EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 68
activities
in 05 Dock / Storage
× clear
Code
Activity
Start
Finish
Flt
%
CO05AC0170
05A Install Test Piles
27-Dec-26
27-Dec-26
—
0%
CO05AC0175
05A Test Piles (Load Test)
28-Dec-26
09-Jan-27
-51.0d
0%
WO050C0110
050 Concrete Paving
28-Dec-26
28-Dec-26
0.0d
0%
EK05ACV210
05A COSMO Design Approval (Assuming No Change)
11-Jan-27
16-Jan-27
-51.0d
0%
CO05AC0185
05A Procure Material & Mob Piling Contractor
18-Jan-27
30-Jan-27
-51.0d
0%
CO05AC0150
05A Install Piling - 2101-F Ammonia Tank
01-Feb-27
19-Apr-27
-51.0d
0%
CO05AC0155
05A Install Piling - 2102-F Ammonia Tank
01-Feb-27
19-Apr-27
-40.0d
0%
WO050C0100
050 Concrete & Excavation
01-Feb-27
30-Jul-27
152.0d
0%
CO05AC0160
05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank
20-Apr-27
16-Jun-27
-51.0d
0%
CO05AC0165
05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank
20-Apr-27
16-Jun-27
-40.0d
0%
CO05AV1110
05A Paint Fabricated Pipe Spools
05-May-27
07-Jun-27
166.0d
0%
WO050V1100
050 Paint
05-May-27
12-Apr-28
12.0d
0%
CO05AC0120
05A Form, Pour, Strip Fnds - Sleeper & Rack
11-May-27
14-Jun-27
44.0d
0%
CO05AU4120
05A U/G Piping Installation
13-May-27
07-Jul-27
77.0d
0%
WO050U4100
050 U/G Piping Installation
13-May-27
30-Sep-27
135.0d
0%
CO05BV1110
05B Paint Fabricated Pipe Spools
29-May-27
07-Jun-27
214.0d
0%
CO05BC0110
05B Form, Pour, Strip Fnds - Sleepers
15-Jun-27
30-Jul-27
152.0d
0%
CO05AC0110
05A Form, Pour, Strip Fnds - Major Fnds Gen'l
17-Jun-27
07-Jul-27
77.0d
0%
CO05AU3110
05A U/G Earthing Installation
17-Jun-27
14-Jul-27
77.0d
0%
CO05UP0150
05U LB Pipe Erection (Firewater Piping)
17-Jun-27
30-Sep-27
135.0d
0%
WO050U3100
050 Install U/G Electrical
17-Jun-27
14-Jul-27
77.0d
0%
CO05AS0110
05A Erect Structural Steel - Structure
09-Jul-27
21-Jul-27
23.0d
0%
WO050S0100
050 Erect Steel
09-Jul-27
13-Aug-27
23.0d
0%
CO05BP0130
05B LB Pipe Erection - To Loading Arm
31-Jul-27
21-Sep-27
152.0d
0%
WO050P0100
050 Above Ground Pipe
31-Jul-27
14-Mar-28
19.0d
0%
CO05BM0110
05B Install Loading Arm
02-Aug-27
04-Dec-27
62.0d
0%
WO050M0100
050 Major Equipment
02-Aug-27
04-Dec-27
61.0d
0%
CO05AS0120
05A Erect Misc Steel
06-Aug-27
13-Aug-27
23.0d
0%
CO05BP0140
05B SB Pipe Erection - To Loading Arm
07-Aug-27
28-Sep-27
152.0d
0%
CO05BA0110
05B Erect Dock Control Operating Building
21-Sep-27
19-Oct-27
135.0d
0%
WO050A0100
050 Buildings
21-Sep-27
19-Oct-27
135.0d
0%
CO05BV1120
05B Paint Touch-up - Piping
27-Sep-27
05-Oct-27
170.0d
0%
CO05BE0130
05B Power/Control JB's, Tray, Cable, Termination
19-Oct-27
30-Oct-27
140.0d
0%
CO05BI0120
05B Instrument JB's, Field Instr, Tray, Cable
19-Oct-27
30-Oct-27
140.0d
0%
WO050E0100
050 Above Ground Electrical
19-Oct-27
06-Apr-28
8.0d
0%
WO050I0100
050 Install Instruments & Test
19-Oct-27
25-Mar-28
24.0d
0%
CO05AM0110
05A Set 2202-B Flare & KO Drum
28-Oct-27
04-Dec-27
21.0d
0%
CO05AM0130
05A Set 2101-L Ammonia Refrigeration Package
28-Oct-27
30-Oct-27
46.0d
0%
CO05AM0150
05A Set Rotating Equipment
28-Oct-27
17-Nov-27
31.0d
0%
CO05AP0130
05A LB Pipe Erection
04-Nov-27
29-Feb-28
-29.0d
0%
CO05AP0140
05A SB Pipe Erection
11-Nov-27
07-Mar-28
-29.0d
0%
CO05AE0130
05A Power/Control JB's, Tray, Cable, Termination
18-Nov-27
14-Mar-28
-25.0d
0%
CO05AI0120
05A Instrument JB's, Field Instr, Tray, Cable
18-Nov-27
14-Mar-28
-25.0d
0%
CO05BI0140
05B Continuity Testing
07-Dec-27
07-Dec-27
118.0d
0%
CO05BP0150
05B Punchlist / Test Piping
08-Jan-28
24-Jan-28
63.0d
0%
CO05BV1130
05B Paint Touch-up - Equipment
08-Jan-28
18-Jan-28
62.0d
0%
CO05AP0150
05A Punchlist / Test Piping
19-Jan-28
14-Mar-28
-29.0d
0%
CO05BI0130
05B Install In Line Instruments
24-Jan-28
25-Jan-28
68.0d
0%
CO05BT0110
05B Mechanical Completion
24-Jan-28
24-Jan-28
81.0d
0%
CO05BV2120
05B Insulate - Piping
24-Jan-28
14-Feb-28
63.0d
0%
WO050V2100
050 Insulation
24-Jan-28
10-May-28
-12.0d
0%
CO05BV2110
05B Insulate - Equipment
25-Jan-28
15-Feb-28
62.0d
0%
CO05AV1120
05A Paint Touch-up - Piping
10-Feb-28
14-Mar-28
-2.0d
0%
SC05BT0120
05B RFSU
15-Feb-28
15-Feb-28
72.0d
0%
CO05AK0120
05A Construct Dike (Retaining Wall)
26-Feb-28
05-May-28
-47.0d
0%
CO05AK0130
05A Guard Posts, Fence, Gravel...
26-Feb-28
05-May-28
-47.0d
0%
WO050K0100
050 Site Prep
26-Feb-28
05-May-28
-47.0d
0%
CO05AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
CO06AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
CO05AE0110
05A Lighting JB's, Stands, Tray & Cable
03-Mar-28
30-Mar-28
-22.0d
0%
CO05AI0140
05A Continuity Testing
10-Mar-28
21-Mar-28
-25.0d
0%
CO05AV1130
05A Paint Touch-up - Equipment
10-Mar-28
12-Apr-28
-51.0d
0%
CO05AI0130
05A Install In Line Instruments
15-Mar-28
25-Mar-28
-29.0d
0%
CO05AE0120
05A Lighting Fixture Installation/Termination
24-Mar-28
06-Apr-28
-22.0d
0%
CO05AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
CO06AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
CO05AT0110
05A Mechanical Completion
05-May-28
05-May-28
-47.0d
0%
SC05AT0120
05A RFSU
10-May-28
10-May-28
-59.0d
0%