Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 52 activities in 00 Common × clear
Code
Activity
Start
Finish
Flt
%
EM000MD42C
Prepare & Issue Prelim. RFQ - MD402 to Proc.
12-Feb-25
16-Feb-25
100%
EM000PI025
Develop Piping Specs (PDS)
19-Feb-25
23-Jul-25
100%
EM000MD22C
Prepare & Issue Prelim. RFQ - MD202 to Proc.
26-Feb-25
28-Feb-25
100%
EM000MD44C
Prepare & Issue Prelim. RFQ - MD404 to Proc.
26-Feb-25
28-Feb-25
100%
EM000MD46C
Prepare & Issue Prelim. RFQ - MD411 to Proc.
26-Feb-25
28-Feb-25
100%
EM00MD45C
Prepare & Issue Prelim. RFQ - MD405 to Proc.
26-Feb-25
28-Feb-25
100%
EM000MD22D
Technical Evaluation - MD202
22-Mar-25
18-Apr-25
100%
EM000MD42D
Technical Evaluation - MD402
22-Mar-25
18-Apr-25
100%
EM000MD44D
Technical Evaluation - MD404
22-Mar-25
18-Apr-25
100%
EM000MD46D
Technical Evaluation - MD411
22-Mar-25
19-Apr-25
100%
EM000MD45D
Technical Evaluation - MD405
26-Mar-25
18-Apr-25
100%
EM000MD47F
Develop & Issue Inquiry for ERW - MD406
27-Apr-25
11-May-25
100%
EM000MD42E
Prepare & Issue Purchase ERW - MD402
01-May-25
04-May-25
100%
EM000MD44E
Prepare & Issue Purchase ERW - MD404
03-Jun-25
05-Jun-25
100%
EM000MD45E
Prepare & Issue Purchase ERW - MD405
03-Jun-25
05-Jun-25
100%
EM000MD46E
Prepare & Issue Purchase ERW - MD411
03-Jun-25
05-Jun-25
100%
EM000MD22E
Prepare & Issue Purchase ERW - MD202
10-Jun-25
13-Jun-25
100%
EM000MD47D
Technical Evaluation - MD406
02-Jul-25
06-Jul-25
100%
EM000MD47E
Prepare & Issue Purchase ERW - MD406
16-Aug-25
21-Aug-25
100%
PM000MD45N
Recv. Planning V. Data MD405
16-Aug-25
02-Sep-25
100%
PM000MD42N
Recv. Planning V. Data MD402
16-Aug-25
19-Oct-25
100%
PM000MD22N
Recv. Planning V. Data MD202
16-Aug-25
12-Nov-25
100%
PM000MD46N
Recv. Planning V. Data MD411
27-Aug-25
13-Sep-25
100%
PM000MD44N
Recv. Planning V. Data MD404
17-Sep-25
30-Sep-25
100%
PM000MD47N
Recv. Planning V. Data MD406
23-Sep-25
09-Oct-25
100%
EM000CV164
Issue Anchor Bolts,Rebar, & Misc. Fnd Matl. Take-Off's to OCI
01-Oct-25
29-Oct-25
100%
EM020IC126
Instrument Installation Details (90%) - IFC
07-Oct-25
18-Apr-26
100%
EM000U000
Start U/G Model Reviews
16-Oct-25
16-Oct-25
100%
EM000MCG10
GEN and ADMINISTRATIVE
13-Jan-26
27-Dec-26
29%
EM000ELEH2
01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC
31-Mar-26
27-Dec-26
9%
EM010IC123
UNIT 01 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
9%
EM020IC124
UNIT 02 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
9%
EM020IC128
Instrument Wiring Diagrams - IFC
01-Apr-26
27-Dec-26
9%
EM030IC125
UNIT 03 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
9%
EM050IC130
05B Instr. Location Plans - IFC
01-Apr-26
16-Jan-27
166.0d
8%
EK020IC133
Field Bus J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
0%
EK100ELEK2
01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A
27-Dec-26
27-Dec-26
0%
EK200ELEK2
01H Develop & Issue Cable Ladder Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEJ2
01,03,05 Develop & Issue Lighting Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEK2
01,03,04,05 Develop & Issue Power Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEL2
01,03,04,05 Electrical Routing Plans
27-Dec-26
27-Dec-26
0%
EM000ELEM2
Dev/Issue Elect Cable/Raceway Sched IFC
27-Dec-26
27-Dec-26
0%
EM020IC127
Instrument Installation Details (10%) - IFC
27-Dec-26
27-Dec-26
0%
EM020IC129
Instrument Loop Diagrams - IFC
27-Dec-26
27-Dec-26
0%
EM020IC132
Traditional J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
0%
EM020IC134
DCS Marshalling Report - IFC
27-Dec-26
27-Dec-26
0%
EM020IC135
SIS Termination Report - IFC
27-Dec-26
27-Dec-26
0%
EM020IC136
ITCC Termination Report - IFC
27-Dec-26
27-Dec-26
0%
EM020IC137
Miscellaneous Wiring Report - IFC
27-Dec-26
27-Dec-26
0%
EK020IC131
Instrument Loop Diagrams FF - IFC
30-Dec-26
03-Jan-27
530.0d
0%
EM000ELEN3
01,03 Equipment Interconnection Diagrams
30-Dec-26
30-Jan-27
511.0d
0%
EM000IC100
Instrument Index - IFC
06-Jan-27
06-Jan-27
530.0d
0%
27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
EM000MD42C — Prepare & Issue Prelim. RFQ - MD402 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EM000MD42C EM000PI025 — Develop Piping Specs (PDS) | 19-Feb-25 → 23-Jul-25 | Complete 100% | float — EM000PI025 EM000MD22C — Prepare & Issue Prelim. RFQ - MD202 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM000MD22C EM000MD44C — Prepare & Issue Prelim. RFQ - MD404 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM000MD44C EM000MD46C — Prepare & Issue Prelim. RFQ - MD411 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM000MD46C EM00MD45C — Prepare & Issue Prelim. RFQ - MD405 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM00MD45C EM000MD22D — Technical Evaluation - MD202 | 22-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD22D EM000MD42D — Technical Evaluation - MD402 | 22-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD42D EM000MD44D — Technical Evaluation - MD404 | 22-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD44D EM000MD46D — Technical Evaluation - MD411 | 22-Mar-25 → 19-Apr-25 | Complete 100% | float — EM000MD46D EM000MD45D — Technical Evaluation - MD405 | 26-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD45D EM000MD47F — Develop & Issue Inquiry for ERW - MD406 | 27-Apr-25 → 11-May-25 | Complete 100% | float — EM000MD47F EM000MD42E — Prepare & Issue Purchase ERW - MD402 | 01-May-25 → 04-May-25 | Complete 100% | float — EM000MD42E EM000MD44E — Prepare & Issue Purchase ERW - MD404 | 03-Jun-25 → 05-Jun-25 | Complete 100% | float — EM000MD44E EM000MD45E — Prepare & Issue Purchase ERW - MD405 | 03-Jun-25 → 05-Jun-25 | Complete 100% | float — EM000MD45E EM000MD46E — Prepare & Issue Purchase ERW - MD411 | 03-Jun-25 → 05-Jun-25 | Complete 100% | float — EM000MD46E EM000MD22E — Prepare & Issue Purchase ERW - MD202 | 10-Jun-25 → 13-Jun-25 | Complete 100% | float — EM000MD22E EM000MD47D — Technical Evaluation - MD406 | 02-Jul-25 → 06-Jul-25 | Complete 100% | float — EM000MD47D EM000MD47E — Prepare & Issue Purchase ERW - MD406 | 16-Aug-25 → 21-Aug-25 | Complete 100% | float — EM000MD47E PM000MD45N — Recv. Planning V. Data MD405 | 16-Aug-25 → 02-Sep-25 | Complete 100% | float — PM000MD45N PM000MD42N — Recv. Planning V. Data MD402 | 16-Aug-25 → 19-Oct-25 | Complete 100% | float — PM000MD42N PM000MD22N — Recv. Planning V. Data MD202 | 16-Aug-25 → 12-Nov-25 | Complete 100% | float — PM000MD22N PM000MD46N — Recv. Planning V. Data MD411 | 27-Aug-25 → 13-Sep-25 | Complete 100% | float — PM000MD46N PM000MD44N — Recv. Planning V. Data MD404 | 17-Sep-25 → 30-Sep-25 | Complete 100% | float — PM000MD44N PM000MD47N — Recv. Planning V. Data MD406 | 23-Sep-25 → 09-Oct-25 | Complete 100% | float — PM000MD47N EM000CV164 — Issue Anchor Bolts,Rebar, & Misc. Fnd Matl. Take-Off's to OCI | 01-Oct-25 → 29-Oct-25 | Complete 100% | float — EM000CV164 EM020IC126 — Instrument Installation Details (90%) - IFC | 07-Oct-25 → 18-Apr-26 | Complete 100% | float — EM020IC126 EM000U000 — Start U/G Model Reviews | 16-Oct-25 | Complete EM000MCG10 — GEN and ADMINISTRATIVE | 13-Jan-26 → 27-Dec-26 | In Progress 29% | float — EM000MCG10 EM000ELEH2 — 01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — EM000ELEH2 EM010IC123 — UNIT 01 Instr. Location Plans - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM010IC123 EM020IC124 — UNIT 02 Instr. Location Plans - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM020IC124 EM020IC128 — Instrument Wiring Diagrams - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM020IC128 EM030IC125 — UNIT 03 Instr. Location Plans - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM030IC125 EM050IC130 — 05B Instr. Location Plans - IFC | 01-Apr-26 → 16-Jan-27 | In Progress 8% | float 166.0d EM050IC130 EK020IC133 — Field Bus J-boxes Wiring Reports - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK100ELEK2 — 01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK200ELEK2 — 01H Develop & Issue Cable Ladder Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEJ2 — 01,03,05 Develop & Issue Lighting Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEK2 — 01,03,04,05 Develop & Issue Power Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEL2 — 01,03,04,05 Electrical Routing Plans | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEM2 — Dev/Issue Elect Cable/Raceway Sched IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC127 — Instrument Installation Details (10%) - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC129 — Instrument Loop Diagrams - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC132 — Traditional J-boxes Wiring Reports - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC134 — DCS Marshalling Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC135 — SIS Termination Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC136 — ITCC Termination Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC137 — Miscellaneous Wiring Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK020IC131 — Instrument Loop Diagrams FF - IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 530.0d EK020IC131 EM000ELEN3 — 01,03 Equipment Interconnection Diagrams | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EM000ELEN3 EM000IC100 — Instrument Index - IFC | 06-Jan-27 → 06-Jan-27 | Not Started 0% | float 530.0d