EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in 01 Offsites × clear
Code
Activity
Start
Finish
Flt
%
PO01EA0135
01E Guard House Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
200.0d
0%
PO01FA0135
01F Mosque Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
143.0d
0%
EK01EA0140
01E Guard House Design Drawings - Approval
03-Jan-27
16-Jan-27
175.0d
0%
EK01FA0140
01F Mosque Design Drawings - Approval
03-Jan-27
16-Jan-27
119.0d
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
PO01EA0135 — 01E Guard House Design Drawings - Submit to KBR | 28-Dec-26 → 02-Jan-27 | Not Started 0% | float 200.0d PO01EA0135 PO01FA0135 — 01F Mosque Design Drawings - Submit to KBR | 28-Dec-26 → 02-Jan-27 | Not Started 0% | float 143.0d PO01FA0135 EK01EA0140 — 01E Guard House Design Drawings - Approval | 03-Jan-27 → 16-Jan-27 | Not Started 0% | float 175.0d EK01EA0140 EK01FA0140 — 01F Mosque Design Drawings - Approval | 03-Jan-27 → 16-Jan-27 | Not Started 0% | float 119.0d EK01FA0140