Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 68 activities in 05 Dock / Storage × clear
Code
Activity
Start
Finish
Flt
%
CO05AC0170
05A Install Test Piles
27-Dec-26
27-Dec-26
0%
CO05AC0175
05A Test Piles (Load Test)
28-Dec-26
09-Jan-27
-51.0d
0%
WO050C0110
050 Concrete Paving
28-Dec-26
28-Dec-26
0.0d
0%
EK05ACV210
05A COSMO Design Approval (Assuming No Change)
11-Jan-27
16-Jan-27
-51.0d
0%
CO05AC0185
05A Procure Material & Mob Piling Contractor
18-Jan-27
30-Jan-27
-51.0d
0%
CO05AC0150
05A Install Piling - 2101-F Ammonia Tank
01-Feb-27
19-Apr-27
-51.0d
0%
CO05AC0155
05A Install Piling - 2102-F Ammonia Tank
01-Feb-27
19-Apr-27
-40.0d
0%
WO050C0100
050 Concrete & Excavation
01-Feb-27
30-Jul-27
152.0d
0%
CO05AC0160
05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank
20-Apr-27
16-Jun-27
-51.0d
0%
CO05AC0165
05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank
20-Apr-27
16-Jun-27
-40.0d
0%
CO05AV1110
05A Paint Fabricated Pipe Spools
05-May-27
07-Jun-27
166.0d
0%
WO050V1100
050 Paint
05-May-27
12-Apr-28
12.0d
0%
CO05AC0120
05A Form, Pour, Strip Fnds - Sleeper & Rack
11-May-27
14-Jun-27
44.0d
0%
CO05AU4120
05A U/G Piping Installation
13-May-27
07-Jul-27
77.0d
0%
WO050U4100
050 U/G Piping Installation
13-May-27
30-Sep-27
135.0d
0%
CO05BV1110
05B Paint Fabricated Pipe Spools
29-May-27
07-Jun-27
214.0d
0%
CO05BC0110
05B Form, Pour, Strip Fnds - Sleepers
15-Jun-27
30-Jul-27
152.0d
0%
CO05AC0110
05A Form, Pour, Strip Fnds - Major Fnds Gen'l
17-Jun-27
07-Jul-27
77.0d
0%
CO05AU3110
05A U/G Earthing Installation
17-Jun-27
14-Jul-27
77.0d
0%
CO05UP0150
05U LB Pipe Erection (Firewater Piping)
17-Jun-27
30-Sep-27
135.0d
0%
WO050U3100
050 Install U/G Electrical
17-Jun-27
14-Jul-27
77.0d
0%
CO05AS0110
05A Erect Structural Steel - Structure
09-Jul-27
21-Jul-27
23.0d
0%
WO050S0100
050 Erect Steel
09-Jul-27
13-Aug-27
23.0d
0%
CO05BP0130
05B LB Pipe Erection - To Loading Arm
31-Jul-27
21-Sep-27
152.0d
0%
WO050P0100
050 Above Ground Pipe
31-Jul-27
14-Mar-28
19.0d
0%
CO05BM0110
05B Install Loading Arm
02-Aug-27
04-Dec-27
62.0d
0%
WO050M0100
050 Major Equipment
02-Aug-27
04-Dec-27
61.0d
0%
CO05AS0120
05A Erect Misc Steel
06-Aug-27
13-Aug-27
23.0d
0%
CO05BP0140
05B SB Pipe Erection - To Loading Arm
07-Aug-27
28-Sep-27
152.0d
0%
CO05BA0110
05B Erect Dock Control Operating Building
21-Sep-27
19-Oct-27
135.0d
0%
WO050A0100
050 Buildings
21-Sep-27
19-Oct-27
135.0d
0%
CO05BV1120
05B Paint Touch-up - Piping
27-Sep-27
05-Oct-27
170.0d
0%
CO05BE0130
05B Power/Control JB's, Tray, Cable, Termination
19-Oct-27
30-Oct-27
140.0d
0%
CO05BI0120
05B Instrument JB's, Field Instr, Tray, Cable
19-Oct-27
30-Oct-27
140.0d
0%
WO050E0100
050 Above Ground Electrical
19-Oct-27
06-Apr-28
8.0d
0%
WO050I0100
050 Install Instruments & Test
19-Oct-27
25-Mar-28
24.0d
0%
CO05AM0110
05A Set 2202-B Flare & KO Drum
28-Oct-27
04-Dec-27
21.0d
0%
CO05AM0130
05A Set 2101-L Ammonia Refrigeration Package
28-Oct-27
30-Oct-27
46.0d
0%
CO05AM0150
05A Set Rotating Equipment
28-Oct-27
17-Nov-27
31.0d
0%
CO05AP0130
05A LB Pipe Erection
04-Nov-27
29-Feb-28
-29.0d
0%
CO05AP0140
05A SB Pipe Erection
11-Nov-27
07-Mar-28
-29.0d
0%
CO05AE0130
05A Power/Control JB's, Tray, Cable, Termination
18-Nov-27
14-Mar-28
-25.0d
0%
CO05AI0120
05A Instrument JB's, Field Instr, Tray, Cable
18-Nov-27
14-Mar-28
-25.0d
0%
CO05BI0140
05B Continuity Testing
07-Dec-27
07-Dec-27
118.0d
0%
CO05BP0150
05B Punchlist / Test Piping
08-Jan-28
24-Jan-28
63.0d
0%
CO05BV1130
05B Paint Touch-up - Equipment
08-Jan-28
18-Jan-28
62.0d
0%
CO05AP0150
05A Punchlist / Test Piping
19-Jan-28
14-Mar-28
-29.0d
0%
CO05BI0130
05B Install In Line Instruments
24-Jan-28
25-Jan-28
68.0d
0%
CO05BT0110
05B Mechanical Completion
24-Jan-28
24-Jan-28
81.0d
0%
CO05BV2120
05B Insulate - Piping
24-Jan-28
14-Feb-28
63.0d
0%
WO050V2100
050 Insulation
24-Jan-28
10-May-28
-12.0d
0%
CO05BV2110
05B Insulate - Equipment
25-Jan-28
15-Feb-28
62.0d
0%
CO05AV1120
05A Paint Touch-up - Piping
10-Feb-28
14-Mar-28
-2.0d
0%
SC05BT0120
05B RFSU
15-Feb-28
15-Feb-28
72.0d
0%
CO05AK0120
05A Construct Dike (Retaining Wall)
26-Feb-28
05-May-28
-47.0d
0%
CO05AK0130
05A Guard Posts, Fence, Gravel...
26-Feb-28
05-May-28
-47.0d
0%
WO050K0100
050 Site Prep
26-Feb-28
05-May-28
-47.0d
0%
CO05AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
CO06AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
CO05AE0110
05A Lighting JB's, Stands, Tray & Cable
03-Mar-28
30-Mar-28
-22.0d
0%
CO05AI0140
05A Continuity Testing
10-Mar-28
21-Mar-28
-25.0d
0%
CO05AV1130
05A Paint Touch-up - Equipment
10-Mar-28
12-Apr-28
-51.0d
0%
CO05AI0130
05A Install In Line Instruments
15-Mar-28
25-Mar-28
-29.0d
0%
CO05AE0120
05A Lighting Fixture Installation/Termination
24-Mar-28
06-Apr-28
-22.0d
0%
CO05AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
CO06AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
CO05AT0110
05A Mechanical Completion
05-May-28
05-May-28
-47.0d
0%
SC05AT0120
05A RFSU
10-May-28
10-May-28
-59.0d
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 29-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May Data Date
CO05AC0170 — 05A Install Test Piles | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO05AC0175 — 05A Test Piles (Load Test) | 28-Dec-26 → 09-Jan-27 | Not Started 0% | float -51.0d CO05AC0175 WO050C0110 — 050 Concrete Paving | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float 0.0d EK05ACV210 — 05A COSMO Design Approval (Assuming No Change) | 11-Jan-27 → 16-Jan-27 | Not Started 0% | float -51.0d EK05ACV210 CO05AC0185 — 05A Procure Material & Mob Piling Contractor | 18-Jan-27 → 30-Jan-27 | Not Started 0% | float -51.0d CO05AC0185 CO05AC0150 — 05A Install Piling - 2101-F Ammonia Tank | 01-Feb-27 → 19-Apr-27 | Not Started 0% | float -51.0d CO05AC0150 CO05AC0155 — 05A Install Piling - 2102-F Ammonia Tank | 01-Feb-27 → 19-Apr-27 | Not Started 0% | float -40.0d CO05AC0155 WO050C0100 — 050 Concrete & Excavation | 01-Feb-27 → 30-Jul-27 | Not Started 0% | float 152.0d WO050C0100 CO05AC0160 — 05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank | 20-Apr-27 → 16-Jun-27 | Not Started 0% | float -51.0d CO05AC0160 CO05AC0165 — 05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank | 20-Apr-27 → 16-Jun-27 | Not Started 0% | float -40.0d CO05AC0165 CO05AV1110 — 05A Paint Fabricated Pipe Spools | 05-May-27 → 07-Jun-27 | Not Started 0% | float 166.0d CO05AV1110 WO050V1100 — 050 Paint | 05-May-27 → 12-Apr-28 | Not Started 0% | float 12.0d WO050V1100 CO05AC0120 — 05A Form, Pour, Strip Fnds - Sleeper & Rack | 11-May-27 → 14-Jun-27 | Not Started 0% | float 44.0d CO05AC0120 CO05AU4120 — 05A U/G Piping Installation | 13-May-27 → 07-Jul-27 | Not Started 0% | float 77.0d CO05AU4120 WO050U4100 — 050 U/G Piping Installation | 13-May-27 → 30-Sep-27 | Not Started 0% | float 135.0d WO050U4100 CO05BV1110 — 05B Paint Fabricated Pipe Spools | 29-May-27 → 07-Jun-27 | Not Started 0% | float 214.0d CO05BV1110 CO05BC0110 — 05B Form, Pour, Strip Fnds - Sleepers | 15-Jun-27 → 30-Jul-27 | Not Started 0% | float 152.0d CO05BC0110 CO05AC0110 — 05A Form, Pour, Strip Fnds - Major Fnds Gen'l | 17-Jun-27 → 07-Jul-27 | Not Started 0% | float 77.0d CO05AC0110 CO05AU3110 — 05A U/G Earthing Installation | 17-Jun-27 → 14-Jul-27 | Not Started 0% | float 77.0d CO05AU3110 CO05UP0150 — 05U LB Pipe Erection (Firewater Piping) | 17-Jun-27 → 30-Sep-27 | Not Started 0% | float 135.0d CO05UP0150 WO050U3100 — 050 Install U/G Electrical | 17-Jun-27 → 14-Jul-27 | Not Started 0% | float 77.0d WO050U3100 CO05AS0110 — 05A Erect Structural Steel - Structure | 09-Jul-27 → 21-Jul-27 | Not Started 0% | float 23.0d CO05AS0110 WO050S0100 — 050 Erect Steel | 09-Jul-27 → 13-Aug-27 | Not Started 0% | float 23.0d WO050S0100 CO05BP0130 — 05B LB Pipe Erection - To Loading Arm | 31-Jul-27 → 21-Sep-27 | Not Started 0% | float 152.0d CO05BP0130 WO050P0100 — 050 Above Ground Pipe | 31-Jul-27 → 14-Mar-28 | Not Started 0% | float 19.0d WO050P0100 CO05BM0110 — 05B Install Loading Arm | 02-Aug-27 → 04-Dec-27 | Not Started 0% | float 62.0d CO05BM0110 WO050M0100 — 050 Major Equipment | 02-Aug-27 → 04-Dec-27 | Not Started 0% | float 61.0d WO050M0100 CO05AS0120 — 05A Erect Misc Steel | 06-Aug-27 → 13-Aug-27 | Not Started 0% | float 23.0d CO05AS0120 CO05BP0140 — 05B SB Pipe Erection - To Loading Arm | 07-Aug-27 → 28-Sep-27 | Not Started 0% | float 152.0d CO05BP0140 CO05BA0110 — 05B Erect Dock Control Operating Building | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d CO05BA0110 WO050A0100 — 050 Buildings | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d WO050A0100 CO05BV1120 — 05B Paint Touch-up - Piping | 27-Sep-27 → 05-Oct-27 | Not Started 0% | float 170.0d CO05BV1120 CO05BE0130 — 05B Power/Control JB's, Tray, Cable, Termination | 19-Oct-27 → 30-Oct-27 | Not Started 0% | float 140.0d CO05BE0130 CO05BI0120 — 05B Instrument JB's, Field Instr, Tray, Cable | 19-Oct-27 → 30-Oct-27 | Not Started 0% | float 140.0d CO05BI0120 WO050E0100 — 050 Above Ground Electrical | 19-Oct-27 → 06-Apr-28 | Not Started 0% | float 8.0d WO050E0100 WO050I0100 — 050 Install Instruments & Test | 19-Oct-27 → 25-Mar-28 | Not Started 0% | float 24.0d WO050I0100 CO05AM0110 — 05A Set 2202-B Flare & KO Drum | 28-Oct-27 → 04-Dec-27 | Not Started 0% | float 21.0d CO05AM0110 CO05AM0130 — 05A Set 2101-L Ammonia Refrigeration Package | 28-Oct-27 → 30-Oct-27 | Not Started 0% | float 46.0d CO05AM0130 CO05AM0150 — 05A Set Rotating Equipment | 28-Oct-27 → 17-Nov-27 | Not Started 0% | float 31.0d CO05AM0150 CO05AP0130 — 05A LB Pipe Erection | 04-Nov-27 → 29-Feb-28 | Not Started 0% | float -29.0d CO05AP0130 CO05AP0140 — 05A SB Pipe Erection | 11-Nov-27 → 07-Mar-28 | Not Started 0% | float -29.0d CO05AP0140 CO05AE0130 — 05A Power/Control JB's, Tray, Cable, Termination | 18-Nov-27 → 14-Mar-28 | Not Started 0% | float -25.0d CO05AE0130 CO05AI0120 — 05A Instrument JB's, Field Instr, Tray, Cable | 18-Nov-27 → 14-Mar-28 | Not Started 0% | float -25.0d CO05AI0120 CO05BI0140 — 05B Continuity Testing | 07-Dec-27 → 07-Dec-27 | Not Started 0% | float 118.0d CO05BP0150 — 05B Punchlist / Test Piping | 08-Jan-28 → 24-Jan-28 | Not Started 0% | float 63.0d CO05BP0150 CO05BV1130 — 05B Paint Touch-up - Equipment | 08-Jan-28 → 18-Jan-28 | Not Started 0% | float 62.0d CO05BV1130 CO05AP0150 — 05A Punchlist / Test Piping | 19-Jan-28 → 14-Mar-28 | Not Started 0% | float -29.0d CO05AP0150 CO05BI0130 — 05B Install In Line Instruments | 24-Jan-28 → 25-Jan-28 | Not Started 0% | float 68.0d CO05BI0130 CO05BT0110 — 05B Mechanical Completion | 24-Jan-28 | Not Started CO05BV2120 — 05B Insulate - Piping | 24-Jan-28 → 14-Feb-28 | Not Started 0% | float 63.0d CO05BV2120 WO050V2100 — 050 Insulation | 24-Jan-28 → 10-May-28 | Not Started 0% | float -12.0d WO050V2100 CO05BV2110 — 05B Insulate - Equipment | 25-Jan-28 → 15-Feb-28 | Not Started 0% | float 62.0d CO05BV2110 CO05AV1120 — 05A Paint Touch-up - Piping | 10-Feb-28 → 14-Mar-28 | Not Started 0% | float -2.0d CO05AV1120 SC05BT0120 — 05B RFSU | 15-Feb-28 | Not Started CO05AK0120 — 05A Construct Dike (Retaining Wall) | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0120 CO05AK0130 — 05A Guard Posts, Fence, Gravel... | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0130 WO050K0100 — 050 Site Prep | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d WO050K0100 CO05AV2120 — 05A Insulate - Piping | 28-Feb-28 → 11-Apr-28 | Not Started 0% | float -26.0d CO05AV2120 CO06AV2120 — 05A Insulate - Piping | 28-Feb-28 → 11-Apr-28 | Not Started 0% | float -26.0d CO06AV2120 CO05AE0110 — 05A Lighting JB's, Stands, Tray & Cable | 03-Mar-28 → 30-Mar-28 | Not Started 0% | float -22.0d CO05AE0110 CO05AI0140 — 05A Continuity Testing | 10-Mar-28 → 21-Mar-28 | Not Started 0% | float -25.0d CO05AI0140 CO05AV1130 — 05A Paint Touch-up - Equipment | 10-Mar-28 → 12-Apr-28 | Not Started 0% | float -51.0d CO05AV1130 CO05AI0130 — 05A Install In Line Instruments | 15-Mar-28 → 25-Mar-28 | Not Started 0% | float -29.0d CO05AI0130 CO05AE0120 — 05A Lighting Fixture Installation/Termination | 24-Mar-28 → 06-Apr-28 | Not Started 0% | float -22.0d CO05AE0120 CO05AV2110 — 05A Insulate - Equipment | 28-Mar-28 → 10-May-28 | Not Started 0% | float -51.0d CO05AV2110 CO06AV2110 — 05A Insulate - Equipment | 28-Mar-28 → 10-May-28 | Not Started 0% | float -51.0d CO06AV2110 CO05AT0110 — 05A Mechanical Completion | 05-May-28 | Not Started SC05AT0120 — 05A RFSU | 10-May-28 | Not Started