EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 19
activities
in 04 Corridor
× clear
Code
Activity
Start
Finish
Flt
%
CO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
WO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
CO04AU4120
04A U/G Piping Installation
29-Jan-27
09-Aug-27
108.0d
0%
WO04AE0100
04A Above Ground Electrical
29-Jan-27
01-Sep-27
108.0d
0%
WO04AI0100
04A Install Instruments & Test
29-Jan-27
01-Sep-27
108.0d
0%
WO04AM0100
04A Major Equipment
29-Jan-27
01-Sep-27
108.0d
0%
WO04AS0100
04A Erect Steel
29-Jan-27
01-Sep-27
108.0d
0%
WO04AU4100
04A U/G Piping Installation
29-Jan-27
01-Sep-27
108.0d
0%
CO04AU3110
04A U/G Fiber Optic Cable Installation
01-Apr-27
10-Aug-27
137.0d
0%
WO04AU3100
04A Install U/G Electrical
01-Apr-27
10-Aug-27
137.0d
0%
CO04AC0110
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
WO04AC0100
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
CO04AU4130
04A Punchlist / Test U/G Piping
28-Apr-27
01-Sep-27
108.0d
0%
CO04AV2110
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
WO04AV2100
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
CO04AK0110
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
WO04AK0100
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
CO04AT0110
04A Mechanical Completion
05-Oct-27
05-Oct-27
108.0d
0%
SC04AT0120
04A RFSU
02-Nov-27
02-Nov-27
132.0d
0%