Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 11 activities in 03 Utility Plant × clear
Code
Activity
Start
Finish
Flt
%
PK030IC220
030 Control Valves - Recv on Site
27-Dec-26
27-Dec-26
0%
PK03BMU22Z
03B Recv. at Site - 2401-U Sanitary Treatment Pkg
27-Dec-26
27-Dec-26
0%
PK03CMD46Z
03C Recv. at Site - 2203-F & 2204-F Caustic Tank/ Acid Drum
27-Dec-26
27-Dec-26
0%
PK03FMD46Z
03F Recv. at Site - 2006-F Boiler Blowdown Drum
27-Dec-26
27-Dec-26
0%
PK03FMU41Z
03F Recv. at Site - 2002-U Package Boiler
27-Dec-26
27-Dec-26
0%
PK030I1105
Orific Plates - Recv on Site
27-Jan-27
27-Jan-27
592.0d
0%
PK03BMU29Z
03B Recv. at Site - 2404-L Oil Skimmer
01-Mar-27
01-Mar-27
212.0d
0%
PK03EMU33Z
03E Recv. at Site - 2001-U Demineralizer Unit
01-Mar-27
01-Mar-27
135.0d
0%
PK03CMJ36Z
03C Recv. at Site - 2205-J/JA, 2206-J/JA Pumps
15-Mar-27
15-Mar-27
146.0d
0%
PK03DMJ36Z
03D Recv. at Site - 2002-J/JA Demineralized Water Pumps
15-Mar-27
15-Mar-27
158.0d
0%
PK03AML50Z
03A Recv. at Site - 2003-L PAI/IA Compressor Pkg
29-Mar-27
29-Mar-27
95.0d
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
PK030IC220 — 030 Control Valves - Recv on Site | 27-Dec-26 | Not Started PK03BMU22Z — 03B Recv. at Site - 2401-U Sanitary Treatment Pkg | 27-Dec-26 | Not Started PK03CMD46Z — 03C Recv. at Site - 2203-F & 2204-F Caustic Tank/ Acid Drum | 27-Dec-26 | Not Started PK03FMD46Z — 03F Recv. at Site - 2006-F Boiler Blowdown Drum | 27-Dec-26 | Not Started PK03FMU41Z — 03F Recv. at Site - 2002-U Package Boiler | 27-Dec-26 | Not Started PK030I1105 — Orific Plates - Recv on Site | 27-Jan-27 | Not Started PK03BMU29Z — 03B Recv. at Site - 2404-L Oil Skimmer | 01-Mar-27 | Not Started PK03EMU33Z — 03E Recv. at Site - 2001-U Demineralizer Unit | 01-Mar-27 | Not Started PK03CMJ36Z — 03C Recv. at Site - 2205-J/JA, 2206-J/JA Pumps | 15-Mar-27 | Not Started PK03DMJ36Z — 03D Recv. at Site - 2002-J/JA Demineralized Water Pumps | 15-Mar-27 | Not Started PK03AML50Z — 03A Recv. at Site - 2003-L PAI/IA Compressor Pkg | 29-Mar-27 | Not Started