Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in 01 Offsites × clear
Code
Activity
Start
Finish
Flt
%
PO01EA0135
01E Guard House Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
200.0d
0%
PO01FA0135
01F Mosque Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
143.0d
0%
EK01EA0140
01E Guard House Design Drawings - Approval
03-Jan-27
16-Jan-27
175.0d
0%
EK01FA0140
01F Mosque Design Drawings - Approval
03-Jan-27
16-Jan-27
119.0d
0%
30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan Data Date
PO01EA0135 — 01E Guard House Design Drawings - Submit to KBR | 28-Dec-26 → 02-Jan-27 | Not Started 0% | float 200.0d PO01EA0135 PO01FA0135 — 01F Mosque Design Drawings - Submit to KBR | 28-Dec-26 → 02-Jan-27 | Not Started 0% | float 143.0d PO01FA0135 EK01EA0140 — 01E Guard House Design Drawings - Approval | 03-Jan-27 → 16-Jan-27 | Not Started 0% | float 175.0d EK01EA0140 EK01FA0140 — 01F Mosque Design Drawings - Approval | 03-Jan-27 → 16-Jan-27 | Not Started 0% | float 119.0d EK01FA0140