EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 438
activities
in 02 Ammonia Plant
× clear
Code
Activity
Start
Finish
Flt
%
CO02HC0140
02H Form Pour Strip Fnds - Structure
21-Mar-26
27-Dec-26
—
12%
WO020C0100
020 Concrete & Excavation
21-Mar-26
23-Mar-27
215.0d
9%
CO02JC0150
02J Form, Pour, Strip Fnd - 104-D2 (Low Temp Shift Converter)
30-Mar-26
27-Dec-26
—
9%
CO02JC0160
02J Form, Pour, Strip Fnd - 104-D1 (High Temp Shift Converter)
30-Mar-26
27-Dec-26
—
9%
CO02JC0110
02J Form, Pour, Strip Fnds - Major Fnds Gen'l
01-Apr-26
27-Dec-26
—
9%
CO02LC0150
02L Form, Pour, Strip Fnd - 101-E (CO2 Absorber)
03-Apr-26
27-Dec-26
—
8%
CO02MC0110
02M Form, Pour, Strip Fnds - Major Fnds Gen'l
03-Apr-26
27-Dec-26
—
8%
CO02MC0140
02M Form Pour Strip Fnds - Structure
03-Apr-26
27-Dec-26
—
8%
CO02KC0150
02K Form, Pour, Strip Fnd - 114-F (Benfield Solution Tank)
04-Apr-26
27-Dec-26
—
7%
CO02BC0110
02B Form, Pour, Strip Fnds - Major Fnds
09-Apr-26
27-Dec-26
—
6%
CO02AC0110
02A Form, Pour, Strip Fnds - Major Fnds
15-Apr-26
09-Mar-27
189.0d
5%
CO02HC0150
02H Form, Pour, Strip Fnd - 103-D (Secondary Reformer)
21-Apr-26
27-Dec-26
—
5%
CO02CC0160
02C Form, Pour, Strip Fnd - 103-JTC
27-Dec-26
27-Dec-26
—
0%
CO02CM0140
02C Set - 103-JTC Surface Condenser
27-Dec-26
27-Dec-26
—
0%
CO02EC0110
02E Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
—
0%
CO02EC0140
02E Form Pour Strip Fnds - Structure
27-Dec-26
27-Dec-26
—
0%
CO02GC0160
02G Form, Pour, Strip Fnd - 102-J Fd Gas Compr. & Aux.
27-Dec-26
27-Dec-26
—
0%
CO02HC0110
02H Form, Pour, Strip Fnds - 101B (Primary Reformer)
27-Dec-26
27-Dec-26
—
0%
CO02HC0160
02H Form, Pour, Strip Fnd - 156-F (Steam Blowdown Drum)
27-Dec-26
27-Dec-26
—
0%
CO02HM0140
02H Set - 156-F Steam Blowdown Drum
27-Dec-26
27-Dec-26
—
0%
CO02LC0160
02L Form, Pour, Strip Fnd - 102-E (CO2 Stripper)
27-Dec-26
27-Dec-26
—
0%
CO02MC0150
02M Form, Pour, Strip Fnd - 105-D (Ammonia Synthesis Converter)
27-Dec-26
27-Dec-26
—
0%
CO02NC0110
02N Form, Pour, Strip Fnds - Major Fnds
27-Dec-26
27-Dec-26
—
0%
CO02YC0140
02Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
—
0%
CO02AU4120
02A U/G Piping Installation
28-Dec-26
29-Jan-27
222.0d
0%
CO02BU4120
02B U/G Piping Installation
28-Dec-26
29-Jan-27
219.0d
0%
CO02CC0110
02C Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
26-Jan-27
165.0d
0%
CO02CC0150
02C Form, Pour, Strip Fnd - 103/105-J & Table Tops
28-Dec-26
28-Dec-26
—
0%
CO02CM0110
02C Set Static Equipment - 128/167-C
28-Dec-26
28-Dec-26
—
0%
CO02CU4120
02C U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02DC0110
02D Form, Pour, Strip Fnds - Major Fnds
28-Dec-26
09-Jan-27
252.0d
0%
CO02DU4120
02D U/G Piping Installation
28-Dec-26
29-Jan-27
248.0d
0%
CO02EU4120
02E U/G Piping Installation
28-Dec-26
29-Jan-27
227.0d
0%
CO02FC0110
02F Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
234.0d
0%
CO02FU4120
02F U/G Piping Installation
28-Dec-26
29-Jan-27
234.0d
0%
CO02GC0150
02G Form, Pour, Strip Fnd - 101-J/JT & 2ea. Table Tops
28-Dec-26
01-Feb-27
134.0d
0%
CO02GM0140
02G Set/Install - 102-J Fd Gas Compr. & Aux.
28-Dec-26
22-Apr-27
188.0d
0%
CO02HU4120
02H U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02JU4120
02J U/G Piping Installation
28-Dec-26
29-Jan-27
211.0d
0%
CO02KC0110
02K Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
192.0d
0%
CO02KU4120
02K U/G Piping Installation
28-Dec-26
29-Jan-27
214.0d
0%
CO02LC0110
02L Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
123.0d
0%
CO02LC0140
02L Form Pour Strip Fnds - 02L Structure
28-Dec-26
29-Jan-27
45.0d
0%
CO02MU4120
02M U/G Piping Installation
28-Dec-26
29-Jan-27
239.0d
0%
CO02UP0130
02U LB Pipe Erection (CW & Misc Headers)
28-Dec-26
29-Jan-27
71.0d
0%
CO02UV1110
02U Paint Fabricated Pipe Spools (CW & Misc Headers)
28-Dec-26
28-Dec-26
—
0%
CO02YU3110
02Y U/G Earthing Installation
28-Dec-26
29-Jan-27
100.0d
0%
WO020M0100
020 Major Equipment
28-Dec-26
16-Aug-27
156.0d
0%
WO020U3100
020 Install U/G Electrical
28-Dec-26
12-Mar-27
265.0d
0%
WO020U4100
020 U/G Piping Installation
28-Dec-26
26-Feb-27
224.0d
0%
CO02HM0200
02H Start Primary Reformer Erection (101-B)
02-Jan-27
02-Jan-27
108.0d
0%
CO02HM0210
02H Erect Radiant Section Shell (101-B)
02-Jan-27
02-Apr-27
108.0d
0%
CO02LU4120
02L U/G Piping Installation
02-Jan-27
29-Jan-27
123.0d
0%
CO02GU4120
02G U/G Piping Installation
06-Jan-27
26-Feb-27
159.0d
0%
CO02CM0125
02C Set - 103/105-J Compressors
12-Jan-27
16-Jan-27
167.0d
0%
CO02YS0110
02Y Erect Structural Steel - Pipe Rack
12-Jan-27
14-Jun-27
-35.0d
0%
WO020S0100
020 Erect Steel
12-Jan-27
07-Oct-27
69.0d
0%
CO02HU3110
02H U/G Earthing Installation
13-Jan-27
12-Feb-27
162.0d
0%
CO02CU3110
02C U/G Earthing Installation
14-Jan-27
12-Feb-27
168.0d
0%
CO02HC0120
02H Form, Pour, Strip Fnds - Misc Fnds
16-Jan-27
05-Feb-27
174.0d
0%
CO02LU3110
02L U/G Earthing Installation
16-Jan-27
12-Feb-27
129.0d
0%
CO02UP0150
02U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO02CM0130
02C Install - 103/105-J Compressors & Aux. Equip.
18-Jan-27
13-May-27
167.0d
0%
CO02AU3110
02A U/G Earthing Installation
20-Jan-27
05-Feb-27
228.0d
0%
CO02CV1110
02C Paint Fabricated Pipe Spools
20-Jan-27
27-Feb-27
245.0d
0%
WO020V1100
020 Paint
20-Jan-27
14-Feb-28
23.0d
0%
CO02GC0110
02G Form, Pour, Strip Fnds - Major Fnds Gen'l
23-Jan-27
26-Feb-27
159.0d
0%
CO02JU3110
02J U/G Earthing Installation
25-Jan-27
12-Feb-27
211.0d
0%
CO02BM0110
02B Set Static Equipment
25-Jan-27
25-Jan-27
—
0%
CO02BV1130
02B Paint Touch-up - Equipment
25-Jan-27
01-Feb-27
300.0d
0%
CO02KU3110
02K U/G Earthing Installation
26-Jan-27
12-Feb-27
214.0d
0%
CO02EU3110
02E U/G Earthing Installation
28-Jan-27
12-Feb-27
227.0d
0%
CO02FU3110
02F U/G Earthing Installation
29-Jan-27
12-Feb-27
234.0d
0%
CO02BC0120
02B Form, Pour, Strip Fnds - Misc Fnds
29-Jan-27
29-Jan-27
—
0%
CO02CC0120
02C Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
162.0d
0%
CO02DC0120
02D Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
30-Jan-27
260.0d
0%
CO02EC0120
02E Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
227.0d
0%
CO02FC0120
02F Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
234.0d
0%
CO02FM0110
02F Set Static Equipment
30-Jan-27
26-Feb-27
241.0d
0%
CO02JC0120
02J Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
211.0d
0%
CO02KC0120
02K Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
214.0d
0%
CO02LC0120
02L Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
123.0d
0%
CO02MC0120
02M Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
239.0d
0%
CO02MU3110
02M U/G Earthing Installation
30-Jan-27
12-Feb-27
239.0d
0%
CO02YC0130
02Y Install Paving
30-Jan-27
17-Mar-27
71.0d
0%
WO020C0110
020 Concrete Paving
30-Jan-27
22-May-27
210.0d
0%
CO02DU3110
02D U/G Earthing Installation
02-Feb-27
12-Feb-27
248.0d
0%
CO02YV1110
02Y Paint Fabricated Pipe Spools
05-Feb-27
19-Feb-27
131.0d
0%
CO02BU3110
02B U/G Earthing Installation
10-Feb-27
12-Feb-27
289.0d
0%
CO02EV1110
02E Paint Fabricated Pipe Spools
12-Feb-27
04-Mar-27
250.0d
0%
CO02GU3110
02G U/G Earthing Installation
15-Feb-27
12-Mar-27
159.0d
0%
CO02GV1110
02G Paint Fabricated Pipe Spools
16-Feb-27
22-Mar-27
230.0d
0%
CO02CC0130
02C Install Paving
20-Feb-27
05-Mar-27
162.0d
0%
CO02LC0130
02L Install Paving
20-Feb-27
05-Mar-27
123.0d
0%
CO02HM0220
02H Erect Radiant Ducting / Burners (101-B)
22-Feb-27
20-Mar-27
151.0d
0%
CO02UDT110
02U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
SC02UT0120
02U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
CO02GC0120
02G Form, Pour, Strip Fnds - Misc Fnds
27-Feb-27
19-Mar-27
165.0d
0%
CO02GM0110
02G Set Static Equipment - Gen'l
27-Feb-27
31-Mar-27
208.0d
0%
CO02JS0130
02J Pre-Install Misc Steel - 104-D2
01-Mar-27
15-Mar-27
103.0d
0%
CO02JS0140
02J Pre-Install Misc Steel - 104-D1
01-Mar-27
15-Mar-27
108.0d
0%
CO02LS0130
02L Pre-Install Misc Steel - 101-E
01-Mar-27
15-Mar-27
113.0d
0%
CO02GM0125
02G Set - 101-J/JT Air Compr.
08-Mar-27
05-Apr-27
105.0d
0%
CO02AC0120
02A Form, Pour, Strip Fnds - Misc Fnds
10-Mar-27
23-Mar-27
189.0d
0%
CO02AM0150
02A Set Rotating Equipment
10-Mar-27
06-Apr-27
207.0d
0%
CO02GC0130
02G Install Paving
13-Mar-27
26-Mar-27
159.0d
0%
CO02HM0250
02H Set Forced Draft Fan (101-B)
15-Mar-27
12-Apr-27
234.0d
0%
CO02YS0120
02Y Erect Misc Steel - Pipe Rack
19-Mar-27
14-Jun-27
102.0d
0%
CO02HM0246
02H Install Radiant Sect Coils (101-B)
22-Mar-27
17-Apr-27
151.0d
0%
CO02HM0255
02H Set Induced Draft Fan (101-B)
22-Mar-27
19-Apr-27
234.0d
0%
CO02KV1130
02K Paint Touch-up - Equipment
23-Mar-27
15-Apr-27
236.0d
0%
CO02AC0130
02A Install Paving
24-Mar-27
30-Mar-27
189.0d
0%
CO02CM0150
02C Set Rotating Equipment - 112-J/JA/JM
26-Mar-27
30-Mar-27
205.0d
0%
CO02GM0150
02G Set Rotating Equipment
26-Mar-27
10-Apr-27
199.0d
0%
CO02KM0150
02K Set Rotating Equipment
26-Mar-27
01-Apr-27
163.0d
0%
CO02LM0150
02L Set Rotating Equipment
26-Mar-27
27-Apr-27
170.0d
0%
CO02HS0140
02H Install Misc Steel - 156-F
27-Mar-27
09-Apr-27
102.0d
0%
CO02JV1110
02J Paint Fabricated Pipe Spools
27-Mar-27
27-Mar-27
164.0d
0%
CO02AV1130
02A Paint Touch-up - Equipment
30-Mar-27
20-Apr-27
232.0d
0%
CO02MV1110
02M Paint Fabricated Pipe Spools
01-Apr-27
14-Apr-27
215.0d
0%
CO02NV1110
02N Paint Fabricated Pipe Spools
01-Apr-27
03-Apr-27
216.0d
0%
CO02DM0150
02D Set Rotating Equipment
02-Apr-27
15-Apr-27
182.0d
0%
CO02HC0130
02H Install Paving
03-Apr-27
16-Apr-27
120.0d
0%
CO02HM0230
02H Set Convection Sections (101-B)
03-Apr-27
30-Apr-27
108.0d
0%
CO02HM0240
02H Set Stack for (101-B)
03-Apr-27
30-Apr-27
223.0d
0%
CO02JC0130
02J Install Paving
05-Apr-27
10-Apr-27
168.0d
0%
CO02GM0130
02G Install - 101-J/JT Air Compr. & Gen. Turb. & Aux.
05-Apr-27
30-Jul-27
105.0d
0%
CO02HS0130
02H Pre-Install Misc Steel - 103-D
05-Apr-27
19-Apr-27
68.0d
0%
CO02FV1110
02F Paint Fabricated Pipe Spools
09-Apr-27
27-Apr-27
204.0d
0%
CO02LV1110
02L Paint Fabricated Pipe Spools
09-Apr-27
29-May-27
162.0d
0%
CO02KV1110
02K Paint Fabricated Pipe Spools
10-Apr-27
04-May-27
181.0d
0%
CO02LS0110
02L Erect Structure
10-Apr-27
18-Jun-27
-15.0d
0%
CO02KC0130
02K Install Paving
12-Apr-27
17-Apr-27
165.0d
0%
CO02YP0130
02Y LB Pipe Erection
13-Apr-27
05-Oct-27
-35.0d
0%
WO020P0100
020 Above Ground Pipe
13-Apr-27
14-Feb-28
-1.0d
0%
CO02DV1130
02D Paint Touch-up - Equipment
15-Apr-27
29-Apr-27
224.0d
0%
CO02FM0150
02F Set Rotating Equipment
16-Apr-27
13-May-27
176.0d
0%
CO02QV1110
02Q Paint Fabricated Pipe Spools
16-Apr-27
20-Apr-27
210.0d
0%
CO020M0110
Mobilize / Assemble / Test Heavy Lift Crane
19-Apr-27
01-May-27
56.0d
0%
CO02EC0130
02E Install Paving
19-Apr-27
24-Apr-27
172.0d
0%
CO02HM0248
02H Install Effluent Transfer Line (107-D)
19-Apr-27
01-May-27
151.0d
0%
CO02LS0140
02L Pre-Install Misc Steel - 102-E
19-Apr-27
03-May-27
76.0d
0%
CO02DV1110
02D Paint Fabricated Pipe Spools
23-Apr-27
07-May-27
177.0d
0%
CO02MS0110
02M Erect Structural Steel - Structure
24-Apr-27
14-May-27
123.0d
0%
CO02PV1110
02P Paint Fabricated Pipe Spools
24-Apr-27
28-Apr-27
199.0d
0%
CO02FC0130
02F Install Paving
26-Apr-27
01-May-27
173.0d
0%
CO02HV1110
02H Paint Fabricated Pipe Spools
26-Apr-27
05-Jun-27
54.0d
0%
CO02CS0120
02C Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
83.0d
0%
CO02GS0130
02G Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
107.0d
0%
CO02HM0235
02H Erect Preheater (101-B)
01-May-27
25-Jun-27
175.0d
0%
CO020M0120
Heavy Lift Crane Useage
03-May-27
04-Aug-27
56.0d
0%
CO02HM0130
02H Set (Heavy Lift) - 103-D (Secondary Reformer)
03-May-27
07-May-27
56.0d
0%
CO02HM0225
02H Erect Penthouse Roof, & Siding (101-B)
03-May-27
29-May-27
151.0d
0%
CO02MC0130
02M Install Paving
03-May-27
08-May-27
172.0d
0%
CO02KS0130
02K Pre-Install Misc Steel - Static Equipment
03-May-27
17-May-27
101.0d
0%
CO02GP0130
02G LB Pipe Erection
04-May-27
10-Sep-27
105.0d
0%
CO02CP0130
02C LB Pipe Erection
08-May-27
08-Oct-27
83.0d
0%
CO02DS0110
02D Erect Structural Steel
08-May-27
28-May-27
93.0d
0%
CO02JM0130
02J Set (Heavy Lift) - 104-D2 (Low Temp Shift Converter)
08-May-27
13-May-27
56.0d
0%
CO02LS0120
02L Erect Misc Steel
08-May-27
04-Jun-27
39.0d
0%
CO02DC0130
02D Install Paving
10-May-27
15-May-27
175.0d
0%
CO02FV1130
02F Paint Touch-up - Equipment
10-May-27
27-May-27
200.0d
0%
CO02MS0130
02M Pre-Install Misc Steel - 105-D
10-May-27
24-May-27
63.0d
0%
CO02YP0140
02Y SB Pipe Erection
11-May-27
02-Nov-27
-29.0d
0%
CO02GP0140
02G SB Pipe Erection
11-May-27
25-Sep-27
105.0d
0%
CO02CV1130
02C Paint Touch-up - Equipment
14-May-27
22-Jun-27
190.0d
0%
CO02JM0140
02J Set (Heavy Lift) - 104-D1 (High Temp Shift Converter)
14-May-27
19-May-27
56.0d
0%
CO02AS0110
02A Erect Structural Steel
15-May-27
04-Jun-27
103.0d
0%
CO02CP0140
02C SB Pipe Erection
15-May-27
15-Oct-27
83.0d
0%
CO02MM0110
02M Set Static Equipment - Gen'l
15-May-27
16-Jun-27
147.0d
0%
CO02BC0130
02B Install Paving
17-May-27
22-May-27
210.0d
0%
CO02KM0110
02K Set Static Equipment - Gen'l
17-May-27
07-Jun-27
101.0d
0%
CO02AV1110
02A Paint Fabricated Pipe Spools
20-May-27
02-Jun-27
172.0d
0%
CO02LM0130
02L Set (Heavy Lift) - 101-E (CO2 Absorber)
20-May-27
25-May-27
56.0d
0%
CO02ES0110
02E Erect Structural Steel
22-May-27
11-Jun-27
127.0d
0%
CO02ES0120
02E Erect Misc Steel
22-May-27
11-Jun-27
67.0d
0%
CO02FS0120
02F Erect Misc Steel
22-May-27
11-Jun-27
133.0d
0%
CO02JS0110
02J Erect Structural Steel - Structure
22-May-27
04-Jun-27
98.0d
0%
CO02MS0120
02M Erect Misc Steel - Structure
22-May-27
11-Jun-27
123.0d
0%
CO02BV1110
02B Paint Fabricated Pipe Spools
25-May-27
31-May-27
175.0d
0%
CO02LM0140
02L Set (Heavy Lift) - 102-E (CO2 Stripper)
26-May-27
31-May-27
56.0d
0%
CO02GE0130
02G Power/Control JB's, Tray, Cable, Termination
26-May-27
02-Oct-27
108.0d
0%
CO02GI0120
02G Instrument JB's, Field Instr, Tray, Cable
26-May-27
02-Oct-27
108.0d
0%
WO020E0100
020 Above Ground Electrical
26-May-27
14-Feb-28
23.0d
0%
WO020I0100
020 Install Instruments & Test
26-May-27
01-Mar-28
9.0d
0%
CO02CV2110
02C Insulate - Equipment
28-May-27
06-Jul-27
190.0d
0%
WO020V2100
020 Insulation
28-May-27
13-Mar-28
-1.0d
0%
CO02DM0110
02D Set Static Equipment
29-May-27
11-Jun-27
133.0d
0%
CO02DS0120
02D Erect Misc Steel
29-May-27
18-Jun-27
93.0d
0%
CO02EP0130
02E LB Pipe Erection
29-May-27
06-Nov-27
67.0d
0%
CO02HM0260
02H Compete Installation of Ducts (101-B)
29-May-27
23-Jul-27
175.0d
0%
CO02HM0215
02H Erect Fuel Gas Lines (101-B)
31-May-27
26-Jun-27
151.0d
0%
CO02HM0227
02H Install Spring Hangers & Align (101-B)
31-May-27
10-Jul-27
186.0d
0%
CO02HM0245
02H Install Insulation (101-B)
31-May-27
24-Jul-27
174.0d
0%
CO02CE0130
02C Power/Control JB's, Tray, Cable, Termination
01-Jun-27
22-Oct-27
88.0d
0%
CO02CI0120
02C Instrument JB's, Field Instr, Tray, Cable
01-Jun-27
22-Oct-27
88.0d
0%
CO02JM0110
02J Set Static Equipment - Gen'l
01-Jun-27
11-Jun-27
98.0d
0%
CO02MM0130
02M Set (Heavy Lift) - 105-D (Ammonia Converter)
01-Jun-27
05-Jun-27
56.0d
0%
CO02AM0110
02A Set Static Equipment
05-Jun-27
18-Jun-27
144.0d
0%
CO02JS0120
02J Erect Misc Steel - Structure
05-Jun-27
11-Jun-27
98.0d
0%
CO02LE0110
02L Lighting JB's, Stands, Tray & Cable
05-Jun-27
16-Jul-27
163.0d
0%
CO02FV2110
02F Insulate - Equipment
07-Jun-27
24-Jun-27
200.0d
0%
CO02MM0140
02M Set (Heavy Lift) - 121-C (Ammonia Conv./ Effl Exch.)
07-Jun-27
11-Jun-27
56.0d
0%
CO02KS0120
02K Erect Misc Steel
07-Jun-27
28-Jun-27
101.0d
0%
CO02KV2110
02K Insulate - Equipment
10-Jun-27
05-Jul-27
192.0d
0%
CO02AS0120
02A Erect Misc Steel
12-Jun-27
02-Jul-27
103.0d
0%
CO02BE0110
02B Lighting JB's, Stands, Tray & Cable
12-Jun-27
25-Jun-27
193.0d
0%
CO02EE0110
02E Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02EM0110
02E Set Static Equipment
12-Jun-27
09-Jul-27
127.0d
0%
CO02FE0110
02F Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02JE0110
02J Lighting JB's, Stands, Tray & Cable
12-Jun-27
23-Jul-27
157.0d
0%
CO02JP0130
02J LB Pipe Erection
12-Jun-27
27-Sep-27
98.0d
0%
CO02ME0110
02M Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02MV1130
02M Paint Touch-up - Equipment
12-Jun-27
29-Jun-27
172.0d
0%
CO02NM0110
02N Set (Heavy Lift) - 120-C (Ammonia Unitized Chiller)
12-Jun-27
17-Jun-27
56.0d
0%
CO02BV2110
02B Insulate - Equipment
14-Jun-27
19-Jun-27
204.0d
0%
CO02PM0110
02P Set 101-U Dearator
15-Jun-27
28-Jun-27
103.0d
0%
CO02QM0110
02Q Set 101-F Steam Drum
15-Jun-27
21-Jun-27
101.0d
0%
CO02NS0120
02N Erect Misc Steel
18-Jun-27
22-Jul-27
56.0d
0%
CO02DE0110
02D Lighting JB's, Stands, Tray & Cable
19-Jun-27
16-Jul-27
169.0d
0%
CO02JP0140
02J SB Pipe Erection
19-Jun-27
04-Oct-27
98.0d
0%
CO02LM0110
02L Set Static Equipment - Gen'l
19-Jun-27
21-Jul-27
103.0d
0%
CO02LM0120
02L Set Static Equipment - 02L Structure
19-Jun-27
30-Jul-27
-15.0d
0%
CO02QS0120
02Q Erect Misc Steel
22-Jun-27
12-Jul-27
101.0d
0%
CO02AV2110
02A Insulate - Equipment
25-Jun-27
16-Jul-27
181.0d
0%
CO02DV2110
02D Insulate - Equipment
25-Jun-27
09-Jul-27
187.0d
0%
CO02NP0130
02N LB Pipe Erection
25-Jun-27
10-Nov-27
56.0d
0%
CO02BE0120
02B Lighting Fixture Installation/Termination
26-Jun-27
02-Jul-27
193.0d
0%
CO02MP0130
02M LB Pipe Erection
28-Jun-27
08-Oct-27
92.0d
0%
CO02KE0110
02K Lighting JB's, Stands, Tray & Cable
28-Jun-27
09-Aug-27
144.0d
0%
CO02PS0120
02P Erect Misc Steel
29-Jun-27
26-Jul-27
103.0d
0%
CO02QP0130
02Q LB Pipe Erection
29-Jun-27
28-Sep-27
101.0d
0%
CO02YE0110
02Y Lighting JB's, Stands, Tray & Cable
29-Jun-27
12-Oct-27
90.0d
0%
CO02JE0130
02J Power/Control JB's, Tray, Cable, Termination
02-Jul-27
11-Oct-27
98.0d
0%
CO02JI0120
02J Instrument JB's, Field Instr, Tray, Cable
02-Jul-27
11-Oct-27
98.0d
0%
CO02AE0110
02A Lighting JB's, Stands, Tray & Cable
03-Jul-27
30-Jul-27
157.0d
0%
CO02EV1130
02E Paint Touch-up - Equipment
03-Jul-27
23-Jul-27
151.0d
0%
CO02FP0130
02F LB Pipe Erection
05-Jul-27
27-Sep-27
102.0d
0%
CO02GE0110
02G Lighting JB's, Stands, Tray & Cable
06-Jul-27
18-Aug-27
149.0d
0%
CO02PP0130
02P LB Pipe Erection
06-Jul-27
21-Sep-27
103.0d
0%
CO02EE0120
02E Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02FE0120
02F Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02ME0120
02M Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02MV2110
02M Insulate - Equipment
10-Jul-27
27-Jul-27
172.0d
0%
CO02DP0130
02D LB Pipe Erection
12-Jul-27
22-Oct-27
62.0d
0%
CO02FP0140
02F SB Pipe Erection
12-Jul-27
04-Oct-27
102.0d
0%
CO02KP0130
02K LB Pipe Erection
12-Jul-27
23-Oct-27
77.0d
0%
CO02QE0110
02Q Lighting JB's, Stands, Tray & Cable
13-Jul-27
19-Jul-27
162.0d
0%
CO02GP0150
02G Punchlist / Test Piping
16-Jul-27
02-Oct-27
105.0d
0%
CO02DE0120
02D Lighting Fixture Installation/Termination
17-Jul-27
30-Jul-27
169.0d
0%
CO02LE0120
02L Lighting Fixture Installation/Termination
17-Jul-27
06-Aug-27
163.0d
0%
CO02LP0130
02L LB Pipe Erection
17-Jul-27
31-Jan-28
-15.0d
0%
CO02LV1130
02L Paint Touch-up - Equipment
17-Jul-27
28-Sep-27
69.0d
0%
CO02AP0130
02A LB Pipe Erection
19-Jul-27
23-Oct-27
78.0d
0%
CO02BP0130
02B LB Pipe Erection
19-Jul-27
16-Aug-27
120.0d
0%
CO02KP0140
02K SB Pipe Erection
19-Jul-27
30-Oct-27
77.0d
0%
CO02QE0120
02Q Lighting Fixture Installation/Termination
20-Jul-27
26-Jul-27
173.0d
0%
CO02YE0130
02Y Power/Control JB's, Tray, Cable, Termination
20-Jul-27
16-Nov-27
-35.0d
0%
CO02YI0120
02Y Instrument JB's, Field Instr, Tray, Cable
20-Jul-27
16-Nov-27
-35.0d
0%
CO02FE0130
02F Power/Control JB's, Tray, Cable, Termination
22-Jul-27
11-Oct-27
104.0d
0%
CO02FI0120
02F Instrument JB's, Field Instr, Tray, Cable
22-Jul-27
11-Oct-27
104.0d
0%
CO02NE0110
02N Lighting JB's, Stands, Tray & Cable
23-Jul-27
12-Aug-27
152.0d
0%
CO02NV1130
02N Paint Touch-up - Equipment
23-Jul-27
29-Jul-27
146.0d
0%
CO02JE0120
02J Lighting Fixture Installation/Termination
24-Jul-27
13-Aug-27
157.0d
0%
CO02LP0140
02L SB Pipe Erection
24-Jul-27
07-Feb-28
-15.0d
0%
CO02HM0275
02H Complete Primary Reformer Erection (101-B)
24-Jul-27
24-Jul-27
174.0d
0%
CO02AP0140
02A SB Pipe Erection
26-Jul-27
30-Oct-27
78.0d
0%
CO02HP0130
02H LB Pipe Erection
27-Jul-27
05-Jan-28
10.0d
0%
CO02MP0140
02M SB Pipe Erection
27-Jul-27
15-Oct-27
92.0d
0%
CO02PE0110
02P Lighting JB's, Stands, Tray & Cable
27-Jul-27
02-Aug-27
150.0d
0%
CO02YV1120
02Y Paint Touch-up - Piping
27-Jul-27
09-Nov-27
101.0d
0%
CO02YV1130
02Y Paint Touch-up - Pipe Rack
27-Jul-27
09-Nov-27
101.0d
0%
CO02CP0150
02C Punchlist / Test Piping
28-Jul-27
22-Oct-27
83.0d
0%
CO02HM0120
02H Set (Heavey Lift) - 101-C & 102-C
30-Jul-27
04-Aug-27
10.0d
0%
CO02GV1130
02G Paint Touch-up - Equipment
30-Jul-27
25-Sep-27
116.0d
0%
CO02KE0130
02K Power/Control JB's, Tray, Cable, Termination
30-Jul-27
06-Nov-27
77.0d
0%
CO02KI0120
02K Instrument JB's, Field Instr, Tray, Cable
30-Jul-27
06-Nov-27
77.0d
0%
CO02AE0120
02A Lighting Fixture Installation/Termination
31-Jul-27
13-Aug-27
157.0d
0%
CO02EV2110
02E Insulate - Equipment
31-Jul-27
27-Aug-27
151.0d
0%
CO02CE0110
02C Lighting JB's, Stands, Tray & Cable
03-Aug-27
05-Oct-27
113.0d
0%
CO02GE0120
02G Lighting Fixture Installation/Termination
03-Aug-27
01-Sep-27
149.0d
0%
CO02HP0140
02H SB Pipe Erection
03-Aug-27
12-Jan-28
10.0d
0%
CO02PE0120
02P Lighting Fixture Installation/Termination
03-Aug-27
09-Aug-27
161.0d
0%
CO020M0130
Demobilize Heavy Lift Crane
05-Aug-27
16-Aug-27
56.0d
0%
CO02HS0110
02H Erect Structural Steel - Structure
05-Aug-27
07-Oct-27
10.0d
0%
CO02GV1120
02G Paint Touch-up - Piping
06-Aug-27
02-Oct-27
134.0d
0%
CO02AE0130
02A Power/Control JB's, Tray, Cable, Termination
07-Aug-27
06-Nov-27
78.0d
0%
CO02AI0120
02A Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
06-Nov-27
78.0d
0%
CO02ME0130
02M Power/Control JB's, Tray, Cable, Termination
07-Aug-27
22-Oct-27
95.0d
0%
CO02MI0120
02M Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
22-Oct-27
95.0d
0%
CO02BP0140
02B SB Pipe Erection
09-Aug-27
30-Aug-27
120.0d
0%
CO02JP0150
02J Punchlist / Test Piping
09-Aug-27
11-Oct-27
102.0d
0%
CO02KE0120
02K Lighting Fixture Installation/Termination
09-Aug-27
21-Sep-27
144.0d
0%
CO02YP0150
02Y Punchlist / Test Piping
10-Aug-27
09-Nov-27
65.0d
0%
CO02LE0130
02L Power/Control JB's, Tray, Cable, Termination
11-Aug-27
14-Feb-28
-12.0d
0%
CO02LI0120
02L Instrument JB's, Field Instr, Tray, Cable
11-Aug-27
14-Feb-28
-12.0d
0%
CO02NE0120
02N Lighting Fixture Installation/Termination
13-Aug-27
25-Aug-27
152.0d
0%
CO02NV2110
02N Insulate - Equipment
13-Aug-27
08-Sep-27
146.0d
0%
CO02EP0140
02E SB Pipe Erection
16-Aug-27
13-Nov-27
67.0d
0%
CO02LV2110
02L Insulate - Equipment
16-Aug-27
26-Oct-27
69.0d
0%
CO02HE0130
02H Power/Control JB's, Tray, Cable, Termination
23-Aug-27
19-Jan-28
15.0d
0%
CO02HI0120
02H Instrument JB's, Field Instr, Tray, Cable
23-Aug-27
19-Jan-28
15.0d
0%
CO02FP0150
02F Punchlist / Test Piping
25-Aug-27
11-Oct-27
102.0d
0%
CO02BE0130
02B Power/Control JB's, Tray, Cable, Termination
30-Aug-27
20-Sep-27
136.0d
0%
CO02BI0120
02B Instrument JB's, Field Instr, Tray, Cable
30-Aug-27
20-Sep-27
136.0d
0%
CO02PP0140
02P SB Pipe Erection
30-Aug-27
28-Sep-27
103.0d
0%
CO02BP0150
02B Punchlist / Test Piping
01-Sep-27
20-Sep-27
120.0d
0%
CO02BV1120
02B Paint Touch-up - Piping
01-Sep-27
20-Sep-27
144.0d
0%
CO02CV1120
02C Paint Touch-up - Piping
01-Sep-27
22-Oct-27
116.0d
0%
CO02GV2120
02G Insulate - Piping
03-Sep-27
30-Oct-27
110.0d
0%
CO02JV1120
02J Paint Touch-up - Piping
06-Sep-27
11-Oct-27
102.0d
0%
CO02JV1130
02J Paint Touch-up - Equipment
06-Sep-27
11-Oct-27
102.0d
0%
CO02EE0130
02E Power/Control JB's, Tray, Cable, Termination
08-Sep-27
26-Nov-27
67.0d
0%
CO02EI0120
02E Instrument JB's, Field Instr, Tray, Cable
08-Sep-27
26-Nov-27
67.0d
0%
CO02HV1130
02H Paint Touch-up - Equipment
10-Sep-27
28-Oct-27
52.0d
0%
CO02GV2110
02G Insulate - Equipment
10-Sep-27
23-Oct-27
116.0d
0%
CO02QP0140
02Q SB Pipe Erection
20-Sep-27
05-Oct-27
101.0d
0%
CO02BI0130
02B Install In Line Instruments
21-Sep-27
22-Sep-27
130.0d
0%
CO02PI0120
02P Instrument JB's, Field Instr, Tray, Cable
21-Sep-27
05-Oct-27
121.0d
0%
CO02FV1120
02F Paint Touch-up - Piping
23-Sep-27
11-Oct-27
126.0d
0%
CO02HE0110
02H Lighting JB's, Stands, Tray & Cable
24-Sep-27
04-Nov-27
87.0d
0%
CO02MP0150
02M Punchlist / Test Piping
24-Sep-27
22-Oct-27
92.0d
0%
CO02KP0150
02K Punchlist / Test Piping
27-Sep-27
06-Nov-27
80.0d
0%
CO02PP0150
02P Punchlist / Test Piping
28-Sep-27
05-Oct-27
107.0d
0%
CO02QI0120
02Q Instrument JB's, Field Instr, Tray, Cable
28-Sep-27
12-Oct-27
115.0d
0%
CO02CV2120
02C Insulate - Piping
29-Sep-27
25-Nov-27
92.0d
0%
CO02PV1130
02P Paint Touch-up - Equipment
29-Sep-27
02-Oct-27
103.0d
0%
CO02YV2120
02Y Insulate - Piping
29-Sep-27
27-Dec-27
65.0d
0%
CO02DP0140
02D SB Pipe Erection
30-Sep-27
25-Nov-27
62.0d
0%
CO02AP0150
02A Punchlist / Test Piping
01-Oct-27
06-Nov-27
79.0d
0%
CO02PV1120
02P Paint Touch-up - Piping
01-Oct-27
05-Oct-27
125.0d
0%
CO02GI0130
02G Install In Line Instruments
02-Oct-27
13-Oct-27
105.0d
0%
CO02QP0150
02Q Punchlist / Test Piping
05-Oct-27
12-Oct-27
101.0d
0%
CO02CE0120
02C Lighting Fixture Installation/Termination
06-Oct-27
26-Oct-27
113.0d
0%
CO02JV2120
02J Insulate - Piping
06-Oct-27
08-Nov-27
102.0d
0%
CO02MV1120
02M Paint Touch-up - Piping
06-Oct-27
22-Oct-27
116.0d
0%
CO02PI0130
02P Install In Line Instruments
06-Oct-27
06-Oct-27
118.0d
0%
CO02QV1120
02Q Paint Touch-up - Piping
06-Oct-27
09-Oct-27
121.0d
0%
CO02QV1130
02Q Paint Touch-up - Equipment
06-Oct-27
09-Oct-27
121.0d
0%
CO02DE0130
02D Power/Control JB's, Tray, Cable, Termination
11-Oct-27
02-Dec-27
68.0d
0%
CO02DI0120
02D Instrument JB's, Field Instr, Tray, Cable
11-Oct-27
02-Dec-27
68.0d
0%
CO02QV2110
02Q Insulate - Equipment
11-Oct-27
16-Oct-27
121.0d
0%
CO02BV2120
02B Insulate - Piping
12-Oct-27
18-Oct-27
120.0d
0%
CO02FI0130
02F Install In Line Instruments
12-Oct-27
16-Oct-27
109.0d
0%
CO02JI0130
02J Install In Line Instruments
12-Oct-27
19-Oct-27
104.0d
0%
CO02QI0130
02Q Install In Line Instruments
13-Oct-27
13-Oct-27
112.0d
0%
CO02YE0120
02Y Lighting Fixture Installation/Termination
13-Oct-27
27-Nov-27
90.0d
0%
CO02KV1120
02K Paint Touch-up - Piping
13-Oct-27
06-Nov-27
104.0d
0%
CO02FV2120
02F Insulate - Piping
14-Oct-27
08-Nov-27
102.0d
0%
CO02JV2110
02J Insulate - Equipment
14-Oct-27
08-Nov-27
102.0d
0%
CO02AV1120
02A Paint Touch-up - Piping
16-Oct-27
06-Nov-27
103.0d
0%
CO02HV2110
02H Insulate - Equipment
16-Oct-27
01-Dec-27
52.0d
0%
CO02EP0150
02E Punchlist / Test Piping
18-Oct-27
26-Nov-27
67.0d
0%
CO02CI0130
02C Install In Line Instruments
23-Oct-27
04-Nov-27
83.0d
0%
CO02MI0130
02M Install In Line Instruments
23-Oct-27
28-Oct-27
99.0d
0%
CO02PV2120
02P Insulate - Piping
27-Oct-27
02-Nov-27
107.0d
0%
CO02MV2120
02M Insulate - Piping
28-Oct-27
25-Nov-27
92.0d
0%
CO020K0100
020 Site Prep - Guard Posts & Gravel
01-Nov-27
01-Mar-28
9.0d
0%
CO02EV1120
02E Paint Touch-up - Piping
01-Nov-27
26-Nov-27
91.0d
0%
CO02PV2110
02P Insulate - Equipment
01-Nov-27
06-Nov-27
103.0d
0%
WO020K0100
020 Site Prep
01-Nov-27
01-Mar-28
9.0d
0%
CO02DP0150
02D Punchlist / Test Piping
02-Nov-27
02-Dec-27
62.0d
0%
CO02KV2120
02K Insulate - Piping
02-Nov-27
10-Dec-27
80.0d
0%
CO02QV2120
02Q Insulate - Piping
03-Nov-27
09-Nov-27
101.0d
0%
CO02AV2120
02A Insulate - Piping
05-Nov-27
10-Dec-27
79.0d
0%
CO02HE0120
02H Lighting Fixture Installation/Termination
05-Nov-27
01-Dec-27
87.0d
0%
CO02KI0130
02K Install In Line Instruments
06-Nov-27
15-Nov-27
83.0d
0%
CO02AI0130
02A Install In Line Instruments
08-Nov-27
13-Nov-27
84.0d
0%
CO02NP0140
02N SB Pipe Erection
08-Nov-27
17-Nov-27
56.0d
0%
CO02YI0130
02Y Install In Line Instruments
10-Nov-27
13-Dec-27
65.0d
0%
CO02HP0150
02H Punchlist / Test Piping
11-Nov-27
19-Jan-28
10.0d
0%
CO02DV1120
02D Paint Touch-up - Piping
12-Nov-27
02-Dec-27
86.0d
0%
CO02NE0130
02N Power/Control JB's, Tray, Cable, Termination
15-Nov-27
30-Nov-27
80.0d
0%
CO02NI0120
02N Instrument JB's, Field Instr, Tray, Cable
15-Nov-27
30-Nov-27
80.0d
0%
CO02LP0150
02L Punchlist / Test Piping
16-Nov-27
14-Feb-28
-15.0d
0%
CO02NV1120
02N Paint Touch-up - Piping
18-Nov-27
30-Nov-27
88.0d
0%
CO02NP0150
02N Punchlist / Test Piping
26-Nov-27
30-Nov-27
56.0d
0%
CO02EI0130
02E Install In Line Instruments
27-Nov-27
03-Dec-27
73.0d
0%
CO02EV2120
02E Insulate - Piping
27-Nov-27
24-Dec-27
67.0d
0%
CO02NI0130
02N Install In Line Instruments
01-Dec-27
01-Dec-27
75.0d
0%
CO02DI0130
02D Install In Line Instruments
03-Dec-27
07-Dec-27
70.0d
0%
CO02GI0140
02G Continuity Testing
07-Dec-27
16-Dec-27
54.0d
0%
CO02YI0140
02Y Continuity Testing
07-Dec-27
03-Jan-28
53.0d
0%
CO02DV2120
02D Insulate - Piping
10-Dec-27
30-Dec-27
62.0d
0%
CO02HV1120
02H Paint Touch-up - Piping
10-Dec-27
19-Jan-28
45.0d
0%
CO02AI0140
02A Continuity Testing
14-Dec-27
20-Dec-27
52.0d
0%
CO02BI0140
02B Continuity Testing
14-Dec-27
15-Dec-27
73.0d
0%
CO02KI0140
02K Continuity Testing
15-Dec-27
22-Dec-27
48.0d
0%
CO02BT0110
02B Mechanical Completion
15-Dec-27
15-Dec-27
75.0d
0%
CO02DI0140
02D Continuity Testing
16-Dec-27
20-Dec-27
59.0d
0%
CO02GT0110
02G Mechanical Completion
16-Dec-27
16-Dec-27
74.0d
0%
CO02CI0140
02C Continuity Testing
17-Dec-27
29-Dec-27
41.0d
0%
SC02BT0120
02B RFSU
18-Dec-27
18-Dec-27
85.0d
0%
CO02AT0110
02A Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02DT0110
02D Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02EI0140
02E Continuity Testing
21-Dec-27
27-Dec-27
47.0d
0%
CO02JI0140
02J Continuity Testing
21-Dec-27
28-Dec-27
42.0d
0%
CO02MI0140
02M Continuity Testing
21-Dec-27
25-Dec-27
51.0d
0%
CO02NI0140
02N Continuity Testing
22-Dec-27
22-Dec-27
67.0d
0%
CO02KT0110
02K Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02NT0110
02N Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02PI0140
02P Continuity Testing
23-Dec-27
23-Dec-27
64.0d
0%
CO02PT0110
02P Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
CO02HV2120
02H Insulate - Piping
24-Dec-27
16-Feb-28
21.0d
0%
CO02NV2120
02N Insulate - Piping
24-Dec-27
06-Jan-28
56.0d
0%
CO02QI0140
02Q Continuity Testing
24-Dec-27
24-Dec-27
63.0d
0%
CO02QT0110
02Q Mechanical Completion
24-Dec-27
24-Dec-27
67.0d
0%
CO02LV1120
02L Paint Touch-up - Piping
25-Dec-27
14-Feb-28
23.0d
0%
CO02MT0110
02M Mechanical Completion
25-Dec-27
25-Dec-27
66.0d
0%
CO02ET0110
02E Mechanical Completion
27-Dec-27
27-Dec-27
65.0d
0%
CO02FI0140
02F Continuity Testing
28-Dec-27
01-Jan-28
44.0d
0%
CO02JT0110
02J Mechanical Completion
28-Dec-27
28-Dec-27
64.0d
0%
SC02PT0120
02P RFSU
28-Dec-27
28-Dec-27
75.0d
0%
CO02CT0110
02C Mechanical Completion
29-Dec-27
29-Dec-27
63.0d
0%
SC02QT0120
02Q RFSU
29-Dec-27
29-Dec-27
74.0d
0%
CO02FT0110
02F Mechanical Completion
01-Jan-28
01-Jan-28
60.0d
0%
CO02YT0110
02Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
SC02DT0120
02D RFSU
04-Jan-28
04-Jan-28
68.0d
0%
CO02LV2120
02L Insulate - Piping
05-Jan-28
13-Mar-28
-1.0d
0%
SC02NT0120
02N RFSU
06-Jan-28
06-Jan-28
66.0d
0%
SC02GT0120
02G RFSU
09-Jan-28
09-Jan-28
63.0d
0%
SC02YT0120
02Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC02AT0120
02A RFSU
12-Jan-28
12-Jan-28
60.0d
0%
SC02MT0120
02M RFSU
12-Jan-28
12-Jan-28
60.0d
0%
CO02HI0140
02H Continuity Testing
14-Jan-28
26-Jan-28
15.0d
0%
SC02KT0120
02K RFSU
16-Jan-28
16-Jan-28
56.0d
0%
SC02ET0120
02E RFSU
17-Jan-28
17-Jan-28
55.0d
0%
CO02HI0130
02H Install In Line Instruments
20-Jan-28
01-Feb-28
10.0d
0%
SC02FT0120
02F RFSU
20-Jan-28
20-Jan-28
52.0d
0%
SC02JT0120
02J RFSU
23-Jan-28
23-Jan-28
49.0d
0%
SC02CT0120
02C RFSU
24-Jan-28
24-Jan-28
48.0d
0%
CO02HI0145
02H Contingency (101-B)
27-Jan-28
23-Feb-28
15.0d
0%
CO02LI0140
02L Continuity Testing
05-Feb-28
21-Feb-28
-12.0d
0%
CO02LI0130
02L Install In Line Instruments
15-Feb-28
01-Mar-28
-15.0d
0%
CO02LT0110
02L Mechanical Completion
21-Feb-28
21-Feb-28
17.0d
0%
CO02HT0110
02H Mechanical Completion
23-Feb-28
23-Feb-28
15.0d
0%
SC02HT0120
02H RFSU
29-Feb-28
29-Feb-28
12.0d
0%
SC02LT0120
02L RFSU
29-Mar-28
29-Mar-28
-17.0d
0%