EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 19 activities in 04 Corridor × clear
Code
Activity
Start
Finish
Flt
%
CO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
WO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
CO04AU4120
04A U/G Piping Installation
29-Jan-27
09-Aug-27
108.0d
0%
WO04AE0100
04A Above Ground Electrical
29-Jan-27
01-Sep-27
108.0d
0%
WO04AI0100
04A Install Instruments & Test
29-Jan-27
01-Sep-27
108.0d
0%
WO04AM0100
04A Major Equipment
29-Jan-27
01-Sep-27
108.0d
0%
WO04AS0100
04A Erect Steel
29-Jan-27
01-Sep-27
108.0d
0%
WO04AU4100
04A U/G Piping Installation
29-Jan-27
01-Sep-27
108.0d
0%
CO04AU3110
04A U/G Fiber Optic Cable Installation
01-Apr-27
10-Aug-27
137.0d
0%
WO04AU3100
04A Install U/G Electrical
01-Apr-27
10-Aug-27
137.0d
0%
CO04AC0110
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
WO04AC0100
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
CO04AU4130
04A Punchlist / Test U/G Piping
28-Apr-27
01-Sep-27
108.0d
0%
CO04AV2110
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
WO04AV2100
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
CO04AK0110
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
WO04AK0100
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
CO04AT0110
04A Mechanical Completion
05-Oct-27
05-Oct-27
108.0d
0%
SC04AT0120
04A RFSU
02-Nov-27
02-Nov-27
132.0d
0%
Q4 2026 Q1 2027 Q2 2027 Q3 2027 Q4 2027 Data Date
CO04AV1100 — 04A Paint | 28-Dec-26 → 25-May-27 | Not Started 0% | float 148.0d CO04AV1100 WO04AV1100 — 04A Paint | 28-Dec-26 → 25-May-27 | Not Started 0% | float 148.0d WO04AV1100 CO04AU4120 — 04A U/G Piping Installation | 29-Jan-27 → 09-Aug-27 | Not Started 0% | float 108.0d CO04AU4120 WO04AE0100 — 04A Above Ground Electrical | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AE0100 WO04AI0100 — 04A Install Instruments & Test | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AI0100 WO04AM0100 — 04A Major Equipment | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AM0100 WO04AS0100 — 04A Erect Steel | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AS0100 WO04AU4100 — 04A U/G Piping Installation | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AU4100 CO04AU3110 — 04A U/G Fiber Optic Cable Installation | 01-Apr-27 → 10-Aug-27 | Not Started 0% | float 137.0d CO04AU3110 WO04AU3100 — 04A Install U/G Electrical | 01-Apr-27 → 10-Aug-27 | Not Started 0% | float 137.0d WO04AU3100 CO04AC0110 — 04A Concrete (Valve Boxes & Paving) | 23-Apr-27 → 23-Aug-27 | Not Started 0% | float 130.0d CO04AC0110 WO04AC0100 — 04A Concrete (Valve Boxes & Paving) | 23-Apr-27 → 23-Aug-27 | Not Started 0% | float 130.0d WO04AC0100 CO04AU4130 — 04A Punchlist / Test U/G Piping | 28-Apr-27 → 01-Sep-27 | Not Started 0% | float 108.0d CO04AU4130 CO04AV2110 — 04A Insulation | 12-May-27 → 28-Sep-27 | Not Started 0% | float 108.0d CO04AV2110 WO04AV2100 — 04A Insulation | 12-May-27 → 28-Sep-27 | Not Started 0% | float 108.0d WO04AV2100 CO04AK0110 — 04A Site Prep (Leveling) | 19-May-27 → 05-Oct-27 | Not Started 0% | float 108.0d CO04AK0110 WO04AK0100 — 04A Site Prep (Leveling) | 19-May-27 → 05-Oct-27 | Not Started 0% | float 108.0d WO04AK0100 CO04AT0110 — 04A Mechanical Completion | 05-Oct-27 | Not Started SC04AT0120 — 04A RFSU | 02-Nov-27 | Not Started