EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in 05 Dock / Storage × clear
Code
Activity
Start
Finish
Flt
%
CO05AM0145
05A Tank Erection 2101-F (Ammonia Storage Tank)
01-Jul-27
25-Feb-28
-51.0d
0%
WT050M0100
05A Tank Erection
01-Jul-27
09-Mar-28
-51.0d
0%
CO05AM0155
05A Tank Erection 2102-F (Ammonia Storage Tank)
14-Jul-27
09-Mar-28
-51.0d
0%
CO05AM0160
05A Tank Erection 2105-F (Fire Water Tank)
23-Aug-27
16-Oct-27
-29.0d
0%
Q3 2027 Q4 2027 Q1 2028 Data Date
CO05AM0145 — 05A Tank Erection 2101-F (Ammonia Storage Tank) | 01-Jul-27 → 25-Feb-28 | Not Started 0% | float -51.0d CO05AM0145 WT050M0100 — 05A Tank Erection | 01-Jul-27 → 09-Mar-28 | Not Started 0% | float -51.0d WT050M0100 CO05AM0155 — 05A Tank Erection 2102-F (Ammonia Storage Tank) | 14-Jul-27 → 09-Mar-28 | Not Started 0% | float -51.0d CO05AM0155 CO05AM0160 — 05A Tank Erection 2105-F (Fire Water Tank) | 23-Aug-27 → 16-Oct-27 | Not Started 0% | float -29.0d CO05AM0160