EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 438 activities in 02 Ammonia Plant × clear
Code
Activity
Start
Finish
Flt
%
CO02HC0140
02H Form Pour Strip Fnds - Structure
21-Mar-26
27-Dec-26
12%
WO020C0100
020 Concrete & Excavation
21-Mar-26
23-Mar-27
215.0d
9%
CO02JC0150
02J Form, Pour, Strip Fnd - 104-D2 (Low Temp Shift Converter)
30-Mar-26
27-Dec-26
9%
CO02JC0160
02J Form, Pour, Strip Fnd - 104-D1 (High Temp Shift Converter)
30-Mar-26
27-Dec-26
9%
CO02JC0110
02J Form, Pour, Strip Fnds - Major Fnds Gen'l
01-Apr-26
27-Dec-26
9%
CO02LC0150
02L Form, Pour, Strip Fnd - 101-E (CO2 Absorber)
03-Apr-26
27-Dec-26
8%
CO02MC0110
02M Form, Pour, Strip Fnds - Major Fnds Gen'l
03-Apr-26
27-Dec-26
8%
CO02MC0140
02M Form Pour Strip Fnds - Structure
03-Apr-26
27-Dec-26
8%
CO02KC0150
02K Form, Pour, Strip Fnd - 114-F (Benfield Solution Tank)
04-Apr-26
27-Dec-26
7%
CO02BC0110
02B Form, Pour, Strip Fnds - Major Fnds
09-Apr-26
27-Dec-26
6%
CO02AC0110
02A Form, Pour, Strip Fnds - Major Fnds
15-Apr-26
09-Mar-27
189.0d
5%
CO02HC0150
02H Form, Pour, Strip Fnd - 103-D (Secondary Reformer)
21-Apr-26
27-Dec-26
5%
CO02CC0160
02C Form, Pour, Strip Fnd - 103-JTC
27-Dec-26
27-Dec-26
0%
CO02CM0140
02C Set - 103-JTC Surface Condenser
27-Dec-26
27-Dec-26
0%
CO02EC0110
02E Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
0%
CO02EC0140
02E Form Pour Strip Fnds - Structure
27-Dec-26
27-Dec-26
0%
CO02GC0160
02G Form, Pour, Strip Fnd - 102-J Fd Gas Compr. & Aux.
27-Dec-26
27-Dec-26
0%
CO02HC0110
02H Form, Pour, Strip Fnds - 101B (Primary Reformer)
27-Dec-26
27-Dec-26
0%
CO02HC0160
02H Form, Pour, Strip Fnd - 156-F (Steam Blowdown Drum)
27-Dec-26
27-Dec-26
0%
CO02HM0140
02H Set - 156-F Steam Blowdown Drum
27-Dec-26
27-Dec-26
0%
CO02LC0160
02L Form, Pour, Strip Fnd - 102-E (CO2 Stripper)
27-Dec-26
27-Dec-26
0%
CO02MC0150
02M Form, Pour, Strip Fnd - 105-D (Ammonia Synthesis Converter)
27-Dec-26
27-Dec-26
0%
CO02NC0110
02N Form, Pour, Strip Fnds - Major Fnds
27-Dec-26
27-Dec-26
0%
CO02YC0140
02Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
0%
CO02AU4120
02A U/G Piping Installation
28-Dec-26
29-Jan-27
222.0d
0%
CO02BU4120
02B U/G Piping Installation
28-Dec-26
29-Jan-27
219.0d
0%
CO02CC0110
02C Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
26-Jan-27
165.0d
0%
CO02CC0150
02C Form, Pour, Strip Fnd - 103/105-J & Table Tops
28-Dec-26
28-Dec-26
0%
CO02CM0110
02C Set Static Equipment - 128/167-C
28-Dec-26
28-Dec-26
0%
CO02CU4120
02C U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02DC0110
02D Form, Pour, Strip Fnds - Major Fnds
28-Dec-26
09-Jan-27
252.0d
0%
CO02DU4120
02D U/G Piping Installation
28-Dec-26
29-Jan-27
248.0d
0%
CO02EU4120
02E U/G Piping Installation
28-Dec-26
29-Jan-27
227.0d
0%
CO02FC0110
02F Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
234.0d
0%
CO02FU4120
02F U/G Piping Installation
28-Dec-26
29-Jan-27
234.0d
0%
CO02GC0150
02G Form, Pour, Strip Fnd - 101-J/JT & 2ea. Table Tops
28-Dec-26
01-Feb-27
134.0d
0%
CO02GM0140
02G Set/Install - 102-J Fd Gas Compr. & Aux.
28-Dec-26
22-Apr-27
188.0d
0%
CO02HU4120
02H U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02JU4120
02J U/G Piping Installation
28-Dec-26
29-Jan-27
211.0d
0%
CO02KC0110
02K Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
192.0d
0%
CO02KU4120
02K U/G Piping Installation
28-Dec-26
29-Jan-27
214.0d
0%
CO02LC0110
02L Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
123.0d
0%
CO02LC0140
02L Form Pour Strip Fnds - 02L Structure
28-Dec-26
29-Jan-27
45.0d
0%
CO02MU4120
02M U/G Piping Installation
28-Dec-26
29-Jan-27
239.0d
0%
CO02UP0130
02U LB Pipe Erection (CW & Misc Headers)
28-Dec-26
29-Jan-27
71.0d
0%
CO02UV1110
02U Paint Fabricated Pipe Spools (CW & Misc Headers)
28-Dec-26
28-Dec-26
0%
CO02YU3110
02Y U/G Earthing Installation
28-Dec-26
29-Jan-27
100.0d
0%
WO020M0100
020 Major Equipment
28-Dec-26
16-Aug-27
156.0d
0%
WO020U3100
020 Install U/G Electrical
28-Dec-26
12-Mar-27
265.0d
0%
WO020U4100
020 U/G Piping Installation
28-Dec-26
26-Feb-27
224.0d
0%
CO02HM0200
02H Start Primary Reformer Erection (101-B)
02-Jan-27
02-Jan-27
108.0d
0%
CO02HM0210
02H Erect Radiant Section Shell (101-B)
02-Jan-27
02-Apr-27
108.0d
0%
CO02LU4120
02L U/G Piping Installation
02-Jan-27
29-Jan-27
123.0d
0%
CO02GU4120
02G U/G Piping Installation
06-Jan-27
26-Feb-27
159.0d
0%
CO02CM0125
02C Set - 103/105-J Compressors
12-Jan-27
16-Jan-27
167.0d
0%
CO02YS0110
02Y Erect Structural Steel - Pipe Rack
12-Jan-27
14-Jun-27
-35.0d
0%
WO020S0100
020 Erect Steel
12-Jan-27
07-Oct-27
69.0d
0%
CO02HU3110
02H U/G Earthing Installation
13-Jan-27
12-Feb-27
162.0d
0%
CO02CU3110
02C U/G Earthing Installation
14-Jan-27
12-Feb-27
168.0d
0%
CO02HC0120
02H Form, Pour, Strip Fnds - Misc Fnds
16-Jan-27
05-Feb-27
174.0d
0%
CO02LU3110
02L U/G Earthing Installation
16-Jan-27
12-Feb-27
129.0d
0%
CO02UP0150
02U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO02CM0130
02C Install - 103/105-J Compressors & Aux. Equip.
18-Jan-27
13-May-27
167.0d
0%
CO02AU3110
02A U/G Earthing Installation
20-Jan-27
05-Feb-27
228.0d
0%
CO02CV1110
02C Paint Fabricated Pipe Spools
20-Jan-27
27-Feb-27
245.0d
0%
WO020V1100
020 Paint
20-Jan-27
14-Feb-28
23.0d
0%
CO02GC0110
02G Form, Pour, Strip Fnds - Major Fnds Gen'l
23-Jan-27
26-Feb-27
159.0d
0%
CO02JU3110
02J U/G Earthing Installation
25-Jan-27
12-Feb-27
211.0d
0%
CO02BM0110
02B Set Static Equipment
25-Jan-27
25-Jan-27
0%
CO02BV1130
02B Paint Touch-up - Equipment
25-Jan-27
01-Feb-27
300.0d
0%
CO02KU3110
02K U/G Earthing Installation
26-Jan-27
12-Feb-27
214.0d
0%
CO02EU3110
02E U/G Earthing Installation
28-Jan-27
12-Feb-27
227.0d
0%
CO02FU3110
02F U/G Earthing Installation
29-Jan-27
12-Feb-27
234.0d
0%
CO02BC0120
02B Form, Pour, Strip Fnds - Misc Fnds
29-Jan-27
29-Jan-27
0%
CO02CC0120
02C Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
162.0d
0%
CO02DC0120
02D Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
30-Jan-27
260.0d
0%
CO02EC0120
02E Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
227.0d
0%
CO02FC0120
02F Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
234.0d
0%
CO02FM0110
02F Set Static Equipment
30-Jan-27
26-Feb-27
241.0d
0%
CO02JC0120
02J Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
211.0d
0%
CO02KC0120
02K Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
214.0d
0%
CO02LC0120
02L Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
123.0d
0%
CO02MC0120
02M Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
239.0d
0%
CO02MU3110
02M U/G Earthing Installation
30-Jan-27
12-Feb-27
239.0d
0%
CO02YC0130
02Y Install Paving
30-Jan-27
17-Mar-27
71.0d
0%
WO020C0110
020 Concrete Paving
30-Jan-27
22-May-27
210.0d
0%
CO02DU3110
02D U/G Earthing Installation
02-Feb-27
12-Feb-27
248.0d
0%
CO02YV1110
02Y Paint Fabricated Pipe Spools
05-Feb-27
19-Feb-27
131.0d
0%
CO02BU3110
02B U/G Earthing Installation
10-Feb-27
12-Feb-27
289.0d
0%
CO02EV1110
02E Paint Fabricated Pipe Spools
12-Feb-27
04-Mar-27
250.0d
0%
CO02GU3110
02G U/G Earthing Installation
15-Feb-27
12-Mar-27
159.0d
0%
CO02GV1110
02G Paint Fabricated Pipe Spools
16-Feb-27
22-Mar-27
230.0d
0%
CO02CC0130
02C Install Paving
20-Feb-27
05-Mar-27
162.0d
0%
CO02LC0130
02L Install Paving
20-Feb-27
05-Mar-27
123.0d
0%
CO02HM0220
02H Erect Radiant Ducting / Burners (101-B)
22-Feb-27
20-Mar-27
151.0d
0%
CO02UDT110
02U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
SC02UT0120
02U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
CO02GC0120
02G Form, Pour, Strip Fnds - Misc Fnds
27-Feb-27
19-Mar-27
165.0d
0%
CO02GM0110
02G Set Static Equipment - Gen'l
27-Feb-27
31-Mar-27
208.0d
0%
CO02JS0130
02J Pre-Install Misc Steel - 104-D2
01-Mar-27
15-Mar-27
103.0d
0%
CO02JS0140
02J Pre-Install Misc Steel - 104-D1
01-Mar-27
15-Mar-27
108.0d
0%
CO02LS0130
02L Pre-Install Misc Steel - 101-E
01-Mar-27
15-Mar-27
113.0d
0%
CO02GM0125
02G Set - 101-J/JT Air Compr.
08-Mar-27
05-Apr-27
105.0d
0%
CO02AC0120
02A Form, Pour, Strip Fnds - Misc Fnds
10-Mar-27
23-Mar-27
189.0d
0%
CO02AM0150
02A Set Rotating Equipment
10-Mar-27
06-Apr-27
207.0d
0%
CO02GC0130
02G Install Paving
13-Mar-27
26-Mar-27
159.0d
0%
CO02HM0250
02H Set Forced Draft Fan (101-B)
15-Mar-27
12-Apr-27
234.0d
0%
CO02YS0120
02Y Erect Misc Steel - Pipe Rack
19-Mar-27
14-Jun-27
102.0d
0%
CO02HM0246
02H Install Radiant Sect Coils (101-B)
22-Mar-27
17-Apr-27
151.0d
0%
CO02HM0255
02H Set Induced Draft Fan (101-B)
22-Mar-27
19-Apr-27
234.0d
0%
CO02KV1130
02K Paint Touch-up - Equipment
23-Mar-27
15-Apr-27
236.0d
0%
CO02AC0130
02A Install Paving
24-Mar-27
30-Mar-27
189.0d
0%
CO02CM0150
02C Set Rotating Equipment - 112-J/JA/JM
26-Mar-27
30-Mar-27
205.0d
0%
CO02GM0150
02G Set Rotating Equipment
26-Mar-27
10-Apr-27
199.0d
0%
CO02KM0150
02K Set Rotating Equipment
26-Mar-27
01-Apr-27
163.0d
0%
CO02LM0150
02L Set Rotating Equipment
26-Mar-27
27-Apr-27
170.0d
0%
CO02HS0140
02H Install Misc Steel - 156-F
27-Mar-27
09-Apr-27
102.0d
0%
CO02JV1110
02J Paint Fabricated Pipe Spools
27-Mar-27
27-Mar-27
164.0d
0%
CO02AV1130
02A Paint Touch-up - Equipment
30-Mar-27
20-Apr-27
232.0d
0%
CO02MV1110
02M Paint Fabricated Pipe Spools
01-Apr-27
14-Apr-27
215.0d
0%
CO02NV1110
02N Paint Fabricated Pipe Spools
01-Apr-27
03-Apr-27
216.0d
0%
CO02DM0150
02D Set Rotating Equipment
02-Apr-27
15-Apr-27
182.0d
0%
CO02HC0130
02H Install Paving
03-Apr-27
16-Apr-27
120.0d
0%
CO02HM0230
02H Set Convection Sections (101-B)
03-Apr-27
30-Apr-27
108.0d
0%
CO02HM0240
02H Set Stack for (101-B)
03-Apr-27
30-Apr-27
223.0d
0%
CO02JC0130
02J Install Paving
05-Apr-27
10-Apr-27
168.0d
0%
CO02GM0130
02G Install - 101-J/JT Air Compr. & Gen. Turb. & Aux.
05-Apr-27
30-Jul-27
105.0d
0%
CO02HS0130
02H Pre-Install Misc Steel - 103-D
05-Apr-27
19-Apr-27
68.0d
0%
CO02FV1110
02F Paint Fabricated Pipe Spools
09-Apr-27
27-Apr-27
204.0d
0%
CO02LV1110
02L Paint Fabricated Pipe Spools
09-Apr-27
29-May-27
162.0d
0%
CO02KV1110
02K Paint Fabricated Pipe Spools
10-Apr-27
04-May-27
181.0d
0%
CO02LS0110
02L Erect Structure
10-Apr-27
18-Jun-27
-15.0d
0%
CO02KC0130
02K Install Paving
12-Apr-27
17-Apr-27
165.0d
0%
CO02YP0130
02Y LB Pipe Erection
13-Apr-27
05-Oct-27
-35.0d
0%
WO020P0100
020 Above Ground Pipe
13-Apr-27
14-Feb-28
-1.0d
0%
CO02DV1130
02D Paint Touch-up - Equipment
15-Apr-27
29-Apr-27
224.0d
0%
CO02FM0150
02F Set Rotating Equipment
16-Apr-27
13-May-27
176.0d
0%
CO02QV1110
02Q Paint Fabricated Pipe Spools
16-Apr-27
20-Apr-27
210.0d
0%
CO020M0110
Mobilize / Assemble / Test Heavy Lift Crane
19-Apr-27
01-May-27
56.0d
0%
CO02EC0130
02E Install Paving
19-Apr-27
24-Apr-27
172.0d
0%
CO02HM0248
02H Install Effluent Transfer Line (107-D)
19-Apr-27
01-May-27
151.0d
0%
CO02LS0140
02L Pre-Install Misc Steel - 102-E
19-Apr-27
03-May-27
76.0d
0%
CO02DV1110
02D Paint Fabricated Pipe Spools
23-Apr-27
07-May-27
177.0d
0%
CO02MS0110
02M Erect Structural Steel - Structure
24-Apr-27
14-May-27
123.0d
0%
CO02PV1110
02P Paint Fabricated Pipe Spools
24-Apr-27
28-Apr-27
199.0d
0%
CO02FC0130
02F Install Paving
26-Apr-27
01-May-27
173.0d
0%
CO02HV1110
02H Paint Fabricated Pipe Spools
26-Apr-27
05-Jun-27
54.0d
0%
CO02CS0120
02C Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
83.0d
0%
CO02GS0130
02G Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
107.0d
0%
CO02HM0235
02H Erect Preheater (101-B)
01-May-27
25-Jun-27
175.0d
0%
CO020M0120
Heavy Lift Crane Useage
03-May-27
04-Aug-27
56.0d
0%
CO02HM0130
02H Set (Heavy Lift) - 103-D (Secondary Reformer)
03-May-27
07-May-27
56.0d
0%
CO02HM0225
02H Erect Penthouse Roof, & Siding (101-B)
03-May-27
29-May-27
151.0d
0%
CO02MC0130
02M Install Paving
03-May-27
08-May-27
172.0d
0%
CO02KS0130
02K Pre-Install Misc Steel - Static Equipment
03-May-27
17-May-27
101.0d
0%
CO02GP0130
02G LB Pipe Erection
04-May-27
10-Sep-27
105.0d
0%
CO02CP0130
02C LB Pipe Erection
08-May-27
08-Oct-27
83.0d
0%
CO02DS0110
02D Erect Structural Steel
08-May-27
28-May-27
93.0d
0%
CO02JM0130
02J Set (Heavy Lift) - 104-D2 (Low Temp Shift Converter)
08-May-27
13-May-27
56.0d
0%
CO02LS0120
02L Erect Misc Steel
08-May-27
04-Jun-27
39.0d
0%
CO02DC0130
02D Install Paving
10-May-27
15-May-27
175.0d
0%
CO02FV1130
02F Paint Touch-up - Equipment
10-May-27
27-May-27
200.0d
0%
CO02MS0130
02M Pre-Install Misc Steel - 105-D
10-May-27
24-May-27
63.0d
0%
CO02YP0140
02Y SB Pipe Erection
11-May-27
02-Nov-27
-29.0d
0%
CO02GP0140
02G SB Pipe Erection
11-May-27
25-Sep-27
105.0d
0%
CO02CV1130
02C Paint Touch-up - Equipment
14-May-27
22-Jun-27
190.0d
0%
CO02JM0140
02J Set (Heavy Lift) - 104-D1 (High Temp Shift Converter)
14-May-27
19-May-27
56.0d
0%
CO02AS0110
02A Erect Structural Steel
15-May-27
04-Jun-27
103.0d
0%
CO02CP0140
02C SB Pipe Erection
15-May-27
15-Oct-27
83.0d
0%
CO02MM0110
02M Set Static Equipment - Gen'l
15-May-27
16-Jun-27
147.0d
0%
CO02BC0130
02B Install Paving
17-May-27
22-May-27
210.0d
0%
CO02KM0110
02K Set Static Equipment - Gen'l
17-May-27
07-Jun-27
101.0d
0%
CO02AV1110
02A Paint Fabricated Pipe Spools
20-May-27
02-Jun-27
172.0d
0%
CO02LM0130
02L Set (Heavy Lift) - 101-E (CO2 Absorber)
20-May-27
25-May-27
56.0d
0%
CO02ES0110
02E Erect Structural Steel
22-May-27
11-Jun-27
127.0d
0%
CO02ES0120
02E Erect Misc Steel
22-May-27
11-Jun-27
67.0d
0%
CO02FS0120
02F Erect Misc Steel
22-May-27
11-Jun-27
133.0d
0%
CO02JS0110
02J Erect Structural Steel - Structure
22-May-27
04-Jun-27
98.0d
0%
CO02MS0120
02M Erect Misc Steel - Structure
22-May-27
11-Jun-27
123.0d
0%
CO02BV1110
02B Paint Fabricated Pipe Spools
25-May-27
31-May-27
175.0d
0%
CO02LM0140
02L Set (Heavy Lift) - 102-E (CO2 Stripper)
26-May-27
31-May-27
56.0d
0%
CO02GE0130
02G Power/Control JB's, Tray, Cable, Termination
26-May-27
02-Oct-27
108.0d
0%
CO02GI0120
02G Instrument JB's, Field Instr, Tray, Cable
26-May-27
02-Oct-27
108.0d
0%
WO020E0100
020 Above Ground Electrical
26-May-27
14-Feb-28
23.0d
0%
WO020I0100
020 Install Instruments & Test
26-May-27
01-Mar-28
9.0d
0%
CO02CV2110
02C Insulate - Equipment
28-May-27
06-Jul-27
190.0d
0%
WO020V2100
020 Insulation
28-May-27
13-Mar-28
-1.0d
0%
CO02DM0110
02D Set Static Equipment
29-May-27
11-Jun-27
133.0d
0%
CO02DS0120
02D Erect Misc Steel
29-May-27
18-Jun-27
93.0d
0%
CO02EP0130
02E LB Pipe Erection
29-May-27
06-Nov-27
67.0d
0%
CO02HM0260
02H Compete Installation of Ducts (101-B)
29-May-27
23-Jul-27
175.0d
0%
CO02HM0215
02H Erect Fuel Gas Lines (101-B)
31-May-27
26-Jun-27
151.0d
0%
CO02HM0227
02H Install Spring Hangers & Align (101-B)
31-May-27
10-Jul-27
186.0d
0%
CO02HM0245
02H Install Insulation (101-B)
31-May-27
24-Jul-27
174.0d
0%
CO02CE0130
02C Power/Control JB's, Tray, Cable, Termination
01-Jun-27
22-Oct-27
88.0d
0%
CO02CI0120
02C Instrument JB's, Field Instr, Tray, Cable
01-Jun-27
22-Oct-27
88.0d
0%
CO02JM0110
02J Set Static Equipment - Gen'l
01-Jun-27
11-Jun-27
98.0d
0%
CO02MM0130
02M Set (Heavy Lift) - 105-D (Ammonia Converter)
01-Jun-27
05-Jun-27
56.0d
0%
CO02AM0110
02A Set Static Equipment
05-Jun-27
18-Jun-27
144.0d
0%
CO02JS0120
02J Erect Misc Steel - Structure
05-Jun-27
11-Jun-27
98.0d
0%
CO02LE0110
02L Lighting JB's, Stands, Tray & Cable
05-Jun-27
16-Jul-27
163.0d
0%
CO02FV2110
02F Insulate - Equipment
07-Jun-27
24-Jun-27
200.0d
0%
CO02MM0140
02M Set (Heavy Lift) - 121-C (Ammonia Conv./ Effl Exch.)
07-Jun-27
11-Jun-27
56.0d
0%
CO02KS0120
02K Erect Misc Steel
07-Jun-27
28-Jun-27
101.0d
0%
CO02KV2110
02K Insulate - Equipment
10-Jun-27
05-Jul-27
192.0d
0%
CO02AS0120
02A Erect Misc Steel
12-Jun-27
02-Jul-27
103.0d
0%
CO02BE0110
02B Lighting JB's, Stands, Tray & Cable
12-Jun-27
25-Jun-27
193.0d
0%
CO02EE0110
02E Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02EM0110
02E Set Static Equipment
12-Jun-27
09-Jul-27
127.0d
0%
CO02FE0110
02F Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02JE0110
02J Lighting JB's, Stands, Tray & Cable
12-Jun-27
23-Jul-27
157.0d
0%
CO02JP0130
02J LB Pipe Erection
12-Jun-27
27-Sep-27
98.0d
0%
CO02ME0110
02M Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02MV1130
02M Paint Touch-up - Equipment
12-Jun-27
29-Jun-27
172.0d
0%
CO02NM0110
02N Set (Heavy Lift) - 120-C (Ammonia Unitized Chiller)
12-Jun-27
17-Jun-27
56.0d
0%
CO02BV2110
02B Insulate - Equipment
14-Jun-27
19-Jun-27
204.0d
0%
CO02PM0110
02P Set 101-U Dearator
15-Jun-27
28-Jun-27
103.0d
0%
CO02QM0110
02Q Set 101-F Steam Drum
15-Jun-27
21-Jun-27
101.0d
0%
CO02NS0120
02N Erect Misc Steel
18-Jun-27
22-Jul-27
56.0d
0%
CO02DE0110
02D Lighting JB's, Stands, Tray & Cable
19-Jun-27
16-Jul-27
169.0d
0%
CO02JP0140
02J SB Pipe Erection
19-Jun-27
04-Oct-27
98.0d
0%
CO02LM0110
02L Set Static Equipment - Gen'l
19-Jun-27
21-Jul-27
103.0d
0%
CO02LM0120
02L Set Static Equipment - 02L Structure
19-Jun-27
30-Jul-27
-15.0d
0%
CO02QS0120
02Q Erect Misc Steel
22-Jun-27
12-Jul-27
101.0d
0%
CO02AV2110
02A Insulate - Equipment
25-Jun-27
16-Jul-27
181.0d
0%
CO02DV2110
02D Insulate - Equipment
25-Jun-27
09-Jul-27
187.0d
0%
CO02NP0130
02N LB Pipe Erection
25-Jun-27
10-Nov-27
56.0d
0%
CO02BE0120
02B Lighting Fixture Installation/Termination
26-Jun-27
02-Jul-27
193.0d
0%
CO02MP0130
02M LB Pipe Erection
28-Jun-27
08-Oct-27
92.0d
0%
CO02KE0110
02K Lighting JB's, Stands, Tray & Cable
28-Jun-27
09-Aug-27
144.0d
0%
CO02PS0120
02P Erect Misc Steel
29-Jun-27
26-Jul-27
103.0d
0%
CO02QP0130
02Q LB Pipe Erection
29-Jun-27
28-Sep-27
101.0d
0%
CO02YE0110
02Y Lighting JB's, Stands, Tray & Cable
29-Jun-27
12-Oct-27
90.0d
0%
CO02JE0130
02J Power/Control JB's, Tray, Cable, Termination
02-Jul-27
11-Oct-27
98.0d
0%
CO02JI0120
02J Instrument JB's, Field Instr, Tray, Cable
02-Jul-27
11-Oct-27
98.0d
0%
CO02AE0110
02A Lighting JB's, Stands, Tray & Cable
03-Jul-27
30-Jul-27
157.0d
0%
CO02EV1130
02E Paint Touch-up - Equipment
03-Jul-27
23-Jul-27
151.0d
0%
CO02FP0130
02F LB Pipe Erection
05-Jul-27
27-Sep-27
102.0d
0%
CO02GE0110
02G Lighting JB's, Stands, Tray & Cable
06-Jul-27
18-Aug-27
149.0d
0%
CO02PP0130
02P LB Pipe Erection
06-Jul-27
21-Sep-27
103.0d
0%
CO02EE0120
02E Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02FE0120
02F Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02ME0120
02M Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02MV2110
02M Insulate - Equipment
10-Jul-27
27-Jul-27
172.0d
0%
CO02DP0130
02D LB Pipe Erection
12-Jul-27
22-Oct-27
62.0d
0%
CO02FP0140
02F SB Pipe Erection
12-Jul-27
04-Oct-27
102.0d
0%
CO02KP0130
02K LB Pipe Erection
12-Jul-27
23-Oct-27
77.0d
0%
CO02QE0110
02Q Lighting JB's, Stands, Tray & Cable
13-Jul-27
19-Jul-27
162.0d
0%
CO02GP0150
02G Punchlist / Test Piping
16-Jul-27
02-Oct-27
105.0d
0%
CO02DE0120
02D Lighting Fixture Installation/Termination
17-Jul-27
30-Jul-27
169.0d
0%
CO02LE0120
02L Lighting Fixture Installation/Termination
17-Jul-27
06-Aug-27
163.0d
0%
CO02LP0130
02L LB Pipe Erection
17-Jul-27
31-Jan-28
-15.0d
0%
CO02LV1130
02L Paint Touch-up - Equipment
17-Jul-27
28-Sep-27
69.0d
0%
CO02AP0130
02A LB Pipe Erection
19-Jul-27
23-Oct-27
78.0d
0%
CO02BP0130
02B LB Pipe Erection
19-Jul-27
16-Aug-27
120.0d
0%
CO02KP0140
02K SB Pipe Erection
19-Jul-27
30-Oct-27
77.0d
0%
CO02QE0120
02Q Lighting Fixture Installation/Termination
20-Jul-27
26-Jul-27
173.0d
0%
CO02YE0130
02Y Power/Control JB's, Tray, Cable, Termination
20-Jul-27
16-Nov-27
-35.0d
0%
CO02YI0120
02Y Instrument JB's, Field Instr, Tray, Cable
20-Jul-27
16-Nov-27
-35.0d
0%
CO02FE0130
02F Power/Control JB's, Tray, Cable, Termination
22-Jul-27
11-Oct-27
104.0d
0%
CO02FI0120
02F Instrument JB's, Field Instr, Tray, Cable
22-Jul-27
11-Oct-27
104.0d
0%
CO02NE0110
02N Lighting JB's, Stands, Tray & Cable
23-Jul-27
12-Aug-27
152.0d
0%
CO02NV1130
02N Paint Touch-up - Equipment
23-Jul-27
29-Jul-27
146.0d
0%
CO02JE0120
02J Lighting Fixture Installation/Termination
24-Jul-27
13-Aug-27
157.0d
0%
CO02LP0140
02L SB Pipe Erection
24-Jul-27
07-Feb-28
-15.0d
0%
CO02HM0275
02H Complete Primary Reformer Erection (101-B)
24-Jul-27
24-Jul-27
174.0d
0%
CO02AP0140
02A SB Pipe Erection
26-Jul-27
30-Oct-27
78.0d
0%
CO02HP0130
02H LB Pipe Erection
27-Jul-27
05-Jan-28
10.0d
0%
CO02MP0140
02M SB Pipe Erection
27-Jul-27
15-Oct-27
92.0d
0%
CO02PE0110
02P Lighting JB's, Stands, Tray & Cable
27-Jul-27
02-Aug-27
150.0d
0%
CO02YV1120
02Y Paint Touch-up - Piping
27-Jul-27
09-Nov-27
101.0d
0%
CO02YV1130
02Y Paint Touch-up - Pipe Rack
27-Jul-27
09-Nov-27
101.0d
0%
CO02CP0150
02C Punchlist / Test Piping
28-Jul-27
22-Oct-27
83.0d
0%
CO02HM0120
02H Set (Heavey Lift) - 101-C & 102-C
30-Jul-27
04-Aug-27
10.0d
0%
CO02GV1130
02G Paint Touch-up - Equipment
30-Jul-27
25-Sep-27
116.0d
0%
CO02KE0130
02K Power/Control JB's, Tray, Cable, Termination
30-Jul-27
06-Nov-27
77.0d
0%
CO02KI0120
02K Instrument JB's, Field Instr, Tray, Cable
30-Jul-27
06-Nov-27
77.0d
0%
CO02AE0120
02A Lighting Fixture Installation/Termination
31-Jul-27
13-Aug-27
157.0d
0%
CO02EV2110
02E Insulate - Equipment
31-Jul-27
27-Aug-27
151.0d
0%
CO02CE0110
02C Lighting JB's, Stands, Tray & Cable
03-Aug-27
05-Oct-27
113.0d
0%
CO02GE0120
02G Lighting Fixture Installation/Termination
03-Aug-27
01-Sep-27
149.0d
0%
CO02HP0140
02H SB Pipe Erection
03-Aug-27
12-Jan-28
10.0d
0%
CO02PE0120
02P Lighting Fixture Installation/Termination
03-Aug-27
09-Aug-27
161.0d
0%
CO020M0130
Demobilize Heavy Lift Crane
05-Aug-27
16-Aug-27
56.0d
0%
CO02HS0110
02H Erect Structural Steel - Structure
05-Aug-27
07-Oct-27
10.0d
0%
CO02GV1120
02G Paint Touch-up - Piping
06-Aug-27
02-Oct-27
134.0d
0%
CO02AE0130
02A Power/Control JB's, Tray, Cable, Termination
07-Aug-27
06-Nov-27
78.0d
0%
CO02AI0120
02A Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
06-Nov-27
78.0d
0%
CO02ME0130
02M Power/Control JB's, Tray, Cable, Termination
07-Aug-27
22-Oct-27
95.0d
0%
CO02MI0120
02M Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
22-Oct-27
95.0d
0%
CO02BP0140
02B SB Pipe Erection
09-Aug-27
30-Aug-27
120.0d
0%
CO02JP0150
02J Punchlist / Test Piping
09-Aug-27
11-Oct-27
102.0d
0%
CO02KE0120
02K Lighting Fixture Installation/Termination
09-Aug-27
21-Sep-27
144.0d
0%
CO02YP0150
02Y Punchlist / Test Piping
10-Aug-27
09-Nov-27
65.0d
0%
CO02LE0130
02L Power/Control JB's, Tray, Cable, Termination
11-Aug-27
14-Feb-28
-12.0d
0%
CO02LI0120
02L Instrument JB's, Field Instr, Tray, Cable
11-Aug-27
14-Feb-28
-12.0d
0%
CO02NE0120
02N Lighting Fixture Installation/Termination
13-Aug-27
25-Aug-27
152.0d
0%
CO02NV2110
02N Insulate - Equipment
13-Aug-27
08-Sep-27
146.0d
0%
CO02EP0140
02E SB Pipe Erection
16-Aug-27
13-Nov-27
67.0d
0%
CO02LV2110
02L Insulate - Equipment
16-Aug-27
26-Oct-27
69.0d
0%
CO02HE0130
02H Power/Control JB's, Tray, Cable, Termination
23-Aug-27
19-Jan-28
15.0d
0%
CO02HI0120
02H Instrument JB's, Field Instr, Tray, Cable
23-Aug-27
19-Jan-28
15.0d
0%
CO02FP0150
02F Punchlist / Test Piping
25-Aug-27
11-Oct-27
102.0d
0%
CO02BE0130
02B Power/Control JB's, Tray, Cable, Termination
30-Aug-27
20-Sep-27
136.0d
0%
CO02BI0120
02B Instrument JB's, Field Instr, Tray, Cable
30-Aug-27
20-Sep-27
136.0d
0%
CO02PP0140
02P SB Pipe Erection
30-Aug-27
28-Sep-27
103.0d
0%
CO02BP0150
02B Punchlist / Test Piping
01-Sep-27
20-Sep-27
120.0d
0%
CO02BV1120
02B Paint Touch-up - Piping
01-Sep-27
20-Sep-27
144.0d
0%
CO02CV1120
02C Paint Touch-up - Piping
01-Sep-27
22-Oct-27
116.0d
0%
CO02GV2120
02G Insulate - Piping
03-Sep-27
30-Oct-27
110.0d
0%
CO02JV1120
02J Paint Touch-up - Piping
06-Sep-27
11-Oct-27
102.0d
0%
CO02JV1130
02J Paint Touch-up - Equipment
06-Sep-27
11-Oct-27
102.0d
0%
CO02EE0130
02E Power/Control JB's, Tray, Cable, Termination
08-Sep-27
26-Nov-27
67.0d
0%
CO02EI0120
02E Instrument JB's, Field Instr, Tray, Cable
08-Sep-27
26-Nov-27
67.0d
0%
CO02HV1130
02H Paint Touch-up - Equipment
10-Sep-27
28-Oct-27
52.0d
0%
CO02GV2110
02G Insulate - Equipment
10-Sep-27
23-Oct-27
116.0d
0%
CO02QP0140
02Q SB Pipe Erection
20-Sep-27
05-Oct-27
101.0d
0%
CO02BI0130
02B Install In Line Instruments
21-Sep-27
22-Sep-27
130.0d
0%
CO02PI0120
02P Instrument JB's, Field Instr, Tray, Cable
21-Sep-27
05-Oct-27
121.0d
0%
CO02FV1120
02F Paint Touch-up - Piping
23-Sep-27
11-Oct-27
126.0d
0%
CO02HE0110
02H Lighting JB's, Stands, Tray & Cable
24-Sep-27
04-Nov-27
87.0d
0%
CO02MP0150
02M Punchlist / Test Piping
24-Sep-27
22-Oct-27
92.0d
0%
CO02KP0150
02K Punchlist / Test Piping
27-Sep-27
06-Nov-27
80.0d
0%
CO02PP0150
02P Punchlist / Test Piping
28-Sep-27
05-Oct-27
107.0d
0%
CO02QI0120
02Q Instrument JB's, Field Instr, Tray, Cable
28-Sep-27
12-Oct-27
115.0d
0%
CO02CV2120
02C Insulate - Piping
29-Sep-27
25-Nov-27
92.0d
0%
CO02PV1130
02P Paint Touch-up - Equipment
29-Sep-27
02-Oct-27
103.0d
0%
CO02YV2120
02Y Insulate - Piping
29-Sep-27
27-Dec-27
65.0d
0%
CO02DP0140
02D SB Pipe Erection
30-Sep-27
25-Nov-27
62.0d
0%
CO02AP0150
02A Punchlist / Test Piping
01-Oct-27
06-Nov-27
79.0d
0%
CO02PV1120
02P Paint Touch-up - Piping
01-Oct-27
05-Oct-27
125.0d
0%
CO02GI0130
02G Install In Line Instruments
02-Oct-27
13-Oct-27
105.0d
0%
CO02QP0150
02Q Punchlist / Test Piping
05-Oct-27
12-Oct-27
101.0d
0%
CO02CE0120
02C Lighting Fixture Installation/Termination
06-Oct-27
26-Oct-27
113.0d
0%
CO02JV2120
02J Insulate - Piping
06-Oct-27
08-Nov-27
102.0d
0%
CO02MV1120
02M Paint Touch-up - Piping
06-Oct-27
22-Oct-27
116.0d
0%
CO02PI0130
02P Install In Line Instruments
06-Oct-27
06-Oct-27
118.0d
0%
CO02QV1120
02Q Paint Touch-up - Piping
06-Oct-27
09-Oct-27
121.0d
0%
CO02QV1130
02Q Paint Touch-up - Equipment
06-Oct-27
09-Oct-27
121.0d
0%
CO02DE0130
02D Power/Control JB's, Tray, Cable, Termination
11-Oct-27
02-Dec-27
68.0d
0%
CO02DI0120
02D Instrument JB's, Field Instr, Tray, Cable
11-Oct-27
02-Dec-27
68.0d
0%
CO02QV2110
02Q Insulate - Equipment
11-Oct-27
16-Oct-27
121.0d
0%
CO02BV2120
02B Insulate - Piping
12-Oct-27
18-Oct-27
120.0d
0%
CO02FI0130
02F Install In Line Instruments
12-Oct-27
16-Oct-27
109.0d
0%
CO02JI0130
02J Install In Line Instruments
12-Oct-27
19-Oct-27
104.0d
0%
CO02QI0130
02Q Install In Line Instruments
13-Oct-27
13-Oct-27
112.0d
0%
CO02YE0120
02Y Lighting Fixture Installation/Termination
13-Oct-27
27-Nov-27
90.0d
0%
CO02KV1120
02K Paint Touch-up - Piping
13-Oct-27
06-Nov-27
104.0d
0%
CO02FV2120
02F Insulate - Piping
14-Oct-27
08-Nov-27
102.0d
0%
CO02JV2110
02J Insulate - Equipment
14-Oct-27
08-Nov-27
102.0d
0%
CO02AV1120
02A Paint Touch-up - Piping
16-Oct-27
06-Nov-27
103.0d
0%
CO02HV2110
02H Insulate - Equipment
16-Oct-27
01-Dec-27
52.0d
0%
CO02EP0150
02E Punchlist / Test Piping
18-Oct-27
26-Nov-27
67.0d
0%
CO02CI0130
02C Install In Line Instruments
23-Oct-27
04-Nov-27
83.0d
0%
CO02MI0130
02M Install In Line Instruments
23-Oct-27
28-Oct-27
99.0d
0%
CO02PV2120
02P Insulate - Piping
27-Oct-27
02-Nov-27
107.0d
0%
CO02MV2120
02M Insulate - Piping
28-Oct-27
25-Nov-27
92.0d
0%
CO020K0100
020 Site Prep - Guard Posts & Gravel
01-Nov-27
01-Mar-28
9.0d
0%
CO02EV1120
02E Paint Touch-up - Piping
01-Nov-27
26-Nov-27
91.0d
0%
CO02PV2110
02P Insulate - Equipment
01-Nov-27
06-Nov-27
103.0d
0%
WO020K0100
020 Site Prep
01-Nov-27
01-Mar-28
9.0d
0%
CO02DP0150
02D Punchlist / Test Piping
02-Nov-27
02-Dec-27
62.0d
0%
CO02KV2120
02K Insulate - Piping
02-Nov-27
10-Dec-27
80.0d
0%
CO02QV2120
02Q Insulate - Piping
03-Nov-27
09-Nov-27
101.0d
0%
CO02AV2120
02A Insulate - Piping
05-Nov-27
10-Dec-27
79.0d
0%
CO02HE0120
02H Lighting Fixture Installation/Termination
05-Nov-27
01-Dec-27
87.0d
0%
CO02KI0130
02K Install In Line Instruments
06-Nov-27
15-Nov-27
83.0d
0%
CO02AI0130
02A Install In Line Instruments
08-Nov-27
13-Nov-27
84.0d
0%
CO02NP0140
02N SB Pipe Erection
08-Nov-27
17-Nov-27
56.0d
0%
CO02YI0130
02Y Install In Line Instruments
10-Nov-27
13-Dec-27
65.0d
0%
CO02HP0150
02H Punchlist / Test Piping
11-Nov-27
19-Jan-28
10.0d
0%
CO02DV1120
02D Paint Touch-up - Piping
12-Nov-27
02-Dec-27
86.0d
0%
CO02NE0130
02N Power/Control JB's, Tray, Cable, Termination
15-Nov-27
30-Nov-27
80.0d
0%
CO02NI0120
02N Instrument JB's, Field Instr, Tray, Cable
15-Nov-27
30-Nov-27
80.0d
0%
CO02LP0150
02L Punchlist / Test Piping
16-Nov-27
14-Feb-28
-15.0d
0%
CO02NV1120
02N Paint Touch-up - Piping
18-Nov-27
30-Nov-27
88.0d
0%
CO02NP0150
02N Punchlist / Test Piping
26-Nov-27
30-Nov-27
56.0d
0%
CO02EI0130
02E Install In Line Instruments
27-Nov-27
03-Dec-27
73.0d
0%
CO02EV2120
02E Insulate - Piping
27-Nov-27
24-Dec-27
67.0d
0%
CO02NI0130
02N Install In Line Instruments
01-Dec-27
01-Dec-27
75.0d
0%
CO02DI0130
02D Install In Line Instruments
03-Dec-27
07-Dec-27
70.0d
0%
CO02GI0140
02G Continuity Testing
07-Dec-27
16-Dec-27
54.0d
0%
CO02YI0140
02Y Continuity Testing
07-Dec-27
03-Jan-28
53.0d
0%
CO02DV2120
02D Insulate - Piping
10-Dec-27
30-Dec-27
62.0d
0%
CO02HV1120
02H Paint Touch-up - Piping
10-Dec-27
19-Jan-28
45.0d
0%
CO02AI0140
02A Continuity Testing
14-Dec-27
20-Dec-27
52.0d
0%
CO02BI0140
02B Continuity Testing
14-Dec-27
15-Dec-27
73.0d
0%
CO02KI0140
02K Continuity Testing
15-Dec-27
22-Dec-27
48.0d
0%
CO02BT0110
02B Mechanical Completion
15-Dec-27
15-Dec-27
75.0d
0%
CO02DI0140
02D Continuity Testing
16-Dec-27
20-Dec-27
59.0d
0%
CO02GT0110
02G Mechanical Completion
16-Dec-27
16-Dec-27
74.0d
0%
CO02CI0140
02C Continuity Testing
17-Dec-27
29-Dec-27
41.0d
0%
SC02BT0120
02B RFSU
18-Dec-27
18-Dec-27
85.0d
0%
CO02AT0110
02A Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02DT0110
02D Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02EI0140
02E Continuity Testing
21-Dec-27
27-Dec-27
47.0d
0%
CO02JI0140
02J Continuity Testing
21-Dec-27
28-Dec-27
42.0d
0%
CO02MI0140
02M Continuity Testing
21-Dec-27
25-Dec-27
51.0d
0%
CO02NI0140
02N Continuity Testing
22-Dec-27
22-Dec-27
67.0d
0%
CO02KT0110
02K Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02NT0110
02N Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02PI0140
02P Continuity Testing
23-Dec-27
23-Dec-27
64.0d
0%
CO02PT0110
02P Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
CO02HV2120
02H Insulate - Piping
24-Dec-27
16-Feb-28
21.0d
0%
CO02NV2120
02N Insulate - Piping
24-Dec-27
06-Jan-28
56.0d
0%
CO02QI0140
02Q Continuity Testing
24-Dec-27
24-Dec-27
63.0d
0%
CO02QT0110
02Q Mechanical Completion
24-Dec-27
24-Dec-27
67.0d
0%
CO02LV1120
02L Paint Touch-up - Piping
25-Dec-27
14-Feb-28
23.0d
0%
CO02MT0110
02M Mechanical Completion
25-Dec-27
25-Dec-27
66.0d
0%
CO02ET0110
02E Mechanical Completion
27-Dec-27
27-Dec-27
65.0d
0%
CO02FI0140
02F Continuity Testing
28-Dec-27
01-Jan-28
44.0d
0%
CO02JT0110
02J Mechanical Completion
28-Dec-27
28-Dec-27
64.0d
0%
SC02PT0120
02P RFSU
28-Dec-27
28-Dec-27
75.0d
0%
CO02CT0110
02C Mechanical Completion
29-Dec-27
29-Dec-27
63.0d
0%
SC02QT0120
02Q RFSU
29-Dec-27
29-Dec-27
74.0d
0%
CO02FT0110
02F Mechanical Completion
01-Jan-28
01-Jan-28
60.0d
0%
CO02YT0110
02Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
SC02DT0120
02D RFSU
04-Jan-28
04-Jan-28
68.0d
0%
CO02LV2120
02L Insulate - Piping
05-Jan-28
13-Mar-28
-1.0d
0%
SC02NT0120
02N RFSU
06-Jan-28
06-Jan-28
66.0d
0%
SC02GT0120
02G RFSU
09-Jan-28
09-Jan-28
63.0d
0%
SC02YT0120
02Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC02AT0120
02A RFSU
12-Jan-28
12-Jan-28
60.0d
0%
SC02MT0120
02M RFSU
12-Jan-28
12-Jan-28
60.0d
0%
CO02HI0140
02H Continuity Testing
14-Jan-28
26-Jan-28
15.0d
0%
SC02KT0120
02K RFSU
16-Jan-28
16-Jan-28
56.0d
0%
SC02ET0120
02E RFSU
17-Jan-28
17-Jan-28
55.0d
0%
CO02HI0130
02H Install In Line Instruments
20-Jan-28
01-Feb-28
10.0d
0%
SC02FT0120
02F RFSU
20-Jan-28
20-Jan-28
52.0d
0%
SC02JT0120
02J RFSU
23-Jan-28
23-Jan-28
49.0d
0%
SC02CT0120
02C RFSU
24-Jan-28
24-Jan-28
48.0d
0%
CO02HI0145
02H Contingency (101-B)
27-Jan-28
23-Feb-28
15.0d
0%
CO02LI0140
02L Continuity Testing
05-Feb-28
21-Feb-28
-12.0d
0%
CO02LI0130
02L Install In Line Instruments
15-Feb-28
01-Mar-28
-15.0d
0%
CO02LT0110
02L Mechanical Completion
21-Feb-28
21-Feb-28
17.0d
0%
CO02HT0110
02H Mechanical Completion
23-Feb-28
23-Feb-28
15.0d
0%
SC02HT0120
02H RFSU
29-Feb-28
29-Feb-28
12.0d
0%
SC02LT0120
02L RFSU
29-Mar-28
29-Mar-28
-17.0d
0%
23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan 07-Feb 14-Feb 21-Feb 28-Feb 06-Mar 13-Mar 20-Mar 27-Mar Data Date
CO02HC0140 — 02H Form Pour Strip Fnds - Structure | 21-Mar-26 → 27-Dec-26 | In Progress 12% | float — CO02HC0140 WO020C0100 — 020 Concrete & Excavation | 21-Mar-26 → 23-Mar-27 | In Progress 9% | float 215.0d WO020C0100 CO02JC0150 — 02J Form, Pour, Strip Fnd - 104-D2 (Low Temp Shift Converter) | 30-Mar-26 → 27-Dec-26 | In Progress 9% | float — CO02JC0150 CO02JC0160 — 02J Form, Pour, Strip Fnd - 104-D1 (High Temp Shift Converter) | 30-Mar-26 → 27-Dec-26 | In Progress 9% | float — CO02JC0160 CO02JC0110 — 02J Form, Pour, Strip Fnds - Major Fnds Gen'l | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — CO02JC0110 CO02LC0150 — 02L Form, Pour, Strip Fnd - 101-E (CO2 Absorber) | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — CO02LC0150 CO02MC0110 — 02M Form, Pour, Strip Fnds - Major Fnds Gen'l | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — CO02MC0110 CO02MC0140 — 02M Form Pour Strip Fnds - Structure | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — CO02MC0140 CO02KC0150 — 02K Form, Pour, Strip Fnd - 114-F (Benfield Solution Tank) | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — CO02KC0150 CO02BC0110 — 02B Form, Pour, Strip Fnds - Major Fnds | 09-Apr-26 → 27-Dec-26 | In Progress 6% | float — CO02BC0110 CO02AC0110 — 02A Form, Pour, Strip Fnds - Major Fnds | 15-Apr-26 → 09-Mar-27 | In Progress 5% | float 189.0d CO02AC0110 CO02HC0150 — 02H Form, Pour, Strip Fnd - 103-D (Secondary Reformer) | 21-Apr-26 → 27-Dec-26 | In Progress 5% | float — CO02HC0150 CO02CC0160 — 02C Form, Pour, Strip Fnd - 103-JTC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02CM0140 — 02C Set - 103-JTC Surface Condenser | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02EC0110 — 02E Form, Pour, Strip Fnds - Major Fnds Gen'l | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02EC0140 — 02E Form Pour Strip Fnds - Structure | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02GC0160 — 02G Form, Pour, Strip Fnd - 102-J Fd Gas Compr. & Aux. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HC0110 — 02H Form, Pour, Strip Fnds - 101B (Primary Reformer) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HC0160 — 02H Form, Pour, Strip Fnd - 156-F (Steam Blowdown Drum) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HM0140 — 02H Set - 156-F Steam Blowdown Drum | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02LC0160 — 02L Form, Pour, Strip Fnd - 102-E (CO2 Stripper) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02MC0150 — 02M Form, Pour, Strip Fnd - 105-D (Ammonia Synthesis Converter) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02NC0110 — 02N Form, Pour, Strip Fnds - Major Fnds | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02YC0140 — 02Y Form Pour Strip Fnds - Pipe Rack | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02AU4120 — 02A U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 222.0d CO02AU4120 CO02BU4120 — 02B U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 219.0d CO02BU4120 CO02CC0110 — 02C Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 26-Jan-27 | Not Started 0% | float 165.0d CO02CC0110 CO02CC0150 — 02C Form, Pour, Strip Fnd - 103/105-J & Table Tops | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO02CM0110 — 02C Set Static Equipment - 128/167-C | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO02CU4120 — 02C U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 162.0d CO02CU4120 CO02DC0110 — 02D Form, Pour, Strip Fnds - Major Fnds | 28-Dec-26 → 09-Jan-27 | Not Started 0% | float 252.0d CO02DC0110 CO02DU4120 — 02D U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 248.0d CO02DU4120 CO02EU4120 — 02E U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 227.0d CO02EU4120 CO02FC0110 — 02F Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 234.0d CO02FC0110 CO02FU4120 — 02F U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 234.0d CO02FU4120 CO02GC0150 — 02G Form, Pour, Strip Fnd - 101-J/JT & 2ea. Table Tops | 28-Dec-26 → 01-Feb-27 | Not Started 0% | float 134.0d CO02GC0150 CO02GM0140 — 02G Set/Install - 102-J Fd Gas Compr. & Aux. | 28-Dec-26 → 22-Apr-27 | Not Started 0% | float 188.0d CO02GM0140 CO02HU4120 — 02H U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 162.0d CO02HU4120 CO02JU4120 — 02J U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 211.0d CO02JU4120 CO02KC0110 — 02K Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 192.0d CO02KC0110 CO02KU4120 — 02K U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 214.0d CO02KU4120 CO02LC0110 — 02L Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 123.0d CO02LC0110 CO02LC0140 — 02L Form Pour Strip Fnds - 02L Structure | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 45.0d CO02LC0140 CO02MU4120 — 02M U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 239.0d CO02MU4120 CO02UP0130 — 02U LB Pipe Erection (CW & Misc Headers) | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 71.0d CO02UP0130 CO02UV1110 — 02U Paint Fabricated Pipe Spools (CW & Misc Headers) | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO02YU3110 — 02Y U/G Earthing Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 100.0d CO02YU3110 WO020M0100 — 020 Major Equipment | 28-Dec-26 → 16-Aug-27 | Not Started 0% | float 156.0d WO020M0100 WO020U3100 — 020 Install U/G Electrical | 28-Dec-26 → 12-Mar-27 | Not Started 0% | float 265.0d WO020U3100 WO020U4100 — 020 U/G Piping Installation | 28-Dec-26 → 26-Feb-27 | Not Started 0% | float 224.0d WO020U4100 CO02HM0200 — 02H Start Primary Reformer Erection (101-B) | 02-Jan-27 | Not Started CO02HM0210 — 02H Erect Radiant Section Shell (101-B) | 02-Jan-27 → 02-Apr-27 | Not Started 0% | float 108.0d CO02HM0210 CO02LU4120 — 02L U/G Piping Installation | 02-Jan-27 → 29-Jan-27 | Not Started 0% | float 123.0d CO02LU4120 CO02GU4120 — 02G U/G Piping Installation | 06-Jan-27 → 26-Feb-27 | Not Started 0% | float 159.0d CO02GU4120 CO02CM0125 — 02C Set - 103/105-J Compressors | 12-Jan-27 → 16-Jan-27 | Not Started 0% | float 167.0d CO02CM0125 CO02YS0110 — 02Y Erect Structural Steel - Pipe Rack | 12-Jan-27 → 14-Jun-27 | Not Started 0% | float -35.0d CO02YS0110 WO020S0100 — 020 Erect Steel | 12-Jan-27 → 07-Oct-27 | Not Started 0% | float 69.0d WO020S0100 CO02HU3110 — 02H U/G Earthing Installation | 13-Jan-27 → 12-Feb-27 | Not Started 0% | float 162.0d CO02HU3110 CO02CU3110 — 02C U/G Earthing Installation | 14-Jan-27 → 12-Feb-27 | Not Started 0% | float 168.0d CO02CU3110 CO02HC0120 — 02H Form, Pour, Strip Fnds - Misc Fnds | 16-Jan-27 → 05-Feb-27 | Not Started 0% | float 174.0d CO02HC0120 CO02LU3110 — 02L U/G Earthing Installation | 16-Jan-27 → 12-Feb-27 | Not Started 0% | float 129.0d CO02LU3110 CO02UP0150 — 02U LB Pipe Erection (Firewater Piping) | 16-Jan-27 → 06-Feb-27 | Not Started 0% | float 212.0d CO02UP0150 CO02CM0130 — 02C Install - 103/105-J Compressors & Aux. Equip. | 18-Jan-27 → 13-May-27 | Not Started 0% | float 167.0d CO02CM0130 CO02AU3110 — 02A U/G Earthing Installation | 20-Jan-27 → 05-Feb-27 | Not Started 0% | float 228.0d CO02AU3110 CO02CV1110 — 02C Paint Fabricated Pipe Spools | 20-Jan-27 → 27-Feb-27 | Not Started 0% | float 245.0d CO02CV1110 WO020V1100 — 020 Paint | 20-Jan-27 → 14-Feb-28 | Not Started 0% | float 23.0d WO020V1100 CO02GC0110 — 02G Form, Pour, Strip Fnds - Major Fnds Gen'l | 23-Jan-27 → 26-Feb-27 | Not Started 0% | float 159.0d CO02GC0110 CO02JU3110 — 02J U/G Earthing Installation | 25-Jan-27 → 12-Feb-27 | Not Started 0% | float 211.0d CO02JU3110 CO02BM0110 — 02B Set Static Equipment | 25-Jan-27 → 25-Jan-27 | Not Started 0% | float — CO02BV1130 — 02B Paint Touch-up - Equipment | 25-Jan-27 → 01-Feb-27 | Not Started 0% | float 300.0d CO02BV1130 CO02KU3110 — 02K U/G Earthing Installation | 26-Jan-27 → 12-Feb-27 | Not Started 0% | float 214.0d CO02KU3110 CO02EU3110 — 02E U/G Earthing Installation | 28-Jan-27 → 12-Feb-27 | Not Started 0% | float 227.0d CO02EU3110 CO02FU3110 — 02F U/G Earthing Installation | 29-Jan-27 → 12-Feb-27 | Not Started 0% | float 234.0d CO02FU3110 CO02BC0120 — 02B Form, Pour, Strip Fnds - Misc Fnds | 29-Jan-27 → 29-Jan-27 | Not Started 0% | float — CO02CC0120 — 02C Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 19-Feb-27 | Not Started 0% | float 162.0d CO02CC0120 CO02DC0120 — 02D Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 30-Jan-27 | Not Started 0% | float 260.0d CO02EC0120 — 02E Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 227.0d CO02EC0120 CO02FC0120 — 02F Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 234.0d CO02FC0120 CO02FM0110 — 02F Set Static Equipment | 30-Jan-27 → 26-Feb-27 | Not Started 0% | float 241.0d CO02FM0110 CO02JC0120 — 02J Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 211.0d CO02JC0120 CO02KC0120 — 02K Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 214.0d CO02KC0120 CO02LC0120 — 02L Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 19-Feb-27 | Not Started 0% | float 123.0d CO02LC0120 CO02MC0120 — 02M Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 239.0d CO02MC0120 CO02MU3110 — 02M U/G Earthing Installation | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 239.0d CO02MU3110 CO02YC0130 — 02Y Install Paving | 30-Jan-27 → 17-Mar-27 | Not Started 0% | float 71.0d CO02YC0130 WO020C0110 — 020 Concrete Paving | 30-Jan-27 → 22-May-27 | Not Started 0% | float 210.0d WO020C0110 CO02DU3110 — 02D U/G Earthing Installation | 02-Feb-27 → 12-Feb-27 | Not Started 0% | float 248.0d CO02DU3110 CO02YV1110 — 02Y Paint Fabricated Pipe Spools | 05-Feb-27 → 19-Feb-27 | Not Started 0% | float 131.0d CO02YV1110 CO02BU3110 — 02B U/G Earthing Installation | 10-Feb-27 → 12-Feb-27 | Not Started 0% | float 289.0d CO02BU3110 CO02EV1110 — 02E Paint Fabricated Pipe Spools | 12-Feb-27 → 04-Mar-27 | Not Started 0% | float 250.0d CO02EV1110 CO02GU3110 — 02G U/G Earthing Installation | 15-Feb-27 → 12-Mar-27 | Not Started 0% | float 159.0d CO02GU3110 CO02GV1110 — 02G Paint Fabricated Pipe Spools | 16-Feb-27 → 22-Mar-27 | Not Started 0% | float 230.0d CO02GV1110 CO02CC0130 — 02C Install Paving | 20-Feb-27 → 05-Mar-27 | Not Started 0% | float 162.0d CO02CC0130 CO02LC0130 — 02L Install Paving | 20-Feb-27 → 05-Mar-27 | Not Started 0% | float 123.0d CO02LC0130 CO02HM0220 — 02H Erect Radiant Ducting / Burners (101-B) | 22-Feb-27 → 20-Mar-27 | Not Started 0% | float 151.0d CO02HM0220 CO02UDT110 — 02U Mechanical Completion | 26-Feb-27 | Not Started SC02UT0120 — 02U RFSU | 26-Feb-27 | Not Started CO02GC0120 — 02G Form, Pour, Strip Fnds - Misc Fnds | 27-Feb-27 → 19-Mar-27 | Not Started 0% | float 165.0d CO02GC0120 CO02GM0110 — 02G Set Static Equipment - Gen'l | 27-Feb-27 → 31-Mar-27 | Not Started 0% | float 208.0d CO02GM0110 CO02JS0130 — 02J Pre-Install Misc Steel - 104-D2 | 01-Mar-27 → 15-Mar-27 | Not Started 0% | float 103.0d CO02JS0130 CO02JS0140 — 02J Pre-Install Misc Steel - 104-D1 | 01-Mar-27 → 15-Mar-27 | Not Started 0% | float 108.0d CO02JS0140 CO02LS0130 — 02L Pre-Install Misc Steel - 101-E | 01-Mar-27 → 15-Mar-27 | Not Started 0% | float 113.0d CO02LS0130 CO02GM0125 — 02G Set - 101-J/JT Air Compr. | 08-Mar-27 → 05-Apr-27 | Not Started 0% | float 105.0d CO02GM0125 CO02AC0120 — 02A Form, Pour, Strip Fnds - Misc Fnds | 10-Mar-27 → 23-Mar-27 | Not Started 0% | float 189.0d CO02AC0120 CO02AM0150 — 02A Set Rotating Equipment | 10-Mar-27 → 06-Apr-27 | Not Started 0% | float 207.0d CO02AM0150 CO02GC0130 — 02G Install Paving | 13-Mar-27 → 26-Mar-27 | Not Started 0% | float 159.0d CO02GC0130 CO02HM0250 — 02H Set Forced Draft Fan (101-B) | 15-Mar-27 → 12-Apr-27 | Not Started 0% | float 234.0d CO02HM0250 CO02YS0120 — 02Y Erect Misc Steel - Pipe Rack | 19-Mar-27 → 14-Jun-27 | Not Started 0% | float 102.0d CO02YS0120 CO02HM0246 — 02H Install Radiant Sect Coils (101-B) | 22-Mar-27 → 17-Apr-27 | Not Started 0% | float 151.0d CO02HM0246 CO02HM0255 — 02H Set Induced Draft Fan (101-B) | 22-Mar-27 → 19-Apr-27 | Not Started 0% | float 234.0d CO02HM0255 CO02KV1130 — 02K Paint Touch-up - Equipment | 23-Mar-27 → 15-Apr-27 | Not Started 0% | float 236.0d CO02KV1130 CO02AC0130 — 02A Install Paving | 24-Mar-27 → 30-Mar-27 | Not Started 0% | float 189.0d CO02AC0130 CO02CM0150 — 02C Set Rotating Equipment - 112-J/JA/JM | 26-Mar-27 → 30-Mar-27 | Not Started 0% | float 205.0d CO02CM0150 CO02GM0150 — 02G Set Rotating Equipment | 26-Mar-27 → 10-Apr-27 | Not Started 0% | float 199.0d CO02GM0150 CO02KM0150 — 02K Set Rotating Equipment | 26-Mar-27 → 01-Apr-27 | Not Started 0% | float 163.0d CO02KM0150 CO02LM0150 — 02L Set Rotating Equipment | 26-Mar-27 → 27-Apr-27 | Not Started 0% | float 170.0d CO02LM0150 CO02HS0140 — 02H Install Misc Steel - 156-F | 27-Mar-27 → 09-Apr-27 | Not Started 0% | float 102.0d CO02HS0140 CO02JV1110 — 02J Paint Fabricated Pipe Spools | 27-Mar-27 → 27-Mar-27 | Not Started 0% | float 164.0d CO02AV1130 — 02A Paint Touch-up - Equipment | 30-Mar-27 → 20-Apr-27 | Not Started 0% | float 232.0d CO02AV1130 CO02MV1110 — 02M Paint Fabricated Pipe Spools | 01-Apr-27 → 14-Apr-27 | Not Started 0% | float 215.0d CO02MV1110 CO02NV1110 — 02N Paint Fabricated Pipe Spools | 01-Apr-27 → 03-Apr-27 | Not Started 0% | float 216.0d CO02NV1110 CO02DM0150 — 02D Set Rotating Equipment | 02-Apr-27 → 15-Apr-27 | Not Started 0% | float 182.0d CO02DM0150 CO02HC0130 — 02H Install Paving | 03-Apr-27 → 16-Apr-27 | Not Started 0% | float 120.0d CO02HC0130 CO02HM0230 — 02H Set Convection Sections (101-B) | 03-Apr-27 → 30-Apr-27 | Not Started 0% | float 108.0d CO02HM0230 CO02HM0240 — 02H Set Stack for (101-B) | 03-Apr-27 → 30-Apr-27 | Not Started 0% | float 223.0d CO02HM0240 CO02JC0130 — 02J Install Paving | 05-Apr-27 → 10-Apr-27 | Not Started 0% | float 168.0d CO02JC0130 CO02GM0130 — 02G Install - 101-J/JT Air Compr. & Gen. Turb. & Aux. | 05-Apr-27 → 30-Jul-27 | Not Started 0% | float 105.0d CO02GM0130 CO02HS0130 — 02H Pre-Install Misc Steel - 103-D | 05-Apr-27 → 19-Apr-27 | Not Started 0% | float 68.0d CO02HS0130 CO02FV1110 — 02F Paint Fabricated Pipe Spools | 09-Apr-27 → 27-Apr-27 | Not Started 0% | float 204.0d CO02FV1110 CO02LV1110 — 02L Paint Fabricated Pipe Spools | 09-Apr-27 → 29-May-27 | Not Started 0% | float 162.0d CO02LV1110 CO02KV1110 — 02K Paint Fabricated Pipe Spools | 10-Apr-27 → 04-May-27 | Not Started 0% | float 181.0d CO02KV1110 CO02LS0110 — 02L Erect Structure | 10-Apr-27 → 18-Jun-27 | Not Started 0% | float -15.0d CO02LS0110 CO02KC0130 — 02K Install Paving | 12-Apr-27 → 17-Apr-27 | Not Started 0% | float 165.0d CO02KC0130 CO02YP0130 — 02Y LB Pipe Erection | 13-Apr-27 → 05-Oct-27 | Not Started 0% | float -35.0d CO02YP0130 WO020P0100 — 020 Above Ground Pipe | 13-Apr-27 → 14-Feb-28 | Not Started 0% | float -1.0d WO020P0100 CO02DV1130 — 02D Paint Touch-up - Equipment | 15-Apr-27 → 29-Apr-27 | Not Started 0% | float 224.0d CO02DV1130 CO02FM0150 — 02F Set Rotating Equipment | 16-Apr-27 → 13-May-27 | Not Started 0% | float 176.0d CO02FM0150 CO02QV1110 — 02Q Paint Fabricated Pipe Spools | 16-Apr-27 → 20-Apr-27 | Not Started 0% | float 210.0d CO02QV1110 CO020M0110 — Mobilize / Assemble / Test Heavy Lift Crane | 19-Apr-27 → 01-May-27 | Not Started 0% | float 56.0d CO020M0110 CO02EC0130 — 02E Install Paving | 19-Apr-27 → 24-Apr-27 | Not Started 0% | float 172.0d CO02EC0130 CO02HM0248 — 02H Install Effluent Transfer Line (107-D) | 19-Apr-27 → 01-May-27 | Not Started 0% | float 151.0d CO02HM0248 CO02LS0140 — 02L Pre-Install Misc Steel - 102-E | 19-Apr-27 → 03-May-27 | Not Started 0% | float 76.0d CO02LS0140 CO02DV1110 — 02D Paint Fabricated Pipe Spools | 23-Apr-27 → 07-May-27 | Not Started 0% | float 177.0d CO02DV1110 CO02MS0110 — 02M Erect Structural Steel - Structure | 24-Apr-27 → 14-May-27 | Not Started 0% | float 123.0d CO02MS0110 CO02PV1110 — 02P Paint Fabricated Pipe Spools | 24-Apr-27 → 28-Apr-27 | Not Started 0% | float 199.0d CO02PV1110 CO02FC0130 — 02F Install Paving | 26-Apr-27 → 01-May-27 | Not Started 0% | float 173.0d CO02FC0130 CO02HV1110 — 02H Paint Fabricated Pipe Spools | 26-Apr-27 → 05-Jun-27 | Not Started 0% | float 54.0d CO02HV1110 CO02CS0120 — 02C Erect Misc. Steel (Platforms) | 01-May-27 → 02-Aug-27 | Not Started 0% | float 83.0d CO02CS0120 CO02GS0130 — 02G Erect Misc. Steel (Platforms) | 01-May-27 → 02-Aug-27 | Not Started 0% | float 107.0d CO02GS0130 CO02HM0235 — 02H Erect Preheater (101-B) | 01-May-27 → 25-Jun-27 | Not Started 0% | float 175.0d CO02HM0235 CO020M0120 — Heavy Lift Crane Useage | 03-May-27 → 04-Aug-27 | Not Started 0% | float 56.0d CO020M0120 CO02HM0130 — 02H Set (Heavy Lift) - 103-D (Secondary Reformer) | 03-May-27 → 07-May-27 | Not Started 0% | float 56.0d CO02HM0130 CO02HM0225 — 02H Erect Penthouse Roof, & Siding (101-B) | 03-May-27 → 29-May-27 | Not Started 0% | float 151.0d CO02HM0225 CO02MC0130 — 02M Install Paving | 03-May-27 → 08-May-27 | Not Started 0% | float 172.0d CO02MC0130 CO02KS0130 — 02K Pre-Install Misc Steel - Static Equipment | 03-May-27 → 17-May-27 | Not Started 0% | float 101.0d CO02KS0130 CO02GP0130 — 02G LB Pipe Erection | 04-May-27 → 10-Sep-27 | Not Started 0% | float 105.0d CO02GP0130 CO02CP0130 — 02C LB Pipe Erection | 08-May-27 → 08-Oct-27 | Not Started 0% | float 83.0d CO02CP0130 CO02DS0110 — 02D Erect Structural Steel | 08-May-27 → 28-May-27 | Not Started 0% | float 93.0d CO02DS0110 CO02JM0130 — 02J Set (Heavy Lift) - 104-D2 (Low Temp Shift Converter) | 08-May-27 → 13-May-27 | Not Started 0% | float 56.0d CO02JM0130 CO02LS0120 — 02L Erect Misc Steel | 08-May-27 → 04-Jun-27 | Not Started 0% | float 39.0d CO02LS0120 CO02DC0130 — 02D Install Paving | 10-May-27 → 15-May-27 | Not Started 0% | float 175.0d CO02DC0130 CO02FV1130 — 02F Paint Touch-up - Equipment | 10-May-27 → 27-May-27 | Not Started 0% | float 200.0d CO02FV1130 CO02MS0130 — 02M Pre-Install Misc Steel - 105-D | 10-May-27 → 24-May-27 | Not Started 0% | float 63.0d CO02MS0130 CO02YP0140 — 02Y SB Pipe Erection | 11-May-27 → 02-Nov-27 | Not Started 0% | float -29.0d CO02YP0140 CO02GP0140 — 02G SB Pipe Erection | 11-May-27 → 25-Sep-27 | Not Started 0% | float 105.0d CO02GP0140 CO02CV1130 — 02C Paint Touch-up - Equipment | 14-May-27 → 22-Jun-27 | Not Started 0% | float 190.0d CO02CV1130 CO02JM0140 — 02J Set (Heavy Lift) - 104-D1 (High Temp Shift Converter) | 14-May-27 → 19-May-27 | Not Started 0% | float 56.0d CO02JM0140 CO02AS0110 — 02A Erect Structural Steel | 15-May-27 → 04-Jun-27 | Not Started 0% | float 103.0d CO02AS0110 CO02CP0140 — 02C SB Pipe Erection | 15-May-27 → 15-Oct-27 | Not Started 0% | float 83.0d CO02CP0140 CO02MM0110 — 02M Set Static Equipment - Gen'l | 15-May-27 → 16-Jun-27 | Not Started 0% | float 147.0d CO02MM0110 CO02BC0130 — 02B Install Paving | 17-May-27 → 22-May-27 | Not Started 0% | float 210.0d CO02BC0130 CO02KM0110 — 02K Set Static Equipment - Gen'l | 17-May-27 → 07-Jun-27 | Not Started 0% | float 101.0d CO02KM0110 CO02AV1110 — 02A Paint Fabricated Pipe Spools | 20-May-27 → 02-Jun-27 | Not Started 0% | float 172.0d CO02AV1110 CO02LM0130 — 02L Set (Heavy Lift) - 101-E (CO2 Absorber) | 20-May-27 → 25-May-27 | Not Started 0% | float 56.0d CO02LM0130 CO02ES0110 — 02E Erect Structural Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 127.0d CO02ES0110 CO02ES0120 — 02E Erect Misc Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 67.0d CO02ES0120 CO02FS0120 — 02F Erect Misc Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 133.0d CO02FS0120 CO02JS0110 — 02J Erect Structural Steel - Structure | 22-May-27 → 04-Jun-27 | Not Started 0% | float 98.0d CO02JS0110 CO02MS0120 — 02M Erect Misc Steel - Structure | 22-May-27 → 11-Jun-27 | Not Started 0% | float 123.0d CO02MS0120 CO02BV1110 — 02B Paint Fabricated Pipe Spools | 25-May-27 → 31-May-27 | Not Started 0% | float 175.0d CO02BV1110 CO02LM0140 — 02L Set (Heavy Lift) - 102-E (CO2 Stripper) | 26-May-27 → 31-May-27 | Not Started 0% | float 56.0d CO02LM0140 CO02GE0130 — 02G Power/Control JB's, Tray, Cable, Termination | 26-May-27 → 02-Oct-27 | Not Started 0% | float 108.0d CO02GE0130 CO02GI0120 — 02G Instrument JB's, Field Instr, Tray, Cable | 26-May-27 → 02-Oct-27 | Not Started 0% | float 108.0d CO02GI0120 WO020E0100 — 020 Above Ground Electrical | 26-May-27 → 14-Feb-28 | Not Started 0% | float 23.0d WO020E0100 WO020I0100 — 020 Install Instruments & Test | 26-May-27 → 01-Mar-28 | Not Started 0% | float 9.0d WO020I0100 CO02CV2110 — 02C Insulate - Equipment | 28-May-27 → 06-Jul-27 | Not Started 0% | float 190.0d CO02CV2110 WO020V2100 — 020 Insulation | 28-May-27 → 13-Mar-28 | Not Started 0% | float -1.0d WO020V2100 CO02DM0110 — 02D Set Static Equipment | 29-May-27 → 11-Jun-27 | Not Started 0% | float 133.0d CO02DM0110 CO02DS0120 — 02D Erect Misc Steel | 29-May-27 → 18-Jun-27 | Not Started 0% | float 93.0d CO02DS0120 CO02EP0130 — 02E LB Pipe Erection | 29-May-27 → 06-Nov-27 | Not Started 0% | float 67.0d CO02EP0130 CO02HM0260 — 02H Compete Installation of Ducts (101-B) | 29-May-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02HM0260 CO02HM0215 — 02H Erect Fuel Gas Lines (101-B) | 31-May-27 → 26-Jun-27 | Not Started 0% | float 151.0d CO02HM0215 CO02HM0227 — 02H Install Spring Hangers & Align (101-B) | 31-May-27 → 10-Jul-27 | Not Started 0% | float 186.0d CO02HM0227 CO02HM0245 — 02H Install Insulation (101-B) | 31-May-27 → 24-Jul-27 | Not Started 0% | float 174.0d CO02HM0245 CO02CE0130 — 02C Power/Control JB's, Tray, Cable, Termination | 01-Jun-27 → 22-Oct-27 | Not Started 0% | float 88.0d CO02CE0130 CO02CI0120 — 02C Instrument JB's, Field Instr, Tray, Cable | 01-Jun-27 → 22-Oct-27 | Not Started 0% | float 88.0d CO02CI0120 CO02JM0110 — 02J Set Static Equipment - Gen'l | 01-Jun-27 → 11-Jun-27 | Not Started 0% | float 98.0d CO02JM0110 CO02MM0130 — 02M Set (Heavy Lift) - 105-D (Ammonia Converter) | 01-Jun-27 → 05-Jun-27 | Not Started 0% | float 56.0d CO02MM0130 CO02AM0110 — 02A Set Static Equipment | 05-Jun-27 → 18-Jun-27 | Not Started 0% | float 144.0d CO02AM0110 CO02JS0120 — 02J Erect Misc Steel - Structure | 05-Jun-27 → 11-Jun-27 | Not Started 0% | float 98.0d CO02JS0120 CO02LE0110 — 02L Lighting JB's, Stands, Tray & Cable | 05-Jun-27 → 16-Jul-27 | Not Started 0% | float 163.0d CO02LE0110 CO02FV2110 — 02F Insulate - Equipment | 07-Jun-27 → 24-Jun-27 | Not Started 0% | float 200.0d CO02FV2110 CO02MM0140 — 02M Set (Heavy Lift) - 121-C (Ammonia Conv./ Effl Exch.) | 07-Jun-27 → 11-Jun-27 | Not Started 0% | float 56.0d CO02MM0140 CO02KS0120 — 02K Erect Misc Steel | 07-Jun-27 → 28-Jun-27 | Not Started 0% | float 101.0d CO02KS0120 CO02KV2110 — 02K Insulate - Equipment | 10-Jun-27 → 05-Jul-27 | Not Started 0% | float 192.0d CO02KV2110 CO02AS0120 — 02A Erect Misc Steel | 12-Jun-27 → 02-Jul-27 | Not Started 0% | float 103.0d CO02AS0120 CO02BE0110 — 02B Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 25-Jun-27 | Not Started 0% | float 193.0d CO02BE0110 CO02EE0110 — 02E Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 175.0d CO02EE0110 CO02EM0110 — 02E Set Static Equipment | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 127.0d CO02EM0110 CO02FE0110 — 02F Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 175.0d CO02FE0110 CO02JE0110 — 02J Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 23-Jul-27 | Not Started 0% | float 157.0d CO02JE0110 CO02JP0130 — 02J LB Pipe Erection | 12-Jun-27 → 27-Sep-27 | Not Started 0% | float 98.0d CO02JP0130 CO02ME0110 — 02M Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 175.0d CO02ME0110 CO02MV1130 — 02M Paint Touch-up - Equipment | 12-Jun-27 → 29-Jun-27 | Not Started 0% | float 172.0d CO02MV1130 CO02NM0110 — 02N Set (Heavy Lift) - 120-C (Ammonia Unitized Chiller) | 12-Jun-27 → 17-Jun-27 | Not Started 0% | float 56.0d CO02NM0110 CO02BV2110 — 02B Insulate - Equipment | 14-Jun-27 → 19-Jun-27 | Not Started 0% | float 204.0d CO02BV2110 CO02PM0110 — 02P Set 101-U Dearator | 15-Jun-27 → 28-Jun-27 | Not Started 0% | float 103.0d CO02PM0110 CO02QM0110 — 02Q Set 101-F Steam Drum | 15-Jun-27 → 21-Jun-27 | Not Started 0% | float 101.0d CO02QM0110 CO02NS0120 — 02N Erect Misc Steel | 18-Jun-27 → 22-Jul-27 | Not Started 0% | float 56.0d CO02NS0120 CO02DE0110 — 02D Lighting JB's, Stands, Tray & Cable | 19-Jun-27 → 16-Jul-27 | Not Started 0% | float 169.0d CO02DE0110 CO02JP0140 — 02J SB Pipe Erection | 19-Jun-27 → 04-Oct-27 | Not Started 0% | float 98.0d CO02JP0140 CO02LM0110 — 02L Set Static Equipment - Gen'l | 19-Jun-27 → 21-Jul-27 | Not Started 0% | float 103.0d CO02LM0110 CO02LM0120 — 02L Set Static Equipment - 02L Structure | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float -15.0d CO02LM0120 CO02QS0120 — 02Q Erect Misc Steel | 22-Jun-27 → 12-Jul-27 | Not Started 0% | float 101.0d CO02QS0120 CO02AV2110 — 02A Insulate - Equipment | 25-Jun-27 → 16-Jul-27 | Not Started 0% | float 181.0d CO02AV2110 CO02DV2110 — 02D Insulate - Equipment | 25-Jun-27 → 09-Jul-27 | Not Started 0% | float 187.0d CO02DV2110 CO02NP0130 — 02N LB Pipe Erection | 25-Jun-27 → 10-Nov-27 | Not Started 0% | float 56.0d CO02NP0130 CO02BE0120 — 02B Lighting Fixture Installation/Termination | 26-Jun-27 → 02-Jul-27 | Not Started 0% | float 193.0d CO02BE0120 CO02MP0130 — 02M LB Pipe Erection | 28-Jun-27 → 08-Oct-27 | Not Started 0% | float 92.0d CO02MP0130 CO02KE0110 — 02K Lighting JB's, Stands, Tray & Cable | 28-Jun-27 → 09-Aug-27 | Not Started 0% | float 144.0d CO02KE0110 CO02PS0120 — 02P Erect Misc Steel | 29-Jun-27 → 26-Jul-27 | Not Started 0% | float 103.0d CO02PS0120 CO02QP0130 — 02Q LB Pipe Erection | 29-Jun-27 → 28-Sep-27 | Not Started 0% | float 101.0d CO02QP0130 CO02YE0110 — 02Y Lighting JB's, Stands, Tray & Cable | 29-Jun-27 → 12-Oct-27 | Not Started 0% | float 90.0d CO02YE0110 CO02JE0130 — 02J Power/Control JB's, Tray, Cable, Termination | 02-Jul-27 → 11-Oct-27 | Not Started 0% | float 98.0d CO02JE0130 CO02JI0120 — 02J Instrument JB's, Field Instr, Tray, Cable | 02-Jul-27 → 11-Oct-27 | Not Started 0% | float 98.0d CO02JI0120 CO02AE0110 — 02A Lighting JB's, Stands, Tray & Cable | 03-Jul-27 → 30-Jul-27 | Not Started 0% | float 157.0d CO02AE0110 CO02EV1130 — 02E Paint Touch-up - Equipment | 03-Jul-27 → 23-Jul-27 | Not Started 0% | float 151.0d CO02EV1130 CO02FP0130 — 02F LB Pipe Erection | 05-Jul-27 → 27-Sep-27 | Not Started 0% | float 102.0d CO02FP0130 CO02GE0110 — 02G Lighting JB's, Stands, Tray & Cable | 06-Jul-27 → 18-Aug-27 | Not Started 0% | float 149.0d CO02GE0110 CO02PP0130 — 02P LB Pipe Erection | 06-Jul-27 → 21-Sep-27 | Not Started 0% | float 103.0d CO02PP0130 CO02EE0120 — 02E Lighting Fixture Installation/Termination | 10-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02EE0120 CO02FE0120 — 02F Lighting Fixture Installation/Termination | 10-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02FE0120 CO02ME0120 — 02M Lighting Fixture Installation/Termination | 10-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02ME0120 CO02MV2110 — 02M Insulate - Equipment | 10-Jul-27 → 27-Jul-27 | Not Started 0% | float 172.0d CO02MV2110 CO02DP0130 — 02D LB Pipe Erection | 12-Jul-27 → 22-Oct-27 | Not Started 0% | float 62.0d CO02DP0130 CO02FP0140 — 02F SB Pipe Erection | 12-Jul-27 → 04-Oct-27 | Not Started 0% | float 102.0d CO02FP0140 CO02KP0130 — 02K LB Pipe Erection | 12-Jul-27 → 23-Oct-27 | Not Started 0% | float 77.0d CO02KP0130 CO02QE0110 — 02Q Lighting JB's, Stands, Tray & Cable | 13-Jul-27 → 19-Jul-27 | Not Started 0% | float 162.0d CO02QE0110 CO02GP0150 — 02G Punchlist / Test Piping | 16-Jul-27 → 02-Oct-27 | Not Started 0% | float 105.0d CO02GP0150 CO02DE0120 — 02D Lighting Fixture Installation/Termination | 17-Jul-27 → 30-Jul-27 | Not Started 0% | float 169.0d CO02DE0120 CO02LE0120 — 02L Lighting Fixture Installation/Termination | 17-Jul-27 → 06-Aug-27 | Not Started 0% | float 163.0d CO02LE0120 CO02LP0130 — 02L LB Pipe Erection | 17-Jul-27 → 31-Jan-28 | Not Started 0% | float -15.0d CO02LP0130 CO02LV1130 — 02L Paint Touch-up - Equipment | 17-Jul-27 → 28-Sep-27 | Not Started 0% | float 69.0d CO02LV1130 CO02AP0130 — 02A LB Pipe Erection | 19-Jul-27 → 23-Oct-27 | Not Started 0% | float 78.0d CO02AP0130 CO02BP0130 — 02B LB Pipe Erection | 19-Jul-27 → 16-Aug-27 | Not Started 0% | float 120.0d CO02BP0130 CO02KP0140 — 02K SB Pipe Erection | 19-Jul-27 → 30-Oct-27 | Not Started 0% | float 77.0d CO02KP0140 CO02QE0120 — 02Q Lighting Fixture Installation/Termination | 20-Jul-27 → 26-Jul-27 | Not Started 0% | float 173.0d CO02QE0120 CO02YE0130 — 02Y Power/Control JB's, Tray, Cable, Termination | 20-Jul-27 → 16-Nov-27 | Not Started 0% | float -35.0d CO02YE0130 CO02YI0120 — 02Y Instrument JB's, Field Instr, Tray, Cable | 20-Jul-27 → 16-Nov-27 | Not Started 0% | float -35.0d CO02YI0120 CO02FE0130 — 02F Power/Control JB's, Tray, Cable, Termination | 22-Jul-27 → 11-Oct-27 | Not Started 0% | float 104.0d CO02FE0130 CO02FI0120 — 02F Instrument JB's, Field Instr, Tray, Cable | 22-Jul-27 → 11-Oct-27 | Not Started 0% | float 104.0d CO02FI0120 CO02NE0110 — 02N Lighting JB's, Stands, Tray & Cable | 23-Jul-27 → 12-Aug-27 | Not Started 0% | float 152.0d CO02NE0110 CO02NV1130 — 02N Paint Touch-up - Equipment | 23-Jul-27 → 29-Jul-27 | Not Started 0% | float 146.0d CO02NV1130 CO02JE0120 — 02J Lighting Fixture Installation/Termination | 24-Jul-27 → 13-Aug-27 | Not Started 0% | float 157.0d CO02JE0120 CO02LP0140 — 02L SB Pipe Erection | 24-Jul-27 → 07-Feb-28 | Not Started 0% | float -15.0d CO02LP0140 CO02HM0275 — 02H Complete Primary Reformer Erection (101-B) | 24-Jul-27 | Not Started CO02AP0140 — 02A SB Pipe Erection | 26-Jul-27 → 30-Oct-27 | Not Started 0% | float 78.0d CO02AP0140 CO02HP0130 — 02H LB Pipe Erection | 27-Jul-27 → 05-Jan-28 | Not Started 0% | float 10.0d CO02HP0130 CO02MP0140 — 02M SB Pipe Erection | 27-Jul-27 → 15-Oct-27 | Not Started 0% | float 92.0d CO02MP0140 CO02PE0110 — 02P Lighting JB's, Stands, Tray & Cable | 27-Jul-27 → 02-Aug-27 | Not Started 0% | float 150.0d CO02PE0110 CO02YV1120 — 02Y Paint Touch-up - Piping | 27-Jul-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02YV1120 CO02YV1130 — 02Y Paint Touch-up - Pipe Rack | 27-Jul-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02YV1130 CO02CP0150 — 02C Punchlist / Test Piping | 28-Jul-27 → 22-Oct-27 | Not Started 0% | float 83.0d CO02CP0150 CO02HM0120 — 02H Set (Heavey Lift) - 101-C & 102-C | 30-Jul-27 → 04-Aug-27 | Not Started 0% | float 10.0d CO02HM0120 CO02GV1130 — 02G Paint Touch-up - Equipment | 30-Jul-27 → 25-Sep-27 | Not Started 0% | float 116.0d CO02GV1130 CO02KE0130 — 02K Power/Control JB's, Tray, Cable, Termination | 30-Jul-27 → 06-Nov-27 | Not Started 0% | float 77.0d CO02KE0130 CO02KI0120 — 02K Instrument JB's, Field Instr, Tray, Cable | 30-Jul-27 → 06-Nov-27 | Not Started 0% | float 77.0d CO02KI0120 CO02AE0120 — 02A Lighting Fixture Installation/Termination | 31-Jul-27 → 13-Aug-27 | Not Started 0% | float 157.0d CO02AE0120 CO02EV2110 — 02E Insulate - Equipment | 31-Jul-27 → 27-Aug-27 | Not Started 0% | float 151.0d CO02EV2110 CO02CE0110 — 02C Lighting JB's, Stands, Tray & Cable | 03-Aug-27 → 05-Oct-27 | Not Started 0% | float 113.0d CO02CE0110 CO02GE0120 — 02G Lighting Fixture Installation/Termination | 03-Aug-27 → 01-Sep-27 | Not Started 0% | float 149.0d CO02GE0120 CO02HP0140 — 02H SB Pipe Erection | 03-Aug-27 → 12-Jan-28 | Not Started 0% | float 10.0d CO02HP0140 CO02PE0120 — 02P Lighting Fixture Installation/Termination | 03-Aug-27 → 09-Aug-27 | Not Started 0% | float 161.0d CO02PE0120 CO020M0130 — Demobilize Heavy Lift Crane | 05-Aug-27 → 16-Aug-27 | Not Started 0% | float 56.0d CO020M0130 CO02HS0110 — 02H Erect Structural Steel - Structure | 05-Aug-27 → 07-Oct-27 | Not Started 0% | float 10.0d CO02HS0110 CO02GV1120 — 02G Paint Touch-up - Piping | 06-Aug-27 → 02-Oct-27 | Not Started 0% | float 134.0d CO02GV1120 CO02AE0130 — 02A Power/Control JB's, Tray, Cable, Termination | 07-Aug-27 → 06-Nov-27 | Not Started 0% | float 78.0d CO02AE0130 CO02AI0120 — 02A Instrument JB's, Field Instr, Tray, Cable | 07-Aug-27 → 06-Nov-27 | Not Started 0% | float 78.0d CO02AI0120 CO02ME0130 — 02M Power/Control JB's, Tray, Cable, Termination | 07-Aug-27 → 22-Oct-27 | Not Started 0% | float 95.0d CO02ME0130 CO02MI0120 — 02M Instrument JB's, Field Instr, Tray, Cable | 07-Aug-27 → 22-Oct-27 | Not Started 0% | float 95.0d CO02MI0120 CO02BP0140 — 02B SB Pipe Erection | 09-Aug-27 → 30-Aug-27 | Not Started 0% | float 120.0d CO02BP0140 CO02JP0150 — 02J Punchlist / Test Piping | 09-Aug-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02JP0150 CO02KE0120 — 02K Lighting Fixture Installation/Termination | 09-Aug-27 → 21-Sep-27 | Not Started 0% | float 144.0d CO02KE0120 CO02YP0150 — 02Y Punchlist / Test Piping | 10-Aug-27 → 09-Nov-27 | Not Started 0% | float 65.0d CO02YP0150 CO02LE0130 — 02L Power/Control JB's, Tray, Cable, Termination | 11-Aug-27 → 14-Feb-28 | Not Started 0% | float -12.0d CO02LE0130 CO02LI0120 — 02L Instrument JB's, Field Instr, Tray, Cable | 11-Aug-27 → 14-Feb-28 | Not Started 0% | float -12.0d CO02LI0120 CO02NE0120 — 02N Lighting Fixture Installation/Termination | 13-Aug-27 → 25-Aug-27 | Not Started 0% | float 152.0d CO02NE0120 CO02NV2110 — 02N Insulate - Equipment | 13-Aug-27 → 08-Sep-27 | Not Started 0% | float 146.0d CO02NV2110 CO02EP0140 — 02E SB Pipe Erection | 16-Aug-27 → 13-Nov-27 | Not Started 0% | float 67.0d CO02EP0140 CO02LV2110 — 02L Insulate - Equipment | 16-Aug-27 → 26-Oct-27 | Not Started 0% | float 69.0d CO02LV2110 CO02HE0130 — 02H Power/Control JB's, Tray, Cable, Termination | 23-Aug-27 → 19-Jan-28 | Not Started 0% | float 15.0d CO02HE0130 CO02HI0120 — 02H Instrument JB's, Field Instr, Tray, Cable | 23-Aug-27 → 19-Jan-28 | Not Started 0% | float 15.0d CO02HI0120 CO02FP0150 — 02F Punchlist / Test Piping | 25-Aug-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02FP0150 CO02BE0130 — 02B Power/Control JB's, Tray, Cable, Termination | 30-Aug-27 → 20-Sep-27 | Not Started 0% | float 136.0d CO02BE0130 CO02BI0120 — 02B Instrument JB's, Field Instr, Tray, Cable | 30-Aug-27 → 20-Sep-27 | Not Started 0% | float 136.0d CO02BI0120 CO02PP0140 — 02P SB Pipe Erection | 30-Aug-27 → 28-Sep-27 | Not Started 0% | float 103.0d CO02PP0140 CO02BP0150 — 02B Punchlist / Test Piping | 01-Sep-27 → 20-Sep-27 | Not Started 0% | float 120.0d CO02BP0150 CO02BV1120 — 02B Paint Touch-up - Piping | 01-Sep-27 → 20-Sep-27 | Not Started 0% | float 144.0d CO02BV1120 CO02CV1120 — 02C Paint Touch-up - Piping | 01-Sep-27 → 22-Oct-27 | Not Started 0% | float 116.0d CO02CV1120 CO02GV2120 — 02G Insulate - Piping | 03-Sep-27 → 30-Oct-27 | Not Started 0% | float 110.0d CO02GV2120 CO02JV1120 — 02J Paint Touch-up - Piping | 06-Sep-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02JV1120 CO02JV1130 — 02J Paint Touch-up - Equipment | 06-Sep-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02JV1130 CO02EE0130 — 02E Power/Control JB's, Tray, Cable, Termination | 08-Sep-27 → 26-Nov-27 | Not Started 0% | float 67.0d CO02EE0130 CO02EI0120 — 02E Instrument JB's, Field Instr, Tray, Cable | 08-Sep-27 → 26-Nov-27 | Not Started 0% | float 67.0d CO02EI0120 CO02HV1130 — 02H Paint Touch-up - Equipment | 10-Sep-27 → 28-Oct-27 | Not Started 0% | float 52.0d CO02HV1130 CO02GV2110 — 02G Insulate - Equipment | 10-Sep-27 → 23-Oct-27 | Not Started 0% | float 116.0d CO02GV2110 CO02QP0140 — 02Q SB Pipe Erection | 20-Sep-27 → 05-Oct-27 | Not Started 0% | float 101.0d CO02QP0140 CO02BI0130 — 02B Install In Line Instruments | 21-Sep-27 → 22-Sep-27 | Not Started 0% | float 130.0d CO02PI0120 — 02P Instrument JB's, Field Instr, Tray, Cable | 21-Sep-27 → 05-Oct-27 | Not Started 0% | float 121.0d CO02PI0120 CO02FV1120 — 02F Paint Touch-up - Piping | 23-Sep-27 → 11-Oct-27 | Not Started 0% | float 126.0d CO02FV1120 CO02HE0110 — 02H Lighting JB's, Stands, Tray & Cable | 24-Sep-27 → 04-Nov-27 | Not Started 0% | float 87.0d CO02HE0110 CO02MP0150 — 02M Punchlist / Test Piping | 24-Sep-27 → 22-Oct-27 | Not Started 0% | float 92.0d CO02MP0150 CO02KP0150 — 02K Punchlist / Test Piping | 27-Sep-27 → 06-Nov-27 | Not Started 0% | float 80.0d CO02KP0150 CO02PP0150 — 02P Punchlist / Test Piping | 28-Sep-27 → 05-Oct-27 | Not Started 0% | float 107.0d CO02PP0150 CO02QI0120 — 02Q Instrument JB's, Field Instr, Tray, Cable | 28-Sep-27 → 12-Oct-27 | Not Started 0% | float 115.0d CO02QI0120 CO02CV2120 — 02C Insulate - Piping | 29-Sep-27 → 25-Nov-27 | Not Started 0% | float 92.0d CO02CV2120 CO02PV1130 — 02P Paint Touch-up - Equipment | 29-Sep-27 → 02-Oct-27 | Not Started 0% | float 103.0d CO02PV1130 CO02YV2120 — 02Y Insulate - Piping | 29-Sep-27 → 27-Dec-27 | Not Started 0% | float 65.0d CO02YV2120 CO02DP0140 — 02D SB Pipe Erection | 30-Sep-27 → 25-Nov-27 | Not Started 0% | float 62.0d CO02DP0140 CO02AP0150 — 02A Punchlist / Test Piping | 01-Oct-27 → 06-Nov-27 | Not Started 0% | float 79.0d CO02AP0150 CO02PV1120 — 02P Paint Touch-up - Piping | 01-Oct-27 → 05-Oct-27 | Not Started 0% | float 125.0d CO02PV1120 CO02GI0130 — 02G Install In Line Instruments | 02-Oct-27 → 13-Oct-27 | Not Started 0% | float 105.0d CO02GI0130 CO02QP0150 — 02Q Punchlist / Test Piping | 05-Oct-27 → 12-Oct-27 | Not Started 0% | float 101.0d CO02QP0150 CO02CE0120 — 02C Lighting Fixture Installation/Termination | 06-Oct-27 → 26-Oct-27 | Not Started 0% | float 113.0d CO02CE0120 CO02JV2120 — 02J Insulate - Piping | 06-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02JV2120 CO02MV1120 — 02M Paint Touch-up - Piping | 06-Oct-27 → 22-Oct-27 | Not Started 0% | float 116.0d CO02MV1120 CO02PI0130 — 02P Install In Line Instruments | 06-Oct-27 → 06-Oct-27 | Not Started 0% | float 118.0d CO02QV1120 — 02Q Paint Touch-up - Piping | 06-Oct-27 → 09-Oct-27 | Not Started 0% | float 121.0d CO02QV1120 CO02QV1130 — 02Q Paint Touch-up - Equipment | 06-Oct-27 → 09-Oct-27 | Not Started 0% | float 121.0d CO02QV1130 CO02DE0130 — 02D Power/Control JB's, Tray, Cable, Termination | 11-Oct-27 → 02-Dec-27 | Not Started 0% | float 68.0d CO02DE0130 CO02DI0120 — 02D Instrument JB's, Field Instr, Tray, Cable | 11-Oct-27 → 02-Dec-27 | Not Started 0% | float 68.0d CO02DI0120 CO02QV2110 — 02Q Insulate - Equipment | 11-Oct-27 → 16-Oct-27 | Not Started 0% | float 121.0d CO02QV2110 CO02BV2120 — 02B Insulate - Piping | 12-Oct-27 → 18-Oct-27 | Not Started 0% | float 120.0d CO02BV2120 CO02FI0130 — 02F Install In Line Instruments | 12-Oct-27 → 16-Oct-27 | Not Started 0% | float 109.0d CO02FI0130 CO02JI0130 — 02J Install In Line Instruments | 12-Oct-27 → 19-Oct-27 | Not Started 0% | float 104.0d CO02JI0130 CO02QI0130 — 02Q Install In Line Instruments | 13-Oct-27 → 13-Oct-27 | Not Started 0% | float 112.0d CO02YE0120 — 02Y Lighting Fixture Installation/Termination | 13-Oct-27 → 27-Nov-27 | Not Started 0% | float 90.0d CO02YE0120 CO02KV1120 — 02K Paint Touch-up - Piping | 13-Oct-27 → 06-Nov-27 | Not Started 0% | float 104.0d CO02KV1120 CO02FV2120 — 02F Insulate - Piping | 14-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02FV2120 CO02JV2110 — 02J Insulate - Equipment | 14-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02JV2110 CO02AV1120 — 02A Paint Touch-up - Piping | 16-Oct-27 → 06-Nov-27 | Not Started 0% | float 103.0d CO02AV1120 CO02HV2110 — 02H Insulate - Equipment | 16-Oct-27 → 01-Dec-27 | Not Started 0% | float 52.0d CO02HV2110 CO02EP0150 — 02E Punchlist / Test Piping | 18-Oct-27 → 26-Nov-27 | Not Started 0% | float 67.0d CO02EP0150 CO02CI0130 — 02C Install In Line Instruments | 23-Oct-27 → 04-Nov-27 | Not Started 0% | float 83.0d CO02CI0130 CO02MI0130 — 02M Install In Line Instruments | 23-Oct-27 → 28-Oct-27 | Not Started 0% | float 99.0d CO02MI0130 CO02PV2120 — 02P Insulate - Piping | 27-Oct-27 → 02-Nov-27 | Not Started 0% | float 107.0d CO02PV2120 CO02MV2120 — 02M Insulate - Piping | 28-Oct-27 → 25-Nov-27 | Not Started 0% | float 92.0d CO02MV2120 CO020K0100 — 020 Site Prep - Guard Posts & Gravel | 01-Nov-27 → 01-Mar-28 | Not Started 0% | float 9.0d CO020K0100 CO02EV1120 — 02E Paint Touch-up - Piping | 01-Nov-27 → 26-Nov-27 | Not Started 0% | float 91.0d CO02EV1120 CO02PV2110 — 02P Insulate - Equipment | 01-Nov-27 → 06-Nov-27 | Not Started 0% | float 103.0d CO02PV2110 WO020K0100 — 020 Site Prep | 01-Nov-27 → 01-Mar-28 | Not Started 0% | float 9.0d WO020K0100 CO02DP0150 — 02D Punchlist / Test Piping | 02-Nov-27 → 02-Dec-27 | Not Started 0% | float 62.0d CO02DP0150 CO02KV2120 — 02K Insulate - Piping | 02-Nov-27 → 10-Dec-27 | Not Started 0% | float 80.0d CO02KV2120 CO02QV2120 — 02Q Insulate - Piping | 03-Nov-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02QV2120 CO02AV2120 — 02A Insulate - Piping | 05-Nov-27 → 10-Dec-27 | Not Started 0% | float 79.0d CO02AV2120 CO02HE0120 — 02H Lighting Fixture Installation/Termination | 05-Nov-27 → 01-Dec-27 | Not Started 0% | float 87.0d CO02HE0120 CO02KI0130 — 02K Install In Line Instruments | 06-Nov-27 → 15-Nov-27 | Not Started 0% | float 83.0d CO02KI0130 CO02AI0130 — 02A Install In Line Instruments | 08-Nov-27 → 13-Nov-27 | Not Started 0% | float 84.0d CO02AI0130 CO02NP0140 — 02N SB Pipe Erection | 08-Nov-27 → 17-Nov-27 | Not Started 0% | float 56.0d CO02NP0140 CO02YI0130 — 02Y Install In Line Instruments | 10-Nov-27 → 13-Dec-27 | Not Started 0% | float 65.0d CO02YI0130 CO02HP0150 — 02H Punchlist / Test Piping | 11-Nov-27 → 19-Jan-28 | Not Started 0% | float 10.0d CO02HP0150 CO02DV1120 — 02D Paint Touch-up - Piping | 12-Nov-27 → 02-Dec-27 | Not Started 0% | float 86.0d CO02DV1120 CO02NE0130 — 02N Power/Control JB's, Tray, Cable, Termination | 15-Nov-27 → 30-Nov-27 | Not Started 0% | float 80.0d CO02NE0130 CO02NI0120 — 02N Instrument JB's, Field Instr, Tray, Cable | 15-Nov-27 → 30-Nov-27 | Not Started 0% | float 80.0d CO02NI0120 CO02LP0150 — 02L Punchlist / Test Piping | 16-Nov-27 → 14-Feb-28 | Not Started 0% | float -15.0d CO02LP0150 CO02NV1120 — 02N Paint Touch-up - Piping | 18-Nov-27 → 30-Nov-27 | Not Started 0% | float 88.0d CO02NV1120 CO02NP0150 — 02N Punchlist / Test Piping | 26-Nov-27 → 30-Nov-27 | Not Started 0% | float 56.0d CO02NP0150 CO02EI0130 — 02E Install In Line Instruments | 27-Nov-27 → 03-Dec-27 | Not Started 0% | float 73.0d CO02EI0130 CO02EV2120 — 02E Insulate - Piping | 27-Nov-27 → 24-Dec-27 | Not Started 0% | float 67.0d CO02EV2120 CO02NI0130 — 02N Install In Line Instruments | 01-Dec-27 → 01-Dec-27 | Not Started 0% | float 75.0d CO02DI0130 — 02D Install In Line Instruments | 03-Dec-27 → 07-Dec-27 | Not Started 0% | float 70.0d CO02DI0130 CO02GI0140 — 02G Continuity Testing | 07-Dec-27 → 16-Dec-27 | Not Started 0% | float 54.0d CO02GI0140 CO02YI0140 — 02Y Continuity Testing | 07-Dec-27 → 03-Jan-28 | Not Started 0% | float 53.0d CO02YI0140 CO02DV2120 — 02D Insulate - Piping | 10-Dec-27 → 30-Dec-27 | Not Started 0% | float 62.0d CO02DV2120 CO02HV1120 — 02H Paint Touch-up - Piping | 10-Dec-27 → 19-Jan-28 | Not Started 0% | float 45.0d CO02HV1120 CO02AI0140 — 02A Continuity Testing | 14-Dec-27 → 20-Dec-27 | Not Started 0% | float 52.0d CO02AI0140 CO02BI0140 — 02B Continuity Testing | 14-Dec-27 → 15-Dec-27 | Not Started 0% | float 73.0d CO02KI0140 — 02K Continuity Testing | 15-Dec-27 → 22-Dec-27 | Not Started 0% | float 48.0d CO02KI0140 CO02BT0110 — 02B Mechanical Completion | 15-Dec-27 | Not Started CO02DI0140 — 02D Continuity Testing | 16-Dec-27 → 20-Dec-27 | Not Started 0% | float 59.0d CO02DI0140 CO02GT0110 — 02G Mechanical Completion | 16-Dec-27 | Not Started CO02CI0140 — 02C Continuity Testing | 17-Dec-27 → 29-Dec-27 | Not Started 0% | float 41.0d CO02CI0140 SC02BT0120 — 02B RFSU | 18-Dec-27 | Not Started CO02AT0110 — 02A Mechanical Completion | 20-Dec-27 | Not Started CO02DT0110 — 02D Mechanical Completion | 20-Dec-27 | Not Started CO02EI0140 — 02E Continuity Testing | 21-Dec-27 → 27-Dec-27 | Not Started 0% | float 47.0d CO02EI0140 CO02JI0140 — 02J Continuity Testing | 21-Dec-27 → 28-Dec-27 | Not Started 0% | float 42.0d CO02JI0140 CO02MI0140 — 02M Continuity Testing | 21-Dec-27 → 25-Dec-27 | Not Started 0% | float 51.0d CO02MI0140 CO02NI0140 — 02N Continuity Testing | 22-Dec-27 → 22-Dec-27 | Not Started 0% | float 67.0d CO02KT0110 — 02K Mechanical Completion | 22-Dec-27 | Not Started CO02NT0110 — 02N Mechanical Completion | 22-Dec-27 | Not Started CO02PI0140 — 02P Continuity Testing | 23-Dec-27 → 23-Dec-27 | Not Started 0% | float 64.0d CO02PT0110 — 02P Mechanical Completion | 23-Dec-27 | Not Started CO02HV2120 — 02H Insulate - Piping | 24-Dec-27 → 16-Feb-28 | Not Started 0% | float 21.0d CO02HV2120 CO02NV2120 — 02N Insulate - Piping | 24-Dec-27 → 06-Jan-28 | Not Started 0% | float 56.0d CO02NV2120 CO02QI0140 — 02Q Continuity Testing | 24-Dec-27 → 24-Dec-27 | Not Started 0% | float 63.0d CO02QT0110 — 02Q Mechanical Completion | 24-Dec-27 | Not Started CO02LV1120 — 02L Paint Touch-up - Piping | 25-Dec-27 → 14-Feb-28 | Not Started 0% | float 23.0d CO02LV1120 CO02MT0110 — 02M Mechanical Completion | 25-Dec-27 | Not Started CO02ET0110 — 02E Mechanical Completion | 27-Dec-27 | Not Started CO02FI0140 — 02F Continuity Testing | 28-Dec-27 → 01-Jan-28 | Not Started 0% | float 44.0d CO02FI0140 CO02JT0110 — 02J Mechanical Completion | 28-Dec-27 | Not Started SC02PT0120 — 02P RFSU | 28-Dec-27 | Not Started CO02CT0110 — 02C Mechanical Completion | 29-Dec-27 | Not Started SC02QT0120 — 02Q RFSU | 29-Dec-27 | Not Started CO02FT0110 — 02F Mechanical Completion | 01-Jan-28 | Not Started CO02YT0110 — 02Y Mechanical Completion | 03-Jan-28 | Not Started SC02DT0120 — 02D RFSU | 04-Jan-28 | Not Started CO02LV2120 — 02L Insulate - Piping | 05-Jan-28 → 13-Mar-28 | Not Started 0% | float -1.0d CO02LV2120 SC02NT0120 — 02N RFSU | 06-Jan-28 | Not Started SC02GT0120 — 02G RFSU | 09-Jan-28 | Not Started SC02YT0120 — 02Y RFSU | 10-Jan-28 | Not Started SC02AT0120 — 02A RFSU | 12-Jan-28 | Not Started SC02MT0120 — 02M RFSU | 12-Jan-28 | Not Started CO02HI0140 — 02H Continuity Testing | 14-Jan-28 → 26-Jan-28 | Not Started 0% | float 15.0d CO02HI0140 SC02KT0120 — 02K RFSU | 16-Jan-28 | Not Started SC02ET0120 — 02E RFSU | 17-Jan-28 | Not Started CO02HI0130 — 02H Install In Line Instruments | 20-Jan-28 → 01-Feb-28 | Not Started 0% | float 10.0d CO02HI0130 SC02FT0120 — 02F RFSU | 20-Jan-28 | Not Started SC02JT0120 — 02J RFSU | 23-Jan-28 | Not Started SC02CT0120 — 02C RFSU | 24-Jan-28 | Not Started CO02HI0145 — 02H Contingency (101-B) | 27-Jan-28 → 23-Feb-28 | Not Started 0% | float 15.0d CO02HI0145 CO02LI0140 — 02L Continuity Testing | 05-Feb-28 → 21-Feb-28 | Not Started 0% | float -12.0d CO02LI0140 CO02LI0130 — 02L Install In Line Instruments | 15-Feb-28 → 01-Mar-28 | Not Started 0% | float -15.0d CO02LI0130 CO02LT0110 — 02L Mechanical Completion | 21-Feb-28 | Not Started CO02HT0110 — 02H Mechanical Completion | 23-Feb-28 | Not Started SC02HT0120 — 02H RFSU | 29-Feb-28 | Not Started SC02LT0120 — 02L RFSU | 29-Mar-28 | Not Started