EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in 02 Ammonia Plant × clear
Code
Activity
Start
Finish
Flt
%
CO02KM0130
02K Tank Erection 114-F (Benfield Solution Tank)
28-Dec-26
08-Jan-27
97.0d
0%
WT020M0100
020 Tank Erection
28-Dec-26
08-Jan-27
97.0d
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
CO02KM0130 — 02K Tank Erection 114-F (Benfield Solution Tank) | 28-Dec-26 → 08-Jan-27 | Not Started 0% | float 97.0d CO02KM0130 WT020M0100 — 020 Tank Erection | 28-Dec-26 → 08-Jan-27 | Not Started 0% | float 97.0d WT020M0100