK000MD32B
Develop & Issue Design Data for ERW - MD302
16-Mar-25
19-Mar-25
100%
EK000MD34B
Develop & Issue Design Data for ERW - MD304
16-Mar-25
19-Mar-25
100%
EK000MJ22D
Technical Evaluation - MJ201
16-Mar-25
19-Mar-25
100%
EK000MD45A
Develop & Issue Load Sheets for ERW - MD405
16-Mar-25
20-Mar-25
100%
EK000ML43A
Develop & Issue Load Sheets for ERW - ML430
16-Mar-25
20-Mar-25
100%
EK000ML44A
Develop & Issue Load Sheets for ERW - ML440
16-Mar-25
20-Mar-25
100%
EK000PE095
Disciplines Load WMS with Budgets & Deliverables
16-Mar-25
20-Apr-25
100%
EK000MD34D
Technical Evaluation - MD304
16-Mar-25
23-Apr-25
100%
EK000MD41D
Technical Evaluation - MD401
16-Mar-25
23-Apr-25
100%
EK000ML42A
Develop & Issue Load Sheets for ERW - ML420
19-Mar-25
20-Mar-25
100%
EK000MU35A
Develop & Issue Load Sheets for ERW - MU350
19-Mar-25
20-Mar-25
100%
EK000MU41B
Develop & Issue Design Data for ERW - MU410
19-Mar-25
21-Mar-25
100%
EK000MU30F
Develop & Issue Inquiry for ERW - MU300
19-Mar-25
26-Mar-25
100%
EK000MF33B
Develop/Issue Load Sht & Design Data ERW - MF311
19-Mar-25
26-Mar-25
100%
EK000MF32B
Develop/Issue Load Sht & Design Data ERW - MF302
19-Mar-25
06-Apr-25
100%
EK000MD21B
Develop & Issue Design Data for ERW - MD201
19-Mar-25
08-May-25
100%
EK000ML42F
Update/Issue Formal Inquiry for ERW - ML420
19-Mar-25
24-Apr-25
100%
EK000MC63A
Develop & Issue Load Sheets for ERW - MC630
20-Mar-25
22-Mar-25
100%
EK000MU61F
Develop & Issue Inquiry for ERW - MU611
20-Mar-25
25-Mar-25
100%
EK000I210D
000 Control Valves - Technical Evaluation
20-Mar-25
23-May-25
100%
EK000MU35F
Update/Issue Formal Inquiry for ERW - MU350
21-Mar-25
22-Mar-25
100%
EK000MD47A
Develop & Issue Load Sheets for ERW - MD406
21-Mar-25
23-Mar-25
100%
EK000MD51B
Develop & Issue Design Data for ERW - MD501
21-Mar-25
28-Mar-25
100%
EK000MC61D
Technical Evaluation - MC610
21-Mar-25
01-Apr-25
100%
EK000MC61F
Finalize Equip. Data Sheets for ERW - MC610
21-Mar-25
10-Apr-25
100%
EK000MJ32B
Develop & Issue Design Data for ERW - MJ302
21-Mar-25
13-Apr-25
100%
EK000MD34F
Update/Issue Formal Inquiry for ERW - MD304
21-Mar-25
20-Apr-25
100%
EK000EV010
Develop design basis for evaporation pond
22-Mar-25
11-May-25
100%
EK000YA802
(EP-03) Issue Process Plan
22-Mar-25
22-Mar-25
100%
EK000MB51F
Prepare & Issue Purchase ERW - MB511
23-Mar-25
17-Apr-25
100%
EK000MJ39B
Develop/Issue Load Sht & Design Data ERW - MJ391
25-Mar-25
29-Mar-25
100%
EK000ML50D
Technical Evaluation - ML500
25-Mar-25
27-Apr-25
100%
EK000MD025
Prepare job quality drawings for ERW
25-Mar-25
28-May-25
100%
EK000ML44B
Develop & Issue Design Data for ERW - ML440
26-Mar-25
27-Mar-25
100%
EK000MF31P
Confirm Analytical Design for ERW - MF301
26-Mar-25
29-Mar-25
100%
EK000PR070
Effluent Summary
26-Mar-25
30-Mar-25
100%
EK000MD51D
Technical Evaluation - MD501
26-Mar-25
03-Apr-25
100%
EK000MU33F
Update/Issue Formal Inquiry for ERW - MU330
26-Mar-25
04-Apr-25
100%
EK000MD33F
Update/Issue Formal Inquiry for ERW - MD303
26-Mar-25
11-May-25
100%
EK000MF32F
Develop & Issue Design Data for Tank Subcontract - MF302
26-Mar-25
08-Apr-25
100%
EK000I131D
Technical Evaluation - Transmitters
26-Mar-25
23-May-25
100%
EK000MJ35D
Technical Evaluation - MJ305
27-Mar-25
02-Apr-25
100%
EK000MJ36D
Technical Evaluation - MJ306
27-Mar-25
02-Apr-25
100%
EK000MF33F
Develop & Issue Design Data for Tank Subcontract - MF311
27-Mar-25
09-Apr-25
100%
EK000CVK35
OSBL Rough Grading/Road
27-Mar-25
23-May-25
100%
EK000MD51F
Update/Issue Formal Inquiry for ERW - MD501
29-Mar-25
08-Apr-25
100%
EK000MD45P
Confirm Analytical Design for ERW - MD405
29-Mar-25
25-Apr-25
100%
EK000MB62D
Technical Evaluation - MB621
30-Mar-25
18-Apr-25
100%
EK000MB63D
Technical Evaluation - MB630
30-Mar-25
24-Jun-25
100%
EK000MF31B
Develop & Issue Design Data for Tank Subcontrac - MF301
01-Apr-25
08-Apr-25
100%
EK000MJ34B
Develop/Issue Load Sht & Design Data ERW - MJ304
01-Apr-25
08-Apr-25
100%
EK000PR065
Catalyst and Chemical Specs
01-Apr-25
09-Apr-25
100%
EK000MB070
101-B Foundation Loads
01-Apr-25
19-Apr-25
100%
EK000PR075
Process Description
01-Apr-25
25-Apr-25
100%
EK000MJ39F
Update/Issue Formal Inquiry for ERW - MJ391
01-Apr-25
27-Apr-25
100%
EK000QM020
Develop/ Issue/ Approval of QA/QC Manual (EBIC/EXIM Verification)
01-Apr-25
31-Oct-25
100%
EK000MD44P
Confirm Analytical Design for ERW - MD404
02-Apr-25
03-Apr-25
100%
EK000MD31F
Update/Issue Formal Inquiry for ERW - MD301
02-Apr-25
16-Apr-25
100%
EK000MU61B
Develop/Issue Load Sht & Design Data ERW - MU611
02-Apr-25
14-May-25
100%
EK000MB51D
Technical Evaluation - MB511
02-Apr-25
16-Apr-25
100%
EK000MD32F
Update/Issue Formal Inquiry for ERW - MD302
02-Apr-25
20-Apr-25
100%
EK000MD43D
Technical Evaluation - MD403
02-Apr-25
25-Apr-25
100%
EK000MC61B
Develop & Issue Design Data for ERW - MC610
04-Apr-25
20-Apr-25
100%
EK000MJ35B
Develop & Issue Design Data for ERW - MJ305
05-Apr-25
09-May-25
100%
EK000MB080
101-B Convection Coil Design
05-Apr-25
12-Apr-25
100%
EK000ML31D
Technical Evaluation - ML313
05-Apr-25
19-Apr-25
100%
EK000MB050
101-B Radiant coil design
06-Apr-25
12-Apr-25
100%
EK000MD22P
Confirm Analytical Design for ERW - MD202
06-Apr-25
15-Apr-25
100%
EK000MB33F
MB333 - Develop & Issue Purchase ERW 101-B
06-Apr-25
23-Apr-25
100%
EK000MBP4D
Technical Evaluation - 101-B Cast Material
06-Apr-25
01-May-25
100%
EK000PI131
Devlop Balance Tech P-Class specs for Procuremnt
06-Apr-25
25-May-25
100%
EK000FP050
FP Overall Firewater P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK000MD43B
Develop & Issue Design Data for ERW - MD403
08-Apr-25
12-Apr-25
100%
EK000MU35D
Technical Evaluation - MU350
08-Apr-25
19-Apr-25
100%
EK000MC21D
Technical Evaluation - MC210
08-Apr-25
23-Apr-25
100%
EK000MC23D
Technical Evaluation - MC230
08-Apr-25
23-Apr-25
100%
EK000MD45B
Develop & Issue Design Data for ERW - MD405
08-Apr-25
08-May-25
100%
EK000MC23B
Develop & Issue Design Data for ERW - MC230
09-Apr-25
13-Apr-25
100%
EK000MD42B
Develop & Issue Design Data for ERW - MD402
09-Apr-25
13-Apr-25
100%
EK000MD41B
Develop & Issue Design Data for ERW - MD401
09-Apr-25
18-Apr-25
100%
EK000MU30B
Develop/Issue Load Sht & Design Data ERW - MU300
09-Apr-25
25-Apr-25
100%
EK000PS010
Level III CPM Schedule / First Planner
09-Apr-25
24-May-25
100%
EK000ML42D
Technical Evaluation - ML420
09-Apr-25
19-Apr-25
100%
EK000MJ34F
Update/Issue Formal Inquiry for ERW - MJ304
09-Apr-25
26-Apr-25
100%
EK000MB41D
Technical Evaluation - MB410
10-Apr-25
01-May-25
100%
EK000MJ33B
Develop/Issue Load Sht & Design Data ERW - MJ303
11-Apr-25
23-May-25
100%
EK000MJ32D
Technical Evaluation - MJ302
12-Apr-25
19-Apr-25
100%
EK000MJ31D
Technical Evaluation - MJ301
12-Apr-25
25-Apr-25
100%
EK000MB055
101-B Radiant coil BOM
15-Apr-25
19-Apr-25
100%
EK000MB075
101-B Convection Coil BOM
15-Apr-25
19-Apr-25
100%
EK000ML51B
Develop/Issue Load Sht & Design Data ERW - ML512
15-Apr-25
19-Apr-25
100%
EK000MC63B
Develop & Issue Design Data for ERW - MC630
15-Apr-25
20-Apr-25
100%
EK000MB61E
Prepare & Issue Purchase ERW - MB610
15-Apr-25
22-Apr-25
100%
EK000MD43F
Update/Issue Formal Inquiry for ERW - MD403
15-Apr-25
25-Apr-25
100%
EK000MD32D
Technical Evaluation - MD302
15-Apr-25
04-May-25
100%
EK000IC36D
DCS (MIV) - Tech Evaluation
15-Apr-25
17-May-25
100%
EK000MC31P
Develop & Issue Setting Plans for ERW - MC310
15-Apr-25
28-May-25
100%
EK000MC21P
Develop & Issue Setting Plans for ERW - MC210
15-Apr-25
20-Jun-25
100%
EK000CS025
Turnover System Definition for ISBL
15-Apr-25
31-Jan-26
100%
EK000MD42F
Update/Issue Formal Inquiry for ERW - MD402
16-Apr-25
19-Apr-25
100%
EK000ML42B
Develop & Issue Design Data for ERW - ML420
16-Apr-25
20-Apr-25
100%
EK000MD31D
Technical Evaluation - MD301
16-Apr-25
25-Apr-25
100%
EK000ML33B
Develop/Issue Load Sht & Design Data ERW - ML330
16-Apr-25
25-Apr-25
100%
EK000MD33D
Technical Evaluation - MD303
16-Apr-25
04-May-25
100%
EK000MBP3D
Technical Evaluation - 101-B Pressure Parts
16-Apr-25
10-May-25
100%
EK000MD21F
Develop & Issue Inquiry ERW - MD201
17-Apr-25
17-Jun-25
100%
EK000PR140
Formal Issue of Process Release
18-Apr-25
08-May-25
100%
EK000MD47P
Confirm Analytical Design for ERW - MD406
18-Apr-25
22-Apr-25
100%
EK000MJ37B
Develop & Issue Design Data for ERW - MJ340
19-Apr-25
09-May-25
100%
EK000MD41F
Update/Issue Formal Inquiry for ERW - MD401
20-Apr-25
26-Apr-25
100%
EK000MD44Q
Develop Analytical Sketches for ERW - MD404
20-Apr-25
27-Apr-25
100%
EK000MJ73B
Develop/Issue Load Sht & Design Data ERW - MJ730
20-Apr-25
30-Apr-25
100%
EK000EV015
Issue load sheets for wastewater systems
20-Apr-25
31-May-25
100%
EK000MD44B
Develop & Issue Design Data for ERW - MD404
22-Apr-25
25-Apr-25
100%
EK000MD47B
Develop & Issue Design Data for ERW - MD406
22-Apr-25
25-Apr-25
100%
EK000MD46B
Develop/Issue Load Sht & Design Data ERW - MD411
22-Apr-25
03-May-25
100%
EK000MU11B
05B MU311 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU25B
02G MU225 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU32B
01D MU322 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MD22B
Develop & Issue Design Data for ERW - MD202
23-Apr-25
01-May-25
100%
EK000MU31B
Develop/Issue Load Sht & Design Data ERW - MU310
23-Apr-25
16-May-25
100%
EK000MC23F
Finalize Equip. Data Sheets for ERW - MC230
23-Apr-25
13-Jun-25
100%
EK000CV036
Issue Geotech S/C PKG
26-Apr-25
02-May-25
100%
EK000CV140
Issue Site Survey S/C PKG
26-Apr-25
14-May-25
100%
EK000CV145
Issue Site Leveling PKG
26-Apr-25
16-May-25
100%
EK000MD44F
Update/Issue Formal Inquiry for ERW - MD404
27-Apr-25
01-May-25
100%
EK000ML51F
Develop & Issue Inquiry for ERW - ML512
27-Apr-25
01-May-25
100%
EK000MJ31F
Update/Issue Formal Inquiry for ERW - MJ301
27-Apr-25
08-May-25
100%
EK000MBP1E
Prepare & Issue Purchase ERW 101-B Shop Fab
27-Apr-25
10-May-25
100%
EK000ML33F
Develop & Issue Inquiry for ERW - ML330
27-Apr-25
13-May-25
100%
EK000MJ32F
Update/Issue Formal Inquiry for ERW - MJ302
27-Apr-25
29-May-25
100%
EK000MB63F
Prepare & Issue Purchase ERW - MB630
27-Apr-25
29-May-25
100%
EK000MJ36B
Develop/Issue Load Sht & Design Data ERW - MJ306
27-Apr-25
08-Jun-25
100%
EK000MU35B
Develop & Issue Design Data for ERW - MU350
01-May-25
14-May-25
100%
EK000IC010
Make decision of FF vs. Traditional DCS system
01-May-25
17-May-25
100%
EK000MJ75B
Develop & Issue Design Data for ERW - MJ750
01-May-25
20-May-25
100%
EK000CV136
Issue Rough Grade (Ammonia) S/C PKG
01-May-25
27-May-25
100%
EK000MJ73F
Develop & Issue Inquiry for ERW - MJ730
01-May-25
12-Jun-25
100%
EK000MD22F
Update/Issue Formal Inquiry for ERW - MD202
01-May-25
17-May-25
100%
EK000MC23P
Develop & Issue Setting Plans for ERW - MC230
01-May-25
21-Jun-25
100%
EK000MU11O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU25O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU310
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU32O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MD46P
Confirm Analytical Design for ERW - MD411
02-May-25
11-May-25
100%
EK000MJ34D
Technical Evaluation - MJ304
02-May-25
03-May-25
100%
EK000MC32P
Develop & Issue Setting Plans for ERW - MC311
02-May-25
20-Jun-25
100%
EK000MU41D
Technical Evaluation - MU410
03-May-25
28-Jun-25
100%
EK000MD31E
Prepare & Issue Purchase ERW - MD301
04-May-25
11-May-25
100%
EK000MD34E
Prepare & Issue Purchase ERW - MD304
04-May-25
11-May-25
100%
EK000MBP4E
Prepare & Issue Purchase ERW 101-B Cast Material
04-May-25
17-May-25
100%
EK000PC020
Load PCMS & Issue First Cost Report
04-May-25
18-May-25
100%
EK000MB41E
Prepare & Issue Purchase ERW - MB410
04-May-25
20-May-25
100%
EK000MD32E
Prepare & Issue Purchase ERW - MD302
06-May-25
10-May-25
100%
EK000MD43E
Prepare & Issue Purchase ERW - MD403
06-May-25
11-May-25
100%
EK000MU33B
Develop/Issue Load Sht & Design Data ERW - MU330
07-May-25
20-May-25
100%
EK000MC31D
Technical Evaluation - MC310
07-May-25
24-May-25
100%
EK000MC32D
Technical Evaluation - MC311
07-May-25
24-May-25
100%
EK020MC31D
MC312 - (120,121-C) - Technical Evaluation
07-May-25
24-May-25
100%
EK000MU61D
Technical Evaluation - MU611
07-May-25
20-Jun-25
100%
PK000PIA1C
Bulk Piping A/G & U/G - Tech Evaluation
07-May-25
21-Jun-25
100%
EK000MU21B
Develop/Issue Load Sht & Design Data ERW - MU221
08-May-25
10-May-25
100%
EK000MU22B
Develop/Issue Load Sht & Design Data ERW - MU222
08-May-25
20-May-25
100%
EK000MU29B
Develop/Issue Load Sht & Design Data ERW - MU292
08-May-25
20-May-25
100%
EK000YA005
Process Release
08-May-25
08-May-25
100%
EK000YA811
(EP-12) Issue Process Release
08-May-25
08-May-25
100%
EK000MD51E
Prepare & Issue Purchase ERW - MD501
09-May-25
11-May-25
100%
EK000MJ37F
Develop & Issue Inquiry for ERW - MJ340
09-May-25
05-Jun-25
100%
EK000MJ35F
Update/Issue Formal Inquiry for ERW - MJ305
10-May-25
24-May-25
100%
EK000MBP3E
Prepare & Issue Purchase ERW 101-B Pressure Part
13-May-25
16-May-25
100%
EK000I220A
Issue Preliminary ERW Pkg - MOV Valves
13-May-25
31-May-25
100%
EK000MD45F
Update/Issue Formal Inquiry for ERW - MD405
13-May-25
31-May-25
100%
EK000I354A
ITCC - Engr ERW Issued
13-May-25
23-Jul-25
100%
EK000MU30D
Technical Evaluation - MU300
13-May-25
27-Sep-25
100%
EK000MD46F
Update/Issue Formal Inquiry for ERW - MD411
14-May-25
31-May-25
100%
EK000MB62F
Prepare & Issue Purchase ERW - MB621
14-May-25
05-Jun-25
100%
EK000MB045
Catalyst Vac data sheets
20-May-25
28-May-25
100%
EK000CV065
Review Perimeter Wall Design - IFC (by OCI)
20-May-25
14-Jun-25
100%
EK000MJ75F
Develop & Issue Inquiry for ERW - MJ750
21-May-25
28-May-25
100%
EK000YA806
(EP-07) Issue Project Plan
24-May-25
24-May-25
100%
EK000MBG10
General & Administrative
28-May-25
27-Dec-26
57%
EK000I110D
Technical Evaluation - Orific Plates
28-May-25
10-Jun-25
100%
EK000I115D
Technical Evaluation - Annubars
28-May-25
10-Jun-25
100%
EK000I116D
Technical Evaluation - Wedge Flow Meters
28-May-25
10-Jun-25
100%
EK000I121D
Technical Evaluation - Vortex Meters
28-May-25
10-Jun-25
100%
EK000I122D
Technical Evaluation - Coriolis Meters
28-May-25
10-Jun-25
100%
EK000I124D
Technical Evaluation - Rotameters
28-May-25
10-Jun-25
100%
EK000I611D
Technical Evaluation - Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I612D
Technical Evaluation - Differential Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I616D
Technical Evaluation - Steam Drum Lvl Gauges
28-May-25
10-Jun-25
100%
EK000I617D
Technical Evaluation - Magnetic Lvl Gauges
28-May-25
10-Jun-25
100%
EK000MJ33F
Develop & Issue Inquiry for ERW - MJ303
28-May-25
18-Jun-25
100%
EK000MJ36F
Update/Issue Formal Inquiry for ERW - MJ306
28-May-25
19-Jun-25
100%
EK000I127D
Magnetic Flow Meters - Technical Evaluation
28-May-25
26-Jun-25
100%
EK000MB33D
MB333 - Technical Evaluation 101-B
28-May-25
01-Jul-25
100%
EK000YA801
(EP-02) Issue 30 day Look Ahead Schedule
28-May-25
28-May-25
100%
EK000MJ75D
Technical Evaluation - MJ750
29-May-25
30-May-25
100%
EK000ML43F
Develop & Issue Inquiry for ERW - ML430
31-May-25
06-Jun-25
100%
EK000MB69F
Prepare & IssuePurchase ERW - MB691
03-Jun-25
17-Jun-25
100%
EK000MU33D
Technical Evaluation - MU330
04-Jun-25
01-Jul-25
100%
EK000QM025
Training - Management System
05-Jun-25
05-Jun-25
100%
EK000I230A
Issue Preliminary ERW Pkg - On/Off Valves
05-Jun-25
15-Jun-25
100%
EK000PS040
Incorporate Comments / Issue Baseline Schedule
05-Jun-25
15-Jun-25
100%
EK000MU22F
Develop & Issue Inquiry for ERW - MU222
05-Jun-25
26-Jun-25
100%
EK000MB65F
Develop & Issue Purchase ERW - MB622
06-Jun-25
17-Jun-25
100%
PK000PIA4C
Product Line Piping - Tech Evaluation
07-Jun-25
04-Jul-25
100%
EK000I112D
Technical Evaluation - Venturis
10-Jun-25
14-Jun-25
100%
EK000PS030
Schedule Risk Analysis
10-Jun-25
20-Jun-25
100%
EK000MB66F
Prepare & IssuePurchase ERW - MB660
10-Jun-25
21-Jun-25
100%
EK000MU34B
Develop/Issue Load Sht & Design Data ERW - Chlorination Unit
11-Jun-25
15-Jun-25
100%
EK000MB68F
Prepare & Issue Purchase ERW - MB692
13-Jun-25
26-Jun-25
100%
EK000MB21F
Prepare & Issue Purchase ERW - MB212
17-Jun-25
25-Jun-25
100%
EK000MB42F
Prepare & Issue Purchase ERW - MB420
17-Jun-25
26-Jun-25
100%
EK000FP055
FP Overall Firewater P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK000MB34F
Prepare & Issue Purchase ERW - MB340
20-Jun-25
21-Jun-25
100%
EK000I221D
000 Everest Control Valves - Technical Evaluation
25-Jun-25
10-Jul-25
100%
EK000YA809
(EP-10) Locate Utility Tie-Ins
26-Jun-25
26-Jun-25
100%
EK000MU21F
Develop & Issue Inquiry for ERW - MU221
26-Jun-25
03-Jul-25
100%
EK000MD33E
Prepare & Issue Purchase ERW - MD303
01-Jul-25
04-Jul-25
100%
EK000MD41E
Prepare & Issue Purchase ERW - MD401
01-Jul-25
04-Jul-25
100%
EK000MB64F
Prepare & Issue Purchase ERW - MB640
02-Jul-25
11-Jul-25
100%
EK000ML33D
Technical Evaluation - ML330
10-Jul-25
23-Aug-25
100%
EK000ML43D
Technical Evaluation - ML430
10-Jul-25
06-Sep-25
100%
EK000I220D
Technical Evaluation - MOV's
16-Jul-25
23-Jul-25
100%
EK000MD21D
Technical Evaluation - MD201
16-Jul-25
10-Aug-25
100%
EK000I230D
Technical Evaluation - On/Off Valves
17-Jul-25
24-Jul-25
100%
EK000MB65D
Technical Evaluation - MB622
19-Jul-25
02-Aug-25
100%
EK000I618D
Technical Evaluation - Temperature Gauges
22-Jul-25
26-Jul-25
100%
EK000I621D
Technical Evaluation - Temperature Elements
22-Jul-25
26-Jul-25
100%
EK000I623D
Technical Evaluation - Multi-Point Thermocouples
22-Jul-25
26-Jul-25
100%
EK000I352A
SIS - Engr ERW Issued
22-Jul-25
02-Aug-25
100%
EK000MB69D
Technical Evaluation - MB691
22-Jul-25
07-Aug-25
100%
EK000MU22D
Technical Evaluation - MU222
22-Jul-25
06-Sep-25
100%
EK000MJ37D
Technical Evaluation - MJ340
24-Jul-25
28-Aug-25
100%
EK000MJ39D
Technical Evaluation - MJ391
25-Jul-25
21-Dec-25
100%
EK000MJ31X
Technical Evaluation - MJ301
25-Jul-25
10-Aug-25
100%
PK000MJ32X
Technical Evaluation - MJ302
25-Jul-25
10-Aug-25
100%
EK000MU11L
05B MU311 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MU25L
02G MU225 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MU32L
01D MU322 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MB68D
Technical Evaluation - MB692
29-Jul-25
30-Aug-25
100%
EK000MU31L
Define Chemical Treatment Requirements - MU310
30-Jul-25
10-Aug-25
100%
EK000MB66D
Technical Evaluation - MB660
30-Jul-25
13-Aug-25
100%
EK000MB34D
Technical Evaluation - MB340
30-Jul-25
13-Aug-25
100%
EK000ML51D
Technical Evaluation - ML512
30-Jul-25
19-Aug-25
100%
EK000MU21D
Technical Evaluation - MU221
30-Jul-25
14-Sep-25
100%
EK000MU35E
Prepare & Issue Purchase ERW - MU350
01-Aug-25
13-Aug-25
100%
EK000YA810
(EP-11) Issue Level 3 CPM Schedule
03-Aug-25
03-Aug-25
100%
EK000QM005
Training - Object Engineering
06-Aug-25
13-Aug-25
100%
EK000I444A
Develop & Issue Inquiry ERW - Analyzer Shelter
06-Aug-25
17-Aug-25
100%
EK000MJ73D
Technical Evaluation - MJ730
06-Aug-25
16-Sep-25
100%
EK000CV165
Issue ISBL Rough Grade Design Pkg.
09-Aug-25
04-Oct-25
100%
PK000MJ21N
Recv. Planning V. Data MJ202
09-Aug-25
30-Aug-25
100%
PK000MJ75N
Recv. Planning V. Data MJ750
09-Aug-25
30-Aug-25
100%
PK000MD31N
Recv. Planning V. Data MD301
09-Aug-25
09-Sep-25
100%
PK000ML31N
Recv. Planning V. Data ML313
09-Aug-25
12-Sep-25
100%
PK000MD41N
Recv. Planning V. Data MD401
09-Aug-25
17-Sep-25
100%
PK000MD33N
Recv. Planning V. Data MD303
09-Aug-25
25-Sep-25
100%
PK000MD43N
Recv. Planning V. Data MD403
09-Aug-25
14-Oct-25
100%
EK000MB64D
Technical Evaluation - MB640
09-Aug-25
17-Oct-25
100%
EK000EB015
Notice to Proceed (Eng. & Procurement Only)
10-Aug-25
10-Aug-25
100%
EK000I221A
000 Everest Control Valves - Issue Inquiry Req
12-Aug-25
16-Aug-25
100%
EK000MJ21E
Prepare & Issue Purchase ERW - MJ202
12-Aug-25
30-Aug-25
100%
PK000MU35N
Recv. Planning V. Data MU350
12-Aug-25
27-Sep-25
100%
EK000IC350
DCS - Develop Design Basis
12-Aug-25
04-Oct-25
100%
EK000MU61E
Prepare & Issue Purchase ERW - MU611
13-Aug-25
16-Aug-25
100%
PK000PTA0F
Engineered Pipe Supports - Planning V. Data
14-Aug-25
24-Jan-26
100%
PK000MD32N
Recv. Planning V. Data MD302
16-Aug-25
02-Oct-25
100%
PK000MD34N
Recv. Planning V. Data MD304
16-Aug-25
12-Nov-25
100%
EK000MJ75E
Prepare & Issue Purchase ERW - MJ750
19-Aug-25
28-Sep-25
100%
EK000PE070
Kick-off meeting at MEC
22-Aug-25
23-Aug-25
100%
PK000MJ35N
Recv. Planning V. Data MJ305
23-Aug-25
27-Sep-25
100%
PK000MJ36N
Recv. Planning V. Data MJ306
23-Aug-25
27-Sep-25
100%
EK000MD21E
Prepare & Issue Purchase ERW - MD201
27-Aug-25
29-Aug-25
100%
PK000MD51N
Recv. Planning V. Data MD501
27-Aug-25
01-Nov-25
100%
EK000MB21D
Technical Evaluation - MB212
29-Aug-25
01-Nov-25
100%
EK000MJ33D
Technical Evaluation - MJ303
30-Aug-25
19-Dec-25
100%
PK000MU21N
Recv. Planning V. Data MU221
01-Sep-25
27-Sep-25
100%
PK000ML42N
Recv. Planning V. Data ML420
02-Sep-25
26-Sep-25
100%
PK000MJ32N
Recv. Planning V. Data MJ302
02-Sep-25
27-Sep-25
100%
PK000MJ34N
Recv. Planning V. Data MJ304
02-Sep-25
27-Sep-25
100%
PK000MJ37N
Recv. Planning V. Data MJ340
02-Sep-25
27-Sep-25
100%
PK000MJ39N
Recv. Planning V. Data MJ391
02-Sep-25
27-Sep-25
100%
PK000MJ73N
Recv. Planning V. Data MJ730
02-Sep-25
27-Sep-25
100%
PK000MU22N
Recv. Planning V. Data MU222
02-Sep-25
27-Sep-25
100%
EK000MB095
101-B Ducting Detail Drawings - IFF
02-Sep-25
05-Apr-26
100%
EK000MD055
Pre-qualification trip to vendors shop (105-D)
03-Sep-25
05-Sep-25
100%
EK000MU41E
Prepare & Issue Purchase ERW - MU410
03-Sep-25
05-Sep-25
100%
PK000MU61N
Recv. Planning V. Data MU611
03-Sep-25
26-Sep-25
100%
PK000MJ22N
Recv. Planning V. Data MJ201
05-Sep-25
27-Sep-25
100%
PK000MJ31N
Recv. Planning V. Data MJ301
06-Sep-25
27-Sep-25
100%
PK000MC61N
Recv. Planning V. Data MC610
10-Sep-25
03-Dec-25
100%
EK000CV137
Issue OSBL Rough Grade Design Pkg.
11-Sep-25
26-Nov-25
100%
EK000ML51E
Prepare & Issue Purchase ERW - ML512
11-Sep-25
25-Sep-25
100%
PK000ML51N
Recv. Planning V. Data ML512
11-Sep-25
27-Sep-25
100%
EK000MJ36E
Prepare & Issue Purchase ERW - MJ306
13-Sep-25
25-Sep-25
100%
EK000MJ35E
Prepare & Issue Purchase ERW - MJ305
13-Sep-25
25-Sep-25
100%
EK000MJ22E
Prepare & Issue Purchase ERW - MJ201
13-Sep-25
13-Nov-25
100%
EK000I444D
Technical Evaluation - Analyzer Shelter
16-Sep-25
11-Dec-25
100%
EK000ML33E
Prepare & Issue Purchase ERW - ML330
17-Sep-25
25-Sep-25
100%
PK000MU41N
Recv. Planning V. Data MU410
17-Sep-25
27-Sep-25
100%
EK020PR20D
PR201 KAAP Catalyst - Technical Evaluation
17-Sep-25
01-Nov-25
100%
EK000MC61E
Prepare & Issue Purchase ERW - MC610
18-Sep-25
25-Sep-25
100%
EK000MJ32E
Prepare & Issue Purchase ERW - MJ302
20-Sep-25
13-Nov-25
100%
PK000ML33N
Recv. Planning V. Data ML330
20-Sep-25
27-Sep-25
100%
PK000ML43N
Recv. Planning V. Data ML430
20-Sep-25
01-Nov-25
100%
EK000MJ34E
Prepare & Issue Final Data Shts - MJ304
21-Sep-25
08-Nov-25
100%
EK000MU33E
Prepare & Issue Purchase ERW - MU330
21-Sep-25
26-Sep-25
100%
EK020MC31C
MC312 - (120,121-C) - Prepare & Issue Purchase ERW
23-Sep-25
27-Sep-25
100%
PK020MC31F
MC312 - (120,121-C) - Planning V. Data (Setting Plans)
23-Sep-25
08-Oct-25
100%
EK000MU31D
Technical Evaluation - MU310
24-Sep-25
30-Sep-25
100%
EK000MC23E
Prepare & Issue Purchase ERW - MC230
30-Sep-25
15-Oct-25
100%
EK000I352D
SIS - Tech Evaluation
30-Sep-25
07-Nov-25
100%
EK000MC21E
Prepare & Issue Purchase ERW - MC210
30-Sep-25
07-Nov-25
100%
EK000MU30E
Prepare & Issue Purchase ERW - MU300
01-Oct-25
14-Oct-25
100%
EK000ML42E
Prepare & Issue Purchase ERW - ML420
01-Oct-25
10-Oct-25
100%
EK000MJ37E
Prepare & Issue Purchase ERW - MJ340
01-Oct-25
16-Oct-25
100%
EK000MU31E
Prepare & Issue Purchase ERW - MU310
04-Oct-25
08-Oct-25
100%
EK000IC351
DCS - Develop Purchase T-Req
05-Oct-25
07-Nov-25
100%
EK000PR600
MD305 Merc. Removal Bed - Develop & Issue Load Sheets for ERW
08-Oct-25
09-Oct-25
100%
EK000MJ31E
Prepare & Issue Purchase ERW - MJ301
08-Oct-25
13-Nov-25
100%
PK000MJ33N
Recv. Planning V. Data MJ303
08-Oct-25
26-Dec-25
100%
EK000ML31E
Prepare & Issue Purchase ERW - ML313
08-Oct-25
09-Jan-26
100%
EK020ELEG2
Cathodic Protection - Subcontract Consultant ERW Package
09-Oct-25
01-Mar-26
100%
EK000MC32E
Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4)
10-Oct-25
15-Nov-25
100%
EK000MD103
MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW
10-Oct-25
26-Nov-25
100%
EK000PR610
MD305 Merc. Removal Bed - Analytical Design
10-Oct-25
26-Nov-25
100%
EK000YA813
(EP-14) Issue Plot Plans for Client Approval
11-Oct-25
11-Oct-25
100%
EK000I354D
ITCC - Tech Evaluation
15-Oct-25
12-Dec-25
100%
EK000MB42D
Technical Evaluation - MB420
16-Oct-25
30-Oct-25
100%
PK000IC35J
DCS - Planning V. Data
17-Oct-25
27-Dec-26
43%
PK000MU33N
03E MU330 2001-U - Piping Conceptual V. Data
30-Oct-25
02-Feb-26
100%
EK000ML43E
Prepare & Issue Purchase ERW - ML430
01-Nov-25
07-Nov-25
100%
EK000MJ37R
Develop & Issue Load Sheets for ERW - MJ307
04-Nov-25
08-Nov-25
100%
EK000MJ38R
Develop & Issue Load Sheets for ERW - MJ308
04-Nov-25
08-Nov-25
100%
EK000MU21E
Prepare & Issue Purchase ERW - MU221
05-Nov-25
22-Nov-25
100%
EK000MU22E
Prepare & Issue Purchase ERW - MU222
05-Nov-25
22-Nov-25
100%
EK000MU29F
Develop & Issue Inquiry for ERW - MU292
05-Nov-25
23-Nov-25
100%
EK000MJ37S
Develop & Issue Design Data for ERW - MJ307
11-Nov-25
15-Nov-25
100%
EK000MJ38S
Develop & Issue Design Data for ERW - MJ308
11-Nov-25
15-Nov-25
100%
EK000IC352
DCS - Final Tech Evaluation for Purchase
13-Nov-25
15-Nov-25
100%
EK000MJ37T
Update/Issue Formal Inquiry for ERW - MJ307
18-Nov-25
26-Nov-25
100%
EK000MJ73E
Prepare & Issue Purchase ERW - MJ730
19-Nov-25
05-Dec-25
100%
EK000FA005
Issue First Invoice to EBIC
19-Nov-25
19-Nov-25
100%
PK000MU30N
Recv. Planning V. Data MU300 - EDR Unit
19-Nov-25
10-Jan-26
100%
EK000E001A
Sub Stations - Issue ERW
22-Nov-25
31-Dec-25
100%
EK000MD102
MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur.
26-Nov-25
05-Dec-25
100%
EK000ML50Z
Technical Evaluation - ML500
10-Dec-25
31-Dec-25
100%
EK000E002A
Transformer - Issue ERW
18-Dec-25
30-Dec-25
100%
EK000MJ33E
Prepare & Issue Purchase ERW - MJ303
19-Dec-25
27-Dec-25
100%
PK000PSA8C
000 Relief Valves - Technical Evaluation
23-Dec-25
27-Dec-25
100%
EK000MU32D
01D MU322 Technical Evaluation
23-Dec-25
31-Jan-26
100%
EK000ELEJ1
Lighting, Installation Details
28-Dec-25
31-Dec-25
100%
EK000ELEK1
A/G Power & Control, Details
28-Dec-25
31-Dec-25
100%
EK000GE025
First Check Estimate
30-Dec-25
27-Feb-26
100%
EK000MU11D
05B MU311 Technical Evaluation
03-Jan-26
01-Feb-26
100%
EK000MC31E
Prepare & Issue Purchase ERW - MC310
03-Jan-26
12-Feb-26
100%
EK000MD104
MD305 Merc. Removal Bed - Technical Evaluation
13-Jan-26
29-Jan-26
100%
EK000IC353
DCS - Software Programming by KBR
15-Jan-26
27-Dec-26
29%
EK000CV045
Prepare Foundation Design Criteria
16-Jan-26
14-Mar-26
100%
EK000MJ37C
Prepare & Issue Purchase ERW - MJ307
17-Jan-26
20-Jan-26
100%
EK000MU29D
Technical Evaluation - MU292
20-Jan-26
03-Mar-26
100%
PK000PTA0H
Engineered Pipe Supports - Production V. Data
24-Jan-26
29-Jan-26
100%
EK000SY095
010 P&ID's - Tech Review
28-Jan-26
29-Jan-26
100%
EK000I3540
ITCC - Develop Final Design Basis
28-Jan-26
04-Mar-26
100%
EK000I3520
SIS - Develop Final Design Basis
28-Jan-26
12-Mar-26
100%
EK000MU25D
02G MU225 Technical Evaluation
28-Jan-26
21-Feb-26
100%
EK000MD105
MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW
29-Jan-26
01-Feb-26
100%
PK000ML50N
Recv. Planning V. Data ML500
29-Jan-26
24-Feb-26
100%
EK010E008A
540-SB Admin. Area Pwr Supply - ERW Package
01-Feb-26
14-Feb-26
100%
EK00012210
000 Everest Control Valves - D/S,Sizing,Tech Eval
03-Feb-26
05-Mar-26
100%
EK000YA822
(EP-22) Issue for Planning (IPL) >90% OSBL P&ID's
09-Feb-26
09-Feb-26
100%
EK000YA824
(EP-23) Issue For Planning (IPL) >90% ISBL P&ID's
09-Feb-26
09-Feb-26
100%
EK000MU11E
05B MU311 Prepare & Issue Purchase ERW
11-Feb-26
13-Feb-26
100%
EK000PS00C
000 SP Items - Technical Evaluation
11-Feb-26
01-Mar-26
100%
PK000MU11N
05B MU311 Recv. Planning V. Data
13-Feb-26
28-Feb-26
100%
EK000I444B
Develop Final Design Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000I444M
Develop Final Deign Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000E004A
UPS System - Issue ERW
17-Feb-26
28-Mar-26
100%
EK000E001D
Sub Stations - Tech Evaluation
19-Feb-26
27-Dec-26
21%
EK000CS027
Turnover System Definition for OSBL
25-Feb-26
27-Dec-26
19%
EK000I444F
Planning V. Data - Shelters/ Analyzers
25-Feb-26
27-Dec-26
19%
PK000I352J
SIS - Planning V. Data
25-Feb-26
27-Dec-26
19%
PK000I354J
ITCC - Planning V. Data
25-Feb-26
27-Dec-26
19%
EK000MJ38T
Update/Issue Formal Inquiry for ERW - MJ308
25-Feb-26
03-Mar-26
100%
EK000ML50E
Prepare & Issue Purchase ERW - ML500
25-Feb-26
08-Mar-26
100%
EK000YA831
(EP-26) Complete Hazard Review Meeting on >90% ISBL P&ID's
25-Feb-26
25-Feb-26
100%
EK000MJ39E
Prepare & Issue Purchase ERW - MJ391
27-Feb-26
09-Apr-26
100%
EK000I3541
ITCC - Develop Purchase T-Req
27-Feb-26
05-Mar-26
100%
EK000E002D
Transformer - Tech Evaluation
04-Mar-26
27-Dec-26
17%
EK000YA826
(EP-27) Begin Issuing Area Line Installation Details (IDF Files)
04-Mar-26
04-Mar-26
100%
EK000I221F
000 Everest Control Valves - Purchase ERW
11-Mar-26
27-Dec-26
15%
PK000MU29N
Recv. Planning V. Data MU292
19-Mar-26
09-Apr-26
100%
EK000MU29E
Prepare & Issue Purchase ERW - MU292
24-Mar-26
27-Mar-26
100%
EK000MU32E
01D MU322 Prepare & Issue Purchase ERW
31-Mar-26
31-Mar-26
100%
EK000I3521
SIS - Develop Purchase T-Req
31-Mar-26
03-Apr-26
100%
EK000MU25E
02G MU225 Prepare & Issue Purchase ERW
01-Apr-26
27-Dec-26
9%
EK000I3542
ITCC - Final Tech Evaluation for Purchase
01-Apr-26
03-Apr-26
100%
EK000I444C
Develop / Issue T-Req - Shelters/ Analyzers
01-Apr-26
03-Apr-26
100%
EK010E008D
540-SB Admin. Area Pwr Supply - Tech Evaluation
03-Apr-26
27-Dec-26
8%
EK000I3523
SIS - Software Programming by KBR
18-Apr-26
27-Dec-26
5%
EK000MJ38C
Prepare & Issue Purchase ERW - MJ308
23-Apr-26
27-Dec-26
5%
EK000E004D
UPS System - Tech Evaluation
27-Dec-26
27-Dec-26
0%
EK000ELEG0
Electrical Heat Tracing - ERW Package
27-Dec-26
27-Dec-26
0%
EK000FP060
FP Overall Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
0%
EK000FP065
FP Overall Firewater P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
0%
EK000GE030
Production Check Estimate
27-Dec-26
27-Dec-26
0%
EK000I3522
SIS - Final Tech Evaluation for Purchase
27-Dec-26
27-Dec-26
0%
EK000I352M
SIS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I354M
ITCC - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I444E
Final Tech Evaluation - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
EK000I444G
Review / Approve V. Data - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
EK000YA832
(EP-32) Issue OSBL (Units01/03) found./UG pipe work package
27-Dec-26
27-Dec-26
0%
EK000YA833
(EP-33) Issue > 90% ISBL Civil Foundations
27-Dec-26
27-Dec-26
0%
EK000YA839
(EP-35) Issue >90% OSBL P&ID's For Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA841
(EP-29) Issue OSBL Plot Plan for Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA848
(EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA888
(TLA-02) Second TLA Payment
27-Dec-26
27-Dec-26
0%
EK020ELEG5
Cathodic Protection - Design & Specs Package (By Consultant)
27-Dec-26
27-Dec-26
0%
PK000E001J
Sub Stations - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E002J
Transformer - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E004J
UPS System - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000IC35M
DCS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
PK010E008J
540-SG Admin. Area Pwr Supply - Planning V. Data
27-Dec-26
27-Dec-26
0%
EK000YA500
Issue ISBL Paint & Insulation Work Package
28-Dec-26
08-Mar-27
750.0d
0%
EK000ELEGP
Electrical Heat Tracing - Design & BOM by Consultant
30-Dec-26
30-Jan-27
91.0d
0%
EK000ELEN1
01,03,04 LV Wiring Diagrams - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN2
01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN3
01,03, Equipment Interconnection Diagrams - IFC
30-Dec-26
30-Jan-27
511.0d
0%
EK020ELEG6
Cathodic Protection - Material Supply (By Consultant)
30-Dec-26
02-May-27
6.0d
0%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
0%
EK000YA838
(EP-34) Issue >90% ISBL P&ID's For Construction (IFC)
03-Jan-27
03-Jan-27
0%
EK000YA030
Last PDS Planning Release
24-Jan-27
24-Jan-27
515.0d
0%
EK000YA040
Engineering 95% Complete
30-Jan-27
30-Jan-27
0%
PK000E001Z
Sub Stations - FAT
17-Feb-27
28-Feb-27
62.0d
0%
EK000YA835
(EP-36) Issue >90% Area Line Installation Details
21-Feb-27
21-Feb-27
0%
EK000YA847
(EP-39) Issue >90% OSBL Electrical Design Drawings
21-Feb-27
21-Feb-27
0%
EK000YA889
(TLA-03) Complete > TLA Payments
03-May-27
03-May-27
623.0d
0%
Jul 2024 Aug 2024 Sep 2024 Oct 2024 Nov 2024 Dec 2024 Jan 2025 Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 May 2027 Data Date
EK000CK085 — Establish bank account in Egypt | 02-Jul-24 → 24-Jan-26 | Complete 100% | float — EK000CK085 EK000SY005 — Systems Work Plan & Project Setup | 21-Jan-25 → 25-Mar-25 | Complete 100% | float — EK000SY005 EK000YA002 — Start Project | 22-Jan-25 | Complete EK000PR025 — Pressure Profile | 22-Jan-25 → 01-Feb-25 | Complete 100% | float — EK000PR025 EK000PR050 — Electrical Load Summary - Initial | 22-Jan-25 → 01-Feb-25 | Complete 100% | float — EK000PR050 EK000MD005 — Attend Alignment & strategy meetings | 22-Jan-25 → 09-Feb-25 | Complete 100% | float — EK000MD005 EK000PR015 — Process Configuration | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR015 EK000PR030 — Stream Summary | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR030 EK000PR035 — Process Flow Diagrams PFD's - EOR | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR035 EK000PR040 — Steam Balance Diagram - EOR | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR040 EK000GE005 — Estimate Escalation Check - Info to Estimating | 22-Jan-25 → 14-Feb-25 | Complete 100% | float — EK000GE005 EK000PR045 — Cooling Water Balance - EOR | 22-Jan-25 → 15-Feb-25 | Complete 100% | float — EK000PR045 EK000PE025 — Document Management Plan - Issue for Review | 22-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000PE025 EK000SY010 — MEC Convert prelim P&ID's to Smart Plant P&ID's | 22-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000SY010 EK000MD015 — Conversion of drawings to metric units | 22-Jan-25 → 19-Feb-25 | Complete 100% | float — EK000MD015 EK000PM015 — Project Coordination Procedure - IFA | 22-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PM015 EK000PR020 — Heat & Material Balances (SOR & EOR) | 22-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PR020 EK000PE085 — Participate in Escalation confirmation effort | 22-Jan-25 → 01-Mar-25 | Complete 100% | float — EK000PE085 EK000IM030 — Project Portal & Dashboard | 22-Jan-25 → 06-Mar-25 | Complete 100% | float — EK000IM030 EK000IC030 — Develop & Issue FieldBus Main Instr Vendor ERW | 22-Jan-25 → 08-Mar-25 | Complete 100% | float — EK000IC030 EK000PR055 — Feed & Fuel Summary | 22-Jan-25 → 09-Mar-25 | Complete 100% | float — EK000PR055 EK000IM020 — IM Strategy plan | 22-Jan-25 → 12-Mar-25 | Complete 100% | float — EK000IM020 EK000IM025 — IM Execution plan | 22-Jan-25 → 12-Mar-25 | Complete 100% | float — EK000IM025 EK000PR010 — Process Work Plan | 22-Jan-25 → 23-Mar-25 | Complete 100% | float — EK000PR010 EK000AR020 — Gather Bldg Requirements & Coordinate w/ Constr | 22-Jan-25 → 12-Apr-25 | Complete 100% | float — EK000AR020 EK000IM010 — Object Engineering set-up & procedures | 22-Jan-25 → 13-Apr-25 | Complete 100% | float — EK000IM010 EK000CV005 — Identify scope / Project set-up | 23-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000CV005 EK000PE125 — Preliminary Issue - Equipment List | 29-Jan-25 → 12-Feb-25 | Complete 100% | float — EK000PE125 EK000CV020 — Review FMCL documents - Specs & Drawings | 29-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000CV020 EK000IM040 — Establish Citrix for Test of PDS (HOC-MEC) | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000IM040 EK000PI080 — Develop Split of work | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PI080 EK000IM005 — Equipment List (MEL) Definition | 29-Jan-25 → 30-Mar-25 | Complete 100% | float — EK000IM005 EK000PE050 — Confirm of Split of Work for MEC | 02-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PE050 EK000IC35A — DCS - Engr ERW Issued | 04-Feb-25 → 12-Feb-25 | Complete 100% | float — EK000IC35A EK000IM035 — Establish Documentum | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000IM035 EK000PE010 — Publish Unit conversion standard | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE010 EK000PE040 — Devlop & Issue List of Project Specs & Standards | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE040 EK000CV025 — Review SEGAS Wind & Earthquake Specs | 05-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000CV025 EK000PI120 — Identify priority pipe classes | 05-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000PI120 EK000PS015 — Issue 90 Day look ahead schedule | 05-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000PS015 EK000MJ005 — Prepare Machinery Specs (Motors, Pkg Equipment) | 05-Feb-25 → 25-Feb-25 | Complete 100% | float — EK000MJ005 EK000IC015 — Modify Package Equipment Spec for IEC basis | 05-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000IC015 EK000PE110 — Issue Draft Project Design Data | 05-Feb-25 → 06-Mar-25 | Complete 100% | float — EK000PE110 EK000MC010 — Develop & Issue Exchanger Work Plan | 05-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000MC010 EK000PI115 — Develop Piping Class Index (IOPMC) | 05-Feb-25 → 13-Mar-25 | Complete 100% | float — EK000PI115 EK000SY015 — Develop Utility & offsite block flow diagrams | 05-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000SY015 EK000PI132 — Develop Early Tech P-Class specs for Procurement | 05-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PI132 EK000SY065 — Complete Utility Flow Diagrams | 05-Feb-25 → 03-Apr-25 | Complete 100% | float — EK000SY065 EK000CV010 — HOC / MEC split of Work | 07-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV010 EK000CV030 — Prepare EBIC Wind & EarthquakeSpecs | 07-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000CV030 EK000QM010 — Training - Export Compliance | 08-Feb-25 → 08-Feb-25 | Complete 100% | float — EK000ELZE0 — Area Classification | 11-Feb-25 → 30-Dec-25 | Complete 100% | float — EK000ELZE0 EK000MD31C — Prepare & Issue Prelim. RFQ - MD301 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD31C EK000MD32C — Prepare & Issue Prelim. RFQ - MD302 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD32C EK000MD34C — Prepare & Issue Prelim. RFQ - MD304 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD34C EK000MD51C — Prepare & Issue Prelim. RFQ - MD501 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD51C EK000CV040 — Prepare Topo Survey S/C Pkg | 12-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000CV040 EK000PE090 — Develop & Issue Engineering Plan | 12-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PE090 EK000EL005 — Electrical Work Plans | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000EL005 EK000PI040 — Prepare technology work plan - Piping Engr. | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI040 EK000PI060 — Prepare Other Project Documentation | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI060 EK000PI051 — Prepare P/Mech Support Details | 12-Feb-25 → 15-Mar-25 | Complete 100% | float — EK000PI051 EK000CV015 — Civil work Plan & Safety check list | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV015 EK000CV050 — Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV050 EK000MB005 — Develop & Issue Furnance Job Plan | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000MB005 EK000MJ31C — Prepare & Issue Prelim. RFQ - MJ301 to Proc. | 13-Feb-25 → 13-Feb-25 | Complete 100% | float — EK000MJ32C — Prepare & Issue Prelim. RFQ - MJ302 to Proc. | 13-Feb-25 → 13-Feb-25 | Complete 100% | float — EK000MB33A — 101-B Develop & Issue Load Sheet | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD33A — Develop & Issue Load Sheets for ERW - MD303 | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MJ22A — Develop & Issue Load Sheets for ERW - MJ201 | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MJ21A — Develop & Issue Load Sheets for ERW - MJ202 | 14-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MJ21A EK000PI110 — Locate FMCL Documents | 14-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PI110 EK000PR060 — Process Load Sheets | 14-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PR060 EK000PC005 — Prepare Estimate for Escalation Check | 15-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PC005 EK000PE015 — MSD (From Metallurgy) - ISBL | 15-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000PE015 EK000MC31C — Prepare & Issue Prelim. RFQ - MC310 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MC61C — Prepare & Issue Prelim. RFQ - MC610 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MBP1C — 101-B Prepare & Issue Prelim. Shop Fab to Proc. | 16-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MBP1C EK000QM015 — Develop & Issue Quality Plan | 16-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000QM015 EK000MC32C — Issue Prelim. RFQ - MC311 | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000MJ22C — Prepare & Issue Prelim. RFQ - MJ201 to Proc. | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK020MC31A — MC312 - (120,121-C) - Issue Prelim. RFQ | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000MD21A — Develop & Issue Load Sheets for ERW - MD201 | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD41C — Prepare & Issue Prelim. RFQ - MD401 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD43C — Prepare & Issue Prelim. RFQ - MD403 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD43A — Develop & Issue Load Sheets for ERW - MD403 | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MJ31A — Develop & Issue Load Sheets for ERW - MJ301 | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MD33C — Prepare & Issue Prelim. RFQ - MD303 to Proc. | 19-Feb-25 → 22-Feb-25 | Complete 100% | float — EK000EL020 — Define bulk material requirements | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000EL020 EK000MJ22B — Develop & Issue Design Data for ERW - MJ201 | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MJ22B EK000ML31C — Prepare & Issue Prelim. RFQ - ML313 to Proc. | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000ML31C EK000PR115 — Issue Prelim Load Sht for Air Cooling Study | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PR115 EK000MC210 — Cooling Water Balance Review | 19-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MC210 EK000IM045 — Establish IPMS | 19-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000IM045 EK000IC005 — Develop Typical SIL Values Worksheet | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000IC005 EK000MJ35C — Prepare & Issue Prelim. RFQ - MJ305 to Proc. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MJ35C EK000MJ36C — Prepare & Issue Prelim. RFQ - MJ306 to Proc. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MJ36C EK000PK030 — Provide Job Specific SDR2 Priorities to Purch. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PK030 EK000PI160 — P&ID Area Break Mark-up | 19-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000PI160 EK000MJ39C — Prepare & Issue Prelim. RFQ - MJ391 to Proc. | 19-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000MJ39C EK000PR076 — Identify Risk of Equipment Changes | 19-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PR076 EK000PE035 — Rvw Lesson Learn w/Prj. Team&Develop Action List | 19-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000PE035 EK000EV005 — Conceptual Design of Wastewater Systems | 19-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000EV005 EK000PR145 — Eng. Studies - Ammonia Product Line U/G vs. A/G | 19-Feb-25 → 29-Mar-25 | Complete 100% | float — EK000PR145 EK000MB010 — 101-B Furnance Analytical - Convection Design | 19-Feb-25 → 30-Mar-25 | Complete 100% | float — EK000MB010 EK000CV070 — Validate Concrete & Steel by Planning Areas | 19-Feb-25 → 15-Apr-25 | Complete 100% | float — EK000CV070 EK000MD33P — Develop Analytical Sketches for ERW - MD303 | 19-Feb-25 → 04-May-25 | Complete 100% | float — EK000MD33P EK000PM055 — Complete EPC Insurance Forms | 19-Feb-25 → 04-May-25 | Complete 100% | float — EK000PM055 EK000PI020 — Develop Piping Specs (Paper) | 19-Feb-25 → 28-May-25 | Complete 100% | float — EK000PI020 EK000MJ21C — Prepare & Issue Prelim. RFQ - MJ202 to Proc. | 20-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000ML50C — Prepare & Issue Prelim. RFQ - ML500 to Proc. | 20-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000ML50C EK000MD44A — Develop & Issue Load Sheets for ERW - MD404 | 20-Feb-25 → 20-Mar-25 | Complete 100% | float — EK000MD44A EK000MB61C — Prepare & Issue Prelim. RFQ - MB610 to Proc. | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MB62C — Prepare & Issue Prelim. RFQ - MB621 to Proc. | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MD34A — Develop & Issue Load Sheets for ERW - MD304 | 21-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MD34A EK000MJ21B — Develop & Issue Design Data for ERW - MJ202 | 22-Feb-25 → 07-Mar-25 | Complete 100% | float — EK000MJ21B EK000MD21P — Develop Prelim Analytical Sktch for ERW - MD201 | 22-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000MD21P EK000MD21Q — Develop Final Analytical Sktch for ERW - MD201 | 22-Feb-25 → 26-Apr-25 | Complete 100% | float — EK000MD21Q EK000YA804 — (EP-05) Issue Heat and Material Balance for Process Release | 22-Feb-25 | Complete EK000YA805 — (EP-06) Issue Equipment List for review | 22-Feb-25 | Complete EK000YA807 — (EP-08) Issue Utility Balances for Initial Release | 22-Feb-25 | Complete EK000FP025 — FP Gas Detection Location Plans - Not Required | 22-Feb-25 → 23-Aug-25 | Complete 100% | float — EK000FP025 EK000MC32A — Develop & Issue Load Sheets for ERW - MC311 | 23-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MC32A EK000CK080 — Expedite legal issues associated w/ KBRII | 23-Feb-25 → 28-Feb-26 | Complete 100% | float — EK000CK080 EK000MB060 — 101-B General Arrangement Drawing | 25-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000MB060 EK000MF31A — Develop & Issue Load Sheets for ERW - MF301 | 26-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MB41C — Prepare & Issue Prelim. RFQ - MB410 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC21C — Prepare & Issue Prelim. RFQ - MC210 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC23C — Prepare & Issue Prelim. RFQ - MC230 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD31A — Develop & Issue Load Sheets for ERW - MD301 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD32A — Develop & Issue Load Sheets for ERW - MD302 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD41A — Develop & Issue Load Sheets for ERW - MD401 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000EL015 — Split of work with MEC and Other Discipline | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MB63C — Prepare & Issue Prelim. RFQ - MB630 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MBP4C — Prepare & Issue Prelim. RFQ Cast Material | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE060 — Define Task Force Area in MEC | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE075 — MEC Organization Chart | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PM030 — Estimate Escalation Check - IRC Approvals | 26-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000PR095 — Steam Balance - Startup, 103-J, Etc | 26-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PR095 EK000MBP3C — Prepare & Issue Prelim. RFQ Pressure Parts | 26-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000MBP3C EK000MD33B — Develop & Issue Design Data for ERW - MD303 | 26-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000MD33B EK000EV025 — Develop & Issue Enviromental Work Plan | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000EV025 EK000IC020 — Establlish data warehouse - Intools Basic Setup | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC020 EK000IC025 — Review Instr. & Installation Details - ID Change | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC025 EK000MJ22F — Update/Issue Formal Inquiry for ERW - MJ201 | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000MJ22F EK000PK010 — Issue critical req'n submittal sched to Procmnt | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PK010 EK000GE010 — Eng. Studies - Air Coolers vs. Cooling Water | 26-Feb-25 → 12-Mar-25 | Complete 100% | float — EK000GE010 EK000CV060 — Civil project highlights | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV060 EK000PI005 — Locate Permanent Tie in pnts Gas, Wtr, Storm wtr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000PI005 EK000PE065 — Develop & Issue HOC - MEC Coordination Plan | 26-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000PE065 EK000PI133 — Dvlp/Issue V-class specs & Standads for Procurmt | 26-Feb-25 → 09-Apr-25 | Complete 100% | float — EK000PI133 EK000MB085 — 101-B Radiant Detail Drawings - IFF | 26-Feb-25 → 12-Apr-25 | Complete 100% | float — EK000MB085 EK000MB090 — 101-B Convection Detail Drawings - IFF | 26-Feb-25 → 12-Apr-25 | Complete 100% | float — EK000MB090 EK000CV035 — Prepare Geotech S/C Pkgs | 26-Feb-25 → 27-Apr-25 | Complete 100% | float — EK000CV035 EK000EL025 — Develop installation details | 26-Feb-25 → 07-May-25 | Complete 100% | float — EK000EL025 EK000IC045 — Develop & Issue CSE Work Plan | 26-Feb-25 → 08-May-25 | Complete 100% | float — EK000IC045 EK000PM045 — Issue Execution Strategy /Project Execution Plan | 26-Feb-25 → 24-May-25 | Complete 100% | float — EK000PM045 EK000MC31A — Develop & Issue Load Sheets for ERW - MC310 | 27-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000ML50B — Develop/Issue Load Sht & Design Data ERW - ML500 | 27-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000ML50B EK000MD42A — Develop & Issue Load Sheets for ERW - MD402 | 28-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000MD51A — Develop & Issue Load Sheets for ERW - MD501 | 28-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000MD51A EK000MJ35A — Develop & Issue Load Sheets for ERW - MJ305 | 28-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000MJ35A EK000YA808 — (EP-09) Issue Engineering Plan | 01-Mar-25 | Complete EK000MD060 — Prepare Vessel work plan & other quality documents | 02-Mar-25 → 02-Mar-25 | Complete 100% | float — EK000MC31B — Develop & Issue Design Data for ERW - MC310 | 02-Mar-25 → 13-Mar-25 | Complete 100% | float — EK000MC31B EK000MC31F — Finalize Equip. Data Sheets for ERW - MC310 | 02-Mar-25 → 12-Apr-25 | Complete 100% | float — EK000MC31F EK000PI125 — Validate new plot layout (impacts on pipe stress | 02-Mar-25 → 21-May-25 | Complete 100% | float — EK000PI125 EK000MJ21D — Technical Evaluation - MJ202 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000MJ75A — Develop & Issue Load Sheets for ERW - MJ750 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000ML31A — Develop & Issue Load Sheets for ERW - ML313 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000MB51C — Prepare & Issue Prelim. RFQ - MB511 to Proc. | 05-Mar-25 → 07-Mar-25 | Complete 100% | float — EK000CV075 — Egyptian Professional Engineer - Define Reqmnts | 05-Mar-25 → 08-Mar-25 | Complete 100% | float — EK000MC21A — Develop & Issue Load Sheets for ERW - MC210 | 05-Mar-25 → 08-Mar-25 | Complete 100% | float — EK000EL035 — Voltage drop table | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000EL035 EK000ML42C — Prepare & Issue Prelim. RFQ - ML420 to Proc. | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000ML42C EK000MU33C — Prepare & Issue Prelim. RFQ - MU330 to Proc. | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MU33C EK000CS030 — Start-up Schedule (Prelim for 1st Planner) | 05-Mar-25 → 14-Mar-25 | Complete 100% | float — EK000CS030 EK000MC32B — Develop & Issue Design Data for ERW - MC311 | 05-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MC32B EK000MC23A — Develop & Issue Load Sheets for ERW - MC230 | 05-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MC23A EK000MC32F — Finalize Equip. Data Sheets for ERW - MC311 | 05-Mar-25 → 24-May-25 | Complete 100% | float — EK000MC32F EK000MD22A — Develop & Issue Load Sheets for ERW - MD202 | 06-Mar-25 → 06-Mar-25 | Complete 100% | float — EK000MBP1D — 101-B Technical Bid Evaluation Shop Fab | 06-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MJ37A — Develop & Issue Load Sheets for ERW - MJ340 | 06-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000ML31B — Develop & Issue Design Data for ERW - ML313 | 06-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000ML31B EK000MD42P — Confirm Analytical Design for ERW - MD402 | 06-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MD42P EK000ML50F — Update/Issue Formal Inquiry for ERW - ML500 | 06-Mar-25 → 27-Apr-25 | Complete 100% | float — EK000ML50F EK000PE020 — WMS Setup & Development | 07-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PE020 EK000CV080 — Egyptian Professional Eng. - Issue P.O/Subc. Pkg | 08-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MJ21F — Update/Issue Formal Inquiry for ERW - MJ202 | 08-Mar-25 → 13-Mar-25 | Complete 100% | float — EK000MJ21F EK000MC21B — Develop & Issue Design Data for ERW - MC210 | 08-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MC21B EK000MJ31B — Develop & Issue Design Data for ERW - MJ301 | 08-Mar-25 → 12-Apr-25 | Complete 100% | float — EK000MJ31B EK000PI055 — Prepare Object Engineering Work Instruction | 08-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI055 EK000PC010 — Estimate Turnover to Project Team | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PC010 EK000PI085 — Estimate/Schedule Review | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI085 EK000MD34R — Develop Final Analytical Sktch for ERW - MD304 | 09-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD34R EK000MD43P — Confirm Analytical Design for ERW - MD403 | 09-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD43P EK000MC61A — Develop & Issue Load Sheets for ERW - MC610 | 09-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MC61A EK000PC015 — Estimate Recast & Develop Project Control Budget | 09-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000PC015 EK000PI105 — Performance Test of Citrix for PDS w/MEC | 12-Mar-25 → 12-Mar-25 | Complete 100% | float — EK000MU41F — Develop & Issue Inquiry for ERW - MU410 | 12-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MU41F EK000MD34P — Confirm Analytical Design for ERW - MD304 | 12-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MD34P EK000MU41A — Develop & Issue Load Sheets for ERW - MU410 | 12-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU41A EK000MD31P — Confirm Analytical Design for ERW - MD301 | 12-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000MD31P EK000MD32P — Confirm Analytical Design for ERW - MD302 | 12-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MD32P EK000PI100 — Critical Line List | 12-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000PI100 EK000EV020 — Develop Preliminary noise model | 12-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000EV020 EK000MC21F — Finalize Equip. Data Sheets for ERW - MC210 | 12-Mar-25 → 13-Jun-25 | Complete 100% | float — EK000MC21F EK000MD020 — Equipment Modeling for Vessel - MEC | 13-Mar-25 → 25-Mar-26 | Complete 100% | float — EK000MD020 EK000MB61D — Technical Evaluation - MB610 | 14-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MB61D EK000PR080 — Input to Process Guarantees | 14-Mar-25 → 03-May-25 | Complete 100% | float — EK000PR080 EK000IC35D — DCS - Tech Evaluation | 14-Mar-25 → 14-May-25 | Complete 100% | float — EK000IC35D EK000MJ32A — Develop & Issue Load Sheets for ERW - MJ302 | 15-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MJ32A EK000ML31F — Update/Issue Formal Inquiry for ERW - ML313 | 16-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD31B — Develop & Issue Design Data for ERW - MD301 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD32B — Develop & Issue Design Data for ERW - MD302 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD34B — Develop & Issue Design Data for ERW - MD304 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MJ22D — Technical Evaluation - MJ201 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD45A — Develop & Issue Load Sheets for ERW - MD405 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MD45A EK000ML43A — Develop & Issue Load Sheets for ERW - ML430 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML43A EK000ML44A — Develop & Issue Load Sheets for ERW - ML440 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML44A EK000PE095 — Disciplines Load WMS with Budgets & Deliverables | 16-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000PE095 EK000MD34D — Technical Evaluation - MD304 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD34D EK000MD41D — Technical Evaluation - MD401 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD41D EK000ML42A — Develop & Issue Load Sheets for ERW - ML420 | 19-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU35A — Develop & Issue Load Sheets for ERW - MU350 | 19-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU41B — Develop & Issue Design Data for ERW - MU410 | 19-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MU30F — Develop & Issue Inquiry for ERW - MU300 | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MU30F EK000MF33B — Develop/Issue Load Sht & Design Data ERW - MF311 | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MF33B EK000MF32B — Develop/Issue Load Sht & Design Data ERW - MF302 | 19-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000MF32B EK000MD21B — Develop & Issue Design Data for ERW - MD201 | 19-Mar-25 → 08-May-25 | Complete 100% | float — EK000MD21B EK000ML42F — Update/Issue Formal Inquiry for ERW - ML420 | 19-Mar-25 → 24-Apr-25 | Complete 100% | float — EK000ML42F EK000MC63A — Develop & Issue Load Sheets for ERW - MC630 | 20-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MU61F — Develop & Issue Inquiry for ERW - MU611 | 20-Mar-25 → 25-Mar-25 | Complete 100% | float — EK000MU61F EK000I210D — 000 Control Valves - Technical Evaluation | 20-Mar-25 → 23-May-25 | Complete 100% | float — EK000I210D EK000MU35F — Update/Issue Formal Inquiry for ERW - MU350 | 21-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MD47A — Develop & Issue Load Sheets for ERW - MD406 | 21-Mar-25 → 23-Mar-25 | Complete 100% | float — EK000MD51B — Develop & Issue Design Data for ERW - MD501 | 21-Mar-25 → 28-Mar-25 | Complete 100% | float — EK000MD51B EK000MC61D — Technical Evaluation - MC610 | 21-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MC61D EK000MC61F — Finalize Equip. Data Sheets for ERW - MC610 | 21-Mar-25 → 10-Apr-25 | Complete 100% | float — EK000MC61F EK000MJ32B — Develop & Issue Design Data for ERW - MJ302 | 21-Mar-25 → 13-Apr-25 | Complete 100% | float — EK000MJ32B EK000MD34F — Update/Issue Formal Inquiry for ERW - MD304 | 21-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000MD34F EK000EV010 — Develop design basis for evaporation pond | 22-Mar-25 → 11-May-25 | Complete 100% | float — EK000EV010 EK000YA802 — (EP-03) Issue Process Plan | 22-Mar-25 | Complete EK000MB51F — Prepare & Issue Purchase ERW - MB511 | 23-Mar-25 → 17-Apr-25 | Complete 100% | float — EK000MB51F EK000MJ39B — Develop/Issue Load Sht & Design Data ERW - MJ391 | 25-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000MJ39B EK000ML50D — Technical Evaluation - ML500 | 25-Mar-25 → 27-Apr-25 | Complete 100% | float — EK000ML50D EK000MD025 — Prepare job quality drawings for ERW | 25-Mar-25 → 28-May-25 | Complete 100% | float — EK000MD025 EK000ML44B — Develop & Issue Design Data for ERW - ML440 | 26-Mar-25 → 27-Mar-25 | Complete 100% | float — EK000MF31P — Confirm Analytical Design for ERW - MF301 | 26-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000PR070 — Effluent Summary | 26-Mar-25 → 30-Mar-25 | Complete 100% | float — EK000PR070 EK000MD51D — Technical Evaluation - MD501 | 26-Mar-25 → 03-Apr-25 | Complete 100% | float — EK000MD51D EK000MU33F — Update/Issue Formal Inquiry for ERW - MU330 | 26-Mar-25 → 04-Apr-25 | Complete 100% | float — EK000MU33F EK000MD33F — Update/Issue Formal Inquiry for ERW - MD303 | 26-Mar-25 → 11-May-25 | Complete 100% | float — EK000MD33F EK000MF32F — Develop & Issue Design Data for Tank Subcontract - MF302 | 26-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000MF32F EK000I131D — Technical Evaluation - Transmitters | 26-Mar-25 → 23-May-25 | Complete 100% | float — EK000I131D EK000MJ35D — Technical Evaluation - MJ305 | 27-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MJ35D EK000MJ36D — Technical Evaluation - MJ306 | 27-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MJ36D EK000MF33F — Develop & Issue Design Data for Tank Subcontract - MF311 | 27-Mar-25 → 09-Apr-25 | Complete 100% | float — EK000MF33F EK000CVK35 — OSBL Rough Grading/Road | 27-Mar-25 → 23-May-25 | Complete 100% | float — EK000CVK35 EK000MD51F — Update/Issue Formal Inquiry for ERW - MD501 | 29-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000MD51F EK000MD45P — Confirm Analytical Design for ERW - MD405 | 29-Mar-25 → 25-Apr-25 | Complete 100% | float — EK000MD45P EK000MB62D — Technical Evaluation - MB621 | 30-Mar-25 → 18-Apr-25 | Complete 100% | float — EK000MB62D EK000MB63D — Technical Evaluation - MB630 | 30-Mar-25 → 24-Jun-25 | Complete 100% | float — EK000MB63D EK000MF31B — Develop & Issue Design Data for Tank Subcontrac - MF301 | 01-Apr-25 → 08-Apr-25 | Complete 100% | float — EK000MF31B EK000MJ34B — Develop/Issue Load Sht & Design Data ERW - MJ304 | 01-Apr-25 → 08-Apr-25 | Complete 100% | float — EK000MJ34B EK000PR065 — Catalyst and Chemical Specs | 01-Apr-25 → 09-Apr-25 | Complete 100% | float — EK000PR065 EK000MB070 — 101-B Foundation Loads | 01-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MB070 EK000PR075 — Process Description | 01-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000PR075 EK000MJ39F — Update/Issue Formal Inquiry for ERW - MJ391 | 01-Apr-25 → 27-Apr-25 | Complete 100% | float — EK000MJ39F EK000QM020 — Develop/ Issue/ Approval of QA/QC Manual (EBIC/EXIM Verification) | 01-Apr-25 → 31-Oct-25 | Complete 100% | float — EK000QM020 EK000MD44P — Confirm Analytical Design for ERW - MD404 | 02-Apr-25 → 03-Apr-25 | Complete 100% | float — EK000MD31F — Update/Issue Formal Inquiry for ERW - MD301 | 02-Apr-25 → 16-Apr-25 | Complete 100% | float — EK000MD31F EK000MU61B — Develop/Issue Load Sht & Design Data ERW - MU611 | 02-Apr-25 → 14-May-25 | Complete 100% | float — EK000MU61B EK000MB51D — Technical Evaluation - MB511 | 02-Apr-25 → 16-Apr-25 | Complete 100% | float — EK000MB51D EK000MD32F — Update/Issue Formal Inquiry for ERW - MD302 | 02-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MD32F EK000MD43D — Technical Evaluation - MD403 | 02-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD43D EK000MC61B — Develop & Issue Design Data for ERW - MC610 | 04-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MC61B EK000MJ35B — Develop & Issue Design Data for ERW - MJ305 | 05-Apr-25 → 09-May-25 | Complete 100% | float — EK000MJ35B EK000MB080 — 101-B Convection Coil Design | 05-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MB080 EK000ML31D — Technical Evaluation - ML313 | 05-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML31D EK000MB050 — 101-B Radiant coil design | 06-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MB050 EK000MD22P — Confirm Analytical Design for ERW - MD202 | 06-Apr-25 → 15-Apr-25 | Complete 100% | float — EK000MD22P EK000MB33F — MB333 - Develop & Issue Purchase ERW 101-B | 06-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MB33F EK000MBP4D — Technical Evaluation - 101-B Cast Material | 06-Apr-25 → 01-May-25 | Complete 100% | float — EK000MBP4D EK000PI131 — Devlop Balance Tech P-Class specs for Procuremnt | 06-Apr-25 → 25-May-25 | Complete 100% | float — EK000PI131 EK000FP050 — FP Overall Firewater P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK000FP050 EK000MD43B — Develop & Issue Design Data for ERW - MD403 | 08-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MD43B EK000MU35D — Technical Evaluation - MU350 | 08-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MU35D EK000MC21D — Technical Evaluation - MC210 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MC21D EK000MC23D — Technical Evaluation - MC230 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MC23D EK000MD45B — Develop & Issue Design Data for ERW - MD405 | 08-Apr-25 → 08-May-25 | Complete 100% | float — EK000MD45B EK000MC23B — Develop & Issue Design Data for ERW - MC230 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MC23B EK000MD42B — Develop & Issue Design Data for ERW - MD402 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MD42B EK000MD41B — Develop & Issue Design Data for ERW - MD401 | 09-Apr-25 → 18-Apr-25 | Complete 100% | float — EK000MD41B EK000MU30B — Develop/Issue Load Sht & Design Data ERW - MU300 | 09-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MU30B EK000PS010 — Level III CPM Schedule / First Planner | 09-Apr-25 → 24-May-25 | Complete 100% | float — EK000PS010 EK000ML42D — Technical Evaluation - ML420 | 09-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML42D EK000MJ34F — Update/Issue Formal Inquiry for ERW - MJ304 | 09-Apr-25 → 26-Apr-25 | Complete 100% | float — EK000MJ34F EK000MB41D — Technical Evaluation - MB410 | 10-Apr-25 → 01-May-25 | Complete 100% | float — EK000MB41D EK000MJ33B — Develop/Issue Load Sht & Design Data ERW - MJ303 | 11-Apr-25 → 23-May-25 | Complete 100% | float — EK000MJ33B EK000MJ32D — Technical Evaluation - MJ302 | 12-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MJ32D EK000MJ31D — Technical Evaluation - MJ301 | 12-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MJ31D EK000MB055 — 101-B Radiant coil BOM | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MB055 EK000MB075 — 101-B Convection Coil BOM | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MB075 EK000ML51B — Develop/Issue Load Sht & Design Data ERW - ML512 | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML51B EK000MC63B — Develop & Issue Design Data for ERW - MC630 | 15-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MC63B EK000MB61E — Prepare & Issue Purchase ERW - MB610 | 15-Apr-25 → 22-Apr-25 | Complete 100% | float — EK000MB61E EK000MD43F — Update/Issue Formal Inquiry for ERW - MD403 | 15-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD43F EK000MD32D — Technical Evaluation - MD302 | 15-Apr-25 → 04-May-25 | Complete 100% | float — EK000MD32D EK000IC36D — DCS (MIV) - Tech Evaluation | 15-Apr-25 → 17-May-25 | Complete 100% | float — EK000IC36D EK000MC31P — Develop & Issue Setting Plans for ERW - MC310 | 15-Apr-25 → 28-May-25 | Complete 100% | float — EK000MC31P EK000MC21P — Develop & Issue Setting Plans for ERW - MC210 | 15-Apr-25 → 20-Jun-25 | Complete 100% | float — EK000MC21P EK000CS025 — Turnover System Definition for ISBL | 15-Apr-25 → 31-Jan-26 | Complete 100% | float — EK000CS025 EK000MD42F — Update/Issue Formal Inquiry for ERW - MD402 | 16-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML42B — Develop & Issue Design Data for ERW - ML420 | 16-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000ML42B EK000MD31D — Technical Evaluation - MD301 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD31D EK000ML33B — Develop/Issue Load Sht & Design Data ERW - ML330 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000ML33B EK000MD33D — Technical Evaluation - MD303 | 16-Apr-25 → 04-May-25 | Complete 100% | float — EK000MD33D EK000MBP3D — Technical Evaluation - 101-B Pressure Parts | 16-Apr-25 → 10-May-25 | Complete 100% | float — EK000MBP3D EK000MD21F — Develop & Issue Inquiry ERW - MD201 | 17-Apr-25 → 17-Jun-25 | Complete 100% | float — EK000MD21F EK000PR140 — Formal Issue of Process Release | 18-Apr-25 → 08-May-25 | Complete 100% | float — EK000PR140 EK000MD47P — Confirm Analytical Design for ERW - MD406 | 18-Apr-25 → 22-Apr-25 | Complete 100% | float — EK000MD47P EK000MJ37B — Develop & Issue Design Data for ERW - MJ340 | 19-Apr-25 → 09-May-25 | Complete 100% | float — EK000MJ37B EK000MD41F — Update/Issue Formal Inquiry for ERW - MD401 | 20-Apr-25 → 26-Apr-25 | Complete 100% | float — EK000MD41F EK000MD44Q — Develop Analytical Sketches for ERW - MD404 | 20-Apr-25 → 27-Apr-25 | Complete 100% | float — EK000MD44Q EK000MJ73B — Develop/Issue Load Sht & Design Data ERW - MJ730 | 20-Apr-25 → 30-Apr-25 | Complete 100% | float — EK000MJ73B EK000EV015 — Issue load sheets for wastewater systems | 20-Apr-25 → 31-May-25 | Complete 100% | float — EK000EV015 EK000MD44B — Develop & Issue Design Data for ERW - MD404 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD47B — Develop & Issue Design Data for ERW - MD406 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD46B — Develop/Issue Load Sht & Design Data ERW - MD411 | 22-Apr-25 → 03-May-25 | Complete 100% | float — EK000MD46B EK000MU11B — 05B MU311 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU11B EK000MU25B — 02G MU225 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU25B EK000MU32B — 01D MU322 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU32B EK000MD22B — Develop & Issue Design Data for ERW - MD202 | 23-Apr-25 → 01-May-25 | Complete 100% | float — EK000MD22B EK000MU31B — Develop/Issue Load Sht & Design Data ERW - MU310 | 23-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU31B EK000MC23F — Finalize Equip. Data Sheets for ERW - MC230 | 23-Apr-25 → 13-Jun-25 | Complete 100% | float — EK000MC23F EK000CV036 — Issue Geotech S/C PKG | 26-Apr-25 → 02-May-25 | Complete 100% | float — EK000CV036 EK000CV140 — Issue Site Survey S/C PKG | 26-Apr-25 → 14-May-25 | Complete 100% | float — EK000CV140 EK000CV145 — Issue Site Leveling PKG | 26-Apr-25 → 16-May-25 | Complete 100% | float — EK000CV145 EK000MD44F — Update/Issue Formal Inquiry for ERW - MD404 | 27-Apr-25 → 01-May-25 | Complete 100% | float — EK000MD44F EK000ML51F — Develop & Issue Inquiry for ERW - ML512 | 27-Apr-25 → 01-May-25 | Complete 100% | float — EK000ML51F EK000MJ31F — Update/Issue Formal Inquiry for ERW - MJ301 | 27-Apr-25 → 08-May-25 | Complete 100% | float — EK000MJ31F EK000MBP1E — Prepare & Issue Purchase ERW 101-B Shop Fab | 27-Apr-25 → 10-May-25 | Complete 100% | float — EK000MBP1E EK000ML33F — Develop & Issue Inquiry for ERW - ML330 | 27-Apr-25 → 13-May-25 | Complete 100% | float — EK000ML33F EK000MJ32F — Update/Issue Formal Inquiry for ERW - MJ302 | 27-Apr-25 → 29-May-25 | Complete 100% | float — EK000MJ32F EK000MB63F — Prepare & Issue Purchase ERW - MB630 | 27-Apr-25 → 29-May-25 | Complete 100% | float — EK000MB63F EK000MJ36B — Develop/Issue Load Sht & Design Data ERW - MJ306 | 27-Apr-25 → 08-Jun-25 | Complete 100% | float — EK000MJ36B EK000MU35B — Develop & Issue Design Data for ERW - MU350 | 01-May-25 → 14-May-25 | Complete 100% | float — EK000MU35B EK000IC010 — Make decision of FF vs. Traditional DCS system | 01-May-25 → 17-May-25 | Complete 100% | float — EK000IC010 EK000MJ75B — Develop & Issue Design Data for ERW - MJ750 | 01-May-25 → 20-May-25 | Complete 100% | float — EK000MJ75B EK000CV136 — Issue Rough Grade (Ammonia) S/C PKG | 01-May-25 → 27-May-25 | Complete 100% | float — EK000CV136 EK000MJ73F — Develop & Issue Inquiry for ERW - MJ730 | 01-May-25 → 12-Jun-25 | Complete 100% | float — EK000MJ73F EK000MD22F — Update/Issue Formal Inquiry for ERW - MD202 | 01-May-25 → 17-May-25 | Complete 100% | float — EK000MD22F EK000MC23P — Develop & Issue Setting Plans for ERW - MC230 | 01-May-25 → 21-Jun-25 | Complete 100% | float — EK000MC23P EK000MU11O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU11O EK000MU25O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU25O EK000MU310 — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU310 EK000MU32O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU32O EK000MD46P — Confirm Analytical Design for ERW - MD411 | 02-May-25 → 11-May-25 | Complete 100% | float — EK000MD46P EK000MJ34D — Technical Evaluation - MJ304 | 02-May-25 → 03-May-25 | Complete 100% | float — EK000MC32P — Develop & Issue Setting Plans for ERW - MC311 | 02-May-25 → 20-Jun-25 | Complete 100% | float — EK000MC32P EK000MU41D — Technical Evaluation - MU410 | 03-May-25 → 28-Jun-25 | Complete 100% | float — EK000MU41D EK000MD31E — Prepare & Issue Purchase ERW - MD301 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MD31E EK000MD34E — Prepare & Issue Purchase ERW - MD304 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MD34E EK000MBP4E — Prepare & Issue Purchase ERW 101-B Cast Material | 04-May-25 → 17-May-25 | Complete 100% | float — EK000MBP4E EK000PC020 — Load PCMS & Issue First Cost Report | 04-May-25 → 18-May-25 | Complete 100% | float — EK000PC020 EK000MB41E — Prepare & Issue Purchase ERW - MB410 | 04-May-25 → 20-May-25 | Complete 100% | float — EK000MB41E EK000MD32E — Prepare & Issue Purchase ERW - MD302 | 06-May-25 → 10-May-25 | Complete 100% | float — EK000MD32E EK000MD43E — Prepare & Issue Purchase ERW - MD403 | 06-May-25 → 11-May-25 | Complete 100% | float — EK000MD43E EK000MU33B — Develop/Issue Load Sht & Design Data ERW - MU330 | 07-May-25 → 20-May-25 | Complete 100% | float — EK000MU33B EK000MC31D — Technical Evaluation - MC310 | 07-May-25 → 24-May-25 | Complete 100% | float — EK000MC31D EK000MC32D — Technical Evaluation - MC311 | 07-May-25 → 24-May-25 | Complete 100% | float — EK000MC32D EK020MC31D — MC312 - (120,121-C) - Technical Evaluation | 07-May-25 → 24-May-25 | Complete 100% | float — EK020MC31D EK000MU61D — Technical Evaluation - MU611 | 07-May-25 → 20-Jun-25 | Complete 100% | float — EK000MU61D PK000PIA1C — Bulk Piping A/G & U/G - Tech Evaluation | 07-May-25 → 21-Jun-25 | Complete 100% | float — PK000PIA1C EK000MU21B — Develop/Issue Load Sht & Design Data ERW - MU221 | 08-May-25 → 10-May-25 | Complete 100% | float — EK000MU22B — Develop/Issue Load Sht & Design Data ERW - MU222 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000MU22B EK000MU29B — Develop/Issue Load Sht & Design Data ERW - MU292 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000MU29B EK000YA005 — Process Release | 08-May-25 | Complete EK000YA811 — (EP-12) Issue Process Release | 08-May-25 | Complete EK000MD51E — Prepare & Issue Purchase ERW - MD501 | 09-May-25 → 11-May-25 | Complete 100% | float — EK000MJ37F — Develop & Issue Inquiry for ERW - MJ340 | 09-May-25 → 05-Jun-25 | Complete 100% | float — EK000MJ37F EK000MJ35F — Update/Issue Formal Inquiry for ERW - MJ305 | 10-May-25 → 24-May-25 | Complete 100% | float — EK000MJ35F EK000MBP3E — Prepare & Issue Purchase ERW 101-B Pressure Part | 13-May-25 → 16-May-25 | Complete 100% | float — EK000I220A — Issue Preliminary ERW Pkg - MOV Valves | 13-May-25 → 31-May-25 | Complete 100% | float — EK000I220A EK000MD45F — Update/Issue Formal Inquiry for ERW - MD405 | 13-May-25 → 31-May-25 | Complete 100% | float — EK000MD45F EK000I354A — ITCC - Engr ERW Issued | 13-May-25 → 23-Jul-25 | Complete 100% | float — EK000I354A EK000MU30D — Technical Evaluation - MU300 | 13-May-25 → 27-Sep-25 | Complete 100% | float — EK000MU30D EK000MD46F — Update/Issue Formal Inquiry for ERW - MD411 | 14-May-25 → 31-May-25 | Complete 100% | float — EK000MD46F EK000MB62F — Prepare & Issue Purchase ERW - MB621 | 14-May-25 → 05-Jun-25 | Complete 100% | float — EK000MB62F EK000MB045 — Catalyst Vac data sheets | 20-May-25 → 28-May-25 | Complete 100% | float — EK000MB045 EK000CV065 — Review Perimeter Wall Design - IFC (by OCI) | 20-May-25 → 14-Jun-25 | Complete 100% | float — EK000CV065 EK000MJ75F — Develop & Issue Inquiry for ERW - MJ750 | 21-May-25 → 28-May-25 | Complete 100% | float — EK000MJ75F EK000YA806 — (EP-07) Issue Project Plan | 24-May-25 | Complete EK000MBG10 — General & Administrative | 28-May-25 → 27-Dec-26 | In Progress 57% | float — EK000MBG10 EK000I110D — Technical Evaluation - Orific Plates | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I110D EK000I115D — Technical Evaluation - Annubars | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I115D EK000I116D — Technical Evaluation - Wedge Flow Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I116D EK000I121D — Technical Evaluation - Vortex Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I121D EK000I122D — Technical Evaluation - Coriolis Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I122D EK000I124D — Technical Evaluation - Rotameters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I124D EK000I611D — Technical Evaluation - Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I611D EK000I612D — Technical Evaluation - Differential Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I612D EK000I616D — Technical Evaluation - Steam Drum Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I616D EK000I617D — Technical Evaluation - Magnetic Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I617D EK000MJ33F — Develop & Issue Inquiry for ERW - MJ303 | 28-May-25 → 18-Jun-25 | Complete 100% | float — EK000MJ33F EK000MJ36F — Update/Issue Formal Inquiry for ERW - MJ306 | 28-May-25 → 19-Jun-25 | Complete 100% | float — EK000MJ36F EK000I127D — Magnetic Flow Meters - Technical Evaluation | 28-May-25 → 26-Jun-25 | Complete 100% | float — EK000I127D EK000MB33D — MB333 - Technical Evaluation 101-B | 28-May-25 → 01-Jul-25 | Complete 100% | float — EK000MB33D EK000YA801 — (EP-02) Issue 30 day Look Ahead Schedule | 28-May-25 | Complete EK000MJ75D — Technical Evaluation - MJ750 | 29-May-25 → 30-May-25 | Complete 100% | float — EK000ML43F — Develop & Issue Inquiry for ERW - ML430 | 31-May-25 → 06-Jun-25 | Complete 100% | float — EK000ML43F EK000MB69F — Prepare & IssuePurchase ERW - MB691 | 03-Jun-25 → 17-Jun-25 | Complete 100% | float — EK000MB69F EK000MU33D — Technical Evaluation - MU330 | 04-Jun-25 → 01-Jul-25 | Complete 100% | float — EK000MU33D EK000QM025 — Training - Management System | 05-Jun-25 → 05-Jun-25 | Complete 100% | float — EK000I230A — Issue Preliminary ERW Pkg - On/Off Valves | 05-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000I230A EK000PS040 — Incorporate Comments / Issue Baseline Schedule | 05-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000PS040 EK000MU22F — Develop & Issue Inquiry for ERW - MU222 | 05-Jun-25 → 26-Jun-25 | Complete 100% | float — EK000MU22F EK000MB65F — Develop & Issue Purchase ERW - MB622 | 06-Jun-25 → 17-Jun-25 | Complete 100% | float — EK000MB65F PK000PIA4C — Product Line Piping - Tech Evaluation | 07-Jun-25 → 04-Jul-25 | Complete 100% | float — PK000PIA4C EK000I112D — Technical Evaluation - Venturis | 10-Jun-25 → 14-Jun-25 | Complete 100% | float — EK000I112D EK000PS030 — Schedule Risk Analysis | 10-Jun-25 → 20-Jun-25 | Complete 100% | float — EK000PS030 EK000MB66F — Prepare & IssuePurchase ERW - MB660 | 10-Jun-25 → 21-Jun-25 | Complete 100% | float — EK000MB66F EK000MU34B — Develop/Issue Load Sht & Design Data ERW - Chlorination Unit | 11-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000MU34B EK000MB68F — Prepare & Issue Purchase ERW - MB692 | 13-Jun-25 → 26-Jun-25 | Complete 100% | float — EK000MB68F EK000MB21F — Prepare & Issue Purchase ERW - MB212 | 17-Jun-25 → 25-Jun-25 | Complete 100% | float — EK000MB21F EK000MB42F — Prepare & Issue Purchase ERW - MB420 | 17-Jun-25 → 26-Jun-25 | Complete 100% | float — EK000MB42F EK000FP055 — FP Overall Firewater P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK000FP055 EK000MB34F — Prepare & Issue Purchase ERW - MB340 | 20-Jun-25 → 21-Jun-25 | Complete 100% | float — EK000I221D — 000 Everest Control Valves - Technical Evaluation | 25-Jun-25 → 10-Jul-25 | Complete 100% | float — EK000I221D EK000YA809 — (EP-10) Locate Utility Tie-Ins | 26-Jun-25 | Complete EK000MU21F — Develop & Issue Inquiry for ERW - MU221 | 26-Jun-25 → 03-Jul-25 | Complete 100% | float — EK000MU21F EK000MD33E — Prepare & Issue Purchase ERW - MD303 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — EK000MD41E — Prepare & Issue Purchase ERW - MD401 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — EK000MB64F — Prepare & Issue Purchase ERW - MB640 | 02-Jul-25 → 11-Jul-25 | Complete 100% | float — EK000MB64F EK000ML33D — Technical Evaluation - ML330 | 10-Jul-25 → 23-Aug-25 | Complete 100% | float — EK000ML33D EK000ML43D — Technical Evaluation - ML430 | 10-Jul-25 → 06-Sep-25 | Complete 100% | float — EK000ML43D EK000I220D — Technical Evaluation - MOV's | 16-Jul-25 → 23-Jul-25 | Complete 100% | float — EK000I220D EK000MD21D — Technical Evaluation - MD201 | 16-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000MD21D EK000I230D — Technical Evaluation - On/Off Valves | 17-Jul-25 → 24-Jul-25 | Complete 100% | float — EK000I230D EK000MB65D — Technical Evaluation - MB622 | 19-Jul-25 → 02-Aug-25 | Complete 100% | float — EK000MB65D EK000I618D — Technical Evaluation - Temperature Gauges | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I618D EK000I621D — Technical Evaluation - Temperature Elements | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I621D EK000I623D — Technical Evaluation - Multi-Point Thermocouples | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I623D EK000I352A — SIS - Engr ERW Issued | 22-Jul-25 → 02-Aug-25 | Complete 100% | float — EK000I352A EK000MB69D — Technical Evaluation - MB691 | 22-Jul-25 → 07-Aug-25 | Complete 100% | float — EK000MB69D EK000MU22D — Technical Evaluation - MU222 | 22-Jul-25 → 06-Sep-25 | Complete 100% | float — EK000MU22D EK000MJ37D — Technical Evaluation - MJ340 | 24-Jul-25 → 28-Aug-25 | Complete 100% | float — EK000MJ37D EK000MJ39D — Technical Evaluation - MJ391 | 25-Jul-25 → 21-Dec-25 | Complete 100% | float — EK000MJ39D EK000MJ31X — Technical Evaluation - MJ301 | 25-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000MJ31X PK000MJ32X — Technical Evaluation - MJ302 | 25-Jul-25 → 10-Aug-25 | Complete 100% | float — PK000MJ32X EK000MU11L — 05B MU311 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU11L EK000MU25L — 02G MU225 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU25L EK000MU32L — 01D MU322 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU32L EK000MB68D — Technical Evaluation - MB692 | 29-Jul-25 → 30-Aug-25 | Complete 100% | float — EK000MB68D EK000MU31L — Define Chemical Treatment Requirements - MU310 | 30-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000MU31L EK000MB66D — Technical Evaluation - MB660 | 30-Jul-25 → 13-Aug-25 | Complete 100% | float — EK000MB66D EK000MB34D — Technical Evaluation - MB340 | 30-Jul-25 → 13-Aug-25 | Complete 100% | float — EK000MB34D EK000ML51D — Technical Evaluation - ML512 | 30-Jul-25 → 19-Aug-25 | Complete 100% | float — EK000ML51D EK000MU21D — Technical Evaluation - MU221 | 30-Jul-25 → 14-Sep-25 | Complete 100% | float — EK000MU21D EK000MU35E — Prepare & Issue Purchase ERW - MU350 | 01-Aug-25 → 13-Aug-25 | Complete 100% | float — EK000MU35E EK000YA810 — (EP-11) Issue Level 3 CPM Schedule | 03-Aug-25 | Complete EK000QM005 — Training - Object Engineering | 06-Aug-25 → 13-Aug-25 | Complete 100% | float — EK000QM005 EK000I444A — Develop & Issue Inquiry ERW - Analyzer Shelter | 06-Aug-25 → 17-Aug-25 | Complete 100% | float — EK000I444A EK000MJ73D — Technical Evaluation - MJ730 | 06-Aug-25 → 16-Sep-25 | Complete 100% | float — EK000MJ73D EK000CV165 — Issue ISBL Rough Grade Design Pkg. | 09-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000CV165 PK000MJ21N — Recv. Planning V. Data MJ202 | 09-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000MJ21N PK000MJ75N — Recv. Planning V. Data MJ750 | 09-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000MJ75N PK000MD31N — Recv. Planning V. Data MD301 | 09-Aug-25 → 09-Sep-25 | Complete 100% | float — PK000MD31N PK000ML31N — Recv. Planning V. Data ML313 | 09-Aug-25 → 12-Sep-25 | Complete 100% | float — PK000ML31N PK000MD41N — Recv. Planning V. Data MD401 | 09-Aug-25 → 17-Sep-25 | Complete 100% | float — PK000MD41N PK000MD33N — Recv. Planning V. Data MD303 | 09-Aug-25 → 25-Sep-25 | Complete 100% | float — PK000MD33N PK000MD43N — Recv. Planning V. Data MD403 | 09-Aug-25 → 14-Oct-25 | Complete 100% | float — PK000MD43N EK000MB64D — Technical Evaluation - MB640 | 09-Aug-25 → 17-Oct-25 | Complete 100% | float — EK000MB64D EK000EB015 — Notice to Proceed (Eng. & Procurement Only) | 10-Aug-25 | Complete EK000I221A — 000 Everest Control Valves - Issue Inquiry Req | 12-Aug-25 → 16-Aug-25 | Complete 100% | float — EK000I221A EK000MJ21E — Prepare & Issue Purchase ERW - MJ202 | 12-Aug-25 → 30-Aug-25 | Complete 100% | float — EK000MJ21E PK000MU35N — Recv. Planning V. Data MU350 | 12-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MU35N EK000IC350 — DCS - Develop Design Basis | 12-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000IC350 EK000MU61E — Prepare & Issue Purchase ERW - MU611 | 13-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000PTA0F — Engineered Pipe Supports - Planning V. Data | 14-Aug-25 → 24-Jan-26 | Complete 100% | float — PK000PTA0F PK000MD32N — Recv. Planning V. Data MD302 | 16-Aug-25 → 02-Oct-25 | Complete 100% | float — PK000MD32N PK000MD34N — Recv. Planning V. Data MD304 | 16-Aug-25 → 12-Nov-25 | Complete 100% | float — PK000MD34N EK000MJ75E — Prepare & Issue Purchase ERW - MJ750 | 19-Aug-25 → 28-Sep-25 | Complete 100% | float — EK000MJ75E EK000PE070 — Kick-off meeting at MEC | 22-Aug-25 → 23-Aug-25 | Complete 100% | float — PK000MJ35N — Recv. Planning V. Data MJ305 | 23-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MJ35N PK000MJ36N — Recv. Planning V. Data MJ306 | 23-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MJ36N EK000MD21E — Prepare & Issue Purchase ERW - MD201 | 27-Aug-25 → 29-Aug-25 | Complete 100% | float — PK000MD51N — Recv. Planning V. Data MD501 | 27-Aug-25 → 01-Nov-25 | Complete 100% | float — PK000MD51N EK000MB21D — Technical Evaluation - MB212 | 29-Aug-25 → 01-Nov-25 | Complete 100% | float — EK000MB21D EK000MJ33D — Technical Evaluation - MJ303 | 30-Aug-25 → 19-Dec-25 | Complete 100% | float — EK000MJ33D PK000MU21N — Recv. Planning V. Data MU221 | 01-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MU21N PK000ML42N — Recv. Planning V. Data ML420 | 02-Sep-25 → 26-Sep-25 | Complete 100% | float — PK000ML42N PK000MJ32N — Recv. Planning V. Data MJ302 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ32N PK000MJ34N — Recv. Planning V. Data MJ304 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ34N PK000MJ37N — Recv. Planning V. Data MJ340 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ37N PK000MJ39N — Recv. Planning V. Data MJ391 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ39N PK000MJ73N — Recv. Planning V. Data MJ730 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ73N PK000MU22N — Recv. Planning V. Data MU222 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MU22N EK000MB095 — 101-B Ducting Detail Drawings - IFF | 02-Sep-25 → 05-Apr-26 | Complete 100% | float — EK000MB095 EK000MD055 — Pre-qualification trip to vendors shop (105-D) | 03-Sep-25 → 05-Sep-25 | Complete 100% | float — EK000MU41E — Prepare & Issue Purchase ERW - MU410 | 03-Sep-25 → 05-Sep-25 | Complete 100% | float — PK000MU61N — Recv. Planning V. Data MU611 | 03-Sep-25 → 26-Sep-25 | Complete 100% | float — PK000MU61N PK000MJ22N — Recv. Planning V. Data MJ201 | 05-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ22N PK000MJ31N — Recv. Planning V. Data MJ301 | 06-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ31N PK000MC61N — Recv. Planning V. Data MC610 | 10-Sep-25 → 03-Dec-25 | Complete 100% | float — PK000MC61N EK000CV137 — Issue OSBL Rough Grade Design Pkg. | 11-Sep-25 → 26-Nov-25 | Complete 100% | float — EK000CV137 EK000ML51E — Prepare & Issue Purchase ERW - ML512 | 11-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000ML51E PK000ML51N — Recv. Planning V. Data ML512 | 11-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000ML51N EK000MJ36E — Prepare & Issue Purchase ERW - MJ306 | 13-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000MJ36E EK000MJ35E — Prepare & Issue Purchase ERW - MJ305 | 13-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000MJ35E EK000MJ22E — Prepare & Issue Purchase ERW - MJ201 | 13-Sep-25 → 13-Nov-25 | Complete 100% | float — EK000MJ22E EK000I444D — Technical Evaluation - Analyzer Shelter | 16-Sep-25 → 11-Dec-25 | Complete 100% | float — EK000I444D EK000ML33E — Prepare & Issue Purchase ERW - ML330 | 17-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000ML33E PK000MU41N — Recv. Planning V. Data MU410 | 17-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MU41N EK020PR20D — PR201 KAAP Catalyst - Technical Evaluation | 17-Sep-25 → 01-Nov-25 | Complete 100% | float — EK020PR20D EK000MC61E — Prepare & Issue Purchase ERW - MC610 | 18-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000MC61E EK000MJ32E — Prepare & Issue Purchase ERW - MJ302 | 20-Sep-25 → 13-Nov-25 | Complete 100% | float — EK000MJ32E PK000ML33N — Recv. Planning V. Data ML330 | 20-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000ML33N PK000ML43N — Recv. Planning V. Data ML430 | 20-Sep-25 → 01-Nov-25 | Complete 100% | float — PK000ML43N EK000MJ34E — Prepare & Issue Final Data Shts - MJ304 | 21-Sep-25 → 08-Nov-25 | Complete 100% | float — EK000MJ34E EK000MU33E — Prepare & Issue Purchase ERW - MU330 | 21-Sep-25 → 26-Sep-25 | Complete 100% | float — EK000MU33E EK020MC31C — MC312 - (120,121-C) - Prepare & Issue Purchase ERW | 23-Sep-25 → 27-Sep-25 | Complete 100% | float — EK020MC31C PK020MC31F — MC312 - (120,121-C) - Planning V. Data (Setting Plans) | 23-Sep-25 → 08-Oct-25 | Complete 100% | float — PK020MC31F EK000MU31D — Technical Evaluation - MU310 | 24-Sep-25 → 30-Sep-25 | Complete 100% | float — EK000MU31D EK000MC23E — Prepare & Issue Purchase ERW - MC230 | 30-Sep-25 → 15-Oct-25 | Complete 100% | float — EK000MC23E EK000I352D — SIS - Tech Evaluation | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000I352D EK000MC21E — Prepare & Issue Purchase ERW - MC210 | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000MC21E EK000MU30E — Prepare & Issue Purchase ERW - MU300 | 01-Oct-25 → 14-Oct-25 | Complete 100% | float — EK000MU30E EK000ML42E — Prepare & Issue Purchase ERW - ML420 | 01-Oct-25 → 10-Oct-25 | Complete 100% | float — EK000ML42E EK000MJ37E — Prepare & Issue Purchase ERW - MJ340 | 01-Oct-25 → 16-Oct-25 | Complete 100% | float — EK000MJ37E EK000MU31E — Prepare & Issue Purchase ERW - MU310 | 04-Oct-25 → 08-Oct-25 | Complete 100% | float — EK000MU31E EK000IC351 — DCS - Develop Purchase T-Req | 05-Oct-25 → 07-Nov-25 | Complete 100% | float — EK000IC351 EK000PR600 — MD305 Merc. Removal Bed - Develop & Issue Load Sheets for ERW | 08-Oct-25 → 09-Oct-25 | Complete 100% | float — EK000MJ31E — Prepare & Issue Purchase ERW - MJ301 | 08-Oct-25 → 13-Nov-25 | Complete 100% | float — EK000MJ31E PK000MJ33N — Recv. Planning V. Data MJ303 | 08-Oct-25 → 26-Dec-25 | Complete 100% | float — PK000MJ33N EK000ML31E — Prepare & Issue Purchase ERW - ML313 | 08-Oct-25 → 09-Jan-26 | Complete 100% | float — EK000ML31E EK020ELEG2 — Cathodic Protection - Subcontract Consultant ERW Package | 09-Oct-25 → 01-Mar-26 | Complete 100% | float — EK020ELEG2 EK000MC32E — Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4) | 10-Oct-25 → 15-Nov-25 | Complete 100% | float — EK000MC32E EK000MD103 — MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW | 10-Oct-25 → 26-Nov-25 | Complete 100% | float — EK000MD103 EK000PR610 — MD305 Merc. Removal Bed - Analytical Design | 10-Oct-25 → 26-Nov-25 | Complete 100% | float — EK000PR610 EK000YA813 — (EP-14) Issue Plot Plans for Client Approval | 11-Oct-25 | Complete EK000I354D — ITCC - Tech Evaluation | 15-Oct-25 → 12-Dec-25 | Complete 100% | float — EK000I354D EK000MB42D — Technical Evaluation - MB420 | 16-Oct-25 → 30-Oct-25 | Complete 100% | float — EK000MB42D PK000IC35J — DCS - Planning V. Data | 17-Oct-25 → 27-Dec-26 | In Progress 43% | float — PK000IC35J PK000MU33N — 03E MU330 2001-U - Piping Conceptual V. Data | 30-Oct-25 → 02-Feb-26 | Complete 100% | float — PK000MU33N EK000ML43E — Prepare & Issue Purchase ERW - ML430 | 01-Nov-25 → 07-Nov-25 | Complete 100% | float — EK000ML43E EK000MJ37R — Develop & Issue Load Sheets for ERW - MJ307 | 04-Nov-25 → 08-Nov-25 | Complete 100% | float — EK000MJ37R EK000MJ38R — Develop & Issue Load Sheets for ERW - MJ308 | 04-Nov-25 → 08-Nov-25 | Complete 100% | float — EK000MJ38R EK000MU21E — Prepare & Issue Purchase ERW - MU221 | 05-Nov-25 → 22-Nov-25 | Complete 100% | float — EK000MU21E EK000MU22E — Prepare & Issue Purchase ERW - MU222 | 05-Nov-25 → 22-Nov-25 | Complete 100% | float — EK000MU22E EK000MU29F — Develop & Issue Inquiry for ERW - MU292 | 05-Nov-25 → 23-Nov-25 | Complete 100% | float — EK000MU29F EK000MJ37S — Develop & Issue Design Data for ERW - MJ307 | 11-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000MJ37S EK000MJ38S — Develop & Issue Design Data for ERW - MJ308 | 11-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000MJ38S EK000IC352 — DCS - Final Tech Evaluation for Purchase | 13-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000MJ37T — Update/Issue Formal Inquiry for ERW - MJ307 | 18-Nov-25 → 26-Nov-25 | Complete 100% | float — EK000MJ37T EK000MJ73E — Prepare & Issue Purchase ERW - MJ730 | 19-Nov-25 → 05-Dec-25 | Complete 100% | float — EK000MJ73E EK000FA005 — Issue First Invoice to EBIC | 19-Nov-25 | Complete PK000MU30N — Recv. Planning V. Data MU300 - EDR Unit | 19-Nov-25 → 10-Jan-26 | Complete 100% | float — PK000MU30N EK000E001A — Sub Stations - Issue ERW | 22-Nov-25 → 31-Dec-25 | Complete 100% | float — EK000E001A EK000MD102 — MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur. | 26-Nov-25 → 05-Dec-25 | Complete 100% | float — EK000MD102 EK000ML50Z — Technical Evaluation - ML500 | 10-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000ML50Z EK000E002A — Transformer - Issue ERW | 18-Dec-25 → 30-Dec-25 | Complete 100% | float — EK000E002A EK000MJ33E — Prepare & Issue Purchase ERW - MJ303 | 19-Dec-25 → 27-Dec-25 | Complete 100% | float — EK000MJ33E PK000PSA8C — 000 Relief Valves - Technical Evaluation | 23-Dec-25 → 27-Dec-25 | Complete 100% | float — PK000PSA8C EK000MU32D — 01D MU322 Technical Evaluation | 23-Dec-25 → 31-Jan-26 | Complete 100% | float — EK000MU32D EK000ELEJ1 — Lighting, Installation Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000ELEK1 — A/G Power & Control, Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000GE025 — First Check Estimate | 30-Dec-25 → 27-Feb-26 | Complete 100% | float — EK000GE025 EK000MU11D — 05B MU311 Technical Evaluation | 03-Jan-26 → 01-Feb-26 | Complete 100% | float — EK000MU11D EK000MC31E — Prepare & Issue Purchase ERW - MC310 | 03-Jan-26 → 12-Feb-26 | Complete 100% | float — EK000MC31E EK000MD104 — MD305 Merc. Removal Bed - Technical Evaluation | 13-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000MD104 EK000IC353 — DCS - Software Programming by KBR | 15-Jan-26 → 27-Dec-26 | In Progress 29% | float — EK000IC353 EK000CV045 — Prepare Foundation Design Criteria | 16-Jan-26 → 14-Mar-26 | Complete 100% | float — EK000CV045 EK000MJ37C — Prepare & Issue Purchase ERW - MJ307 | 17-Jan-26 → 20-Jan-26 | Complete 100% | float — EK000MU29D — Technical Evaluation - MU292 | 20-Jan-26 → 03-Mar-26 | Complete 100% | float — EK000MU29D PK000PTA0H — Engineered Pipe Supports - Production V. Data | 24-Jan-26 → 29-Jan-26 | Complete 100% | float — PK000PTA0H EK000SY095 — 010 P&ID's - Tech Review | 28-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000I3540 — ITCC - Develop Final Design Basis | 28-Jan-26 → 04-Mar-26 | Complete 100% | float — EK000I3540 EK000I3520 — SIS - Develop Final Design Basis | 28-Jan-26 → 12-Mar-26 | Complete 100% | float — EK000I3520 EK000MU25D — 02G MU225 Technical Evaluation | 28-Jan-26 → 21-Feb-26 | Complete 100% | float — EK000MU25D EK000MD105 — MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW | 29-Jan-26 → 01-Feb-26 | Complete 100% | float — PK000ML50N — Recv. Planning V. Data ML500 | 29-Jan-26 → 24-Feb-26 | Complete 100% | float — PK000ML50N EK010E008A — 540-SB Admin. Area Pwr Supply - ERW Package | 01-Feb-26 → 14-Feb-26 | Complete 100% | float — EK010E008A EK00012210 — 000 Everest Control Valves - D/S,Sizing,Tech Eval | 03-Feb-26 → 05-Mar-26 | Complete 100% | float — EK00012210 EK000YA822 — (EP-22) Issue for Planning (IPL) >90% OSBL P&ID's | 09-Feb-26 | Complete EK000YA824 — (EP-23) Issue For Planning (IPL) >90% ISBL P&ID's | 09-Feb-26 | Complete EK000MU11E — 05B MU311 Prepare & Issue Purchase ERW | 11-Feb-26 → 13-Feb-26 | Complete 100% | float — EK000PS00C — 000 SP Items - Technical Evaluation | 11-Feb-26 → 01-Mar-26 | Complete 100% | float — EK000PS00C PK000MU11N — 05B MU311 Recv. Planning V. Data | 13-Feb-26 → 28-Feb-26 | Complete 100% | float — PK000MU11N EK000I444B — Develop Final Design Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000I444B EK000I444M — Develop Final Deign Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000I444M EK000E004A — UPS System - Issue ERW | 17-Feb-26 → 28-Mar-26 | Complete 100% | float — EK000E004A EK000E001D — Sub Stations - Tech Evaluation | 19-Feb-26 → 27-Dec-26 | In Progress 21% | float — EK000E001D EK000CS027 — Turnover System Definition for OSBL | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000CS027 EK000I444F — Planning V. Data - Shelters/ Analyzers | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000I444F PK000I352J — SIS - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I352J PK000I354J — ITCC - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I354J EK000MJ38T — Update/Issue Formal Inquiry for ERW - MJ308 | 25-Feb-26 → 03-Mar-26 | Complete 100% | float — EK000MJ38T EK000ML50E — Prepare & Issue Purchase ERW - ML500 | 25-Feb-26 → 08-Mar-26 | Complete 100% | float — EK000ML50E EK000YA831 — (EP-26) Complete Hazard Review Meeting on >90% ISBL P&ID's | 25-Feb-26 | Complete EK000MJ39E — Prepare & Issue Purchase ERW - MJ391 | 27-Feb-26 → 09-Apr-26 | Complete 100% | float — EK000MJ39E EK000I3541 — ITCC - Develop Purchase T-Req | 27-Feb-26 → 05-Mar-26 | Complete 100% | float — EK000I3541 EK000E002D — Transformer - Tech Evaluation | 04-Mar-26 → 27-Dec-26 | In Progress 17% | float — EK000E002D EK000YA826 — (EP-27) Begin Issuing Area Line Installation Details (IDF Files) | 04-Mar-26 | Complete EK000I221F — 000 Everest Control Valves - Purchase ERW | 11-Mar-26 → 27-Dec-26 | In Progress 15% | float — EK000I221F PK000MU29N — Recv. Planning V. Data MU292 | 19-Mar-26 → 09-Apr-26 | Complete 100% | float — PK000MU29N EK000MU29E — Prepare & Issue Purchase ERW - MU292 | 24-Mar-26 → 27-Mar-26 | Complete 100% | float — EK000MU32E — 01D MU322 Prepare & Issue Purchase ERW | 31-Mar-26 → 31-Mar-26 | Complete 100% | float — EK000I3521 — SIS - Develop Purchase T-Req | 31-Mar-26 → 03-Apr-26 | Complete 100% | float — EK000MU25E — 02G MU225 Prepare & Issue Purchase ERW | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EK000MU25E EK000I3542 — ITCC - Final Tech Evaluation for Purchase | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK000I444C — Develop / Issue T-Req - Shelters/ Analyzers | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK010E008D — 540-SB Admin. Area Pwr Supply - Tech Evaluation | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — EK010E008D EK000I3523 — SIS - Software Programming by KBR | 18-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK000I3523 EK000MJ38C — Prepare & Issue Purchase ERW - MJ308 | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK000MJ38C EK000E004D — UPS System - Tech Evaluation | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000ELEG0 — Electrical Heat Tracing - ERW Package | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP060 — FP Overall Firewater P&IDs - Development & Issue IFD | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP065 — FP Overall Firewater P&IDs - Development & Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000GE030 — Production Check Estimate | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I3522 — SIS - Final Tech Evaluation for Purchase | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I352M — SIS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I354M — ITCC - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444E — Final Tech Evaluation - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444G — Review / Approve V. Data - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000YA832 — (EP-32) Issue OSBL (Units01/03) found./UG pipe work package | 27-Dec-26 | Not Started EK000YA833 — (EP-33) Issue > 90% ISBL Civil Foundations | 27-Dec-26 | Not Started EK000YA839 — (EP-35) Issue >90% OSBL P&ID's For Construction (IFC) | 27-Dec-26 | Not Started EK000YA841 — (EP-29) Issue OSBL Plot Plan for Construction (IFC) | 27-Dec-26 | Not Started EK000YA848 — (EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC) | 27-Dec-26 | Not Started EK000YA888 — (TLA-02) Second TLA Payment | 27-Dec-26 | Not Started EK020ELEG5 — Cathodic Protection - Design & Specs Package (By Consultant) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001J — Sub Stations - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002J — Transformer - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004J — UPS System - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000IC35M — DCS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008J — 540-SG Admin. Area Pwr Supply - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000YA500 — Issue ISBL Paint & Insulation Work Package | 28-Dec-26 → 08-Mar-27 | Not Started 0% | float 750.0d EK000YA500 EK000ELEGP — Electrical Heat Tracing - Design & BOM by Consultant | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 91.0d EK000ELEGP EK000ELEN1 — 01,03,04 LV Wiring Diagrams - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN1 EK000ELEN2 — 01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN2 EK000ELEN3 — 01,03, Equipment Interconnection Diagrams - IFC | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EK000ELEN3 EK020ELEG6 — Cathodic Protection - Material Supply (By Consultant) | 30-Dec-26 → 02-May-27 | Not Started 0% | float 6.0d EK020ELEG6 EK000PI200 — Final Delta Piping Bulk Quanities for Purchase | 03-Jan-27 | Not Started EK000YA838 — (EP-34) Issue >90% ISBL P&ID's For Construction (IFC) | 03-Jan-27 | Not Started EK000YA030 — Last PDS Planning Release | 24-Jan-27 | Not Started EK000YA040 — Engineering 95% Complete | 30-Jan-27 | Not Started PK000E001Z — Sub Stations - FAT | 17-Feb-27 → 28-Feb-27 | Not Started 0% | float 62.0d PK000E001Z EK000YA835 — (EP-36) Issue >90% Area Line Installation Details | 21-Feb-27 | Not Started EK000YA847 — (EP-39) Issue >90% OSBL Electrical Design Drawings | 21-Feb-27 | Not Started EK000YA889 — (TLA-03) Complete > TLA Payments | 03-May-27 | Not Started