Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 62 activities in 00 Common × clear
Code
Activity
Start
Finish
Flt
%
EK000CK065
Compl. Layout of Temp. Facil. (including OCI)
29-Jan-25
01-Oct-25
100%
EK000CK075
Review Tech & Commercial Proposal - Field Fab Tank
16-Feb-25
02-Oct-25
100%
EK000CK060
Locate tie in pnts for temp water, phone, & pwr
26-Feb-25
16-Mar-25
100%
EK000CK100
Site Visit - Construction
26-Feb-25
16-Mar-25
100%
EK000CK005
OCI Subcontract - Executed
19-Mar-25
19-Nov-25
100%
EK000CK010
OCI Meeting to Define custom clearance requests
20-May-25
19-Jun-25
100%
EK000CK015
Define OCI's Point of Delivery & Liability
20-May-25
19-Jun-25
100%
EK000CV038
Select Geotech Vendor / Issue Award
20-May-25
17-Aug-25
100%
EK000CV039
Geotech Conducts Soil Borings / Draft Prelim Report
24-Aug-25
17-Dec-25
100%
CO000GE105
Commence Admin. Building Design (OCI)
05-Oct-25
05-Oct-25
100%
CO000K0106
Mobilize Temporary Facilities (& Punchlist & Perm. Power)
09-Nov-25
27-Dec-26
40%
EK000GE150
Execute OCI Subcontract (KBR)
16-Nov-25
16-Nov-25
100%
EK000GE170
Issue Material Supply PO to OCI (Elect, Struct, Insul)
11-Dec-25
11-Dec-25
100%
CK000YA306
Establish Tax Free Zone Status
13-Dec-25
31-Jan-26
100%
CO000M0100
Commence Engineering - Field Fab Tanks
04-Jan-26
04-Jan-26
100%
CO000CK110
Set-Up KBR Pipe Fab Shop
24-Mar-26
27-Dec-26
11%
CO000A0110
Start Buildings - Admin, Canteen, Warehouse, Control
31-Mar-26
31-Mar-26
100%
CO000K0100
Start Construction
31-Mar-26
31-Mar-26
100%
CO000A0150
Install Guard Towers
01-Apr-26
14-Apr-26
100%
CO000K0108
Start Foundations - Field Fab Tanks
09-Apr-26
09-Apr-26
100%
CO000K0110
Start Foundations - Equipment & Piperacks
09-Apr-26
09-Apr-26
100%
CO010K0120
010 Construct Perimeter Roads
15-Apr-26
28-Dec-26
5%
CO000M0110
Mobilize Field Fab Tank Contractor
27-Dec-26
27-Dec-26
0%
CO02HM0135
02H Give 30 Day notice to Manufacture Refractory (103-D)
16-Mar-27
16-Mar-27
-40.0d
0%
SC02GI0150
02G Function Testing
07-Dec-27
09-Jan-28
63.0d
0%
WC000T1100
000 Commissioning
07-Dec-27
22-Sep-28
-59.0d
0%
SC03AI0150
03A Function Testing
10-Dec-27
20-Dec-27
-47.0d
0%
SC01DI0150
01D Function Testing
12-Dec-27
29-Dec-27
-28.0d
0%
SC03FI0150
03F Function Testing
14-Dec-27
24-Dec-27
-2.0d
0%
SC02BI0150
02B Function Testing
16-Dec-27
18-Dec-27
85.0d
0%
SC02CI0150
02C Function Testing
17-Dec-27
24-Jan-28
48.0d
0%
SC02YI0150
02Y Function Testing
18-Dec-27
10-Jan-28
62.0d
0%
SC02AI0150
02A Function Testing
21-Dec-27
12-Jan-28
60.0d
0%
SC02DI0150
02D Function Testing
21-Dec-27
04-Jan-28
68.0d
0%
SC03AT0130
03A Commission
21-Dec-27
27-Dec-27
-47.0d
0%
SC02KI0150
02K Function Testing
23-Dec-27
16-Jan-28
56.0d
0%
SC02NI0150
02N Function Testing
23-Dec-27
25-Dec-27
78.0d
0%
SC01CI0150
01C Function Testing
24-Dec-27
29-Dec-27
-14.0d
0%
SC01YI0150
01Y Function Testing
24-Dec-27
10-Jan-28
62.0d
0%
SC02PI0150
02P Function Testing
24-Dec-27
28-Dec-27
75.0d
0%
SC03BI0150
03B Function Testing
24-Dec-27
03-Jan-28
69.0d
0%
SC02QI0150
02Q Function Testing
25-Dec-27
29-Dec-27
74.0d
0%
SC02MI0150
02M Function Testing
26-Dec-27
12-Jan-28
60.0d
0%
SC01DT0130
01D Commission
28-Dec-27
07-Feb-28
-47.0d
0%
SC02EI0150
02E Function Testing
28-Dec-27
17-Jan-28
55.0d
0%
SC03CI0150
03C Function Testing
28-Dec-27
07-Jan-28
-23.0d
0%
SC01AI0150
01A Function Testing
29-Dec-27
29-Dec-27
-14.0d
0%
SC01BI0150
01B Function Testing
29-Dec-27
19-Jan-28
-35.0d
0%
SC02JI0150
02J Function Testing
29-Dec-27
23-Jan-28
49.0d
0%
SC03DI0150
03D Function Testing
30-Dec-27
04-Jan-28
-20.0d
0%
SC03YI0150
03Y Function Testing
01-Jan-28
24-Jan-28
48.0d
0%
SC02FI0150
02F Function Testing
02-Jan-28
20-Jan-28
52.0d
0%
SC03EI0150
03E Function Testing
05-Jan-28
22-Jan-28
-38.0d
0%
SC02HI0150
02H Function Testing
20-Jan-28
29-Feb-28
12.0d
0%
SC05BI0150
05B Function Testing
05-Feb-28
08-Feb-28
79.0d
0%
SC02LI0150
02L Function Testing
08-Feb-28
29-Mar-28
-17.0d
0%
SC03FT0130
03F Commission
08-Feb-28
28-Feb-28
-47.0d
0%
SC000T0100
020 Commission ISBL
29-Feb-28
28-Apr-28
-47.0d
0%
SC05AI0150
05A Function Testing
15-Mar-28
15-Apr-28
-34.0d
0%
SC000T0105
020 Startup ISBL
11-May-28
24-Jun-28
-59.0d
0%
SC000T0110
Performance Test Period
25-Jun-28
22-Sep-28
-59.0d
0%
SC000YA100
Construction Bonus Period
23-Sep-28
15-Mar-29
-59.0d
0%
Jan 2025 Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 May 2027 Jun 2027 Jul 2027 Aug 2027 Sep 2027 Oct 2027 Nov 2027 Dec 2027 Jan 2028 Feb 2028 Mar 2028 Apr 2028 May 2028 Jun 2028 Jul 2028 Aug 2028 Sep 2028 Oct 2028 Nov 2028 Dec 2028 Jan 2029 Feb 2029 Mar 2029 Data Date
EK000CK065 — Compl. Layout of Temp. Facil. (including OCI) | 29-Jan-25 → 01-Oct-25 | Complete 100% | float — EK000CK065 EK000CK075 — Review Tech & Commercial Proposal - Field Fab Tank | 16-Feb-25 → 02-Oct-25 | Complete 100% | float — EK000CK075 EK000CK060 — Locate tie in pnts for temp water, phone, & pwr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CK060 EK000CK100 — Site Visit - Construction | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CK100 EK000CK005 — OCI Subcontract - Executed | 19-Mar-25 → 19-Nov-25 | Complete 100% | float — EK000CK005 EK000CK010 — OCI Meeting to Define custom clearance requests | 20-May-25 → 19-Jun-25 | Complete 100% | float — EK000CK010 EK000CK015 — Define OCI's Point of Delivery & Liability | 20-May-25 → 19-Jun-25 | Complete 100% | float — EK000CK015 EK000CV038 — Select Geotech Vendor / Issue Award | 20-May-25 → 17-Aug-25 | Complete 100% | float — EK000CV038 EK000CV039 — Geotech Conducts Soil Borings / Draft Prelim Report | 24-Aug-25 → 17-Dec-25 | Complete 100% | float — EK000CV039 CO000GE105 — Commence Admin. Building Design (OCI) | 05-Oct-25 | Complete CO000K0106 — Mobilize Temporary Facilities (& Punchlist & Perm. Power) | 09-Nov-25 → 27-Dec-26 | In Progress 40% | float — CO000K0106 EK000GE150 — Execute OCI Subcontract (KBR) | 16-Nov-25 | Complete EK000GE170 — Issue Material Supply PO to OCI (Elect, Struct, Insul) | 11-Dec-25 | Complete CK000YA306 — Establish Tax Free Zone Status | 13-Dec-25 → 31-Jan-26 | Complete 100% | float — CK000YA306 CO000M0100 — Commence Engineering - Field Fab Tanks | 04-Jan-26 | Complete CO000CK110 — Set-Up KBR Pipe Fab Shop | 24-Mar-26 → 27-Dec-26 | In Progress 11% | float — CO000CK110 CO000A0110 — Start Buildings - Admin, Canteen, Warehouse, Control | 31-Mar-26 | Complete CO000K0100 — Start Construction | 31-Mar-26 | Complete CO000A0150 — Install Guard Towers | 01-Apr-26 → 14-Apr-26 | Complete 100% | float — CO000A0150 CO000K0108 — Start Foundations - Field Fab Tanks | 09-Apr-26 | Complete CO000K0110 — Start Foundations - Equipment & Piperacks | 09-Apr-26 | Complete CO010K0120 — 010 Construct Perimeter Roads | 15-Apr-26 → 28-Dec-26 | In Progress 5% | float — CO010K0120 CO000M0110 — Mobilize Field Fab Tank Contractor | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HM0135 — 02H Give 30 Day notice to Manufacture Refractory (103-D) | 16-Mar-27 | Not Started SC02GI0150 — 02G Function Testing | 07-Dec-27 → 09-Jan-28 | Not Started 0% | float 63.0d SC02GI0150 WC000T1100 — 000 Commissioning | 07-Dec-27 → 22-Sep-28 | Not Started 0% | float -59.0d WC000T1100 SC03AI0150 — 03A Function Testing | 10-Dec-27 → 20-Dec-27 | Not Started 0% | float -47.0d SC03AI0150 SC01DI0150 — 01D Function Testing | 12-Dec-27 → 29-Dec-27 | Not Started 0% | float -28.0d SC01DI0150 SC03FI0150 — 03F Function Testing | 14-Dec-27 → 24-Dec-27 | Not Started 0% | float -2.0d SC03FI0150 SC02BI0150 — 02B Function Testing | 16-Dec-27 → 18-Dec-27 | Not Started 0% | float 85.0d SC02CI0150 — 02C Function Testing | 17-Dec-27 → 24-Jan-28 | Not Started 0% | float 48.0d SC02CI0150 SC02YI0150 — 02Y Function Testing | 18-Dec-27 → 10-Jan-28 | Not Started 0% | float 62.0d SC02YI0150 SC02AI0150 — 02A Function Testing | 21-Dec-27 → 12-Jan-28 | Not Started 0% | float 60.0d SC02AI0150 SC02DI0150 — 02D Function Testing | 21-Dec-27 → 04-Jan-28 | Not Started 0% | float 68.0d SC02DI0150 SC03AT0130 — 03A Commission | 21-Dec-27 → 27-Dec-27 | Not Started 0% | float -47.0d SC03AT0130 SC02KI0150 — 02K Function Testing | 23-Dec-27 → 16-Jan-28 | Not Started 0% | float 56.0d SC02KI0150 SC02NI0150 — 02N Function Testing | 23-Dec-27 → 25-Dec-27 | Not Started 0% | float 78.0d SC01CI0150 — 01C Function Testing | 24-Dec-27 → 29-Dec-27 | Not Started 0% | float -14.0d SC01CI0150 SC01YI0150 — 01Y Function Testing | 24-Dec-27 → 10-Jan-28 | Not Started 0% | float 62.0d SC01YI0150 SC02PI0150 — 02P Function Testing | 24-Dec-27 → 28-Dec-27 | Not Started 0% | float 75.0d SC02PI0150 SC03BI0150 — 03B Function Testing | 24-Dec-27 → 03-Jan-28 | Not Started 0% | float 69.0d SC03BI0150 SC02QI0150 — 02Q Function Testing | 25-Dec-27 → 29-Dec-27 | Not Started 0% | float 74.0d SC02QI0150 SC02MI0150 — 02M Function Testing | 26-Dec-27 → 12-Jan-28 | Not Started 0% | float 60.0d SC02MI0150 SC01DT0130 — 01D Commission | 28-Dec-27 → 07-Feb-28 | Not Started 0% | float -47.0d SC01DT0130 SC02EI0150 — 02E Function Testing | 28-Dec-27 → 17-Jan-28 | Not Started 0% | float 55.0d SC02EI0150 SC03CI0150 — 03C Function Testing | 28-Dec-27 → 07-Jan-28 | Not Started 0% | float -23.0d SC03CI0150 SC01AI0150 — 01A Function Testing | 29-Dec-27 → 29-Dec-27 | Not Started 0% | float -14.0d SC01BI0150 — 01B Function Testing | 29-Dec-27 → 19-Jan-28 | Not Started 0% | float -35.0d SC01BI0150 SC02JI0150 — 02J Function Testing | 29-Dec-27 → 23-Jan-28 | Not Started 0% | float 49.0d SC02JI0150 SC03DI0150 — 03D Function Testing | 30-Dec-27 → 04-Jan-28 | Not Started 0% | float -20.0d SC03DI0150 SC03YI0150 — 03Y Function Testing | 01-Jan-28 → 24-Jan-28 | Not Started 0% | float 48.0d SC03YI0150 SC02FI0150 — 02F Function Testing | 02-Jan-28 → 20-Jan-28 | Not Started 0% | float 52.0d SC02FI0150 SC03EI0150 — 03E Function Testing | 05-Jan-28 → 22-Jan-28 | Not Started 0% | float -38.0d SC03EI0150 SC02HI0150 — 02H Function Testing | 20-Jan-28 → 29-Feb-28 | Not Started 0% | float 12.0d SC02HI0150 SC05BI0150 — 05B Function Testing | 05-Feb-28 → 08-Feb-28 | Not Started 0% | float 79.0d SC02LI0150 — 02L Function Testing | 08-Feb-28 → 29-Mar-28 | Not Started 0% | float -17.0d SC02LI0150 SC03FT0130 — 03F Commission | 08-Feb-28 → 28-Feb-28 | Not Started 0% | float -47.0d SC03FT0130 SC000T0100 — 020 Commission ISBL | 29-Feb-28 → 28-Apr-28 | Not Started 0% | float -47.0d SC000T0100 SC05AI0150 — 05A Function Testing | 15-Mar-28 → 15-Apr-28 | Not Started 0% | float -34.0d SC05AI0150 SC000T0105 — 020 Startup ISBL | 11-May-28 → 24-Jun-28 | Not Started 0% | float -59.0d SC000T0105 SC000T0110 — Performance Test Period | 25-Jun-28 → 22-Sep-28 | Not Started 0% | float -59.0d SC000T0110 SC000YA100 — Construction Bonus Period | 23-Sep-28 → 15-Mar-29 | Not Started 0% | float -59.0d SC000YA100