EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 83
activities
in 05 Dock / Storage
× clear
Code
Activity
Start
Finish
Flt
%
EK05BEL150
Switchgear One line diagrams - ICA Dock
12-Feb-25
15-Nov-25
—
100%
EK05BEL170
MCC One line diagrams - ICA Dock
12-Feb-25
22-Nov-25
—
100%
EK050PI005
Develop Plot Plan & ID Areas - Dock/Storage IFI
02-Mar-25
09-Mar-25
—
100%
EK000MF32A
05A MF312 2105-F Water Tank - Process Load Sht.
19-Mar-25
26-Mar-25
—
100%
EK050PI010
Develop Plot Plan & ID Areas - Dock/Storage ICA
23-Mar-25
11-Oct-25
—
100%
EK000MF32C
05A MF312 2105-F Water Tank - Issue Data for Subcontract
27-Mar-25
09-Apr-25
—
100%
EK050SY020
050 Dock/Storage P&ID development IDR Issue
06-Apr-25
25-Apr-25
—
100%
EK050SY030
050 Dock/Storage P&ID IDR Meeting milestone
02-May-25
03-May-25
—
100%
EK050SY040
050 Dock/Storage P&IDs - ICA Issue development
04-May-25
20-Jun-25
—
100%
EK05BPI030
05B Conceptual Layout - Supersketches
07-May-25
27-Dec-26
—
59%
PK000MJ37Q
Prepare & Issue Prelim. RFQ - MJ307 to Proc.
31-May-25
12-Jun-25
—
100%
EK050SY050
050 Dock/Storage P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
—
100%
EK050SY060
050 Dock/Storage P&ID's - IPL Issue Development
25-Jun-25
11-Oct-25
—
100%
PK000MJ37E
Technical Evaluation - MJ307
19-Jul-25
06-Dec-25
—
100%
EK050SY135
050 Dock/Storage CV & FE Process Data
01-Aug-25
15-Aug-25
—
100%
EK05API030
05A Conceptual Layout - Supersketches
12-Aug-25
28-Sep-25
—
100%
EK050SY150
050 Relief Valve Calculations - Dock/Storage
20-Aug-25
25-Sep-25
—
100%
EK050PI012
Plot Plan - Dock/Storage Issue IPL
16-Sep-25
26-Oct-25
—
100%
PK05AMJ154
05A Recv. Planning V. Data - Pumps 2106/7-J
17-Sep-25
17-Sep-25
—
100%
EK050SY185
050 SP Item Data Sheets - Dock/Storage
25-Sep-25
24-Dec-25
—
100%
PK05AML100
05A Recv. Planning V. Data - Special Equip.
01-Oct-25
01-Oct-25
—
100%
PK05BML100
05B Recv. Planning V. Data - Special Equip. 2102-L
01-Oct-25
01-Oct-25
—
100%
EK050I1100
050 Orific Plates - D/S Dock/Storage Area
04-Oct-25
05-Nov-25
—
100%
EK050SY155
050 Issue Requisition - PSA08 Relief Valves - Dock/Storage
05-Oct-25
19-Nov-25
—
100%
EK050SY090
050 Dock/Storage P&IDs IPL Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK05ASY170
05A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK05BSY170
05B OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK050PI011
Plot Plan - Dock/Storage Client ICA Approval
11-Oct-25
26-Oct-25
—
100%
EK05BEL175
Client Review of MCC Oneline Diagrams
11-Nov-25
22-Nov-25
—
100%
EK05BEL155
Client Review of Switchgear Oneline Diagrams
14-Nov-25
22-Nov-25
—
100%
EK05BELED0
Substation Building Layout
28-Dec-25
31-Dec-25
—
100%
PK05AMLV01
05A ML330 2101-L - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV02
05A ML330 2101-L - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV03
05A ML330 2101-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05BMLV03
05B ML512 2102-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMJV01
05A MJ305 2106-J,2107-J - Piping Prod. V. Data
31-Dec-25
03-Mar-26
—
100%
EK050I1105
050 Orific Plates - Purchase ERW Dock/Storage Area
31-Dec-25
11-Mar-26
—
100%
PK05AMJV02
05A MJ305 2106-J,2107-J - Civil Prod. V. Data
31-Dec-25
20-Mar-26
—
100%
PK05AMJV03
05A MJ305 2106-J,2107-J - E&I Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK05BMLV01
05B ML512 2102-L - Piping Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK05BMLV02
05B ML512 2102-L - Civil Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
EK05AIC300
05A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK05BIC300
05B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
PK000MJ38Q
Prepare & Issue Prelim. RFQ - MJ308 to Proc.
01-Jan-26
13-Jan-26
—
100%
EK050PI013
Plot Plan - Dock/Storage Issue IPL
01-Jan-26
23-Jan-26
—
100%
PK05AMJV04
05A MJ307 2100-JA/JB - Piping Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV05
05A MJ307 2100-JA/JB - Civil Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV06
05A MJ307 2100-JA/JB - E&I Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK000MJ37T
Recv. Planning V. Data MJ307
20-Jan-26
23-Jan-26
—
100%
EK050PI014
Plot Plan - Dock/Storage Issue IFC
28-Jan-26
27-Dec-26
—
26%
PK000MJ38E
Technical Evaluation - MJ308
10-Feb-26
27-Mar-26
—
100%
PK05AMF05
05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract)
11-Feb-26
27-Dec-26
—
23%
PK000MF32D
05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK05AMF33
05A MF312 2105-F - Piping Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK05AMF34
05A MF312 2105-F - Civil Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK05AMF35
05A MF312 2105-F - E&I Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK05AMLV04
05A ML501 2103-L - Piping Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV05
05A ML501 2103-L - Civil Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV06
05A ML501 2103-L - E&I Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05BMU06
05B MU311 2109-LA/LB, 2110-L - Piping Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
PK05BMU07
05B MU311 2109-LA/LB, 2110-L - Civil Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
EK050PI006
Site Data Needed - Loading Area (SPDC)
18-Mar-26
27-Dec-26
—
13%
PK05AMJV07
05A MJ392 2105-JA/JB - Piping Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV08
05A MJ392 2105-JA/JB - Civil Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV09
05A MJ392 2105-JA/JB - E&I Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMB46
05A MB710 2202-B/BL - Piping Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK05AMB47
05A MB710 2202-B/BL - Civil Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK05AMB48
05A MB710 2202-B/BL - E&I Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
EK05BEL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK05BEL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK05AIC120
05A Instrument Detail Model / Review
22-Apr-26
27-Dec-26
—
5%
PK000MJ38T
Recv. Planning V. Data MJ308
23-Apr-26
27-Dec-26
—
5%
EK000CV146
Receive Site Survey Data Areas 04 & 05
27-Dec-26
27-Dec-26
—
0%
EK05API050
05A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK05BPI035
05B Plot Plan
27-Dec-26
27-Dec-26
—
0%
PK05AMF25
05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract)
27-Dec-26
27-Dec-26
—
0%
PK05AMJV10
05A MJ731 2108-J - Civil Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK05AMJV11
05A MJ731 2108-J - E&I Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
EK05ACV200
05A Redesign Piling & Ammonia Tank Foundations
30-Dec-26
10-Jan-27
-44.0d
0%
EK05BIC120
05B Instrument Model
30-Dec-26
30-Dec-26
110.0d
0%
EK05BPI050
05B Model Comment Resolution Approval
15-Jan-27
17-Jan-27
75.0d
0%
EK05BEL165
Switchgear One line Diagrams - IFC
27-Jan-27
30-Jan-27
276.0d
0%
EK05BEL185
MCC One line Diagrams - IFC
27-Jan-27
30-Jan-27
286.0d
0%