EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in 04 Corridor × clear
Code
Activity
Start
Finish
Flt
%
EK04API030
04A Conceptual Layout - Supersketches
27-Sep-25
27-Dec-26
46%
EK04ASY170
04A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
100%
EK04AIC300
04A In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
100%
EK04AIC120
04A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Data Date
EK04API030 — 04A Conceptual Layout - Supersketches | 27-Sep-25 → 27-Dec-26 | In Progress 46% | float — EK04API030 EK04ASY170 — 04A OSBL P&IDs IPL & Line List Issue Milestone | 11-Oct-25 | Complete EK04AIC300 — 04A In Line Instrument Approved Vendor Data | 01-Jan-26 → 15-Apr-26 | Complete 100% | float — EK04AIC300 EK04AIC120 — 04A Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —