Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 62 activities in 00 Common × clear
Code
Activity
Start
Finish
Flt
%
EK000CK065
Compl. Layout of Temp. Facil. (including OCI)
29-Jan-25
01-Oct-25
100%
EK000CK075
Review Tech & Commercial Proposal - Field Fab Tank
16-Feb-25
02-Oct-25
100%
EK000CK060
Locate tie in pnts for temp water, phone, & pwr
26-Feb-25
16-Mar-25
100%
EK000CK100
Site Visit - Construction
26-Feb-25
16-Mar-25
100%
EK000CK005
OCI Subcontract - Executed
19-Mar-25
19-Nov-25
100%
EK000CK010
OCI Meeting to Define custom clearance requests
20-May-25
19-Jun-25
100%
EK000CK015
Define OCI's Point of Delivery & Liability
20-May-25
19-Jun-25
100%
EK000CV038
Select Geotech Vendor / Issue Award
20-May-25
17-Aug-25
100%
EK000CV039
Geotech Conducts Soil Borings / Draft Prelim Report
24-Aug-25
17-Dec-25
100%
CO000GE105
Commence Admin. Building Design (OCI)
05-Oct-25
05-Oct-25
100%
CO000K0106
Mobilize Temporary Facilities (& Punchlist & Perm. Power)
09-Nov-25
27-Dec-26
40%
EK000GE150
Execute OCI Subcontract (KBR)
16-Nov-25
16-Nov-25
100%
EK000GE170
Issue Material Supply PO to OCI (Elect, Struct, Insul)
11-Dec-25
11-Dec-25
100%
CK000YA306
Establish Tax Free Zone Status
13-Dec-25
31-Jan-26
100%
CO000M0100
Commence Engineering - Field Fab Tanks
04-Jan-26
04-Jan-26
100%
CO000CK110
Set-Up KBR Pipe Fab Shop
24-Mar-26
27-Dec-26
11%
CO000A0110
Start Buildings - Admin, Canteen, Warehouse, Control
31-Mar-26
31-Mar-26
100%
CO000K0100
Start Construction
31-Mar-26
31-Mar-26
100%
CO000A0150
Install Guard Towers
01-Apr-26
14-Apr-26
100%
CO000K0108
Start Foundations - Field Fab Tanks
09-Apr-26
09-Apr-26
100%
CO000K0110
Start Foundations - Equipment & Piperacks
09-Apr-26
09-Apr-26
100%
CO010K0120
010 Construct Perimeter Roads
15-Apr-26
28-Dec-26
5%
CO000M0110
Mobilize Field Fab Tank Contractor
27-Dec-26
27-Dec-26
0%
CO02HM0135
02H Give 30 Day notice to Manufacture Refractory (103-D)
16-Mar-27
16-Mar-27
-40.0d
0%
SC02GI0150
02G Function Testing
07-Dec-27
09-Jan-28
63.0d
0%
WC000T1100
000 Commissioning
07-Dec-27
22-Sep-28
-59.0d
0%
SC03AI0150
03A Function Testing
10-Dec-27
20-Dec-27
-47.0d
0%
SC01DI0150
01D Function Testing
12-Dec-27
29-Dec-27
-28.0d
0%
SC03FI0150
03F Function Testing
14-Dec-27
24-Dec-27
-2.0d
0%
SC02BI0150
02B Function Testing
16-Dec-27
18-Dec-27
85.0d
0%
SC02CI0150
02C Function Testing
17-Dec-27
24-Jan-28
48.0d
0%
SC02YI0150
02Y Function Testing
18-Dec-27
10-Jan-28
62.0d
0%
SC02AI0150
02A Function Testing
21-Dec-27
12-Jan-28
60.0d
0%
SC02DI0150
02D Function Testing
21-Dec-27
04-Jan-28
68.0d
0%
SC03AT0130
03A Commission
21-Dec-27
27-Dec-27
-47.0d
0%
SC02KI0150
02K Function Testing
23-Dec-27
16-Jan-28
56.0d
0%
SC02NI0150
02N Function Testing
23-Dec-27
25-Dec-27
78.0d
0%
SC01CI0150
01C Function Testing
24-Dec-27
29-Dec-27
-14.0d
0%
SC01YI0150
01Y Function Testing
24-Dec-27
10-Jan-28
62.0d
0%
SC02PI0150
02P Function Testing
24-Dec-27
28-Dec-27
75.0d
0%
SC03BI0150
03B Function Testing
24-Dec-27
03-Jan-28
69.0d
0%
SC02QI0150
02Q Function Testing
25-Dec-27
29-Dec-27
74.0d
0%
SC02MI0150
02M Function Testing
26-Dec-27
12-Jan-28
60.0d
0%
SC01DT0130
01D Commission
28-Dec-27
07-Feb-28
-47.0d
0%
SC02EI0150
02E Function Testing
28-Dec-27
17-Jan-28
55.0d
0%
SC03CI0150
03C Function Testing
28-Dec-27
07-Jan-28
-23.0d
0%
SC01AI0150
01A Function Testing
29-Dec-27
29-Dec-27
-14.0d
0%
SC01BI0150
01B Function Testing
29-Dec-27
19-Jan-28
-35.0d
0%
SC02JI0150
02J Function Testing
29-Dec-27
23-Jan-28
49.0d
0%
SC03DI0150
03D Function Testing
30-Dec-27
04-Jan-28
-20.0d
0%
SC03YI0150
03Y Function Testing
01-Jan-28
24-Jan-28
48.0d
0%
SC02FI0150
02F Function Testing
02-Jan-28
20-Jan-28
52.0d
0%
SC03EI0150
03E Function Testing
05-Jan-28
22-Jan-28
-38.0d
0%
SC02HI0150
02H Function Testing
20-Jan-28
29-Feb-28
12.0d
0%
SC05BI0150
05B Function Testing
05-Feb-28
08-Feb-28
79.0d
0%
SC02LI0150
02L Function Testing
08-Feb-28
29-Mar-28
-17.0d
0%
SC03FT0130
03F Commission
08-Feb-28
28-Feb-28
-47.0d
0%
SC000T0100
020 Commission ISBL
29-Feb-28
28-Apr-28
-47.0d
0%
SC05AI0150
05A Function Testing
15-Mar-28
15-Apr-28
-34.0d
0%
SC000T0105
020 Startup ISBL
11-May-28
24-Jun-28
-59.0d
0%
SC000T0110
Performance Test Period
25-Jun-28
22-Sep-28
-59.0d
0%
SC000YA100
Construction Bonus Period
23-Sep-28
15-Mar-29
-59.0d
0%
30-Dec 06-Jan 13-Jan 20-Jan 27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan 07-Feb 14-Feb 21-Feb 28-Feb 06-Mar 13-Mar 20-Mar 27-Mar 03-Apr 10-Apr 17-Apr 24-Apr 01-May 08-May 15-May 22-May 29-May 05-Jun 12-Jun 19-Jun 26-Jun 03-Jul 10-Jul 17-Jul 24-Jul 31-Jul 07-Aug 14-Aug 21-Aug 28-Aug 04-Sep 11-Sep 18-Sep 25-Sep 02-Oct 09-Oct 16-Oct 23-Oct 30-Oct 06-Nov 13-Nov 20-Nov 27-Nov 04-Dec 11-Dec 18-Dec 25-Dec 01-Jan 08-Jan 15-Jan 22-Jan 29-Jan 05-Feb 12-Feb 19-Feb 26-Feb 05-Mar 12-Mar 19-Mar 26-Mar Data Date
EK000CK065 — Compl. Layout of Temp. Facil. (including OCI) | 29-Jan-25 → 01-Oct-25 | Complete 100% | float — EK000CK065 EK000CK075 — Review Tech & Commercial Proposal - Field Fab Tank | 16-Feb-25 → 02-Oct-25 | Complete 100% | float — EK000CK075 EK000CK060 — Locate tie in pnts for temp water, phone, & pwr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CK060 EK000CK100 — Site Visit - Construction | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CK100 EK000CK005 — OCI Subcontract - Executed | 19-Mar-25 → 19-Nov-25 | Complete 100% | float — EK000CK005 EK000CK010 — OCI Meeting to Define custom clearance requests | 20-May-25 → 19-Jun-25 | Complete 100% | float — EK000CK010 EK000CK015 — Define OCI's Point of Delivery & Liability | 20-May-25 → 19-Jun-25 | Complete 100% | float — EK000CK015 EK000CV038 — Select Geotech Vendor / Issue Award | 20-May-25 → 17-Aug-25 | Complete 100% | float — EK000CV038 EK000CV039 — Geotech Conducts Soil Borings / Draft Prelim Report | 24-Aug-25 → 17-Dec-25 | Complete 100% | float — EK000CV039 CO000GE105 — Commence Admin. Building Design (OCI) | 05-Oct-25 | Complete CO000K0106 — Mobilize Temporary Facilities (& Punchlist & Perm. Power) | 09-Nov-25 → 27-Dec-26 | In Progress 40% | float — CO000K0106 EK000GE150 — Execute OCI Subcontract (KBR) | 16-Nov-25 | Complete EK000GE170 — Issue Material Supply PO to OCI (Elect, Struct, Insul) | 11-Dec-25 | Complete CK000YA306 — Establish Tax Free Zone Status | 13-Dec-25 → 31-Jan-26 | Complete 100% | float — CK000YA306 CO000M0100 — Commence Engineering - Field Fab Tanks | 04-Jan-26 | Complete CO000CK110 — Set-Up KBR Pipe Fab Shop | 24-Mar-26 → 27-Dec-26 | In Progress 11% | float — CO000CK110 CO000A0110 — Start Buildings - Admin, Canteen, Warehouse, Control | 31-Mar-26 | Complete CO000K0100 — Start Construction | 31-Mar-26 | Complete CO000A0150 — Install Guard Towers | 01-Apr-26 → 14-Apr-26 | Complete 100% | float — CO000A0150 CO000K0108 — Start Foundations - Field Fab Tanks | 09-Apr-26 | Complete CO000K0110 — Start Foundations - Equipment & Piperacks | 09-Apr-26 | Complete CO010K0120 — 010 Construct Perimeter Roads | 15-Apr-26 → 28-Dec-26 | In Progress 5% | float — CO010K0120 CO000M0110 — Mobilize Field Fab Tank Contractor | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HM0135 — 02H Give 30 Day notice to Manufacture Refractory (103-D) | 16-Mar-27 | Not Started SC02GI0150 — 02G Function Testing | 07-Dec-27 → 09-Jan-28 | Not Started 0% | float 63.0d SC02GI0150 WC000T1100 — 000 Commissioning | 07-Dec-27 → 22-Sep-28 | Not Started 0% | float -59.0d WC000T1100 SC03AI0150 — 03A Function Testing | 10-Dec-27 → 20-Dec-27 | Not Started 0% | float -47.0d SC03AI0150 SC01DI0150 — 01D Function Testing | 12-Dec-27 → 29-Dec-27 | Not Started 0% | float -28.0d SC01DI0150 SC03FI0150 — 03F Function Testing | 14-Dec-27 → 24-Dec-27 | Not Started 0% | float -2.0d SC03FI0150 SC02BI0150 — 02B Function Testing | 16-Dec-27 → 18-Dec-27 | Not Started 0% | float 85.0d SC02BI0150 SC02CI0150 — 02C Function Testing | 17-Dec-27 → 24-Jan-28 | Not Started 0% | float 48.0d SC02CI0150 SC02YI0150 — 02Y Function Testing | 18-Dec-27 → 10-Jan-28 | Not Started 0% | float 62.0d SC02YI0150 SC02AI0150 — 02A Function Testing | 21-Dec-27 → 12-Jan-28 | Not Started 0% | float 60.0d SC02AI0150 SC02DI0150 — 02D Function Testing | 21-Dec-27 → 04-Jan-28 | Not Started 0% | float 68.0d SC02DI0150 SC03AT0130 — 03A Commission | 21-Dec-27 → 27-Dec-27 | Not Started 0% | float -47.0d SC03AT0130 SC02KI0150 — 02K Function Testing | 23-Dec-27 → 16-Jan-28 | Not Started 0% | float 56.0d SC02KI0150 SC02NI0150 — 02N Function Testing | 23-Dec-27 → 25-Dec-27 | Not Started 0% | float 78.0d SC02NI0150 SC01CI0150 — 01C Function Testing | 24-Dec-27 → 29-Dec-27 | Not Started 0% | float -14.0d SC01CI0150 SC01YI0150 — 01Y Function Testing | 24-Dec-27 → 10-Jan-28 | Not Started 0% | float 62.0d SC01YI0150 SC02PI0150 — 02P Function Testing | 24-Dec-27 → 28-Dec-27 | Not Started 0% | float 75.0d SC02PI0150 SC03BI0150 — 03B Function Testing | 24-Dec-27 → 03-Jan-28 | Not Started 0% | float 69.0d SC03BI0150 SC02QI0150 — 02Q Function Testing | 25-Dec-27 → 29-Dec-27 | Not Started 0% | float 74.0d SC02QI0150 SC02MI0150 — 02M Function Testing | 26-Dec-27 → 12-Jan-28 | Not Started 0% | float 60.0d SC02MI0150 SC01DT0130 — 01D Commission | 28-Dec-27 → 07-Feb-28 | Not Started 0% | float -47.0d SC01DT0130 SC02EI0150 — 02E Function Testing | 28-Dec-27 → 17-Jan-28 | Not Started 0% | float 55.0d SC02EI0150 SC03CI0150 — 03C Function Testing | 28-Dec-27 → 07-Jan-28 | Not Started 0% | float -23.0d SC03CI0150 SC01AI0150 — 01A Function Testing | 29-Dec-27 → 29-Dec-27 | Not Started 0% | float -14.0d SC01BI0150 — 01B Function Testing | 29-Dec-27 → 19-Jan-28 | Not Started 0% | float -35.0d SC01BI0150 SC02JI0150 — 02J Function Testing | 29-Dec-27 → 23-Jan-28 | Not Started 0% | float 49.0d SC02JI0150 SC03DI0150 — 03D Function Testing | 30-Dec-27 → 04-Jan-28 | Not Started 0% | float -20.0d SC03DI0150 SC03YI0150 — 03Y Function Testing | 01-Jan-28 → 24-Jan-28 | Not Started 0% | float 48.0d SC03YI0150 SC02FI0150 — 02F Function Testing | 02-Jan-28 → 20-Jan-28 | Not Started 0% | float 52.0d SC02FI0150 SC03EI0150 — 03E Function Testing | 05-Jan-28 → 22-Jan-28 | Not Started 0% | float -38.0d SC03EI0150 SC02HI0150 — 02H Function Testing | 20-Jan-28 → 29-Feb-28 | Not Started 0% | float 12.0d SC02HI0150 SC05BI0150 — 05B Function Testing | 05-Feb-28 → 08-Feb-28 | Not Started 0% | float 79.0d SC05BI0150 SC02LI0150 — 02L Function Testing | 08-Feb-28 → 29-Mar-28 | Not Started 0% | float -17.0d SC02LI0150 SC03FT0130 — 03F Commission | 08-Feb-28 → 28-Feb-28 | Not Started 0% | float -47.0d SC03FT0130 SC000T0100 — 020 Commission ISBL | 29-Feb-28 → 28-Apr-28 | Not Started 0% | float -47.0d SC000T0100 SC05AI0150 — 05A Function Testing | 15-Mar-28 → 15-Apr-28 | Not Started 0% | float -34.0d SC05AI0150 SC000T0105 — 020 Startup ISBL | 11-May-28 → 24-Jun-28 | Not Started 0% | float -59.0d SC000T0105 SC000T0110 — Performance Test Period | 25-Jun-28 → 22-Sep-28 | Not Started 0% | float -59.0d SC000T0110 SC000YA100 — Construction Bonus Period | 23-Sep-28 → 15-Mar-29 | Not Started 0% | float -59.0d SC000YA100