Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 15 activities in 05 Dock / Storage × clear
Code
Activity
Start
Finish
Flt
%
PK000MU11K
05B MU311 - Fabricate/PO Promise HYDROCHLORIC ACID STORAGE
13-Feb-26
27-Dec-26
22%
PK000MU11S
05B MU311 - Marshaling HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
0%
PK000MU311
05B MU311 Transport/Customes BULK CHEM. STORAGE TANKS
27-Dec-26
27-Dec-26
0%
PK02FMU11Z
05B MU311 Recv. at Site - 2109-LA HYDROCHLORIC ACID STORAGE TANK A
27-Dec-26
27-Dec-26
0%
PK02GMU11Z
05B MU311 Recv. at Site - 2109-LB HYDROCHLORIC ACID STORAGE TANK B
27-Dec-26
27-Dec-26
0%
PK02LMU11Z
05B MU311 Recv. at Site - 2110-L SODIUM HYDROCHLORITE STORAGE
27-Dec-26
27-Dec-26
0%
PK03FMU11Z
05B MU311 Recv. at Site - 2109-L HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
0%
PK050I1105
050 Orfice Plates - Recv on Site Dock/Storage Area
27-Dec-26
27-Dec-26
0%
PK05AML33Z
05A Recv. at Site - 2101-L Ammonia Refrigeration Pkg
27-Dec-26
27-Dec-26
0%
PK05BML51Z
05B Recv. at Site - 2102-L Loading Arm
27-Dec-26
27-Dec-26
0%
PK000MB71Z
05A Recv. at Site - Storage Flare & Flame FRT Gen.
01-Mar-27
01-Mar-27
264.0d
0%
PK000MJ38A
05A Recv. at Site - 2100-JA Pumps - MJ308
15-Mar-27
15-Mar-27
215.0d
0%
PK05AMJ36Z
05A Recv. at Site - 2203-J/JM, 2106-J, 2107-J Pumps
15-Mar-27
15-Mar-27
207.0d
0%
PK05AMJ37A
05A Recv. at Site - 2100-JA Pumps - MJ307
24-Mar-27
24-Mar-27
206.0d
0%
PK000MJ71Z
05A Recv. at Site - 2108-J Emerg Power Generator
19-Apr-27
19-Apr-27
86.0d
0%
26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr Data Date
PK000MU11K — 05B MU311 - Fabricate/PO Promise HYDROCHLORIC ACID STORAGE | 13-Feb-26 → 27-Dec-26 | In Progress 22% | float — PK000MU11K PK000MU11S — 05B MU311 - Marshaling HYDROCHLORIC ACID STORAGE | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU311 — 05B MU311 Transport/Customes BULK CHEM. STORAGE TANKS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK02FMU11Z — 05B MU311 Recv. at Site - 2109-LA HYDROCHLORIC ACID STORAGE TANK A | 27-Dec-26 | Not Started PK02GMU11Z — 05B MU311 Recv. at Site - 2109-LB HYDROCHLORIC ACID STORAGE TANK B | 27-Dec-26 | Not Started PK02LMU11Z — 05B MU311 Recv. at Site - 2110-L SODIUM HYDROCHLORITE STORAGE | 27-Dec-26 | Not Started PK03FMU11Z — 05B MU311 Recv. at Site - 2109-L HYDROCHLORIC ACID STORAGE | 27-Dec-26 | Not Started PK050I1105 — 050 Orfice Plates - Recv on Site Dock/Storage Area | 27-Dec-26 | Not Started PK05AML33Z — 05A Recv. at Site - 2101-L Ammonia Refrigeration Pkg | 27-Dec-26 | Not Started PK05BML51Z — 05B Recv. at Site - 2102-L Loading Arm | 27-Dec-26 | Not Started PK000MB71Z — 05A Recv. at Site - Storage Flare & Flame FRT Gen. | 01-Mar-27 | Not Started PK000MJ38A — 05A Recv. at Site - 2100-JA Pumps - MJ308 | 15-Mar-27 | Not Started PK05AMJ36Z — 05A Recv. at Site - 2203-J/JM, 2106-J, 2107-J Pumps | 15-Mar-27 | Not Started PK05AMJ37A — 05A Recv. at Site - 2100-JA Pumps - MJ307 | 24-Mar-27 | Not Started PK000MJ71Z — 05A Recv. at Site - 2108-J Emerg Power Generator | 19-Apr-27 | Not Started