EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 4
activities
in 01 Offsites
× clear
Code
Activity
Start
Finish
Flt
%
PO01EA0135
01E Guard House Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
200.0d
0%
PO01FA0135
01F Mosque Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
143.0d
0%
EK01EA0140
01E Guard House Design Drawings - Approval
03-Jan-27
16-Jan-27
175.0d
0%
EK01FA0140
01F Mosque Design Drawings - Approval
03-Jan-27
16-Jan-27
119.0d
0%