Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in 04 Corridor × clear
Code
Activity
Start
Finish
Flt
%
EK04API030
04A Conceptual Layout - Supersketches
27-Sep-25
27-Dec-26
46%
EK04ASY170
04A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
100%
EK04AIC300
04A In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
100%
EK04AIC120
04A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec Data Date
EK04API030 — 04A Conceptual Layout - Supersketches | 27-Sep-25 → 27-Dec-26 | In Progress 46% | float — EK04API030 EK04ASY170 — 04A OSBL P&IDs IPL & Line List Issue Milestone | 11-Oct-25 | Complete EK04AIC300 — 04A In Line Instrument Approved Vendor Data | 01-Jan-26 → 15-Apr-26 | Complete 100% | float — EK04AIC300 EK04AIC120 — 04A Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —