EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 15
activities
in 05 Dock / Storage
× clear
Code
Activity
Start
Finish
Flt
%
PK000MU11K
05B MU311 - Fabricate/PO Promise HYDROCHLORIC ACID STORAGE
13-Feb-26
27-Dec-26
—
22%
PK000MU11S
05B MU311 - Marshaling HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
—
0%
PK000MU311
05B MU311 Transport/Customes BULK CHEM. STORAGE TANKS
27-Dec-26
27-Dec-26
—
0%
PK02FMU11Z
05B MU311 Recv. at Site - 2109-LA HYDROCHLORIC ACID STORAGE TANK A
27-Dec-26
27-Dec-26
—
0%
PK02GMU11Z
05B MU311 Recv. at Site - 2109-LB HYDROCHLORIC ACID STORAGE TANK B
27-Dec-26
27-Dec-26
—
0%
PK02LMU11Z
05B MU311 Recv. at Site - 2110-L SODIUM HYDROCHLORITE STORAGE
27-Dec-26
27-Dec-26
—
0%
PK03FMU11Z
05B MU311 Recv. at Site - 2109-L HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
—
0%
PK050I1105
050 Orfice Plates - Recv on Site Dock/Storage Area
27-Dec-26
27-Dec-26
—
0%
PK05AML33Z
05A Recv. at Site - 2101-L Ammonia Refrigeration Pkg
27-Dec-26
27-Dec-26
—
0%
PK05BML51Z
05B Recv. at Site - 2102-L Loading Arm
27-Dec-26
27-Dec-26
—
0%
PK000MB71Z
05A Recv. at Site - Storage Flare & Flame FRT Gen.
01-Mar-27
01-Mar-27
264.0d
0%
PK000MJ38A
05A Recv. at Site - 2100-JA Pumps - MJ308
15-Mar-27
15-Mar-27
215.0d
0%
PK05AMJ36Z
05A Recv. at Site - 2203-J/JM, 2106-J, 2107-J Pumps
15-Mar-27
15-Mar-27
207.0d
0%
PK05AMJ37A
05A Recv. at Site - 2100-JA Pumps - MJ307
24-Mar-27
24-Mar-27
206.0d
0%
PK000MJ71Z
05A Recv. at Site - 2108-J Emerg Power Generator
19-Apr-27
19-Apr-27
86.0d
0%