EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 2035
activities
in E2B2 All Other Areas (HOC)
× clear
Code
Activity
Start
Finish
Flt
%
EK000CK085
Establish bank account in Egypt
02-Jul-24
24-Jan-26
—
100%
EK000SY005
Systems Work Plan & Project Setup
21-Jan-25
25-Mar-25
—
100%
EK000YA002
Start Project
22-Jan-25
22-Jan-25
—
100%
EK000PR025
Pressure Profile
22-Jan-25
01-Feb-25
—
100%
EK000PR050
Electrical Load Summary - Initial
22-Jan-25
01-Feb-25
—
100%
EK000MD005
Attend Alignment & strategy meetings
22-Jan-25
09-Feb-25
—
100%
EK000PR015
Process Configuration
22-Jan-25
13-Feb-25
—
100%
EK000PR030
Stream Summary
22-Jan-25
13-Feb-25
—
100%
EK000PR035
Process Flow Diagrams PFD's - EOR
22-Jan-25
13-Feb-25
—
100%
EK000PR040
Steam Balance Diagram - EOR
22-Jan-25
13-Feb-25
—
100%
EK000GE005
Estimate Escalation Check - Info to Estimating
22-Jan-25
14-Feb-25
—
100%
EK000PR045
Cooling Water Balance - EOR
22-Jan-25
15-Feb-25
—
100%
EK000PE025
Document Management Plan - Issue for Review
22-Jan-25
16-Feb-25
—
100%
EK000SY010
MEC Convert prelim P&ID's to Smart Plant P&ID's
22-Jan-25
16-Feb-25
—
100%
EK000MD015
Conversion of drawings to metric units
22-Jan-25
19-Feb-25
—
100%
EK000PM015
Project Coordination Procedure - IFA
22-Jan-25
23-Feb-25
—
100%
EK000PR020
Heat & Material Balances (SOR & EOR)
22-Jan-25
23-Feb-25
—
100%
EK000PE085
Participate in Escalation confirmation effort
22-Jan-25
01-Mar-25
—
100%
EK000IM030
Project Portal & Dashboard
22-Jan-25
06-Mar-25
—
100%
EK000IC030
Develop & Issue FieldBus Main Instr Vendor ERW
22-Jan-25
08-Mar-25
—
100%
EK000PR055
Feed & Fuel Summary
22-Jan-25
09-Mar-25
—
100%
EK000IM020
IM Strategy plan
22-Jan-25
12-Mar-25
—
100%
EK000IM025
IM Execution plan
22-Jan-25
12-Mar-25
—
100%
EK000PR010
Process Work Plan
22-Jan-25
23-Mar-25
—
100%
EK000AR020
Gather Bldg Requirements & Coordinate w/ Constr
22-Jan-25
12-Apr-25
—
100%
EK000IM010
Object Engineering set-up & procedures
22-Jan-25
13-Apr-25
—
100%
EK000CV005
Identify scope / Project set-up
23-Jan-25
23-Feb-25
—
100%
PK000PK005
Implement use of Procuri and funct'nality (Req?)
29-Jan-25
02-Feb-25
—
100%
EK000PE125
Preliminary Issue - Equipment List
29-Jan-25
12-Feb-25
—
100%
EK000CV020
Review FMCL documents - Specs & Drawings
29-Jan-25
16-Feb-25
—
100%
EK000IM040
Establish Citrix for Test of PDS (HOC-MEC)
29-Jan-25
23-Feb-25
—
100%
EK000PI080
Develop Split of work
29-Jan-25
23-Feb-25
—
100%
PK000MM020
Project requisition matrix
29-Jan-25
02-Mar-25
—
100%
EK000IM005
Equipment List (MEL) Definition
29-Jan-25
30-Mar-25
—
100%
PK000MM010
Project material responsibility matrix
29-Jan-25
04-May-25
—
100%
EK000PE050
Confirm of Split of Work for MEC
02-Feb-25
23-Feb-25
—
100%
PK000PK035
Review ITP as with eng.
02-Feb-25
16-Mar-25
—
100%
EK000IC35A
DCS - Engr ERW Issued
04-Feb-25
12-Feb-25
—
100%
EK000IM035
Establish Documentum
05-Feb-25
16-Feb-25
—
100%
EK000PE010
Publish Unit conversion standard
05-Feb-25
16-Feb-25
—
100%
EK000PE040
Devlop & Issue List of Project Specs & Standards
05-Feb-25
16-Feb-25
—
100%
EK000CV025
Review SEGAS Wind & Earthquake Specs
05-Feb-25
19-Feb-25
—
100%
EK000PI120
Identify priority pipe classes
05-Feb-25
20-Feb-25
—
100%
EK000PS015
Issue 90 Day look ahead schedule
05-Feb-25
21-Feb-25
—
100%
EK000MJ005
Prepare Machinery Specs (Motors, Pkg Equipment)
05-Feb-25
25-Feb-25
—
100%
EK000IC015
Modify Package Equipment Spec for IEC basis
05-Feb-25
05-Mar-25
—
100%
EK000PE110
Issue Draft Project Design Data
05-Feb-25
06-Mar-25
—
100%
EK000MC010
Develop & Issue Exchanger Work Plan
05-Feb-25
09-Mar-25
—
100%
EK000PI115
Develop Piping Class Index (IOPMC)
05-Feb-25
13-Mar-25
—
100%
EK000SY015
Develop Utility & offsite block flow diagrams
05-Feb-25
16-Mar-25
—
100%
EK000PI132
Develop Early Tech P-Class specs for Procurement
05-Feb-25
22-Mar-25
—
100%
EK000SY065
Complete Utility Flow Diagrams
05-Feb-25
03-Apr-25
—
100%
PK000MM025
Piping Bulk Quanities for Mill Run Commitment
05-Feb-25
06-May-25
—
100%
EK000CV010
HOC / MEC split of Work
07-Feb-25
16-Feb-25
—
100%
EK000CV030
Prepare EBIC Wind & EarthquakeSpecs
07-Feb-25
26-Feb-25
—
100%
EK000QM010
Training - Export Compliance
08-Feb-25
08-Feb-25
—
100%
PK000I354H
ITCC - Fabricate Hardware
11-Feb-25
27-Dec-26
—
64%
PK000I210B
000 Control Valves - Issue RFQ
11-Feb-25
18-Feb-25
—
100%
EK000ELZE0
Area Classification
11-Feb-25
30-Dec-25
—
100%
EK000MD31C
Prepare & Issue Prelim. RFQ - MD301 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000MD32C
Prepare & Issue Prelim. RFQ - MD302 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000MD34C
Prepare & Issue Prelim. RFQ - MD304 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000MD51C
Prepare & Issue Prelim. RFQ - MD501 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000CV040
Prepare Topo Survey S/C Pkg
12-Feb-25
23-Feb-25
—
100%
EK000PE090
Develop & Issue Engineering Plan
12-Feb-25
02-Mar-25
—
100%
EK000EL005
Electrical Work Plans
12-Feb-25
09-Mar-25
—
100%
EK000PI040
Prepare technology work plan - Piping Engr.
12-Feb-25
09-Mar-25
—
100%
EK000PI060
Prepare Other Project Documentation
12-Feb-25
09-Mar-25
—
100%
PK000PK01C
Prepare/Issue Critical & Prelim. ERW's to Proc.
12-Feb-25
09-Mar-25
—
100%
EK000PI051
Prepare P/Mech Support Details
12-Feb-25
15-Mar-25
—
100%
EK000CV015
Civil work Plan & Safety check list
12-Feb-25
16-Mar-25
—
100%
EK000CV050
Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis
12-Feb-25
16-Mar-25
—
100%
EK000MB005
Develop & Issue Furnance Job Plan
12-Feb-25
16-Mar-25
—
100%
EK05BEL150
Switchgear One line diagrams - ICA Dock
12-Feb-25
15-Nov-25
—
100%
EK05BEL170
MCC One line diagrams - ICA Dock
12-Feb-25
22-Nov-25
—
100%
EK000MJ31C
Prepare & Issue Prelim. RFQ - MJ301 to Proc.
13-Feb-25
13-Feb-25
—
100%
EK000MJ32C
Prepare & Issue Prelim. RFQ - MJ302 to Proc.
13-Feb-25
13-Feb-25
—
100%
PK000IC35B
DCS - Inquiry REQ/RFQ
13-Feb-25
14-Feb-25
—
100%
EK000MB33A
101-B Develop & Issue Load Sheet
14-Feb-25
16-Feb-25
—
100%
EK000MD33A
Develop & Issue Load Sheets for ERW - MD303
14-Feb-25
16-Feb-25
—
100%
EK000MJ22A
Develop & Issue Load Sheets for ERW - MJ201
14-Feb-25
16-Feb-25
—
100%
EK000MJ21A
Develop & Issue Load Sheets for ERW - MJ202
14-Feb-25
21-Feb-25
—
100%
PK000MJ31G
Issue MJ301 RFQ
14-Feb-25
21-Feb-25
—
100%
PK000MJ32G
Issue MJ302 RFQ
14-Feb-25
21-Feb-25
—
100%
EK000PI110
Locate FMCL Documents
14-Feb-25
23-Feb-25
—
100%
EK000PR060
Process Load Sheets
14-Feb-25
22-Mar-25
—
100%
EK000PC005
Prepare Estimate for Escalation Check
15-Feb-25
23-Feb-25
—
100%
EK000PE015
MSD (From Metallurgy) - ISBL
15-Feb-25
27-Feb-25
—
100%
PK000IC35C
DCS - Receive Bids
15-Feb-25
13-Mar-25
—
100%
EK000MC31C
Prepare & Issue Prelim. RFQ - MC310 to Proc.
16-Feb-25
16-Feb-25
—
100%
EK000MC61C
Prepare & Issue Prelim. RFQ - MC610 to Proc.
16-Feb-25
16-Feb-25
—
100%
EK000MBP1C
101-B Prepare & Issue Prelim. Shop Fab to Proc.
16-Feb-25
20-Feb-25
—
100%
EK000QM015
Develop & Issue Quality Plan
16-Feb-25
16-Mar-25
—
100%
EK000MC32C
Issue Prelim. RFQ - MC311
19-Feb-25
19-Feb-25
—
100%
EK000MJ22C
Prepare & Issue Prelim. RFQ - MJ201 to Proc.
19-Feb-25
19-Feb-25
—
100%
EK020MC31A
MC312 - (120,121-C) - Issue Prelim. RFQ
19-Feb-25
19-Feb-25
—
100%
PK000MJ22G
Issue MJ201 RFQ
19-Feb-25
19-Feb-25
—
100%
EK000MD21A
Develop & Issue Load Sheets for ERW - MD201
19-Feb-25
20-Feb-25
—
100%
EK000MD41C
Prepare & Issue Prelim. RFQ - MD401 to Proc.
19-Feb-25
20-Feb-25
—
100%
EK000MD43C
Prepare & Issue Prelim. RFQ - MD403 to Proc.
19-Feb-25
20-Feb-25
—
100%
EK000MD43A
Develop & Issue Load Sheets for ERW - MD403
19-Feb-25
21-Feb-25
—
100%
EK000MJ31A
Develop & Issue Load Sheets for ERW - MJ301
19-Feb-25
21-Feb-25
—
100%
EK010SY010
010 Issue Marked up FMCL U&O / Dock P&ID's
19-Feb-25
21-Feb-25
—
100%
EK000MD33C
Prepare & Issue Prelim. RFQ - MD303 to Proc.
19-Feb-25
22-Feb-25
—
100%
PK000MD32G
Issue MD302 RFQ
19-Feb-25
22-Feb-25
—
100%
EK000EL020
Define bulk material requirements
19-Feb-25
23-Feb-25
—
100%
EK000MJ22B
Develop & Issue Design Data for ERW - MJ201
19-Feb-25
23-Feb-25
—
100%
EK000ML31C
Prepare & Issue Prelim. RFQ - ML313 to Proc.
19-Feb-25
23-Feb-25
—
100%
EK000PR115
Issue Prelim Load Sht for Air Cooling Study
19-Feb-25
23-Feb-25
—
100%
PK000MD31G
Issue MD301 RFQ
19-Feb-25
23-Feb-25
—
100%
PK000MD34G
Issue MD304 RFQ
19-Feb-25
23-Feb-25
—
100%
PK000MD42G
Issue MD402 RFQ
19-Feb-25
23-Feb-25
—
100%
PK000MD51G
Issue MD501 RFQ
19-Feb-25
23-Feb-25
—
100%
EK000MC210
Cooling Water Balance Review
19-Feb-25
26-Feb-25
—
100%
PK000MC31G
Issue MC310 RFQ
19-Feb-25
26-Feb-25
—
100%
PK000MC61G
Issue MC610 RFQ
19-Feb-25
26-Feb-25
—
100%
PK000PK020
Meeting w/ doc mngmnt & eng. (work process) TREQ
19-Feb-25
28-Feb-25
—
100%
EK000IM045
Establish IPMS
19-Feb-25
01-Mar-25
—
100%
EK000IC005
Develop Typical SIL Values Worksheet
19-Feb-25
02-Mar-25
—
100%
EK000MJ35C
Prepare & Issue Prelim. RFQ - MJ305 to Proc.
19-Feb-25
02-Mar-25
—
100%
EK000MJ36C
Prepare & Issue Prelim. RFQ - MJ306 to Proc.
19-Feb-25
02-Mar-25
—
100%
EK000PK030
Provide Job Specific SDR2 Priorities to Purch.
19-Feb-25
02-Mar-25
—
100%
EK000PI160
P&ID Area Break Mark-up
19-Feb-25
08-Mar-25
—
100%
EK000MJ39C
Prepare & Issue Prelim. RFQ - MJ391 to Proc.
19-Feb-25
09-Mar-25
—
100%
EK000PR076
Identify Risk of Equipment Changes
19-Feb-25
09-Mar-25
—
100%
EK000PE035
Rvw Lesson Learn w/Prj. Team&Develop Action List
19-Feb-25
16-Mar-25
—
100%
PK000MM015
IPMS Initial Setup
19-Feb-25
16-Mar-25
—
100%
EK000EV005
Conceptual Design of Wastewater Systems
19-Feb-25
23-Mar-25
—
100%
EK000PR145
Eng. Studies - Ammonia Product Line U/G vs. A/G
19-Feb-25
29-Mar-25
—
100%
EK000MB010
101-B Furnance Analytical - Convection Design
19-Feb-25
30-Mar-25
—
100%
EK000CV070
Validate Concrete & Steel by Planning Areas
19-Feb-25
15-Apr-25
—
100%
EK000MD33P
Develop Analytical Sketches for ERW - MD303
19-Feb-25
04-May-25
—
100%
EK000PM055
Complete EPC Insurance Forms
19-Feb-25
04-May-25
—
100%
PK000PE030
Coating Supplier of Choice Selection
19-Feb-25
04-May-25
—
100%
EK000PI020
Develop Piping Specs (Paper)
19-Feb-25
28-May-25
—
100%
PK000I210C
000 Control Valves - Receive Quotes
19-Feb-25
19-Mar-25
—
100%
EK000MJ21C
Prepare & Issue Prelim. RFQ - MJ202 to Proc.
20-Feb-25
20-Feb-25
—
100%
PK000MJ21G
Issue MJ202 RFQ
20-Feb-25
20-Feb-25
—
100%
EK000ML50C
Prepare & Issue Prelim. RFQ - ML500 to Proc.
20-Feb-25
26-Feb-25
—
100%
PK000MC32G
Issue MC311 RFQ
20-Feb-25
26-Feb-25
—
100%
PK020MC31B
MC312 - (120,121-C) - Issue RFQ
20-Feb-25
26-Feb-25
—
100%
PK000MJ22H
Receive Quotes MJ201
20-Feb-25
15-Mar-25
—
100%
EK000MD44A
Develop & Issue Load Sheets for ERW - MD404
20-Feb-25
20-Mar-25
—
100%
EK000MB61C
Prepare & Issue Prelim. RFQ - MB610 to Proc.
21-Feb-25
23-Feb-25
—
100%
EK000MB62C
Prepare & Issue Prelim. RFQ - MB621 to Proc.
21-Feb-25
23-Feb-25
—
100%
PK000MBP1G
101-B Prepare & Issue Shop Fab RFQ to Vendors
21-Feb-25
23-Feb-25
—
100%
PK000MD41G
Issue MD401 RFQ
21-Feb-25
23-Feb-25
—
100%
PK000MD43G
Issue MD403 RFQ
21-Feb-25
23-Feb-25
—
100%
EK000MD34A
Develop & Issue Load Sheets for ERW - MD304
21-Feb-25
26-Feb-25
—
100%
PK000MJ21H
Receive Quotes MJ202
21-Feb-25
26-Mar-25
—
100%
EK000MJ21B
Develop & Issue Design Data for ERW - MJ202
22-Feb-25
07-Mar-25
—
100%
EK000MD21P
Develop Prelim Analytical Sktch for ERW - MD201
22-Feb-25
22-Mar-25
—
100%
PK000MJ31H
Receive Quotes MJ301
22-Feb-25
11-Apr-25
—
100%
PK000MJ32H
Receive Quotes MJ302
22-Feb-25
12-Apr-25
—
100%
EK000MD21Q
Develop Final Analytical Sktch for ERW - MD201
22-Feb-25
26-Apr-25
—
100%
EK000YA804
(EP-05) Issue Heat and Material Balance for Process Release
22-Feb-25
22-Feb-25
—
100%
EK000YA805
(EP-06) Issue Equipment List for review
22-Feb-25
22-Feb-25
—
100%
EK000YA807
(EP-08) Issue Utility Balances for Initial Release
22-Feb-25
22-Feb-25
—
100%
EK000FP025
FP Gas Detection Location Plans - Not Required
22-Feb-25
23-Aug-25
—
100%
PK000MD33G
Issue MD303 RFQ
23-Feb-25
23-Feb-25
—
100%
PK000ML31G
Issue ML313 RFQ
23-Feb-25
23-Feb-25
—
100%
EK000MC32A
Develop & Issue Load Sheets for ERW - MC311
23-Feb-25
28-Feb-25
—
100%
PK000MD32H
Receive Quotes MD302
23-Feb-25
01-Apr-25
—
100%
EK000CK080
Expedite legal issues associated w/ KBRII
23-Feb-25
28-Feb-26
—
100%
PK000I131B
Issue RFQ - Transmitters
25-Feb-25
28-Feb-25
—
100%
EK000MB060
101-B General Arrangement Drawing
25-Feb-25
08-Mar-25
—
100%
EK000MF31A
Develop & Issue Load Sheets for ERW - MF301
26-Feb-25
26-Feb-25
—
100%
PK000MB61G
Issue MB610 RFQ
26-Feb-25
26-Feb-25
—
100%
EK000MB41C
Prepare & Issue Prelim. RFQ - MB410 to Proc.
26-Feb-25
27-Feb-25
—
100%
EK000MC21C
Prepare & Issue Prelim. RFQ - MC210 to Proc.
26-Feb-25
27-Feb-25
—
100%
EK000MC23C
Prepare & Issue Prelim. RFQ - MC230 to Proc.
26-Feb-25
27-Feb-25
—
100%
EK000MD31A
Develop & Issue Load Sheets for ERW - MD301
26-Feb-25
27-Feb-25
—
100%
EK000MD32A
Develop & Issue Load Sheets for ERW - MD302
26-Feb-25
27-Feb-25
—
100%
EK000MD41A
Develop & Issue Load Sheets for ERW - MD401
26-Feb-25
27-Feb-25
—
100%
EK000EL015
Split of work with MEC and Other Discipline
26-Feb-25
28-Feb-25
—
100%
EK000MB63C
Prepare & Issue Prelim. RFQ - MB630 to Proc.
26-Feb-25
28-Feb-25
—
100%
EK000MBP4C
Prepare & Issue Prelim. RFQ Cast Material
26-Feb-25
28-Feb-25
—
100%
EK000PE060
Define Task Force Area in MEC
26-Feb-25
28-Feb-25
—
100%
EK000PE075
MEC Organization Chart
26-Feb-25
28-Feb-25
—
100%
PK000MB81G
Issue MB810 RFQ
26-Feb-25
28-Feb-25
—
100%
EK000PM030
Estimate Escalation Check - IRC Approvals
26-Feb-25
01-Mar-25
—
100%
PK000MB62G
Issue MB621 RFQ
26-Feb-25
01-Mar-25
—
100%
EK000PR095
Steam Balance - Startup, 103-J, Etc
26-Feb-25
02-Mar-25
—
100%
EK000MBP3C
Prepare & Issue Prelim. RFQ Pressure Parts
26-Feb-25
05-Mar-25
—
100%
PK000MBP1H
101-B Receive Quotes Shop Fab
26-Feb-25
05-Mar-25
—
100%
EK000MD33B
Develop & Issue Design Data for ERW - MD303
26-Feb-25
08-Mar-25
—
100%
EK000EV025
Develop & Issue Enviromental Work Plan
26-Feb-25
09-Mar-25
—
100%
EK000IC020
Establlish data warehouse - Intools Basic Setup
26-Feb-25
09-Mar-25
—
100%
EK000IC025
Review Instr. & Installation Details - ID Change
26-Feb-25
09-Mar-25
—
100%
EK000MJ22F
Update/Issue Formal Inquiry for ERW - MJ201
26-Feb-25
09-Mar-25
—
100%
EK000PK010
Issue critical req'n submittal sched to Procmnt
26-Feb-25
09-Mar-25
—
100%
EK000GE010
Eng. Studies - Air Coolers vs. Cooling Water
26-Feb-25
12-Mar-25
—
100%
PK000MD34H
Receive Quotes MD304
26-Feb-25
15-Mar-25
—
100%
PK000MD41H
Receive Quotes MD401
26-Feb-25
15-Mar-25
—
100%
EK000CV060
Civil project highlights
26-Feb-25
16-Mar-25
—
100%
EK000PI005
Locate Permanent Tie in pnts Gas, Wtr, Storm wtr
26-Feb-25
16-Mar-25
—
100%
PK000MD42H
Receive Quotes MD402
26-Feb-25
21-Mar-25
—
100%
PK000MD51H
Receive Quotes MD501
26-Feb-25
21-Mar-25
—
100%
EK000PE065
Develop & Issue HOC - MEC Coordination Plan
26-Feb-25
23-Mar-25
—
100%
PK000MD43H
Receive Quotes MD403
26-Feb-25
01-Apr-25
—
100%
PK000ML31H
Receive Quotes ML313
26-Feb-25
04-Apr-25
—
100%
EK000PI133
Dvlp/Issue V-class specs & Standads for Procurmt
26-Feb-25
09-Apr-25
—
100%
EK000MB085
101-B Radiant Detail Drawings - IFF
26-Feb-25
12-Apr-25
—
100%
EK000MB090
101-B Convection Detail Drawings - IFF
26-Feb-25
12-Apr-25
—
100%
PK000MD31H
Receive Quotes MD301
26-Feb-25
13-Apr-25
—
100%
PK000MD33H
Receive Quotes MD303
26-Feb-25
13-Apr-25
—
100%
EK000CV035
Prepare Geotech S/C Pkgs
26-Feb-25
27-Apr-25
—
100%
EK000EL025
Develop installation details
26-Feb-25
07-May-25
—
100%
EK000IC045
Develop & Issue CSE Work Plan
26-Feb-25
08-May-25
—
100%
EK000PM045
Issue Execution Strategy /Project Execution Plan
26-Feb-25
24-May-25
—
100%
EK000MC31A
Develop & Issue Load Sheets for ERW - MC310
27-Feb-25
01-Mar-25
—
100%
PK000ML50G
Issue ML500 RFQ
27-Feb-25
01-Mar-25
—
100%
EK000ML50B
Develop/Issue Load Sht & Design Data ERW - ML500
27-Feb-25
05-Mar-25
—
100%
PK000MB61H
Receive Quotes for MB610
27-Feb-25
13-Mar-25
—
100%
PK000MC61H
Receive Quotes MC610
27-Feb-25
16-Mar-25
—
100%
PK000MC31H
Receive Quotes for MC310
27-Feb-25
04-May-25
—
100%
PK000MC32H
Receive Quotes for MC311
27-Feb-25
04-May-25
—
100%
PK020MC3C
MC312 - (120,121-C) - Receive Quotes
27-Feb-25
04-May-25
—
100%
PK000MC21G
Issue MC210 RFQ
28-Feb-25
28-Feb-25
—
100%
PK000MC23G
Issue MC230 RFQ
28-Feb-25
28-Feb-25
—
100%
EK000MD42A
Develop & Issue Load Sheets for ERW - MD402
28-Feb-25
01-Mar-25
—
100%
PK000MB41G
Issue MB410 RFQ
28-Feb-25
01-Mar-25
—
100%
EK000MD51A
Develop & Issue Load Sheets for ERW - MD501
28-Feb-25
05-Mar-25
—
100%
EK000MJ35A
Develop & Issue Load Sheets for ERW - MJ305
28-Feb-25
23-Mar-25
—
100%
PK000MD22G
Issue MD202 RFQ
01-Mar-25
01-Mar-25
—
100%
PK000MD44G
Issue MD404 RFQ
01-Mar-25
01-Mar-25
—
100%
PK000MD45G
Issue MD405 RFQ
01-Mar-25
01-Mar-25
—
100%
PK000MD46G
Issue MD411 RFQ
01-Mar-25
01-Mar-25
—
100%
PK000MB63G
Issue MB630 RFQ
01-Mar-25
05-Mar-25
—
100%
PK000MBP4G
Issue 101-B Cast Material RFQ
01-Mar-25
05-Mar-25
—
100%
PK000MC21H
Receive Quotes for MC210
01-Mar-25
26-Mar-25
—
100%
PK000MC23H
Receive Quotes for MC230
01-Mar-25
02-Apr-25
—
100%
EK000YA808
(EP-09) Issue Engineering Plan
01-Mar-25
01-Mar-25
—
100%
PK000I131C
Receive Quotes - Transmitters
01-Mar-25
25-Mar-25
—
100%
EK000MD060
Prepare Vessel work plan & other quality documents
02-Mar-25
02-Mar-25
—
100%
EK010PI005
Develop Plot Plan & ID Areas - Overall Site IFI
02-Mar-25
09-Mar-25
—
100%
EK030PI005
Develop Plot Plan & ID Areas - Utility Plant IFI
02-Mar-25
09-Mar-25
—
100%
EK050PI005
Develop Plot Plan & ID Areas - Dock/Storage IFI
02-Mar-25
09-Mar-25
—
100%
EK000MC31B
Develop & Issue Design Data for ERW - MC310
02-Mar-25
13-Mar-25
—
100%
PK000MD22H
Receive Quotes for MD202
02-Mar-25
21-Mar-25
—
100%
PK000MD44H
Receive Quotes MD404
02-Mar-25
21-Mar-25
—
100%
PK000MD45H
Receive Quotes MD405
02-Mar-25
21-Mar-25
—
100%
PK000MD46H
Receive Quotes MD411
02-Mar-25
21-Mar-25
—
100%
PK000ML50H
Receive Quotes ML500
02-Mar-25
22-Mar-25
—
100%
PK000MB81H
Receive Quotes for MB810
02-Mar-25
28-Mar-25
—
100%
PK000MB62H
Receive Quotes for MB621
02-Mar-25
29-Mar-25
—
100%
EK000MC31F
Finalize Equip. Data Sheets for ERW - MC310
02-Mar-25
12-Apr-25
—
100%
PK000MB41H
Receive Quotes for MB410
02-Mar-25
20-Apr-25
—
100%
EK000PI125
Validate new plot layout (impacts on pipe stress
02-Mar-25
21-May-25
—
100%
EK000MJ21D
Technical Evaluation - MJ202
05-Mar-25
05-Mar-25
—
100%
EK000MJ75A
Develop & Issue Load Sheets for ERW - MJ750
05-Mar-25
05-Mar-25
—
100%
EK000ML31A
Develop & Issue Load Sheets for ERW - ML313
05-Mar-25
05-Mar-25
—
100%
EK000MB51C
Prepare & Issue Prelim. RFQ - MB511 to Proc.
05-Mar-25
07-Mar-25
—
100%
EK000CV075
Egyptian Professional Engineer - Define Reqmnts
05-Mar-25
08-Mar-25
—
100%
EK000MC21A
Develop & Issue Load Sheets for ERW - MC210
05-Mar-25
08-Mar-25
—
100%
EK000EL035
Voltage drop table
05-Mar-25
09-Mar-25
—
100%
EK000ML42C
Prepare & Issue Prelim. RFQ - ML420 to Proc.
05-Mar-25
09-Mar-25
—
100%
EK000MU33C
Prepare & Issue Prelim. RFQ - MU330 to Proc.
05-Mar-25
09-Mar-25
—
100%
EK000PI140
Eqvlnt Line Counts / Planning Area-Utility Plant
05-Mar-25
09-Mar-25
—
100%
PK000MJ35G
Issue MJ305 RFQ
05-Mar-25
12-Mar-25
—
100%
PK000MJ36G
Issue MJ306 RFQ
05-Mar-25
12-Mar-25
—
100%
EK000CS030
Start-up Schedule (Prelim for 1st Planner)
05-Mar-25
14-Mar-25
—
100%
EK000MC32B
Develop & Issue Design Data for ERW - MC311
05-Mar-25
19-Mar-25
—
100%
EK000MC23A
Develop & Issue Load Sheets for ERW - MC230
05-Mar-25
22-Mar-25
—
100%
EK000MC32F
Finalize Equip. Data Sheets for ERW - MC311
05-Mar-25
24-May-25
—
100%
EK000MD22A
Develop & Issue Load Sheets for ERW - MD202
06-Mar-25
06-Mar-25
—
100%
PK000MJ21I
Eval Bids & Issue Recmd MJ202
06-Mar-25
06-Mar-25
—
100%
PK000MBP3G
Issue 101-B Pressure Parts RFQ
06-Mar-25
07-Mar-25
—
100%
EK000MBP1D
101-B Technical Bid Evaluation Shop Fab
06-Mar-25
09-Mar-25
—
100%
EK000MJ37A
Develop & Issue Load Sheets for ERW - MJ340
06-Mar-25
09-Mar-25
—
100%
EK000ML31B
Develop & Issue Design Data for ERW - ML313
06-Mar-25
15-Mar-25
—
100%
EK000MD42P
Confirm Analytical Design for ERW - MD402
06-Mar-25
21-Mar-25
—
100%
PK000MB63H
Receive Quotes for MB630
06-Mar-25
29-Mar-25
—
100%
PK000MBP4H
Receive Quotes for 101-B Cast Material
06-Mar-25
03-Apr-25
—
100%
EK000ML50F
Update/Issue Formal Inquiry for ERW - ML500
06-Mar-25
27-Apr-25
—
100%
EK000PE020
WMS Setup & Development
07-Mar-25
15-Mar-25
—
100%
EK000CV080
Egyptian Professional Eng. - Issue P.O/Subc. Pkg
08-Mar-25
09-Mar-25
—
100%
PK000MB51G
Issue MB511 RFQ
08-Mar-25
09-Mar-25
—
100%
EK000MJ21F
Update/Issue Formal Inquiry for ERW - MJ202
08-Mar-25
13-Mar-25
—
100%
EK000MC21B
Develop & Issue Design Data for ERW - MC210
08-Mar-25
01-Apr-25
—
100%
EK000MJ31B
Develop & Issue Design Data for ERW - MJ301
08-Mar-25
12-Apr-25
—
100%
PK000MBP3H
Receive Quotes for 101-B Pressure Part
08-Mar-25
15-Apr-25
—
100%
EK000PI055
Prepare Object Engineering Work Instruction
08-Mar-25
15-Mar-25
—
100%
PK000MJ39G
Issue MJ391/MJ392 RFQ
09-Mar-25
09-Mar-25
—
100%
EK000PC010
Estimate Turnover to Project Team
09-Mar-25
15-Mar-25
—
100%
EK000PI085
Estimate/Schedule Review
09-Mar-25
15-Mar-25
—
100%
EK000MD34R
Develop Final Analytical Sktch for ERW - MD304
09-Mar-25
16-Mar-25
—
100%
EK000MD43P
Confirm Analytical Design for ERW - MD403
09-Mar-25
16-Mar-25
—
100%
EK000MC61A
Develop & Issue Load Sheets for ERW - MC610
09-Mar-25
20-Mar-25
—
100%
PK000IC36B
DCS (MIV) - Inquiry REQ/RFQ
09-Mar-25
21-Mar-25
—
100%
EK000PC015
Estimate Recast & Develop Project Control Budget
09-Mar-25
23-Apr-25
—
100%
EK000PI105
Performance Test of Citrix for PDS w/MEC
12-Mar-25
12-Mar-25
—
100%
PK000MU35G
Issue MU350 RFQ
12-Mar-25
13-Mar-25
—
100%
PK000ML42G
Issue ML420 RFQ
12-Mar-25
15-Mar-25
—
100%
EK000MU41F
Develop & Issue Inquiry for ERW - MU410
12-Mar-25
16-Mar-25
—
100%
PK000PK045
Review ISSP work process with eng.
12-Mar-25
16-Mar-25
—
100%
PK000PK050
Est Preselect low cost redundent bid items
12-Mar-25
16-Mar-25
—
100%
EK000SY060
010 Util & Offsites Conceptual Design revw mtngs
12-Mar-25
19-Mar-25
—
100%
EK000MD34P
Confirm Analytical Design for ERW - MD304
12-Mar-25
20-Mar-25
—
100%
EK000MU41A
Develop & Issue Load Sheets for ERW - MU410
12-Mar-25
20-Mar-25
—
100%
EK000MD31P
Confirm Analytical Design for ERW - MD301
12-Mar-25
29-Mar-25
—
100%
PK000MB51H
Receive Quotes for MB511
12-Mar-25
02-Apr-25
—
100%
EK000MD32P
Confirm Analytical Design for ERW - MD302
12-Mar-25
02-Apr-25
—
100%
EK000PI100
Critical Line List
12-Mar-25
06-Apr-25
—
100%
PK000MJ39H
Receive Quotes MJ391/MJ392
12-Mar-25
09-Apr-25
—
100%
EK000EV020
Develop Preliminary noise model
12-Mar-25
20-Apr-25
—
100%
PK000MJ22M
Requote/Bid Condition/Final Tab - MJ201
12-Mar-25
18-May-25
—
100%
EK000MC21F
Finalize Equip. Data Sheets for ERW - MC210
12-Mar-25
13-Jun-25
—
100%
EK000SY075
010 OSBL Hydraulic Calculations
12-Mar-25
30-Jul-25
—
100%
PK000MBP1I
Eval Bids & Issue Recmd 101-B Shop Fab
13-Mar-25
13-Mar-25
—
100%
PK000MJ35H
Receive Quotes MJ305
13-Mar-25
26-Mar-25
—
100%
PK000MJ36H
Receive Quotes MJ306
13-Mar-25
26-Mar-25
—
100%
EK000MD020
Equipment Modeling for Vessel - MEC
13-Mar-25
25-Mar-26
—
100%
EK000MB61D
Technical Evaluation - MB610
14-Mar-25
20-Mar-25
—
100%
PK000MU35H
Receive Quotes MU350
14-Mar-25
06-Apr-25
—
100%
PK000MJ21M
Requote/Bid Condition/Final Tab - MJ202
14-Mar-25
01-May-25
—
100%
EK000PR080
Input to Process Guarantees
14-Mar-25
03-May-25
—
100%
EK000IC35D
DCS - Tech Evaluation
14-Mar-25
14-May-25
—
100%
EK000MJ32A
Develop & Issue Load Sheets for ERW - MJ302
15-Mar-25
20-Mar-25
—
100%
PK000MBP1J
Final Negotiate/Interim Award - 101-B Shop Fab
15-Mar-25
09-Aug-25
—
100%
EK000ML31F
Update/Issue Formal Inquiry for ERW - ML313
16-Mar-25
16-Mar-25
—
100%
EK000MD31B
Develop & Issue Design Data for ERW - MD301
16-Mar-25
19-Mar-25
—
100%
EK000MD32B
Develop & Issue Design Data for ERW - MD302
16-Mar-25
19-Mar-25
—
100%
EK000MD34B
Develop & Issue Design Data for ERW - MD304
16-Mar-25
19-Mar-25
—
100%
EK000MJ22D
Technical Evaluation - MJ201
16-Mar-25
19-Mar-25
—
100%
EK000MD45A
Develop & Issue Load Sheets for ERW - MD405
16-Mar-25
20-Mar-25
—
100%
EK000ML43A
Develop & Issue Load Sheets for ERW - ML430
16-Mar-25
20-Mar-25
—
100%
EK000ML44A
Develop & Issue Load Sheets for ERW - ML440
16-Mar-25
20-Mar-25
—
100%
PK000ML42H
Receive Quotes ML420
16-Mar-25
08-Apr-25
—
100%
EK000PE095
Disciplines Load WMS with Budgets & Deliverables
16-Mar-25
20-Apr-25
—
100%
EK000MD34D
Technical Evaluation - MD304
16-Mar-25
23-Apr-25
—
100%
EK000MD41D
Technical Evaluation - MD401
16-Mar-25
23-Apr-25
—
100%
PK000PIA1A
Bulk Piping A/G & U/G - Issue REQ/RFQ to Vend
18-Mar-25
20-Mar-25
—
100%
EK000ML42A
Develop & Issue Load Sheets for ERW - ML420
19-Mar-25
20-Mar-25
—
100%
EK000MU35A
Develop & Issue Load Sheets for ERW - MU350
19-Mar-25
20-Mar-25
—
100%
EK000MU41B
Develop & Issue Design Data for ERW - MU410
19-Mar-25
21-Mar-25
—
100%
EK000MU30F
Develop & Issue Inquiry for ERW - MU300
19-Mar-25
26-Mar-25
—
100%
EK000MF32A
05A MF312 2105-F Water Tank - Process Load Sht.
19-Mar-25
26-Mar-25
—
100%
EK000MF33B
Develop/Issue Load Sht & Design Data ERW - MF311
19-Mar-25
26-Mar-25
—
100%
EK000MF32B
Develop/Issue Load Sht & Design Data ERW - MF302
19-Mar-25
06-Apr-25
—
100%
EK000MD21B
Develop & Issue Design Data for ERW - MD201
19-Mar-25
08-May-25
—
100%
PK000ML31M
Requote/Bid Condition/Final Tab - ML313
19-Mar-25
30-Jul-25
—
100%
EK000ML42F
Update/Issue Formal Inquiry for ERW - ML420
19-Mar-25
24-Apr-25
—
100%
PK000MJ22I
Eval Bids & Issue Recmd MJ201
20-Mar-25
22-Mar-25
—
100%
EK000MC63A
Develop & Issue Load Sheets for ERW - MC630
20-Mar-25
22-Mar-25
—
100%
PK000MU41G
Issue MU410 RFQ
20-Mar-25
21-Mar-25
—
100%
EK000MU61F
Develop & Issue Inquiry for ERW - MU611
20-Mar-25
25-Mar-25
—
100%
EK000I210D
000 Control Valves - Technical Evaluation
20-Mar-25
23-May-25
—
100%
EK000MU35F
Update/Issue Formal Inquiry for ERW - MU350
21-Mar-25
22-Mar-25
—
100%
EK000MD47A
Develop & Issue Load Sheets for ERW - MD406
21-Mar-25
23-Mar-25
—
100%
EK000MD51B
Develop & Issue Design Data for ERW - MD501
21-Mar-25
28-Mar-25
—
100%
EK000MC61D
Technical Evaluation - MC610
21-Mar-25
01-Apr-25
—
100%
EK000MC61F
Finalize Equip. Data Sheets for ERW - MC610
21-Mar-25
10-Apr-25
—
100%
EK000MJ32B
Develop & Issue Design Data for ERW - MJ302
21-Mar-25
13-Apr-25
—
100%
EK000MD34F
Update/Issue Formal Inquiry for ERW - MD304
21-Mar-25
20-Apr-25
—
100%
PK000MB61I
Eval Bids & Issue Recmd MB610
21-Mar-25
25-Apr-25
—
100%
PK000PIA1B
Bulk Piping A/G & U/G - Receive Bids
21-Mar-25
04-May-25
—
100%
PK000IC36C
DCS (MIV) - Receive Bids
22-Mar-25
12-Apr-25
—
100%
EK000EV010
Develop design basis for evaporation pond
22-Mar-25
11-May-25
—
100%
EK000YA802
(EP-03) Issue Process Plan
22-Mar-25
22-Mar-25
—
100%
EK000MB51F
Prepare & Issue Purchase ERW - MB511
23-Mar-25
17-Apr-25
—
100%
EK010PI010
Develop Plot Plan & ID Areas - Overall Site (Drwg 0101) ICA
23-Mar-25
31-Aug-25
—
100%
EK030PI010
Develop Plot Plan & ID Areas - Utility Plant ICA
23-Mar-25
11-Oct-25
—
100%
EK050PI010
Develop Plot Plan & ID Areas - Dock/Storage ICA
23-Mar-25
11-Oct-25
—
100%
PK000MU41H
Receive Quotes MU410
23-Mar-25
25-Apr-25
—
100%
EK000MJ39B
Develop/Issue Load Sht & Design Data ERW - MJ391
25-Mar-25
29-Mar-25
—
100%
EK000ML50D
Technical Evaluation - ML500
25-Mar-25
27-Apr-25
—
100%
EK000MD025
Prepare job quality drawings for ERW
25-Mar-25
28-May-25
—
100%
EK000ML44B
Develop & Issue Design Data for ERW - ML440
26-Mar-25
27-Mar-25
—
100%
EK000MF31P
Confirm Analytical Design for ERW - MF301
26-Mar-25
29-Mar-25
—
100%
EK000PR070
Effluent Summary
26-Mar-25
30-Mar-25
—
100%
EK000MD51D
Technical Evaluation - MD501
26-Mar-25
03-Apr-25
—
100%
EK000MU33F
Update/Issue Formal Inquiry for ERW - MU330
26-Mar-25
04-Apr-25
—
100%
EK000MD33F
Update/Issue Formal Inquiry for ERW - MD303
26-Mar-25
11-May-25
—
100%
PK000MU30G
Issue MU300 RFQ
26-Mar-25
28-Mar-25
—
100%
PK000MU61G
Issue MU611 RFQ
26-Mar-25
04-Apr-25
—
100%
EK000MF32F
Develop & Issue Design Data for Tank Subcontract - MF302
26-Mar-25
08-Apr-25
—
100%
PK000MJ35I
Eval Bids & Issue Recmd MJ305
26-Mar-25
02-May-25
—
100%
EK000I131D
Technical Evaluation - Transmitters
26-Mar-25
23-May-25
—
100%
EK000MJ35D
Technical Evaluation - MJ305
27-Mar-25
02-Apr-25
—
100%
EK000MJ36D
Technical Evaluation - MJ306
27-Mar-25
02-Apr-25
—
100%
EK000MF32C
05A MF312 2105-F Water Tank - Issue Data for Subcontract
27-Mar-25
09-Apr-25
—
100%
EK000MF33F
Develop & Issue Design Data for Tank Subcontract - MF311
27-Mar-25
09-Apr-25
—
100%
EK000CVK35
OSBL Rough Grading/Road
27-Mar-25
23-May-25
—
100%
EK000MD51F
Update/Issue Formal Inquiry for ERW - MD501
29-Mar-25
08-Apr-25
—
100%
EK000MD45P
Confirm Analytical Design for ERW - MD405
29-Mar-25
25-Apr-25
—
100%
PK000MU30H
Receive Quotes MU300
29-Mar-25
10-May-25
—
100%
EK000MB62D
Technical Evaluation - MB621
30-Mar-25
18-Apr-25
—
100%
EK000MB63D
Technical Evaluation - MB630
30-Mar-25
24-Jun-25
—
100%
EK000MF31B
Develop & Issue Design Data for Tank Subcontrac - MF301
01-Apr-25
08-Apr-25
—
100%
EK000MJ34B
Develop/Issue Load Sht & Design Data ERW - MJ304
01-Apr-25
08-Apr-25
—
100%
EK000PR065
Catalyst and Chemical Specs
01-Apr-25
09-Apr-25
—
100%
EK000MB070
101-B Foundation Loads
01-Apr-25
19-Apr-25
—
100%
EK000PR075
Process Description
01-Apr-25
25-Apr-25
—
100%
EK000MJ39F
Update/Issue Formal Inquiry for ERW - MJ391
01-Apr-25
27-Apr-25
—
100%
EK000QM020
Develop/ Issue/ Approval of QA/QC Manual (EBIC/EXIM Verification)
01-Apr-25
31-Oct-25
—
100%
EK000MD44P
Confirm Analytical Design for ERW - MD404
02-Apr-25
03-Apr-25
—
100%
EK000MD31F
Update/Issue Formal Inquiry for ERW - MD301
02-Apr-25
16-Apr-25
—
100%
EK000MU61B
Develop/Issue Load Sht & Design Data ERW - MU611
02-Apr-25
14-May-25
—
100%
EK000MB51D
Technical Evaluation - MB511
02-Apr-25
16-Apr-25
—
100%
EK000MD32F
Update/Issue Formal Inquiry for ERW - MD302
02-Apr-25
20-Apr-25
—
100%
EK000MD43D
Technical Evaluation - MD403
02-Apr-25
25-Apr-25
—
100%
PK000MC61I
Eval Bids & Issue Recmd MC610
03-Apr-25
05-Apr-25
—
100%
EK000MC61B
Develop & Issue Design Data for ERW - MC610
04-Apr-25
20-Apr-25
—
100%
PK000PSA8A
000 Relief Valves - Issue RFQ
04-Apr-25
10-Apr-25
—
100%
EK000MJ35B
Develop & Issue Design Data for ERW - MJ305
05-Apr-25
09-May-25
—
100%
EK000MB080
101-B Convection Coil Design
05-Apr-25
12-Apr-25
—
100%
EK000ML31D
Technical Evaluation - ML313
05-Apr-25
19-Apr-25
—
100%
PK000MJ36I
Eval Bids & Issue Recmd MJ306
06-Apr-25
12-Apr-25
—
100%
PK000PK040
Establish Project Warranty Criteria
06-Apr-25
12-Apr-25
—
100%
EK000MB050
101-B Radiant coil design
06-Apr-25
12-Apr-25
—
100%
EK000MD22P
Confirm Analytical Design for ERW - MD202
06-Apr-25
15-Apr-25
—
100%
EK000MB33F
MB333 - Develop & Issue Purchase ERW 101-B
06-Apr-25
23-Apr-25
—
100%
EK010SY020
010 CW Twr & FW Tanks P&ID development IDR Issue
06-Apr-25
25-Apr-25
—
100%
EK030SY020
030 Utility Plant P&ID development IDR Issue
06-Apr-25
25-Apr-25
—
100%
EK050SY020
050 Dock/Storage P&ID development IDR Issue
06-Apr-25
25-Apr-25
—
100%
EK000MBP4D
Technical Evaluation - 101-B Cast Material
06-Apr-25
01-May-25
—
100%
PK000MU61H
Receive Quotes MU611
06-Apr-25
02-May-25
—
100%
PK000MD51I
Eval Bids & Issue Recmd MD501
06-Apr-25
24-May-25
—
100%
EK000PI131
Devlop Balance Tech P-Class specs for Procuremnt
06-Apr-25
25-May-25
—
100%
EK000FP050
FP Overall Firewater P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
—
100%
EK010FP011
FP Firewater Pump P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
—
100%
EK010FP050
FP Deluge P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
—
100%
PK000MU33G
Issue MU330 RFQ
08-Apr-25
09-Apr-25
—
100%
EK000MD43B
Develop & Issue Design Data for ERW - MD403
08-Apr-25
12-Apr-25
—
100%
EK000MU35D
Technical Evaluation - MU350
08-Apr-25
19-Apr-25
—
100%
EK000MC21D
Technical Evaluation - MC210
08-Apr-25
23-Apr-25
—
100%
EK000MC23D
Technical Evaluation - MC230
08-Apr-25
23-Apr-25
—
100%
EK000MD45B
Develop & Issue Design Data for ERW - MD405
08-Apr-25
08-May-25
—
100%
PK000MC61M
Requote/Bid Condition/Final Tab - MC610
08-Apr-25
04-Sep-25
—
100%
EK000MC23B
Develop & Issue Design Data for ERW - MC230
09-Apr-25
13-Apr-25
—
100%
EK000MD42B
Develop & Issue Design Data for ERW - MD402
09-Apr-25
13-Apr-25
—
100%
EK000MD41B
Develop & Issue Design Data for ERW - MD401
09-Apr-25
18-Apr-25
—
100%
EK000MU30B
Develop/Issue Load Sht & Design Data ERW - MU300
09-Apr-25
25-Apr-25
—
100%
EK000PS010
Level III CPM Schedule / First Planner
09-Apr-25
24-May-25
—
100%
PK000IC35E
DCS - Eval Bids/Issue Recmd
09-Apr-25
31-May-25
—
100%
EK000ML42D
Technical Evaluation - ML420
09-Apr-25
19-Apr-25
—
100%
EK000MJ34F
Update/Issue Formal Inquiry for ERW - MJ304
09-Apr-25
26-Apr-25
—
100%
PK000MD51M
Requote/Bid Condition/Final Tab - MD501
09-Apr-25
03-May-25
—
100%
EK000MB41D
Technical Evaluation - MB410
10-Apr-25
01-May-25
—
100%
PK000MU33H
Receive Quotes MU330
10-Apr-25
20-May-25
—
100%
PK000PSA8B
000 Relief Valves - Receive Quotes
10-Apr-25
20-Jun-25
—
100%
EK000MJ33B
Develop/Issue Load Sht & Design Data ERW - MJ303
11-Apr-25
23-May-25
—
100%
EK000MJ32D
Technical Evaluation - MJ302
12-Apr-25
19-Apr-25
—
100%
EK000MJ31D
Technical Evaluation - MJ301
12-Apr-25
25-Apr-25
—
100%
EK000MB055
101-B Radiant coil BOM
15-Apr-25
19-Apr-25
—
100%
EK000MB075
101-B Convection Coil BOM
15-Apr-25
19-Apr-25
—
100%
EK000ML51B
Develop/Issue Load Sht & Design Data ERW - ML512
15-Apr-25
19-Apr-25
—
100%
EK000MC63B
Develop & Issue Design Data for ERW - MC630
15-Apr-25
20-Apr-25
—
100%
EK000MB61E
Prepare & Issue Purchase ERW - MB610
15-Apr-25
22-Apr-25
—
100%
EK000MD43F
Update/Issue Formal Inquiry for ERW - MD403
15-Apr-25
25-Apr-25
—
100%
EK000MD32D
Technical Evaluation - MD302
15-Apr-25
04-May-25
—
100%
EK000IC36D
DCS (MIV) - Tech Evaluation
15-Apr-25
17-May-25
—
100%
EK000MC31P
Develop & Issue Setting Plans for ERW - MC310
15-Apr-25
28-May-25
—
100%
EK000MC21P
Develop & Issue Setting Plans for ERW - MC210
15-Apr-25
20-Jun-25
—
100%
EK000CS025
Turnover System Definition for ISBL
15-Apr-25
31-Jan-26
—
100%
EK000MD42F
Update/Issue Formal Inquiry for ERW - MD402
16-Apr-25
19-Apr-25
—
100%
EK000ML42B
Develop & Issue Design Data for ERW - ML420
16-Apr-25
20-Apr-25
—
100%
EK000MD31D
Technical Evaluation - MD301
16-Apr-25
25-Apr-25
—
100%
EK000ML33B
Develop/Issue Load Sht & Design Data ERW - ML330
16-Apr-25
25-Apr-25
—
100%
EK000MD33D
Technical Evaluation - MD303
16-Apr-25
04-May-25
—
100%
EK000MBP3D
Technical Evaluation - 101-B Pressure Parts
16-Apr-25
10-May-25
—
100%
EK000MD21F
Develop & Issue Inquiry ERW - MD201
17-Apr-25
17-Jun-25
—
100%
EK000PR140
Formal Issue of Process Release
18-Apr-25
08-May-25
—
100%
PK000MD31M
Final Tab/Recmd - MD301
18-Apr-25
24-Jul-25
—
100%
EK000MD47P
Confirm Analytical Design for ERW - MD406
18-Apr-25
22-Apr-25
—
100%
PK000MD45I
Eval Bids & Issue Recmd MD405
19-Apr-25
01-May-25
—
100%
PK000MJ36J
Final Negotiate/Interim Award - MJ306
19-Apr-25
02-May-25
—
100%
PK000MD22I
Eval Bids & Issue Recmd MD202
19-Apr-25
03-May-25
—
100%
PK000MD42I
Eval Bids & Issue Recmd MD402
19-Apr-25
04-May-25
—
100%
PK000MD44I
Eval Bids & Issue Recmd MD404
19-Apr-25
04-May-25
—
100%
EK000MJ37B
Develop & Issue Design Data for ERW - MJ340
19-Apr-25
09-May-25
—
100%
EK000MD41F
Update/Issue Formal Inquiry for ERW - MD401
20-Apr-25
26-Apr-25
—
100%
EK000MD44Q
Develop Analytical Sketches for ERW - MD404
20-Apr-25
27-Apr-25
—
100%
EK000MJ73B
Develop/Issue Load Sht & Design Data ERW - MJ730
20-Apr-25
30-Apr-25
—
100%
EK000EV015
Issue load sheets for wastewater systems
20-Apr-25
31-May-25
—
100%
EK000MD44B
Develop & Issue Design Data for ERW - MD404
22-Apr-25
25-Apr-25
—
100%
EK000MD47B
Develop & Issue Design Data for ERW - MD406
22-Apr-25
25-Apr-25
—
100%
PK000I110B
Issue RFQ - Orific Plates
22-Apr-25
25-Apr-25
—
100%
PK000I112B
Issue RFQ - Venturis
22-Apr-25
25-Apr-25
—
100%
PK000I115B
Issue RFQ - Annubars
22-Apr-25
25-Apr-25
—
100%
PK000I116B
Issue RFQ - Wedge Flow Meters
22-Apr-25
25-Apr-25
—
100%
PK000I616B
Issue RFQ - Steam Drum Lvl Gauges
22-Apr-25
25-Apr-25
—
100%
PK000I623B
Issue RFQ - Multi-Point Thermocouples
22-Apr-25
25-Apr-25
—
100%
PK000MB81I
Eval Bids & Issue Recmd MB810
22-Apr-25
25-Apr-25
—
100%
PK000ML31I
Eval Bids & Issue Recmd ML313
22-Apr-25
26-Apr-25
—
100%
PK000ML42I
Eval Bids & Issue Recmd ML420
22-Apr-25
26-Apr-25
—
100%
PK000MU35I
Eval Bids & Issue Recmd MU350
22-Apr-25
26-Apr-25
—
100%
PK000MD42M
Requote/Bid Condition/Final Tab - MD402
22-Apr-25
30-Apr-25
—
100%
EK000MD46B
Develop/Issue Load Sht & Design Data ERW - MD411
22-Apr-25
03-May-25
—
100%
PK000MJ32I
Eval Bids & Issue Recmd MJ302
22-Apr-25
03-May-25
—
100%
PK000MD34M
Requote/Bid Condition/Final Tab - MD304
22-Apr-25
04-May-25
—
100%
PK000MD46I
Eval Bids & Issue Recmd MD411
22-Apr-25
04-May-25
—
100%
EK000MU11B
05B MU311 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
—
100%
EK000MU25B
02G MU225 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
—
100%
EK000MU32B
01D MU322 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
—
100%
EK000MD22B
Develop & Issue Design Data for ERW - MD202
23-Apr-25
01-May-25
—
100%
PK000MD32M
Requote/Bid Condition/Final Tab - MD302
23-Apr-25
10-May-25
—
100%
EK000MU31B
Develop/Issue Load Sht & Design Data ERW - MU310
23-Apr-25
16-May-25
—
100%
EK000MC23F
Finalize Equip. Data Sheets for ERW - MC230
23-Apr-25
13-Jun-25
—
100%
PK000MD41I
Eval Bids & Issue Recmd MD401
23-Apr-25
02-May-25
—
100%
PK000MD34I
Eval Bids & Issue Recmd MD304
24-Apr-25
11-May-25
—
100%
PK000MC21I
Eval Bids & Issue Recmd MC210
24-Apr-25
24-May-25
—
100%
PK000MC23I
Eval Bids & Issue Recmd MC230
24-Apr-25
24-May-25
—
100%
PK000I611B
Issue RFQ - Pressure Gauges
24-Apr-25
30-Apr-25
—
100%
PK000I612B
Issue RFQ - Differential Pressure Gauges
25-Apr-25
30-Apr-25
—
100%
PK000I618B
Issue RFQ - Temperature Gauges
25-Apr-25
30-Apr-25
—
100%
PK000I621B
Issue RFQ - Temperature Elements
25-Apr-25
30-Apr-25
—
100%
PK000I121B
Issue RFQ - Vortex Meters
25-Apr-25
01-May-25
—
100%
PK000I122B
Issue RFQ - Coriolis Meters
25-Apr-25
01-May-25
—
100%
PK000I124B
Issue RFQ - Rotameters
25-Apr-25
01-May-25
—
100%
PK000I127B
Magnetic Flow Meters - Issue RFQ
25-Apr-25
01-May-25
—
100%
PK000ML42M
Requote/Bid Condition/Final Tab - ML420
25-Apr-25
18-Oct-25
—
100%
PK000I617B
Issue RFQ - Magnetic Lvl Gauges
26-Apr-25
01-May-25
—
100%
+
MB333 - Issue RFQ 101-B
26-Apr-25
02-May-25
—
100%
EK000CV036
Issue Geotech S/C PKG
26-Apr-25
02-May-25
—
100%
PK000MJ31I
Eval Bids & Issue Recmd MJ301
26-Apr-25
03-May-25
—
100%
EK000CV140
Issue Site Survey S/C PKG
26-Apr-25
14-May-25
—
100%
PK000I115C
Receive Quotes - Annubars
26-Apr-25
14-May-25
—
100%
PK000I116C
Receive Quotes - Wedge Flow Meters
26-Apr-25
15-May-25
—
100%
EK000CV145
Issue Site Leveling PKG
26-Apr-25
16-May-25
—
100%
PK000I616C
Receive Quotes - Steam Drum Lvl Gauges
26-Apr-25
17-May-25
—
100%
PK000I110C
Receive Quotes - Orific Plates
26-Apr-25
20-May-25
—
100%
PK000I112C
Receive Quotes - Venturis
26-Apr-25
13-Jun-25
—
100%
PK000I623C
Receive Quotes - Multi-Point Thermocouples
26-Apr-25
15-Jul-25
—
100%
PK000MB62I
Eval Bids & Issue Recmd MB621
27-Apr-25
29-Apr-25
—
100%
PK000MJ34G
Issue MJ304 RFQ
27-Apr-25
30-Apr-25
—
100%
EK000MD44F
Update/Issue Formal Inquiry for ERW - MD404
27-Apr-25
01-May-25
—
100%
EK000ML51F
Develop & Issue Inquiry for ERW - ML512
27-Apr-25
01-May-25
—
100%
PK000MD43I
Eval Bids & Issue Recmd MD403
27-Apr-25
04-May-25
—
100%
PK000MD43M
Requote/Bid Condition/Final Tab - MD403
27-Apr-25
04-May-25
—
100%
PK000ML50I
Eval Bids & Issue Recmd ML500
27-Apr-25
04-May-25
—
100%
EK000MJ31F
Update/Issue Formal Inquiry for ERW - MJ301
27-Apr-25
08-May-25
—
100%
EK000MBP1E
Prepare & Issue Purchase ERW 101-B Shop Fab
27-Apr-25
10-May-25
—
100%
EK000ML33F
Develop & Issue Inquiry for ERW - ML330
27-Apr-25
13-May-25
—
100%
PK000MB51I
Eval Bids & Issue Recmd MB511
27-Apr-25
14-May-25
—
100%
EK000MJ32F
Update/Issue Formal Inquiry for ERW - MJ302
27-Apr-25
29-May-25
—
100%
EK000MB63F
Prepare & Issue Purchase ERW - MB630
27-Apr-25
29-May-25
—
100%
EK000MJ36B
Develop/Issue Load Sht & Design Data ERW - MJ306
27-Apr-25
08-Jun-25
—
100%
PK000MU35M
Requote/Bid Condition/Final Tab - MU350
27-Apr-25
15-Jul-25
—
100%
PK000MD41M
Final Tab/Recmd - MD401
27-Apr-25
23-Jul-25
—
100%
PK000ML50M
Requote/Bid Condition/Final Tab - ML500
29-Apr-25
08-Aug-25
—
100%
PK000MJ39M
Requote/Bid Condition/Final Tab - MJ391/MJ392
29-Apr-25
20-Dec-25
—
100%
EK000MU35B
Develop & Issue Design Data for ERW - MU350
01-May-25
14-May-25
—
100%
EK000IC010
Make decision of FF vs. Traditional DCS system
01-May-25
17-May-25
—
100%
EK000MJ75B
Develop & Issue Design Data for ERW - MJ750
01-May-25
20-May-25
—
100%
EK000CV136
Issue Rough Grade (Ammonia) S/C PKG
01-May-25
27-May-25
—
100%
EK000MJ73F
Develop & Issue Inquiry for ERW - MJ730
01-May-25
12-Jun-25
—
100%
PK000MJ34H
Receive Quotes MJ304
01-May-25
01-May-25
—
100%
PK000ML51G
Issue ML512 RFQ
01-May-25
01-May-25
—
100%
EK000MD22F
Update/Issue Formal Inquiry for ERW - MD202
01-May-25
17-May-25
—
100%
PK000I611C
Receive Quotes - Pressure Gauges
01-May-25
22-May-25
—
100%
PK000I612C
Receive Quotes - Differential Pressure Gauges
01-May-25
22-May-25
—
100%
EK000MC23P
Develop & Issue Setting Plans for ERW - MC230
01-May-25
21-Jun-25
—
100%
PK000I621C
Receive Quotes - Temperature Elements
01-May-25
10-Jul-25
—
100%
PK000I618C
Receive Quotes - Temperature Gauges
01-May-25
11-Jul-25
—
100%
EK000MU11O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
—
100%
EK000MU25O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
—
100%
EK000MU310
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
—
100%
EK000MU32O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
—
100%
EK010SY030
010 CW Twr & FW Tanks P&ID IDR Meeting milestone
02-May-25
03-May-25
—
100%
EK030SY030
030 Utility Plant P&ID IDR Meeting milestone
02-May-25
03-May-25
—
100%
EK050SY030
050 Dock/Storage P&ID IDR Meeting milestone
02-May-25
03-May-25
—
100%
PK000MBP4I
Eval Bids & Issue Recmd 101-B Cast Material
02-May-25
10-May-25
—
100%
EK000MD46P
Confirm Analytical Design for ERW - MD411
02-May-25
11-May-25
—
100%
PK000MB41I
Eval Bids & Issue Recmd MB410
02-May-25
20-May-25
—
100%
EK000MJ34D
Technical Evaluation - MJ304
02-May-25
03-May-25
—
100%
PK000I121C
Receive Quotes - Vortex Meters
02-May-25
20-May-25
—
100%
PK000I122C
Receive Quotes - Coriolis Meters
02-May-25
20-May-25
—
100%
PK000I124C
Receive Quotes - Rotameters
02-May-25
20-May-25
—
100%
PK000I127C
Magnetic Flow Meters - Receive Quotes
02-May-25
20-May-25
—
100%
PK000I617C
Receive Quotes - Magnetic Lvl Gauges
02-May-25
22-May-25
—
100%
PK000ML51H
Receive Quotes ML512
02-May-25
17-Jun-25
—
100%
EK000MC32P
Develop & Issue Setting Plans for ERW - MC311
02-May-25
20-Jun-25
—
100%
PK000MJ35J
Final Negotiate/Interim Award - MJ305
02-May-25
23-Aug-25
—
100%
EK000MU41D
Technical Evaluation - MU410
03-May-25
28-Jun-25
—
100%
PK000MU61I
Eval Bids & Issue Recmd MU611
03-May-25
25-Jul-25
—
100%
PK000MD33I
Eval Bids & Issue Recmd MD303
04-May-25
10-May-25
—
100%
EK000MD31E
Prepare & Issue Purchase ERW - MD301
04-May-25
11-May-25
—
100%
EK000MD34E
Prepare & Issue Purchase ERW - MD304
04-May-25
11-May-25
—
100%
EK000MBP4E
Prepare & Issue Purchase ERW 101-B Cast Material
04-May-25
17-May-25
—
100%
EK000PC020
Load PCMS & Issue First Cost Report
04-May-25
18-May-25
—
100%
EK000MB41E
Prepare & Issue Purchase ERW - MB410
04-May-25
20-May-25
—
100%
EK010SY040
010 CW Twr & FW Tanks P&IDs - ICA Issue development
04-May-25
20-Jun-25
—
100%
EK030SY040
030 Utility Plant P&IDs - ICA Issue development
04-May-25
20-Jun-25
—
100%
EK050SY040
050 Dock/Storage P&IDs - ICA Issue development
04-May-25
20-Jun-25
—
100%
EK000MD32E
Prepare & Issue Purchase ERW - MD302
06-May-25
10-May-25
—
100%
PK000MD32I
Eval Bids & Issue Recmd MD302
06-May-25
10-May-25
—
100%
PK000MJ34I
Eval Bids & Issue Recmd MJ304
06-May-25
10-May-25
—
100%
EK000MD43E
Prepare & Issue Purchase ERW - MD403
06-May-25
11-May-25
—
100%
PK000PIA4A
Product Line Piping - Issue REQ/RFQ to Vend
06-May-25
15-May-25
—
100%
EK05BPI030
05B Conceptual Layout - Supersketches
07-May-25
27-Dec-26
—
59%
PK000MD31I
Eval Bids & Issue Recmd MD301
07-May-25
11-May-25
—
100%
EK000MU33B
Develop/Issue Load Sht & Design Data ERW - MU330
07-May-25
20-May-25
—
100%
EK000MC31D
Technical Evaluation - MC310
07-May-25
24-May-25
—
100%
EK000MC32D
Technical Evaluation - MC311
07-May-25
24-May-25
—
100%
EK020MC31D
MC312 - (120,121-C) - Technical Evaluation
07-May-25
24-May-25
—
100%
PK000MB33H
MB333 - Receive Quotes 101-B
07-May-25
08-Jun-25
—
100%
EK000MU61D
Technical Evaluation - MU611
07-May-25
20-Jun-25
—
100%
PK000PIA1C
Bulk Piping A/G & U/G - Tech Evaluation
07-May-25
21-Jun-25
—
100%
PK000PIA1D
Bulk Piping A/G & U/G - Eval Bids/Issue Recmd
07-May-25
01-Jul-25
—
100%
PK000PTA0A
Engineered Pipe Supports - Inquiry REQ/RFQ
07-May-25
04-Jun-25
—
100%
EK000MU21B
Develop/Issue Load Sht & Design Data ERW - MU221
08-May-25
10-May-25
—
100%
EK000MU22B
Develop/Issue Load Sht & Design Data ERW - MU222
08-May-25
20-May-25
—
100%
EK000MU29B
Develop/Issue Load Sht & Design Data ERW - MU292
08-May-25
20-May-25
—
100%
EK000YA005
Process Release
08-May-25
08-May-25
—
100%
EK000YA811
(EP-12) Issue Process Release
08-May-25
08-May-25
—
100%
EK000MD51E
Prepare & Issue Purchase ERW - MD501
09-May-25
11-May-25
—
100%
EK000MJ37F
Develop & Issue Inquiry for ERW - MJ340
09-May-25
05-Jun-25
—
100%
PK000MJ32M
Requote/Bid Condition/Final Tab - MJ302
09-May-25
16-Jul-25
—
100%
PK000MJ31M
Requote/Bid Condition/Final Tab - MJ301
09-May-25
25-Jul-25
—
100%
EK000MJ35F
Update/Issue Formal Inquiry for ERW - MJ305
10-May-25
24-May-25
—
100%
PK000MU30I
Eval Bids & Issue Recmd MU300
10-May-25
29-Oct-25
—
100%
PK000MD47G
Issue MD406 RFQ
13-May-25
13-May-25
—
100%
EK000MBP3E
Prepare & Issue Purchase ERW 101-B Pressure Part
13-May-25
16-May-25
—
100%
PK000MBP3I
Eval Bids & Issue Recmd 101-B Pressure Parts
13-May-25
18-May-25
—
100%
EK000I220A
Issue Preliminary ERW Pkg - MOV Valves
13-May-25
31-May-25
—
100%
EK000MD45F
Update/Issue Formal Inquiry for ERW - MD405
13-May-25
31-May-25
—
100%
PK000MB63I
Eval Bids & Issue Recmd MB630
13-May-25
11-Jul-25
—
100%
EK000I354A
ITCC - Engr ERW Issued
13-May-25
23-Jul-25
—
100%
EK000MU30D
Technical Evaluation - MU300
13-May-25
27-Sep-25
—
100%
EK000MD46F
Update/Issue Formal Inquiry for ERW - MD411
14-May-25
31-May-25
—
100%
EK000MB62F
Prepare & Issue Purchase ERW - MB621
14-May-25
05-Jun-25
—
100%
PK000MD33M
Final Tab/Recmd - MD303
14-May-25
23-Jul-25
—
100%
PK000ML33G
Issue ML330 RFQ
14-May-25
15-May-25
—
100%
PK000MD47H
Receive Quotes MD406
14-May-25
06-Jun-25
—
100%
PK000I115E
Eval Bids / Issue Recmd - Annubars
15-May-25
31-Jul-25
—
100%
PK000PIA4B
Product Line Piping - Receive Bids
16-May-25
06-Jun-25
—
100%
PK000ML33H
Receive Quotes ML330
16-May-25
10-Jul-25
—
100%
PK000I116E
Eval Bids / Issue Recmd - Wedge Flow Meters
16-May-25
31-Jul-25
—
100%
EK000MB045
Catalyst Vac data sheets
20-May-25
28-May-25
—
100%
EK000CV065
Review Perimeter Wall Design - IFC (by OCI)
20-May-25
14-Jun-25
—
100%
PK000MU33I
Eval Bids & Issue Recmd MU330
20-May-25
09-Sep-25
—
100%
EK000MJ75F
Develop & Issue Inquiry for ERW - MJ750
21-May-25
28-May-25
—
100%
PK000I110E
Eval Bids / Issue Recmd - Orific Plates
21-May-25
31-Jul-25
—
100%
PK000I121E
Eval Bids / Issue Recmd - Vortex Meters
21-May-25
31-Jul-25
—
100%
PK000I122E
Eval Bids / Issue Recmd - Coriolis Meters
21-May-25
31-Jul-25
—
100%
PK000I124E
Eval Bids / Issue Recmd - Rotameters
21-May-25
31-Jul-25
—
100%
PK000I616E
Eval Bids / Issue Recmd - Steam Drum Lvl Gauges
21-May-25
31-Jul-25
—
100%
PK000I621E
Eval Bids / Issue Recmd - Temperature Elements
21-May-25
31-Jul-25
—
100%
PK000I611E
Eval Bids / Issue Recmd - Pressure Gauges
22-May-25
31-Jul-25
—
100%
PK000I617E
Eval Bids / Issue Recmd - Magnetic Lvl Gauges
22-May-25
31-Jul-25
—
100%
EK000YA806
(EP-07) Issue Project Plan
24-May-25
24-May-25
—
100%
PK000I131E
Eval Bids / Issue Recmd - Transmitters
24-May-25
31-May-25
—
100%
PK000I210E
000 Control Valves - Eval Bids / Issue Recmd
24-May-25
31-May-25
—
100%
PK000MJ75G
Issue MJ750 RFQ
27-May-25
28-May-25
—
100%
EK000MBG10
General & Administrative
28-May-25
27-Dec-26
—
57%
EK000I110D
Technical Evaluation - Orific Plates
28-May-25
10-Jun-25
—
100%
EK000I115D
Technical Evaluation - Annubars
28-May-25
10-Jun-25
—
100%
EK000I116D
Technical Evaluation - Wedge Flow Meters
28-May-25
10-Jun-25
—
100%
EK000I121D
Technical Evaluation - Vortex Meters
28-May-25
10-Jun-25
—
100%
EK000I122D
Technical Evaluation - Coriolis Meters
28-May-25
10-Jun-25
—
100%
EK000I124D
Technical Evaluation - Rotameters
28-May-25
10-Jun-25
—
100%
EK000I611D
Technical Evaluation - Pressure Gauges
28-May-25
10-Jun-25
—
100%
EK000I612D
Technical Evaluation - Differential Pressure Gauges
28-May-25
10-Jun-25
—
100%
EK000I616D
Technical Evaluation - Steam Drum Lvl Gauges
28-May-25
10-Jun-25
—
100%
EK000I617D
Technical Evaluation - Magnetic Lvl Gauges
28-May-25
10-Jun-25
—
100%
EK000MJ33F
Develop & Issue Inquiry for ERW - MJ303
28-May-25
18-Jun-25
—
100%
EK000MJ36F
Update/Issue Formal Inquiry for ERW - MJ306
28-May-25
19-Jun-25
—
100%
EK000I127D
Magnetic Flow Meters - Technical Evaluation
28-May-25
26-Jun-25
—
100%
EK000MB33D
MB333 - Technical Evaluation 101-B
28-May-25
01-Jul-25
—
100%
PK000I612E
Eval Bids / Issue Recmd - Differential Pressure Gauges
28-May-25
31-Jul-25
—
100%
EK000YA801
(EP-02) Issue 30 day Look Ahead Schedule
28-May-25
28-May-25
—
100%
PK000MJ75H
Receive Quotes MJ750
28-May-25
29-May-25
—
100%
EK000MJ75D
Technical Evaluation - MJ750
29-May-25
30-May-25
—
100%
PK000MJ75I
Eval Bids & Issue Recmd MJ750
29-May-25
30-May-25
—
100%
PK000MJ37G
Issue MJ340 RFQ
31-May-25
11-Jun-25
—
100%
EK000ML43F
Develop & Issue Inquiry for ERW - ML430
31-May-25
06-Jun-25
—
100%
PK000MJ37Q
Prepare & Issue Prelim. RFQ - MJ307 to Proc.
31-May-25
12-Jun-25
—
100%
EK000MB69F
Prepare & IssuePurchase ERW - MB691
03-Jun-25
17-Jun-25
—
100%
PK000I230B
Issue RFQ - On/Off Valves
04-Jun-25
06-Jun-25
—
100%
PK000PTA0B
Engineered Pipe Supports - Receive Bids
04-Jun-25
25-Jun-25
—
100%
EK000MU33D
Technical Evaluation - MU330
04-Jun-25
01-Jul-25
—
100%
EK000QM025
Training - Management System
05-Jun-25
05-Jun-25
—
100%
PK000I220B
Issue RFQ - MOV's
05-Jun-25
06-Jun-25
—
100%
EK000I230A
Issue Preliminary ERW Pkg - On/Off Valves
05-Jun-25
15-Jun-25
—
100%
EK000PS040
Incorporate Comments / Issue Baseline Schedule
05-Jun-25
15-Jun-25
—
100%
EK000MU22F
Develop & Issue Inquiry for ERW - MU222
05-Jun-25
26-Jun-25
—
100%
EK000MB65F
Develop & Issue Purchase ERW - MB622
06-Jun-25
17-Jun-25
—
100%
PK000I221B
000 Everest Control Valves - Issue RFQ
06-Jun-25
06-Jun-25
—
100%
PK000I221C
000 Everest Control Valves - Receive Quotes
06-Jun-25
25-Jun-25
—
100%
PK000I230C
Receive Quotes -On/Off Valves
07-Jun-25
02-Jul-25
—
100%
PK000I220C
Receive Quotes - MOV's
07-Jun-25
02-Jul-25
—
100%
PK000PIA4C
Product Line Piping - Tech Evaluation
07-Jun-25
04-Jul-25
—
100%
PK000MB33I
MB333 - Eval Bids & Issue Recmd 101-B
07-Jun-25
25-Jul-25
—
100%
PK000MD47I
Eval Bids & Issue Recmd MD406
07-Jun-25
19-Sep-25
—
100%
EK000I112D
Technical Evaluation - Venturis
10-Jun-25
14-Jun-25
—
100%
PK000MJ73G
Issue MJ730 RFQ
10-Jun-25
17-Jun-25
—
100%
EK000PS030
Schedule Risk Analysis
10-Jun-25
20-Jun-25
—
100%
EK000MB66F
Prepare & IssuePurchase ERW - MB660
10-Jun-25
21-Jun-25
—
100%
EK000MU34B
Develop/Issue Load Sht & Design Data ERW - Chlorination Unit
11-Jun-25
15-Jun-25
—
100%
PK000MJ37F
Issue MJ307 RFQ
12-Jun-25
21-Jun-25
—
100%
PK000MJ37H
Receive Quotes MJ340
12-Jun-25
18-Jul-25
—
100%
EK000MB68F
Prepare & Issue Purchase ERW - MB692
13-Jun-25
26-Jun-25
—
100%
PK000MD21G
Issue MD201 RFQ
17-Jun-25
20-Jun-25
—
100%
EK000MB21F
Prepare & Issue Purchase ERW - MB212
17-Jun-25
25-Jun-25
—
100%
EK000MB42F
Prepare & Issue Purchase ERW - MB420
17-Jun-25
26-Jun-25
—
100%
PK000ML43G
Issue ML430 RFQ
18-Jun-25
22-Jun-25
—
100%
PK000MB69G
Issue MB691 RFQ
18-Jun-25
25-Jun-25
—
100%
PK000MJ73H
Receive Quotes MJ730
18-Jun-25
06-Aug-25
—
100%
PK000MJ33G
Issue MJ303 RFQ
19-Jun-25
21-Jun-25
—
100%
EK000FP055
FP Overall Firewater P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
—
100%
EK010FP020
FP Firewater Pump P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
—
100%
EK010FP060
FP Deluge P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
—
100%
EK000MB34F
Prepare & Issue Purchase ERW - MB340
20-Jun-25
21-Jun-25
—
100%
PK000MB65G
Issue MB622 RFQ
20-Jun-25
25-Jun-25
—
100%
EK010SY050
010 Twr & FW Tanks P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
—
100%
EK030SY050
030 Utility Plant P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
—
100%
EK050SY050
050 Dock/Storage P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
—
100%
PK000PSA8D
000 Relief Valves - Eval Bids / Issue Recmd
20-Jun-25
26-Sep-25
—
100%
PK000ML43H
Receive Quotes ML430
21-Jun-25
10-Jul-25
—
100%
PK000MJ37D
Receive Quotes MJ307
21-Jun-25
19-Jul-25
—
100%
PK000MU41I
Eval Bids & Issue Recmd MU410
21-Jun-25
24-Jul-25
—
100%
EK030SY135
030 Utility Plant CV & FE Process Data
21-Jun-25
07-Sep-25
—
100%
PK000MC21M
Requote/Bid Condition/Final Tab - MC210
21-Jun-25
27-Sep-25
—
100%
PK000MC23M
Requote/Bid Condition/Final Tab - MC230
21-Jun-25
27-Sep-25
—
100%
PK000MJ33H
Receive Quotes MJ303
22-Jun-25
29-Aug-25
—
100%
PK000MB68G
Issue MB692 RFQ
24-Jun-25
26-Jun-25
—
100%
PK000PIA1E
Bulk Piping A/G & U/G - Reconfirm Pricing
24-Jun-25
01-Jul-25
—
100%
PK000MD21H
Receive Quotes for MD201
24-Jun-25
11-Jul-25
—
100%
EK050SY060
050 Dock/Storage P&ID's - IPL Issue Development
25-Jun-25
11-Oct-25
—
100%
EK010SY060
010 CW Twr & FW Tanks P&ID's - IPL Issue Development
25-Jun-25
31-Oct-25
—
100%
EK030SY060
030 Utility Plant P&ID's - IPL Issue Development
25-Jun-25
19-Nov-25
—
100%
PK000MB66G
Issue MB660 RFQ
25-Jun-25
25-Jun-25
—
100%
EK000I221D
000 Everest Control Valves - Technical Evaluation
25-Jun-25
10-Jul-25
—
100%
PK000MB66H
Receive Quotes for MB660
25-Jun-25
27-Jul-25
—
100%
PK000PTA0C
Engineered Pipe Supports - Eval Bids/Issue Recmd
25-Jun-25
08-Aug-25
—
100%
EK000YA809
(EP-10) Locate Utility Tie-Ins
26-Jun-25
26-Jun-25
—
100%
EK000MU21F
Develop & Issue Inquiry for ERW - MU221
26-Jun-25
03-Jul-25
—
100%
PK000MB65H
Receive Quotes for MB622
26-Jun-25
18-Jul-25
—
100%
PK000MB21G
Issue MB212 RFQ
26-Jun-25
22-Jul-25
—
100%
PK000MB69H
Receive Quotes for MB691
26-Jun-25
22-Jul-25
—
100%
PK000MB68H
Receive Quotes for MB692
27-Jun-25
26-Jul-25
—
100%
PK000I127E
Magnetic Flow Meters - Eval Bids / Issue Recmd
27-Jun-25
31-Jul-25
—
100%
EK000MD33E
Prepare & Issue Purchase ERW - MD303
01-Jul-25
04-Jul-25
—
100%
EK000MD41E
Prepare & Issue Purchase ERW - MD401
01-Jul-25
04-Jul-25
—
100%
PK000MB42G
Issue MB420 RFQ
02-Jul-25
05-Jul-25
—
100%
EK000MB64F
Prepare & Issue Purchase ERW - MB640
02-Jul-25
11-Jul-25
—
100%
PK000MU22G
Issue MU222 RFQ
02-Jul-25
02-Jul-25
—
100%
PK000I220E
Eval Bids / Issue Recmd - MOV's
02-Jul-25
27-Aug-25
—
100%
PK000I230E
Eval Bids / Issue Recmd - On/Off Valves
02-Jul-25
28-Aug-25
—
100%
PK000MB34G
Issue MB340 RFQ
03-Jul-25
03-Jul-25
—
100%
EK03FPI000
03F Preliminary Drawings for Supersketch U-2002
03-Jul-25
04-Jul-25
—
100%
PK000MU21G
Issue MU221 RFQ
03-Jul-25
05-Jul-25
—
100%
PK000MU22H
Receive Quotes MU222
03-Jul-25
22-Jul-25
—
100%
PK000MB34H
Receive Quotes for MB340
03-Jul-25
24-Jul-25
—
100%
PK000PIA4D
Product Line Piping - Eval Bids/Issue Recmd
05-Jul-25
18-Jul-25
—
100%
PK000MB42H
Receive Quotes for MB420
05-Jul-25
20-Sep-25
—
100%
PK000MJ34X
Eval Bids & Issue Recmd MJ304
06-Jul-25
09-Sep-25
—
100%
PK000MU21H
Receive Quotes MU221
08-Jul-25
25-Jul-25
—
100%
PK000MB64G
Issue MB640 RFQ
09-Jul-25
11-Jul-25
—
100%
PK000I221E
000 Everest Control Valves - Eval Bids / Issue Recmd
10-Jul-25
31-Jul-25
—
100%
EK000ML33D
Technical Evaluation - ML330
10-Jul-25
23-Aug-25
—
100%
EK000ML43D
Technical Evaluation - ML430
10-Jul-25
06-Sep-25
—
100%
PK000I618E
Eval Bids / Issue Recmd - Temperature Gauges
11-Jul-25
31-Jul-25
—
100%
PK000MB64H
Receive Quotes for MB640
12-Jul-25
09-Aug-25
—
100%
EK03API000
03A Preliminary Drawings for Supersketch L-2003
13-Jul-25
13-Jul-25
—
100%
PK020MC31E
MC312 - (120,121-C) - Eval Bids & Issue Recmd
13-Jul-25
19-Aug-25
—
100%
PK000MC32I
Eval Bids & Issue Recmd MC311
13-Jul-25
14-Oct-25
—
100%
PK000MC31I
Eval Bids & Issue Recmd MC310
13-Jul-25
20-Dec-25
—
100%
EK03API030
03A Conceptual Layout - Supersketches
15-Jul-25
22-Jul-25
—
100%
PK000MD21I
Eval Bids & Issue Recmd MD201
15-Jul-25
17-Aug-25
—
100%
PK000I623E
Eval Bids / Issue Recmd - Multi-Point Thermocouples
16-Jul-25
31-Jul-25
—
100%
EK000I220D
Technical Evaluation - MOV's
16-Jul-25
23-Jul-25
—
100%
EK000MD21D
Technical Evaluation - MD201
16-Jul-25
10-Aug-25
—
100%
EK000I230D
Technical Evaluation - On/Off Valves
17-Jul-25
24-Jul-25
—
100%
PK000I444B
Issue RFQ - Analyzer Shelter
19-Jul-25
25-Jul-25
—
100%
EK000MB65D
Technical Evaluation - MB622
19-Jul-25
02-Aug-25
—
100%
PK000MJ37E
Technical Evaluation - MJ307
19-Jul-25
06-Dec-25
—
100%
EK01UPICWA
01U Plant Layout Model - Cooling Water
20-Jul-25
23-Aug-25
—
100%
EK000I618D
Technical Evaluation - Temperature Gauges
22-Jul-25
26-Jul-25
—
100%
EK000I621D
Technical Evaluation - Temperature Elements
22-Jul-25
26-Jul-25
—
100%
EK000I623D
Technical Evaluation - Multi-Point Thermocouples
22-Jul-25
26-Jul-25
—
100%
PK000MB33J
MB333 - Final Negotiate/Interim Award 101-B
22-Jul-25
26-Jul-25
—
100%
EK000I352A
SIS - Engr ERW Issued
22-Jul-25
02-Aug-25
—
100%
EK000MB69D
Technical Evaluation - MB691
22-Jul-25
07-Aug-25
—
100%
PK000MB21H
Receive Quotes for MB212
22-Jul-25
28-Aug-25
—
100%
EK000MU22D
Technical Evaluation - MU222
22-Jul-25
06-Sep-25
—
100%
PK000MU41J
Final Negotiate/Interim Award - MU410
24-Jul-25
24-Jul-25
—
100%
PK000I354B
ITCC - Inquiry REQ/RFQ
24-Jul-25
01-Aug-25
—
100%
PK000MB34I
Eval Bids & Issue Recmd MB340
24-Jul-25
14-Aug-25
—
100%
EK000MJ37D
Technical Evaluation - MJ340
24-Jul-25
28-Aug-25
—
100%
PK000MU41P
Issue Formal P.O. for MU410
24-Jul-25
05-Sep-25
—
100%
EK000MJ39D
Technical Evaluation - MJ391
25-Jul-25
21-Dec-25
—
100%
EK000MJ31X
Technical Evaluation - MJ301
25-Jul-25
10-Aug-25
—
100%
PK000MJ32X
Technical Evaluation - MJ302
25-Jul-25
10-Aug-25
—
100%
PK000I444C
Receive Quotes - Analyzer Shelter
25-Jul-25
13-Sep-25
—
100%
PK000MU61J
Final Negotiate/Interim Award - MU611
26-Jul-25
29-Jul-25
—
100%
PK000MB33K
MB333 - Fab/PO Promise 101-B Riser Transition 101-B
29-Jul-25
27-Dec-26
—
52%
PK000I112E
Eval Bids / Issue Recmd - Venturis
29-Jul-25
31-Jul-25
—
100%
EK000MU11L
05B MU311 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
—
100%
EK000MU25L
02G MU225 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
—
100%
EK000MU32L
01D MU322 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
—
100%
EK000MB68D
Technical Evaluation - MB692
29-Jul-25
30-Aug-25
—
100%
PK000MU61P
Issue Formal P.O. for MU611
29-Jul-25
03-Sep-25
—
100%
EK01BPI000
01B Preliminary Drawings for Supersketch J-2001,2003,2004,2007
30-Jul-25
30-Jul-25
—
100%
EK01DPI000
01D Preliminary Drawings for Supersketch J-2202
30-Jul-25
30-Jul-25
—
100%
PK000MD33J
Final Negotiate/Interim Award - MD303
30-Jul-25
09-Aug-25
—
100%
EK000MU31L
Define Chemical Treatment Requirements - MU310
30-Jul-25
10-Aug-25
—
100%
PK000MU35J
Final Negotiate/Interim Award - MU350
30-Jul-25
10-Aug-25
—
100%
EK000MB66D
Technical Evaluation - MB660
30-Jul-25
13-Aug-25
—
100%
EK000MB34D
Technical Evaluation - MB340
30-Jul-25
13-Aug-25
—
100%
EK010SY135
010 CW Twr & FW Tanks CV & FE Process Data
30-Jul-25
17-Aug-25
—
100%
EK000ML51D
Technical Evaluation - ML512
30-Jul-25
19-Aug-25
—
100%
PK000MBP3J
Final Negotiate/Interim Award - Pressure Parts
30-Jul-25
30-Aug-25
—
100%
EK000MU21D
Technical Evaluation - MU221
30-Jul-25
14-Sep-25
—
100%
PK000I110G
Final Negotiation / Interim Award - Orific Plates
31-Jul-25
01-Aug-25
—
100%
PK000I112G
Final Negotiation / Interim Award - Venturis
31-Jul-25
01-Aug-25
—
100%
PK000I115G
Final Negotiation / Interim Award - Annubars
31-Jul-25
01-Aug-25
—
100%
PK000I121G
Final Negotiation / Interim Award - Vortex Meters
31-Jul-25
01-Aug-25
—
100%
PK000I122G
Final Negotiation / Interim Award - Coriolis Meters
31-Jul-25
01-Aug-25
—
100%
PK000I124G
Final Negotiation / Interim Award - Rotameters
31-Jul-25
01-Aug-25
—
100%
PK000I127G
Final Negotiation / Interim Award - Magnetic Flow Meters
31-Jul-25
01-Aug-25
—
100%
PK000I612G
Final Negotiation / Interim Award - Differential Pressure Gauges
31-Jul-25
01-Aug-25
—
100%
PK000I616G
Final Negotiation / Interim Award - Steam Drum Lvl Gauges
31-Jul-25
01-Aug-25
—
100%
PK000I116G
Final Negotiation / Interim Award - Wedge Flow Meters
31-Jul-25
06-Aug-25
—
100%
PK000I611G
Final Negotiation / Interim Award - Pressure Gauges
31-Jul-25
06-Aug-25
—
100%
PK000I617G
Final Negotiation / Interim Award - Magnetic Lvl Gauges
31-Jul-25
06-Aug-25
—
100%
PK000I621G
Final Negotiation / Interim Award - Temperature Elements
31-Jul-25
06-Aug-25
—
100%
PK000I623G
Final Negotiation / Interim Award - Multi-Point Thermocouples
31-Jul-25
06-Aug-25
—
100%
PK000I221G
Final Negotiation / Interim Award - Everest Control Valves
31-Jul-25
14-Aug-25
—
100%
EK03DPI030
03D Conceptual Layout - Supersketches
01-Aug-25
07-Aug-25
—
100%
EK01DPI030
01D Conceptual Layout - Supersketches
01-Aug-25
15-Aug-25
—
100%
PK000I131G
Final Negotiation / Interim Award - Transmitters
01-Aug-25
06-Aug-25
—
100%
PK000MBP4J
Final Negotiate/Interim Award - Cast Material
01-Aug-25
09-Aug-25
—
100%
EK000MU35E
Prepare & Issue Purchase ERW - MU350
01-Aug-25
13-Aug-25
—
100%
EK050SY135
050 Dock/Storage CV & FE Process Data
01-Aug-25
15-Aug-25
—
100%
PK000I354C
ITCC - Receive Bids
01-Aug-25
28-Aug-25
—
100%
EK020FP490
FP OSBL Fire Protection Eqmt. Location Plans - ICA
01-Aug-25
02-Sep-25
—
100%
PK000I115K
Issue Formal Purchase Agreement - Annubars
01-Aug-25
31-Oct-25
—
100%
PK000I121K
Issue Formal Purchase Agreement - Vortex Meters
01-Aug-25
31-Oct-25
—
100%
PK000I122K
Issue Formal Purchase Agreement - Coriolis Meters
01-Aug-25
31-Oct-25
—
100%
PK000I124K
Issue Formal Purchase Agreement - Rotameters
01-Aug-25
31-Oct-25
—
100%
PK000I127K
Magnetic Flow Meters - Issue Formal Purchase Agreement
01-Aug-25
31-Oct-25
—
100%
PK000I110K
Issue Formal Purchase Agreement. - Orific Plates
01-Aug-25
14-Nov-25
—
100%
PK000I112K
Issue Formal Purchase Agreement - Venturis
01-Aug-25
14-Nov-25
—
100%
PK000I616K
Issue Formal Purchase Agreement. - Steam Drum Lvl Gauges
01-Aug-25
30-Dec-25
—
100%
PK000I612K
Issue Formal Purchase Agreement - Differential Pressure Gauges
01-Aug-25
06-Feb-26
—
100%
PK000I352B
SIS - Inquiry REQ/RFQ
02-Aug-25
07-Aug-25
—
100%
EK000YA810
(EP-11) Issue Level 3 CPM Schedule
03-Aug-25
03-Aug-25
—
100%
PK000MB61J
Final Negotiate/Interim Award - MB610
05-Aug-25
09-Aug-25
—
100%
PK000MB62J
Final Negotiate/Interim Award - MB621
05-Aug-25
09-Aug-25
—
100%
PK000MB63J
Final Negotiate/Interim Award - MB630
05-Aug-25
09-Aug-25
—
100%
PK000MB81J
Final Negotiate/Interim Award - MB810
05-Aug-25
09-Aug-25
—
100%
EK000QM005
Training - Object Engineering
06-Aug-25
13-Aug-25
—
100%
EK000I444A
Develop & Issue Inquiry ERW - Analyzer Shelter
06-Aug-25
17-Aug-25
—
100%
EK000MJ73D
Technical Evaluation - MJ730
06-Aug-25
16-Sep-25
—
100%
PK000MJ73I
Eval Bids & Issue Recmd MJ730
06-Aug-25
19-Oct-25
—
100%
PK000MB69I
Eval Bids & Issue Recmd MB691
06-Aug-25
29-Oct-25
—
100%
PK000I131K
Issue Formal Purchase Agreement - Transmitters
06-Aug-25
02-Dec-25
—
100%
PK000I621K
Issue Formal Purchase Agreement - Temperature Elements
06-Aug-25
30-Dec-25
—
100%
PK000I623K
Issue Formal Purchase Agreement - Multi-Point Thermocouples
06-Aug-25
30-Dec-25
—
100%
PK000I617K
Issue Formal Purchase Agreement - Magnetic Lvl Gauges
06-Aug-25
20-Jan-26
—
100%
PK000I611K
Issue Formal Purchase Agreement - Pressure Gauges
06-Aug-25
06-Feb-26
—
100%
PK000I116K
Issue Formal Purchase Agreement - Wedge Flow Meters
06-Aug-25
07-Feb-26
—
100%
PK000I352C
SIS - Receive Bids
07-Aug-25
21-Aug-25
—
100%
PK000PTA0D
Engineered Pipe Supports - Interim Award
08-Aug-25
14-Aug-25
—
100%
EK000CV165
Issue ISBL Rough Grade Design Pkg.
09-Aug-25
04-Oct-25
—
100%
PK000MBP1K
MB221 - Fab/PO Promise 101-B Radiant Steel Panels
09-Aug-25
27-Dec-26
—
51%
PK000MBP1Q
MB221 - Fab/PO Promise 101-B Radiant Coil/Harps
09-Aug-25
27-Dec-26
—
51%
PK000MBP1R
MB221 - Fab/PO Promise 101-B Convection Modules
09-Aug-25
27-Dec-26
—
51%
PK000MBP1S
MB221 - Fabr/PO Promise 101-B Radiant Ducting
09-Aug-25
27-Dec-26
—
51%
PK000MD31K
MD301 - Fabricate/PO Promise 103-D
09-Aug-25
17-Feb-27
55.0d
46%
PK000MD33K
MD303 - Fabricate/PO Promise 105-D
09-Aug-25
20-Mar-27
50.0d
44%
PK000MJ21K
MJ202 - Fabricate/PO Promise 102/3/5-J
09-Aug-25
27-Dec-26
—
51%
PK000I210G
Final Negotiation / Interim Award - Control Valves
09-Aug-25
09-Aug-25
—
100%
PK000MB41J
Final Negotiate/Interim Award - MB410
09-Aug-25
09-Aug-25
—
100%
PK000MD31J
Final Negotiate/Interim Award - MD301
09-Aug-25
09-Aug-25
—
100%
PK000MJ21J
Final Negotiate/Interim Award - MJ202
09-Aug-25
09-Aug-25
—
100%
PK000MJ75J
Final Negotiate/Interim Award - MJ750
09-Aug-25
12-Aug-25
—
100%
PK000PR20B
PR201 KAAP Catalyst - Issue RFQ
09-Aug-25
12-Aug-25
—
100%
PK000MD34J
Final Negotiate/Interim Award - MD304
09-Aug-25
16-Aug-25
—
100%
PK000MD42J
Final Negotiate/Interim Award - MD402
09-Aug-25
16-Aug-25
—
100%
PK000MD44J
Final Negotiate/Interim Award - MD404
09-Aug-25
16-Aug-25
—
100%
PK000MD45J
Final Negotiate/Interim Award - MD405
09-Aug-25
16-Aug-25
—
100%
PK000MD46J
Final Negotiate/Interim Award - MD411
09-Aug-25
16-Aug-25
—
100%
PK000MD22J
Final Negotiate/Interim Award - MD202
09-Aug-25
17-Aug-25
—
100%
PK000MD32J
Final Negotiate/Interim Award - MD302
09-Aug-25
17-Aug-25
—
100%
PK000MD33P
Issue Formal P.O. for MD303
09-Aug-25
19-Aug-25
—
100%
PK000MD41J
Final Negotiate/Interim Award - MD401
09-Aug-25
23-Aug-25
—
100%
PK000MD43J
Final Negotiate/Interim Award - MD403
09-Aug-25
23-Aug-25
—
100%
PK000MD51J
Final Negotiate/Interim Award - MD501
09-Aug-25
27-Aug-25
—
100%
PK000MJ21N
Recv. Planning V. Data MJ202
09-Aug-25
30-Aug-25
—
100%
PK000MJ22J
Final Negotiate/Interim Award - MJ201
09-Aug-25
30-Aug-25
—
100%
PK000MJ75N
Recv. Planning V. Data MJ750
09-Aug-25
30-Aug-25
—
100%
PK000ML31J
Final Negotiate/Interim Award - ML313
09-Aug-25
31-Aug-25
—
100%
PK000MD21J
Final Negotiate/Interim Award - MD201
09-Aug-25
02-Sep-25
—
100%
PK000MB63P
Issue Formal P.O. for MB630
09-Aug-25
09-Sep-25
—
100%
PK000MD31N
Recv. Planning V. Data MD301
09-Aug-25
09-Sep-25
—
100%
PK000MB41P
Issue Formal P.O. for MB410
09-Aug-25
10-Sep-25
—
100%
PK000ML31N
Recv. Planning V. Data ML313
09-Aug-25
12-Sep-25
—
100%
PK000PIA4E
Product Line Piping - Final Negotiation/Interim Award
09-Aug-25
13-Sep-25
—
100%
PK000MD41N
Recv. Planning V. Data MD401
09-Aug-25
17-Sep-25
—
100%
PK000MJ21P
Issue Formal P.O. for MJ202
09-Aug-25
19-Sep-25
—
100%
PK000MBP1P
Issue Formal P.O. for 101-B Shop Fab
09-Aug-25
20-Sep-25
—
100%
PK000MBP4P
Issue Formal P.O. for 101-B Cast Material
09-Aug-25
20-Sep-25
—
100%
PK000MB81P
Issue Formal P.O. for MB810
09-Aug-25
21-Sep-25
—
100%
PK000MU35P
Issue Formal P.O. for MU350
09-Aug-25
23-Sep-25
—
100%
PK000MD33N
Recv. Planning V. Data MD303
09-Aug-25
25-Sep-25
—
100%
PK000MB61P
Issue Formal P.O. for MB610
09-Aug-25
30-Sep-25
—
100%
PK000IC35G
DCS - Interim Award
09-Aug-25
12-Oct-25
—
100%
PK000MD43N
Recv. Planning V. Data MD403
09-Aug-25
14-Oct-25
—
100%
EK000MB64D
Technical Evaluation - MB640
09-Aug-25
17-Oct-25
—
100%
PK000MJ32J
Final Negotiate/Interim Award - MJ302
09-Aug-25
20-Nov-25
—
100%
PK000MJ31J
Final Negotiate/Interim Award - MJ301
09-Aug-25
21-Nov-25
—
100%
PK000MB62P
Issue Formal P.O. for MB621
09-Aug-25
09-Dec-25
—
100%
PK000I210K
000 Control Valves - Issue Formal Purchase Agreement
09-Aug-25
03-Feb-26
—
100%
PK000PIA1G
Bulk Piping A/G & U/G - Fab/Exworks (CS, SS, U/G)
09-Aug-25
31-Mar-26
—
100%
PK000MU35K
MU350 - Fabricate/PO Promise 101-U DEAERATOR
09-Aug-25
23-Apr-26
—
100%
EK000EB015
Notice to Proceed (Eng. & Procurement Only)
10-Aug-25
10-Aug-25
—
100%
EK030SY150
030 Relief Valve Calculations - Utility Plant
10-Aug-25
26-Sep-25
—
100%
PK000MB62K
MB621 - Fabricate/PO Promise 101-B ID & FD Fans
12-Aug-25
27-Dec-26
—
51%
PK000MB81K
MB810 - Fabricate/PO Promise 102-B
12-Aug-25
27-Dec-26
—
51%
EK000I221A
000 Everest Control Valves - Issue Inquiry Req
12-Aug-25
16-Aug-25
—
100%
PK000MJ75P
Issue Formal P.O. for MJ750
12-Aug-25
23-Aug-25
—
100%
EK000MJ21E
Prepare & Issue Purchase ERW - MJ202
12-Aug-25
30-Aug-25
—
100%
PK000PR20C
PR201 KAAP Catalyst - Receive Quotes
12-Aug-25
17-Sep-25
—
100%
PK000MU35N
Recv. Planning V. Data MU350
12-Aug-25
27-Sep-25
—
100%
EK05API030
05A Conceptual Layout - Supersketches
12-Aug-25
28-Sep-25
—
100%
EK000IC350
DCS - Develop Design Basis
12-Aug-25
04-Oct-25
—
100%
PK000IC35K
DCS - Formal Award
12-Aug-25
17-Oct-25
—
100%
PK000MB66I
Eval Bids & Issue Recmd MB660
12-Aug-25
20-Jan-26
—
100%
PK000MB41K
MB410 - Fabricate/PO Promise 101-B Cast Tube Supports
12-Aug-25
27-Feb-26
—
100%
PK000MB61K
MB610 - Fabricate/PO Promise 101-B Burners
12-Aug-25
01-Apr-26
—
100%
PK000MB63K
MB630 - Fabricate/PO Promise 101-B Air Preheater
12-Aug-25
14-Apr-26
—
100%
PK000MD32K
MD302 - Fabricate/PO Promise 104-D1/2
13-Aug-25
10-Jan-27
85.0d
49%
PK000MJ75K
MJ750 - Fabricate/PO Promise SURFACE CONDENSORS
13-Aug-25
27-Dec-26
—
51%
EK000MU61E
Prepare & Issue Purchase ERW - MU611
13-Aug-25
16-Aug-25
—
100%
PK000MD41P
Issue Formal P.O. for MD401
13-Aug-25
20-Aug-25
—
100%
PK000MB34J
Final Negotiate/Interim Award - MB340
13-Aug-25
14-Aug-25
—
100%
EK010SY150
010 Relief Valve Calculations - CW Twr & FW Tanks
14-Aug-25
26-Sep-25
—
100%
PK000MB34K
MB340 - Fabricate/PO Promise 101-B Finning
14-Aug-25
27-Dec-26
—
51%
PK000PTA0G
Engineered Pipe Supports - Fab / Exworks
14-Aug-25
27-Dec-26
—
51%
PK000MB34P
Issue Formal P.O. for MB340
14-Aug-25
10-Sep-25
—
100%
PK000PTA0E
Engineered Pipe Supports - Formal Award
14-Aug-25
30-Dec-25
—
100%
PK000PTA0F
Engineered Pipe Supports - Planning V. Data
14-Aug-25
24-Jan-26
—
100%
PK000I221K
000 Everest Control Valves - Issue Formal Purchase Agreement
14-Aug-25
03-Feb-26
—
100%
EK01BPI030
01B Conceptual Layout - Supersketches
15-Aug-25
31-Aug-25
—
100%
PK000MD22A
MD202 - Fabricate/PO Promise TOWERS 104-E
16-Aug-25
27-Dec-26
—
50%
PK000MD22K
MD202 - Fabricate/PO Promise TOWERS 103/105-E
16-Aug-25
27-Dec-26
—
50%
PK000MD22T
MD202 - Fabricate/PO Promise TOWERS 150-E
16-Aug-25
28-Feb-27
100.0d
45%
PK000MD34K
MD304 - Fabricate/PO Promise 106-D, 109-DA/B
16-Aug-25
29-Jan-27
200.0d
47%
PK000MD34Z
MD304 - Fabricate/PO Promise 108-DA/B
16-Aug-25
27-Dec-26
—
50%
PK000MD42K
MD402 - Fabricate/PO Promise 102-F1, 102-F2
16-Aug-25
21-Mar-27
130.0d
43%
PK000MD42N
MD402 - Fabricate/PO Promise 104-F, 144-F
16-Aug-25
27-Dec-26
—
50%
PK000MD44K
MD404 - Fabricate/PO Promise 109-F
16-Aug-25
27-Dec-26
—
50%
PK000MD44L
MD404 - Fabricate/PO Promise 107-F
16-Aug-25
27-Dec-26
—
50%
PK000MD44T
MD404 - Fabricate/PO Promise 132-F
16-Aug-25
27-Dec-26
—
50%
PK000MD45A
MD405 - Fabricate/PO Promise ISBL DRUMS - 115-F
16-Aug-25
27-Dec-26
—
50%
PK000MD45K
MD405 - Fabricate/PO Promise ISBL DRUMS - 156-F & 157-F
16-Aug-25
27-Dec-26
—
50%
PK000MD46K
MD411 - Fabricate/PO Promise OSBL DRUMS - 2203-F & 2204-F
16-Aug-25
27-Dec-26
—
50%
PK000MD46T
MD411 - Fabricate/PO Promise OSBL DRUMS - 2006-F
16-Aug-25
27-Dec-26
—
50%
PK000MD4Q
MD405 - Fabricate/PO Promise ISBL DRUMS - 118-F
16-Aug-25
27-Dec-26
—
50%
PK000MD42P
Issue Formal P.O. for MD402
16-Aug-25
02-Sep-25
—
100%
PK000MD44P
Issue Formal P.O. for MD404
16-Aug-25
02-Sep-25
—
100%
PK000MD45P
Issue Formal P.O. for MD405
16-Aug-25
02-Sep-25
—
100%
PK000MD46P
Issue Formal P.O. for MD411
16-Aug-25
02-Sep-25
—
100%
PK000MD32P
Issue Formal P.O. for MD302
16-Aug-25
07-Sep-25
—
100%
PK03FMD03
03F MD411 2006-F Boiler Blowdown Drum - Prod. V. Data
16-Aug-25
13-Sep-25
—
100%
PK000MD34P
Issue Formal P.O. for MD304
16-Aug-25
18-Sep-25
—
100%
PK000MD32N
Recv. Planning V. Data MD302
16-Aug-25
02-Oct-25
—
100%
PK000MD34N
Recv. Planning V. Data MD304
16-Aug-25
12-Nov-25
—
100%
PK020MC31G
MC312 - (120,121-C) - Final Negotiate/Interim Award
19-Aug-25
21-Aug-25
—
100%
PK000MBP3M
Requote/Bid Condition/Final Tab - Pressure Parts
19-Aug-25
28-Aug-25
—
100%
PK000ML51I
Eval Bids & Issue Recmd ML512
19-Aug-25
06-Sep-25
—
100%
PK000ML33I
Eval Bids & Issue Recmd ML330
19-Aug-25
13-Sep-25
—
100%
EK000MJ75E
Prepare & Issue Purchase ERW - MJ750
19-Aug-25
28-Sep-25
—
100%
EK050SY150
050 Relief Valve Calculations - Dock/Storage
20-Aug-25
25-Sep-25
—
100%
PK000PIA1F
Bulk Piping A/G & U/G - Formal Award
20-Aug-25
03-Sep-25
—
100%
PK020MC31C
MC312 - Fabricate/PO Promise 121-C
21-Aug-25
28-Feb-27
90.0d
44%
PK020MC31K
MC312 - Fabricate/PO Promise 120-C
21-Aug-25
28-Feb-27
90.0d
44%
EK000PE070
Kick-off meeting at MEC
22-Aug-25
23-Aug-25
—
100%
PK020MC31H
MC312 - (120,121-C) - Issue Formal P.O.
22-Aug-25
19-Sep-25
—
100%
EK03UPIFWA
03U Plant Layout Model - Firewater
22-Aug-25
05-Oct-25
—
100%
EK01UPIFWA
01U Plant Layout Model - Firewater
22-Aug-25
08-Oct-25
—
100%
PK000MJ35P
Issue Formal P.O. for MJ305
22-Aug-25
04-Feb-26
—
100%
PK000MJ36P
Issue Formal P.O. for MJ306
22-Aug-25
04-Feb-26
—
100%
PK000MD41K
MD401 - Fabricate/PO Promise 101-F
23-Aug-25
27-Dec-26
—
50%
PK000MD43K
MD403 - Fabricate/PO Promise 106-F
23-Aug-25
11-Mar-27
135.0d
43%
PK000MJ35K
MJ305 - Fabricate/PO Promise ISBL ANSI/API PUMPS
23-Aug-25
27-Dec-26
—
50%
ZZ2070
MJ305 - Fabricate/PO Promise OSBL ANSI/API PUMPS
23-Aug-25
27-Dec-26
—
50%
PK000MD43P
Issue Formal P.O. for MD403
23-Aug-25
07-Sep-25
—
100%
PK000ML43I
Eval Bids & Issue Recmd ML430
23-Aug-25
12-Sep-25
—
100%
PK000MJ35N
Recv. Planning V. Data MJ305
23-Aug-25
27-Sep-25
—
100%
PK000MJ36N
Recv. Planning V. Data MJ306
23-Aug-25
27-Sep-25
—
100%
PK000MD51P
Issue Formal P.O. for MD501
26-Aug-25
06-Sep-25
—
100%
EK01PIBSA
01U Plant Layout Model - Benfield Sewer
26-Aug-25
05-Oct-25
—
100%
EK01UPISSA
01U Plant Layout Model - Sanitary Sewer
26-Aug-25
05-Oct-25
—
100%
EK000MD21E
Prepare & Issue Purchase ERW - MD201
27-Aug-25
29-Aug-25
—
100%
PK000MB51J
Final Negotiate/Interim Award - MB511
27-Aug-25
02-Sep-25
—
100%
PK000MD22P
Issue Formal P.O. for MD202
27-Aug-25
02-Sep-25
—
100%
PK000MB65I
Eval Bids & Issue Recmd MB622
27-Aug-25
20-Nov-25
—
100%
PK000MD51K
MD501 - Fabricate/PO Promise 107-D
27-Aug-25
27-Dec-26
—
49%
PK000I220G
Final Negotiation / Interim Award - MOV's
27-Aug-25
02-Sep-25
—
100%
PK000MD51N
Recv. Planning V. Data MD501
27-Aug-25
01-Nov-25
—
100%
PK000MBP3P
Issue Formal P.O. for 101-B Pressure Parts
28-Aug-25
16-Oct-25
—
100%
PK000MU31G
Issue MU310 RFQ
28-Aug-25
30-Aug-25
—
100%
PK000I230G
Final Negotiation / Interim Award - On/Off Valves
28-Aug-25
02-Sep-25
—
100%
PK000MJ37I
Eval Bids & Issue Recmd MJ340
28-Aug-25
19-Oct-25
—
100%
PK000MBP3T
MB311 - Shop Recv - 101-B Radiant Fittings
28-Aug-25
03-Mar-26
—
100%
EK000MB21D
Technical Evaluation - MB212
29-Aug-25
01-Nov-25
—
100%
PK000MJ22K
MJ201 - Fabricate/PO Promise 101-J
30-Aug-25
10-Jan-27
86.0d
48%
PK000ML31K
ML313 - Fabricate/PO Promise 160-L
30-Aug-25
27-Dec-26
—
49%
PK000MD31P
Issue Formal P.O. for MD301
30-Aug-25
12-Sep-25
—
100%
PK000ML31P
Issue Formal P.O. for ML313
30-Aug-25
24-Sep-25
—
100%
PK000MJ22P
Issue Formal P.O. for MJ201
30-Aug-25
15-Oct-25
—
100%
EK000MJ33D
Technical Evaluation - MJ303
30-Aug-25
19-Dec-25
—
100%
PK000MB68I
Eval Bids & Issue Recmd MB692
30-Aug-25
27-Feb-26
—
100%
PK000MU21N
Recv. Planning V. Data MU221
01-Sep-25
27-Sep-25
—
100%
PK000MBP3R
MB311 - Fab/Exworks 101-B Crossover Tube & Pipe
02-Sep-25
27-Dec-26
—
49%
PK000MBP3S
MB311 - Fab/Exworks 101-B Crossover Fittings
02-Sep-25
27-Dec-26
—
49%
EK010PI011
Plot Plan - Overall Site (Drwg 0101) Client ICA Approval
02-Sep-25
14-Sep-25
—
100%
PK000MU31H
Receive Quotes MU310
02-Sep-25
23-Sep-25
—
100%
PK000ML42N
Recv. Planning V. Data ML420
02-Sep-25
26-Sep-25
—
100%
PK000MJ32N
Recv. Planning V. Data MJ302
02-Sep-25
27-Sep-25
—
100%
PK000MJ34N
Recv. Planning V. Data MJ304
02-Sep-25
27-Sep-25
—
100%
PK000MJ37N
Recv. Planning V. Data MJ340
02-Sep-25
27-Sep-25
—
100%
PK000MJ39N
Recv. Planning V. Data MJ391
02-Sep-25
27-Sep-25
—
100%
PK000MJ73N
Recv. Planning V. Data MJ730
02-Sep-25
27-Sep-25
—
100%
PK000MU22N
Recv. Planning V. Data MU222
02-Sep-25
27-Sep-25
—
100%
PK000MB51P
Issue Formal P.O. for MB511
02-Sep-25
06-Dec-25
—
100%
PK000MBP3K
MB311 - Fab/Exworks 101-B Radiant Tube & Pipe
02-Sep-25
31-Mar-26
—
100%
EK000MB095
101-B Ducting Detail Drawings - IFF
02-Sep-25
05-Apr-26
—
100%
PK000MBP3O
MB311 - Fab/Exworks 101-B Convection Tube & Pipe
02-Sep-25
15-Apr-26
—
100%
PK000MBP3Q
MB311 - Fab/Exworks 101-B Convection Fittings
02-Sep-25
15-Apr-26
—
100%
EK000MD055
Pre-qualification trip to vendors shop (105-D)
03-Sep-25
05-Sep-25
—
100%
EK000MU41E
Prepare & Issue Purchase ERW - MU410
03-Sep-25
05-Sep-25
—
100%
PK000MD21P
Issue Formal P.O. for MD201
03-Sep-25
18-Sep-25
—
100%
PK000MU61N
Recv. Planning V. Data MU611
03-Sep-25
26-Sep-25
—
100%
PK000MB51K
MB511 - Fabricate/PO Promise 101-B Insulation
03-Sep-25
30-Dec-26
204.0d
48%
PK01DMUV04
01D MU611 2101-U - Piping Prod. V. Data
03-Sep-25
03-Mar-26
—
100%
PK01DMUV05
01D MU611 2101-U - Civil Prod. V. Data
03-Sep-25
03-Mar-26
—
100%
PK01DMUV06
01D MU611 2101-U - E&I Prod. V. Data
03-Sep-25
03-Mar-26
—
100%
PK000MB33P
MB333 - Issue Formal P.O. 101-B
04-Sep-25
06-Sep-25
—
100%
PK000MC61J
Final Negotiate/Interim Award - MC610
05-Sep-25
09-Sep-25
—
100%
PK000MJ22N
Recv. Planning V. Data MJ201
05-Sep-25
27-Sep-25
—
100%
PK000MU41K
MU410 - Fabricate/PO Promise 2002-U PKG BOILER
06-Sep-25
27-Dec-26
—
48%
PK000MU22I
Eval Bids & Issue Recmd MU222
06-Sep-25
19-Sep-25
—
100%
PK000MJ31N
Recv. Planning V. Data MJ301
06-Sep-25
27-Sep-25
—
100%
PK000ML51J
Final Negotiate/Interim Award - ML512
09-Sep-25
11-Sep-25
—
100%
EK030PI011
Plot Plan - Utility Plant Client ICA Approval
09-Sep-25
27-Sep-25
—
100%
PK000MJ34J
Final Negotiate/Interim Award - MJ304
09-Sep-25
14-Oct-25
—
100%
PK000MU33J
Final Negotiate/Interim Award - MU330
09-Sep-25
29-Oct-25
—
100%
PK000MU61K
MU611 - Fabricate/PO Promise 2101-U, 2101-UJA Thru UJG CW TWR & Fans
09-Sep-25
14-Apr-26
—
100%
PK000MU61T
MU611 - Fabricate/PO Promise 2101-UJA Thru UJGM CW Motors
09-Sep-25
14-Apr-26
—
100%
PK000MC61K
MC610 - Fabricate/PO Promise DBL PIPE EXCH 188-CA
10-Sep-25
27-Dec-26
—
48%
PK000MC61P
Issue Formal P.O. for MC610
10-Sep-25
12-Oct-25
—
100%
PK000MC61N
Recv. Planning V. Data MC610
10-Sep-25
03-Dec-25
—
100%
PK000MC61L
MC610 - Fabricate/PO Promise DBL PIPE EXCH 161-C
10-Sep-25
09-Apr-26
—
100%
EK000CV137
Issue OSBL Rough Grade Design Pkg.
11-Sep-25
26-Nov-25
—
100%
PK000MBP4K
MB312 - Fab/PO Promise 101-B Radiant Cast Fittings
11-Sep-25
27-Dec-26
—
48%
PK000MBP4Q
MB312 - Fab/PO Promise 101-B Radiant Cast Stringer Grids
11-Sep-25
27-Dec-26
—
48%
PK000MBP4R
MB312 - Fab/PO Promise 101-B Radiant Cast Tube/Riser/Manifold
11-Sep-25
27-Dec-26
—
48%
PK000ML51K
ML512 - Fabricate/PO Promise 2102-L LOADING ARM
11-Sep-25
27-Dec-26
—
48%
PK000MBP4M
Requote/Bid Condition/Final Tab - Cast Material
11-Sep-25
16-Sep-25
—
100%
EK000ML51E
Prepare & Issue Purchase ERW - ML512
11-Sep-25
25-Sep-25
—
100%
PK000ML51N
Recv. Planning V. Data ML512
11-Sep-25
27-Sep-25
—
100%
PK000ML51P
Issue Formal P.O. for ML512
11-Sep-25
27-Sep-25
—
100%
PK000ML43J
Final Negotiate/Interim Award - ML430
12-Sep-25
14-Oct-25
—
100%
PK000MB71G
Issue MB710 RFQ
13-Sep-25
17-Sep-25
—
100%
PK000ML33J
Final Negotiate/Interim Award - ML330
13-Sep-25
20-Sep-25
—
100%
EK000MJ36E
Prepare & Issue Purchase ERW - MJ306
13-Sep-25
25-Sep-25
—
100%
EK000MJ35E
Prepare & Issue Purchase ERW - MJ305
13-Sep-25
25-Sep-25
—
100%
PK000PIA4F
Product Line Piping - Formal Award
13-Sep-25
02-Oct-25
—
100%
EK000MJ22E
Prepare & Issue Purchase ERW - MJ201
13-Sep-25
13-Nov-25
—
100%
PK03EMU100
03E Recv. Planning V. Data - Utility Equip.
16-Sep-25
16-Sep-25
—
100%
EK050PI012
Plot Plan - Dock/Storage Issue IPL
16-Sep-25
26-Oct-25
—
100%
EK000I444D
Technical Evaluation - Analyzer Shelter
16-Sep-25
11-Dec-25
—
100%
PK000MD21K
MD201 - Fabricate/PO Promise 101-E
17-Sep-25
01-Jan-27
93.0d
46%
PK000MD21M
MD201 - Fabricate/PO Promise 102-E
17-Sep-25
05-Mar-27
62.0d
41%
PK03BMJ154
03B Recv. Planning V. Data - Pumps 2401-J, 2401-JA
17-Sep-25
17-Sep-25
—
100%
PK03CMJ154
03C Recv. Planning V. Data - Pumps 2205-J/JA, 2206-J/JA
17-Sep-25
17-Sep-25
—
100%
PK03DMJ154
03D Recv. Planning V. Data - Pumps 2202-J/JA
17-Sep-25
17-Sep-25
—
100%
PK05AMJ154
05A Recv. Planning V. Data - Pumps 2106/7-J
17-Sep-25
17-Sep-25
—
100%
PK000MU21I
Eval Bids & Issue Recmd MU221
17-Sep-25
19-Sep-25
—
100%
EK000ML33E
Prepare & Issue Purchase ERW - ML330
17-Sep-25
25-Sep-25
—
100%
EK03UPIOSA
03U Plant Layout Model - Outfall Sewer
17-Sep-25
26-Sep-25
—
100%
PK000MU41N
Recv. Planning V. Data MU410
17-Sep-25
27-Sep-25
—
100%
PK000I220K
Issue Formal Purchase Agreement. - MOV's
17-Sep-25
13-Dec-25
—
100%
PK000I230K
Issue Formal Purchase Agreement. - On/Off Valves
17-Sep-25
13-Dec-25
—
100%
EK000FP012
FP Electrical Area Classification OSBL - ICA
17-Sep-25
10-Oct-25
—
100%
PK000MB71H
Receive Quotes for MB710
17-Sep-25
14-Oct-25
—
100%
EK020PR20D
PR201 KAAP Catalyst - Technical Evaluation
17-Sep-25
01-Nov-25
—
100%
PK000MBP4Z
MB312 - Shop Recv. 101-B Radiant Cast Fittings
17-Sep-25
03-Mar-26
—
100%
EK000MC61E
Prepare & Issue Purchase ERW - MC610
18-Sep-25
25-Sep-25
—
100%
PK000MU21J
Final Negotiate/Interim Award - MU221
19-Sep-25
04-Nov-25
—
100%
PK000MU22J
Final Negotiate/Interim Award - MU222
19-Sep-25
04-Nov-25
—
100%
EK000MJ32E
Prepare & Issue Purchase ERW - MJ302
20-Sep-25
13-Nov-25
—
100%
PK000ML33K
ML330 - Fabricate/Po Promise 2101-L
20-Sep-25
27-Dec-26
—
47%
PK000MD47J
Final Negotiate/Interim Award - MD406
20-Sep-25
25-Sep-25
—
100%
PK000ML33N
Recv. Planning V. Data ML330
20-Sep-25
27-Sep-25
—
100%
EK03UPIASA
03U Plant Layout Model - Acid Sewer
20-Sep-25
08-Oct-25
—
100%
EK03UPICSA
03U Plant Layout Model - Caustic Sewer
20-Sep-25
08-Oct-25
—
100%
PK000ML33P
Issue Formal P.O. for ML330
20-Sep-25
31-Oct-25
—
100%
PK000ML43N
Recv. Planning V. Data ML430
20-Sep-25
01-Nov-25
—
100%
EK000MJ34E
Prepare & Issue Final Data Shts - MJ304
21-Sep-25
08-Nov-25
—
100%
EK000MU33E
Prepare & Issue Purchase ERW - MU330
21-Sep-25
26-Sep-25
—
100%
EK020MC31C
MC312 - (120,121-C) - Prepare & Issue Purchase ERW
23-Sep-25
27-Sep-25
—
100%
EK03CPI030
03C Conceptual Layout - Supersketches
23-Sep-25
27-Sep-25
—
100%
PK020MC31F
MC312 - (120,121-C) - Planning V. Data (Setting Plans)
23-Sep-25
08-Oct-25
—
100%
EK010I1240
Rotameters - D/S,Sizing,Tech Eval
23-Sep-25
15-Nov-25
—
100%
EK030I1100
030 Orific Plates - D/S Utility Plant
24-Sep-25
05-Nov-25
—
100%
EK030IC210
030 Control Valves - D/S, Sizing,Tech Eval
24-Sep-25
21-Dec-25
—
100%
EK000MU31D
Technical Evaluation - MU310
24-Sep-25
30-Sep-25
—
100%
PK000MD47P
Issue Formal P.O. for MD406
24-Sep-25
03-Oct-25
—
100%
EK010IC242
MOV Valves - D/S,Sizing,Tech Eval
25-Sep-25
15-Nov-25
—
100%
EK050SY185
050 SP Item Data Sheets - Dock/Storage
25-Sep-25
24-Dec-25
—
100%
EK01JPI030
01J Conceptual Layout - Supersketches
25-Sep-25
03-Oct-25
—
100%
EK010SY185
010 SP Item Data Sheets - CW Twr & FW Tanks
25-Sep-25
24-Dec-25
—
100%
PK000PSA8E
000 Relief Valves - Final Negotiation / Interim Award
26-Sep-25
27-Sep-25
—
100%
EK01UPIPWA
01U Plant Layout Model - Potable Water
26-Sep-25
05-Oct-25
—
100%
PK000MU33P
Issue Formal P.O. for MU330
26-Sep-25
20-Feb-26
—
100%
EK030SY185
030 SP Item Data Sheets - Utiliy Plant
27-Sep-25
24-Dec-25
—
100%
EK04API030
04A Conceptual Layout - Supersketches
27-Sep-25
27-Dec-26
—
46%
PK000PSA8G
000 Relief Valves - Fabricate/Exworks
27-Sep-25
30-Dec-26
257.0d
46%
PK01BMJ154
01B Recv. Planning V. Data - Pumps (2001,4,7,2203,4)
27-Sep-25
27-Sep-25
—
100%
PK000PSA8F
000 Relief Valves - Issue Formal Blanket P.O.
27-Sep-25
20-Dec-25
—
100%
EK01UPIPAA
01U Plant Layout Model - Plant Air
30-Sep-25
30-Sep-25
—
100%
EK01UPIWWA
01U Plant Layout Model - Waste Water
30-Sep-25
05-Oct-25
—
100%
EK000MC23E
Prepare & Issue Purchase ERW - MC230
30-Sep-25
15-Oct-25
—
100%
EK000I352D
SIS - Tech Evaluation
30-Sep-25
07-Nov-25
—
100%
EK000MC21E
Prepare & Issue Purchase ERW - MC210
30-Sep-25
07-Nov-25
—
100%
PK000MD47K
MD406 - Fabricate/PO Promise ISBL DRUMS
01-Oct-25
27-Dec-26
—
45%
PK000MU33K
MU330 - Fabricate/PO Promise 2001-U
01-Oct-25
27-Dec-26
—
45%
PK000PIA1K
Bulk Piping A/G - Fab/Exworks (CROME)
01-Oct-25
27-Dec-26
—
45%
PK000PIA4G
Product Line Piping - Fab/Exworks +/- 5700 Mts.
01-Oct-25
27-Dec-26
—
45%
PK01HMJ135
01H Recv. Planning V.Data - Emerg Pwr Generator
01-Oct-25
01-Oct-25
—
100%
PK05AML100
05A Recv. Planning V. Data - Special Equip.
01-Oct-25
01-Oct-25
—
100%
PK05BML100
05B Recv. Planning V. Data - Special Equip. 2102-L
01-Oct-25
01-Oct-25
—
100%
EK000MU30E
Prepare & Issue Purchase ERW - MU300
01-Oct-25
14-Oct-25
—
100%
EK01API030
01A Conceptual Layout - Supersketches
01-Oct-25
08-Oct-25
—
100%
PK000MC21J
Final Negotiate/Interim Award - MC210
01-Oct-25
09-Oct-25
—
100%
PK000MC23J
Final Negotiate/Interim Award - MC230
01-Oct-25
09-Oct-25
—
100%
EK000ML42E
Prepare & Issue Purchase ERW - ML420
01-Oct-25
10-Oct-25
—
100%
EK000MJ37E
Prepare & Issue Purchase ERW - MJ340
01-Oct-25
16-Oct-25
—
100%
PK000MB42J
Final Negotiate/Interim Award - MB420
01-Oct-25
07-Nov-25
—
100%
PK000PR20E
PR201 KAAP Catalyst - Eval Bids & Issue Recmd
02-Oct-25
17-Oct-25
—
100%
EK03BPI030
03B Conceptual Layout - Supersketches
03-Oct-25
07-Oct-25
—
100%
PK000I352E
SIS - Eval Bids/Issue Recmd
03-Oct-25
28-Dec-25
—
100%
EK010I1100
010 Orific Plates - D/S,Sizing,Tech Eval
04-Oct-25
24-Oct-25
—
100%
EK010I1150
Annubars - D/S,Sizing,Tech Eval
04-Oct-25
02-Nov-25
—
100%
EK010I1210
Vortex Meters - D/S,Sizing,Tech Eval
04-Oct-25
02-Nov-25
—
100%
EK050I1100
050 Orific Plates - D/S Dock/Storage Area
04-Oct-25
05-Nov-25
—
100%
EK010IC210
010 Control Valves - D/S,Sizing,Tech Eval
04-Oct-25
21-Dec-25
—
100%
EK000MU31E
Prepare & Issue Purchase ERW - MU310
04-Oct-25
08-Oct-25
—
100%
EK000IC351
DCS - Develop Purchase T-Req
05-Oct-25
07-Nov-25
—
100%
EK010SY155
010 Issue Requisition - PSA08 Relief Valves - CW Twr & FW Tanks
05-Oct-25
19-Nov-25
—
100%
EK030SY155
030 Issue Requisition - PSA08 Relief Valves - Utility PLant
05-Oct-25
19-Nov-25
—
100%
EK050SY155
050 Issue Requisition - PSA08 Relief Valves - Dock/Storage
05-Oct-25
19-Nov-25
—
100%
PK000IC350
DCS - Vendor Update Pricing / Quote
07-Oct-25
11-Oct-25
—
100%
EK000PR600
MD305 Merc. Removal Bed - Develop & Issue Load Sheets for ERW
08-Oct-25
09-Oct-25
—
100%
EK000MJ31E
Prepare & Issue Purchase ERW - MJ301
08-Oct-25
13-Nov-25
—
100%
PK000MJ33N
Recv. Planning V. Data MJ303
08-Oct-25
26-Dec-25
—
100%
PK000MU31I
Eval Bids & Issue Recmd MU310
08-Oct-25
04-Jan-26
—
100%
EK000ML31E
Prepare & Issue Purchase ERW - ML313
08-Oct-25
09-Jan-26
—
100%
PK000ML42J
Final Negotiate/Interim Award - ML420
09-Oct-25
12-Oct-25
—
100%
PK000MC21K
MC210 - Fabricate/PO Promise 110/115/124/128/130/133/134/160/167/173/174-C
09-Oct-25
27-Dec-26
—
44%
PK000MC21N
MC210 - Fabricate/PO Promise 127-C
09-Oct-25
27-Dec-26
—
44%
PK000MC23A
MC230 - Fabricate/PO Promise 106-C & 109-C
09-Oct-25
27-Dec-26
—
44%
PK000MC23K
MC230 - Fabricate/PO Promise 105/107/172/183-C
09-Oct-25
27-Dec-26
—
44%
PK000MC23N
MC230 - Fabricate/PO Promise 111/114-C
09-Oct-25
27-Dec-26
—
44%
PK000MC23P
Issue Formal P.O. for MC230
09-Oct-25
09-Nov-25
—
100%
PK000MC21P
Issue Formal P.O. for MC210
09-Oct-25
04-Dec-25
—
100%
EK020ELEG2
Cathodic Protection - Subcontract Consultant ERW Package
09-Oct-25
01-Mar-26
—
100%
EK000MC32E
Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4)
10-Oct-25
15-Nov-25
—
100%
EK000MD103
MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW
10-Oct-25
26-Nov-25
—
100%
EK000PR610
MD305 Merc. Removal Bed - Analytical Design
10-Oct-25
26-Nov-25
—
100%
EK000YA813
(EP-14) Issue Plot Plans for Client Approval
11-Oct-25
11-Oct-25
—
100%
EK04ASY170
04A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK050SY090
050 Dock/Storage P&IDs IPL Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK05ASY170
05A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK05BSY170
05B OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK050PI011
Plot Plan - Dock/Storage Client ICA Approval
11-Oct-25
26-Oct-25
—
100%
PK000ML42P
Issue Formal P.O. for ML420
11-Oct-25
30-Oct-25
—
100%
PK000ML42K
ML420 - Fabricate/PO Promise CARTRIDGE FILTERS
11-Oct-25
28-Mar-26
—
100%
PK000MC32J
Final Negotiate/Interim Award - MC311
14-Oct-25
16-Oct-25
—
100%
PK000ML43P
Issue Formal P.O. for ML430
14-Oct-25
06-Nov-25
—
100%
PK000ML43K
ML430 - Fabricate/PO Promise 110-L BENFIELD MIXER
14-Oct-25
11-Mar-26
—
100%
PK000MJ34K
MJ304 - Fabricate/PO Promise MP BFW PUMPS
15-Oct-25
16-Jan-27
186.0d
42%
EK000I354D
ITCC - Tech Evaluation
15-Oct-25
12-Dec-25
—
100%
EK000MB42D
Technical Evaluation - MB420
16-Oct-25
30-Oct-25
—
100%
PK000MC32K
MC311 - Fabricate/PO Promise KBR S&T EXCH
16-Oct-25
16-Jan-27
76.0d
42%
PK000MC32P
Issue Formal P.O. for MC311
16-Oct-25
13-Dec-25
—
100%
PK000IC35J
DCS - Planning V. Data
17-Oct-25
27-Dec-26
—
43%
PK000MB64I
Eval Bids & Issue Recmd MB640
18-Oct-25
11-Nov-25
—
100%
PK000MJ73J
Final Negotiate/Interim Award - MJ730
18-Oct-25
11-Nov-25
—
100%
PK000MJ37J
Final Negotiate/Interim Award - MJ340
18-Oct-25
13-Dec-25
—
100%
PK000MB71I
Eval Bids & Issue Recmd MB710
18-Oct-25
31-Dec-25
—
100%
PK000IC35H
DCS - Fabricate Hardware
21-Oct-25
27-Dec-26
—
43%
PK000MU30J
Final Negotiate/Interim Award - MU300
25-Oct-25
29-Oct-25
—
100%
PK000MJ34P
Issue Formal P.O. for MJ304
30-Oct-25
22-Nov-25
—
100%
PK010I1240
Rotameters - Fabricate/Exworks
30-Oct-25
27-Dec-26
—
42%
PK000MB42I
Eval Bids & Issue Recmd MB420
30-Oct-25
31-Oct-25
—
100%
PK000MB69J
Final Negotiate/Interim Award - MB691
30-Oct-25
02-Nov-25
—
100%
PK000MU32G
01D MU322 Issue RFQ
30-Oct-25
11-Nov-25
—
100%
PK000MU33N
03E MU330 2001-U - Piping Conceptual V. Data
30-Oct-25
02-Feb-26
—
100%
PK010I1150
Annubars - Fabricate/Exworks
31-Oct-25
30-Dec-26
509.0d
41%
EK010SY090
010 CW Twr & FW Tanks P&IDs IPL Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01ASY170
01A OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01BSY170
01B OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01CSY170
01C OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01DSY170
01D OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01ESY170
01E OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01FSY170
01F OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01HSY170
01H OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01JSY170
01J OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK01YSY170
01Y OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
—
100%
EK010FP031
FP Firewater Pump P&IDs - Development & Issue IFD
01-Nov-25
27-Dec-26
—
41%
EK000ML43E
Prepare & Issue Purchase ERW - ML430
01-Nov-25
07-Nov-25
—
100%
PK01FMU100
01F Recv. Planning V. Data - Utility Equip. 2603-K, 2607-K
01-Nov-25
15-Nov-25
—
100%
PK000MB69K
MB691 - Fabricate/PO Promise 101-B
04-Nov-25
27-Dec-26
—
41%
PK000MU21K
MU221 - Fabricate/PO Promise LIFT STATION
04-Nov-25
27-Dec-26
—
41%
PK000MU22K
MU222 - Fabricate/PO Promise 2401-U
04-Nov-25
27-Dec-26
—
41%
PK000MB69P
Issue Formal P.O. for MB691
04-Nov-25
04-Nov-25
—
100%
EK000MJ37R
Develop & Issue Load Sheets for ERW - MJ307
04-Nov-25
08-Nov-25
—
100%
EK000MJ38R
Develop & Issue Load Sheets for ERW - MJ308
04-Nov-25
08-Nov-25
—
100%
PK000PR20F
PR201 KAAP Catalyst - Final Negotiate/Interim Award
04-Nov-25
09-Dec-25
—
100%
PK000MU21P
Issue Formal P.O. for MU221
04-Nov-25
11-Dec-25
—
100%
PK000MU22P
Issue Formal P.O. for MU222
04-Nov-25
11-Dec-25
—
100%
PK000MB21I
Eval Bids & Issue Recmd MB212
05-Nov-25
06-Nov-25
—
100%
EK000MU21E
Prepare & Issue Purchase ERW - MU221
05-Nov-25
22-Nov-25
—
100%
EK000MU22E
Prepare & Issue Purchase ERW - MU222
05-Nov-25
22-Nov-25
—
100%
EK000MU29F
Develop & Issue Inquiry for ERW - MU292
05-Nov-25
23-Nov-25
—
100%
PK000MJ32P
Issue Formal P.O. for MJ302
05-Nov-25
27-Nov-25
—
100%
PK000MB21J
Final Negotiate/Interim Award - MB212
06-Nov-25
07-Nov-25
—
100%
PK000MB21P
Issue Formal P.O. for MB212
07-Nov-25
21-Nov-25
—
100%
PK000MB42K
MB420 - Fabricate/PO Promise 101-B Cast Peep Sites
07-Nov-25
29-Jan-26
—
100%
EK03FPI030
03F Conceptual Layout - Supersketches (Need Dwgs)
07-Nov-25
01-Feb-26
—
100%
PK000MB21K
MB212 - Fabricate/PO Promise Equip. 101-B Siding
07-Nov-25
03-Mar-26
—
100%
PK000MB42P
Issue Formal P.O. for MB420
08-Nov-25
21-Nov-25
—
100%
PK000MJ73P
Issue Formal P.O. for MJ730
11-Nov-25
11-Nov-25
—
100%
EK000MJ37S
Develop & Issue Design Data for ERW - MJ307
11-Nov-25
15-Nov-25
—
100%
EK000MJ38S
Develop & Issue Design Data for ERW - MJ308
11-Nov-25
15-Nov-25
—
100%
EK05BEL175
Client Review of MCC Oneline Diagrams
11-Nov-25
22-Nov-25
—
100%
PK000MU32H
01D MU322 Receive Quotes
11-Nov-25
23-Dec-25
—
100%
PK000MB64J
Final Negotiate/Interim Award - MB640
11-Nov-25
06-Jan-26
—
100%
EK000IC352
DCS - Final Tech Evaluation for Purchase
13-Nov-25
15-Nov-25
—
100%
EK05BEL155
Client Review of Switchgear Oneline Diagrams
14-Nov-25
22-Nov-25
—
100%
PK000IC351
DCS - Vendor Provides Software & Workstations
14-Nov-25
29-Nov-25
—
100%
EK000MJ37T
Update/Issue Formal Inquiry for ERW - MJ307
18-Nov-25
26-Nov-25
—
100%
EK000MJ73E
Prepare & Issue Purchase ERW - MJ730
19-Nov-25
05-Dec-25
—
100%
EK000FA005
Issue First Invoice to EBIC
19-Nov-25
19-Nov-25
—
100%
PK000MU30K
MU300 - Fabricate/PO Promise 2102-U
19-Nov-25
27-Dec-26
—
39%
EK030SY090
030 Utility Plant P&IDs IPL Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03ASY170
03A OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03BSY170
03B OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03CSY170
03C OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03DSY170
03D OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03ESY170
03E OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03FSY170
03F OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03YSY170
03Y OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
PK000MU30N
Recv. Planning V. Data MU300 - EDR Unit
19-Nov-25
10-Jan-26
—
100%
PK000MU30P
Issue Formal P.O. for MU300
19-Nov-25
16-Jan-26
—
100%
PK000MJ31K
MJ301 - Fabricate/ PO Promise 104-J
20-Nov-25
31-Jan-27
168.0d
35%
PK000MJ32K
MJ302 - Fabricate/PO Promise 107-JA/JB/JC
20-Nov-25
17-Jan-27
175.0d
37%
PK000MU11G
05B MU311 Issue RFQ
20-Nov-25
26-Nov-25
—
100%
PK000MJ31P
Issue Formal P.O. for MJ301
20-Nov-25
27-Nov-25
—
100%
PK000MB65J
Final Negotiate/Interim Award - MB622
20-Nov-25
06-Jan-26
—
100%
EK000E001A
Sub Stations - Issue ERW
22-Nov-25
31-Dec-25
—
100%
EK000MD102
MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur.
26-Nov-25
05-Dec-25
—
100%
PK000MU29G
Issue MU292 RFQ
26-Nov-25
06-Dec-25
—
100%
PK000ML50Y
Requote - ML500
26-Nov-25
10-Dec-25
—
100%
PK000MU11H
05B MU311 Receive Quotes
26-Nov-25
03-Jan-26
—
100%
EK010PI012
Plot Plan - Overall Site (Drwg 0101) Issue IPL
28-Nov-25
20-Dec-25
—
100%
EK030PI012
Plot Plan - Utility Plant Issue IPL
28-Nov-25
20-Dec-25
—
100%
PK000MD104
MD305 Merc. Removal Bed - Issue RFQ
05-Dec-25
10-Dec-25
—
100%
PK000MU29H
Receive Quotes MU292
05-Dec-25
20-Jan-26
—
100%
PK000MJ37B
Eval Bids & Issue Recmd MJ307
06-Dec-25
21-Dec-25
—
100%
PK000PR20G
PR201 KAAP Catalyst - Issue Formal P.O.
09-Dec-25
09-Dec-25
—
100%
PK000ML52G
Issue ML501 RFQ
09-Dec-25
31-Dec-25
—
100%
PK000PR20H
PR201 KAAP Catalyst - Fabricate/Exworks
10-Dec-25
03-Nov-27
26.0d
19%
PK000ML90G
Issue ML900 RFQ
10-Dec-25
16-Dec-25
—
100%
EK000ML50Z
Technical Evaluation - ML500
10-Dec-25
31-Dec-25
—
100%
PK000MD106
MD305 Merc. Removal Bed - Receive Quotes
11-Dec-25
10-Jan-26
—
100%
PK000MJ37K
MJ340 - Fabricate/PO Promise METERING PUMPS
13-Dec-25
27-Dec-26
—
35%
PK000MJ37P
Issue Formal P.O. for MJ340
13-Dec-25
20-Jan-26
—
100%
PK000I354E
ITCC - Eval Bids/Issue Recmd
16-Dec-25
28-Dec-25
—
100%
PK000ML90H
Receive Quotes ML900
16-Dec-25
20-Jan-26
—
100%
PK000I444E
Eval Bids / Issue Recmd - Analyzer Shelter
17-Dec-25
20-Dec-25
—
100%
EK03EPI030
03E Conceptual Layout - Supersketches
17-Dec-25
31-Mar-26
—
100%
EK000E002A
Transformer - Issue ERW
18-Dec-25
30-Dec-25
—
100%
PK000MJ33I
Eval Bids & Issue Recmd MJ303
19-Dec-25
24-Dec-25
—
100%
EK000MJ33E
Prepare & Issue Purchase ERW - MJ303
19-Dec-25
27-Dec-25
—
100%
PK000MC31J
Final Negotiate/Interim Award - MC310
20-Dec-25
03-Jan-26
—
100%
PK000I352G
SIS - Interim Award
20-Dec-25
20-Jan-26
—
100%
PK000I354G
ITCC - Interim Award
20-Dec-25
20-Jan-26
—
100%
PK000MJ37M
Final Negotiate/Interim Award - MJ307
20-Dec-25
20-Jan-26
—
100%
PK000MJ39I
Eval Bids & Issue Recmd MJ391/MJ392
20-Dec-25
14-Mar-26
—
100%
PK000PSA8C
000 Relief Valves - Technical Evaluation
23-Dec-25
27-Dec-25
—
100%
EK010PI013
Plot Plan - Overall Site (Drwg 0101) Issue IPL
23-Dec-25
23-Jan-26
—
100%
EK000MU32D
01D MU322 Technical Evaluation
23-Dec-25
31-Jan-26
—
100%
PK000MU32I
01D MU322 Eval Bids & Issue Recmd
23-Dec-25
01-Apr-26
—
100%
PK000MJ33J
Final Negotiate/Interim Award - MJ303
24-Dec-25
03-Jan-26
—
100%
PK000MJ73K
MJ730 - Fabricate/PO Promise EMERG PWR GENERATOR
25-Dec-25
28-Feb-27
70.0d
28%
EK010IC213
010 Control Valves - Purchase ERW
25-Dec-25
27-Dec-26
—
33%
PK01DMJ154
01D Recv. Planning V. Data - Pumps 2210-J
26-Dec-25
26-Dec-25
—
100%
PK03DMJV02
03D MJ305 2002-J/JA - Civil Prod. V. Data
27-Dec-25
27-Dec-26
—
32%
PK000I444G
Final Negotiation / Interim Award - Shelters/ Analyzers
28-Dec-25
17-Feb-26
—
100%
EK000ELEJ1
Lighting, Installation Details
28-Dec-25
31-Dec-25
—
100%
EK000ELEK1
A/G Power & Control, Details
28-Dec-25
31-Dec-25
—
100%
EK05BELED0
Substation Building Layout
28-Dec-25
31-Dec-25
—
100%
PK000EL000
OSBL Motors & Drivers - Prod. V. Data (Information Only)
30-Dec-25
30-Dec-26
—
32%
PK03DMJV01
03D MJ305 2002-J/JA - Piping Prod. V. Data
30-Dec-25
27-Dec-26
—
32%
PK03DMJV03
03D MJ305 2002-J/JA - E&I Prod. V. Data
30-Dec-25
27-Dec-26
—
32%
PK000MU25G
02G MU225 Issue RFQ
30-Dec-25
31-Dec-25
—
100%
EK000GE025
First Check Estimate
30-Dec-25
27-Feb-26
—
100%
PK01BMJV03
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK01HMJV01
01H MJ730 2303-J - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK01HMJV02
01H MJ730 2303-J - E&I Prod. V. Data
31-Dec-25
30-Dec-26
511.0d
31%
PK03BMUV03
03B MU222,MJ305 2401-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03CMJV03
03C MJ305 2205-J/JA,2206-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV01
03E MU330 2001-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV02
03E MU330 2001-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV03
03E MU330 2001-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV03
03F MU222 2401-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV04
03F MU410 2002-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV05
03F MU410 2002-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV06
03F MU410 2002-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV01
05A ML330 2101-L - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV02
05A ML330 2101-L - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV03
05A ML330 2101-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05BMLV03
05B ML512 2102-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK01EMUV01
01E MU221 Warehouse / Maintenance Area - Piping Prod. V. Data
31-Dec-25
31-Dec-25
—
100%
PK01EMUV02
01E MU221 Warehouse / Maintenance Area - Civil Prod. V. Data
31-Dec-25
31-Dec-25
—
100%
PK01EMUV03
01E MU221 Warehouse / Maintenance Area - E&I Prod. V. Data
31-Dec-25
31-Dec-25
—
100%
PK03CMD06
03C MD411 2203-F 50% Caustic Storage Tank - Prod. V. Data
31-Dec-25
31-Dec-25
—
100%
PK03CMD07
03C MD411 2204-F 98% Sulfuric Acid Drum - Prod. V. Data
31-Dec-25
31-Dec-25
—
100%
PK000E002B
Transformer - Inquiry REQ/RFQ
31-Dec-25
16-Jan-26
—
100%
PK03CMJV01
03C MJ305 2205-J/JA,2206-J/JA - Piping Prod. V. Data
31-Dec-25
03-Mar-26
—
100%
PK05AMJV01
05A MJ305 2106-J,2107-J - Piping Prod. V. Data
31-Dec-25
03-Mar-26
—
100%
PK03FMUV01
03F MU222 2401-U - Piping Prod. V. Data
31-Dec-25
05-Mar-26
—
100%
PK03FMUV02
03F MU222 2401-U - Civil Prod. V. Data
31-Dec-25
05-Mar-26
—
100%
PK03BMUV01
03B MU222 2401-J/JA - Piping Prod. V. Data
31-Dec-25
08-Mar-26
—
100%
PK03BMUV02
03B MU222 2401-J/JA - Civil Prod. V. Data
31-Dec-25
08-Mar-26
—
100%
EK010I1105
010 Orific Plates - Purchase ERW
31-Dec-25
11-Mar-26
—
100%
EK030I1105
030 Orific Plates - Purchase ERW Utility Plant
31-Dec-25
11-Mar-26
—
100%
EK050I1105
050 Orific Plates - Purchase ERW Dock/Storage Area
31-Dec-25
11-Mar-26
—
100%
PK05AMJV02
05A MJ305 2106-J,2107-J - Civil Prod. V. Data
31-Dec-25
20-Mar-26
—
100%
PK01BMJV02
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Civil Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK03CMJV02
03C MJ305 2205-J/JA,2206-J/JA - Civil Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK05AMJV03
05A MJ305 2106-J,2107-J - E&I Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK05BMLV01
05B ML512 2102-L - Piping Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK05BMLV02
05B ML512 2102-L - Civil Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK01BMJV01
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Piping Prod. V. Data
31-Dec-25
31-Mar-26
—
100%
PK000E001B
Sub Stations - Inquiry REQ/RFQ
31-Dec-25
31-Dec-25
—
100%
PK000MB71J
Final Negotiate/Interim Award - MB710
31-Dec-25
06-Jan-26
—
100%
PK000MU25H
02G MU225 Receive Quotes
31-Dec-25
29-Jan-26
—
100%
PK000E001C
Sub Stations - Receive Bids
31-Dec-25
19-Feb-26
—
100%
EK030IC213
030 Control Valves - Purchase ERW
01-Jan-26
27-Dec-26
—
31%
EK01AIC300
01A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01BIC300
01B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01CIC300
01C In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01DIC300
01D In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01YIC300
01Y In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03AIC300
03A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03BIC300
03B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03DIC300
03D In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03EIC300
03E In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03FIC300
03F In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03YIC300
03Y In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK05AIC300
05A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK05BIC300
05B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
PK000MJ38Q
Prepare & Issue Prelim. RFQ - MJ308 to Proc.
01-Jan-26
13-Jan-26
—
100%
EK050PI013
Plot Plan - Dock/Storage Issue IPL
01-Jan-26
23-Jan-26
—
100%
EK01JIC300
01J In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
—
100%
EK03CIC300
03C In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
—
100%
EK04AIC300
04A In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
—
100%
PK000MC31K
MC310 - Fabricate/PO Promise 101-C & 102-C (Heavy Lift)
03-Jan-26
30-Jun-27
8.0d
20%
PK000MJ33K
MJ303 - Fabricate/PO Promise CW PUMPS
03-Jan-26
28-Feb-27
27.0d
26%
EK000MU11D
05B MU311 Technical Evaluation
03-Jan-26
01-Feb-26
—
100%
PK000MJ33P
Issue Formal P.O. for MJ303
03-Jan-26
03-Feb-26
—
100%
EK000MC31E
Prepare & Issue Purchase ERW - MC310
03-Jan-26
12-Feb-26
—
100%
PK000MC31P
Issue Formal P.O. for MC310
03-Jan-26
19-Feb-26
—
100%
PK01DMJV01
01D MJ303 2202-JA/JB/JC - Civil Prod. V. Data
03-Jan-26
07-Mar-26
—
100%
PK01DMJV02
01D MJ303 2202-JA/JB/JC - Piping Prod. V. Data
03-Jan-26
07-Mar-26
—
100%
PK000ML90I
Eval Bids & Issue Recmd ML900
03-Jan-26
01-Apr-26
—
100%
PK01DMJV03
01D MJ303 2202-JA/JB/JC - E&I Prod. V. Data
04-Jan-26
27-Dec-26
—
31%
PK000MB64K
MB640 - Fabricate/PO Promise 101-B Springs & Hangers
06-Jan-26
27-Dec-26
—
30%
PK000MB71K
MB710 - Fabricate/PO Promise 2202-B/BL Storage Flare & Flame FRT Gen.
06-Jan-26
27-Dec-26
—
30%
PK000MB64P
Issue Formal P.O. for MB640
06-Jan-26
20-Jan-26
—
100%
PK000MB71P
Issue Formal P.O. for MB710
06-Jan-26
21-Jan-26
—
100%
PK000ML52I
Eval Bids & Issue Recmd ML501
06-Jan-26
01-Feb-26
—
100%
PK000MB65K
MB622 - Fab/PO Promise 101-B Penthouse Circ Fans
07-Jan-26
27-Dec-26
—
30%
PK000MB65P
Issue Formal P.O. for MB622
07-Jan-26
20-Jan-26
—
100%
PK000MU31J
Final Negotiate/Interim Award - MU310
07-Jan-26
14-Jan-26
—
100%
PK01BMU100
01B Recv. Planning V. Data - 2007-L (No Req.)
10-Jan-26
10-Jan-26
—
100%
PK000MJ38F
Issue MJ308 RFQ
13-Jan-26
17-Jan-26
—
100%
EK000MD104
MD305 Merc. Removal Bed - Technical Evaluation
13-Jan-26
29-Jan-26
—
100%
PK000MU31K
MU310 - Fabricate/PO Promise Injection System & Chlorination Unit
14-Jan-26
27-Dec-26
—
29%
PK01DMUV01
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L-Piping Prod. V. Data
14-Jan-26
27-Dec-26
—
29%
PK01DMUV03
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L- E&I Prod. V. Data
14-Jan-26
27-Dec-26
—
29%
PK000MU31P
Issue Formal P.O. for MU310
14-Jan-26
14-Jan-26
—
100%
PK01DMUV02
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L - Civil Prod. V. Data
14-Jan-26
31-Mar-26
—
100%
PK03FMUV07
03F MU310 2001-L - Piping Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03FMUV08
03F MU310 2001-L - Civil Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03FMUV09
03F MU310 2001-L - E&I Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
EK000IC353
DCS - Software Programming by KBR
15-Jan-26
27-Dec-26
—
29%
PK01CMUV01
01C MU300 2102-U - Piping Prod. V. Data
16-Jan-26
27-Dec-26
—
28%
PK01CMUV02
01C MU300 2102-U - Civil Prod. V. Data
16-Jan-26
27-Dec-26
—
28%
PK01CMUV03
01C MU300 2102-U - E&I Prod. V. Data
16-Jan-26
27-Dec-26
—
28%
PK000ML52J
Final Negotiate/Interim Award - ML501
16-Jan-26
31-Jan-26
—
100%
PK000ML50J
Final Negotiate/Interim Award - ML500
16-Jan-26
01-Feb-26
—
100%
PK000E002C
Transformer - Receive Bids
16-Jan-26
04-Mar-26
—
100%
EK000CV045
Prepare Foundation Design Criteria
16-Jan-26
14-Mar-26
—
100%
EK000MJ37C
Prepare & Issue Purchase ERW - MJ307
17-Jan-26
20-Jan-26
—
100%
PK000MJ37U
MJ307 - Fabricate/PO Promise ISBL ANSI/API PUMPS
20-Jan-26
20-Jan-27
192.0d
26%
PK05AMJV04
05A MJ307 2100-JA/JB - Piping Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV05
05A MJ307 2100-JA/JB - Civil Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV06
05A MJ307 2100-JA/JB - E&I Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK000MJ37T
Recv. Planning V. Data MJ307
20-Jan-26
23-Jan-26
—
100%
PK000MB66J
Final Negotiate/Interim Award - MB660
20-Jan-26
24-Jan-26
—
100%
PK000MJ37R
Issue Formal P.O. for MJ307
20-Jan-26
31-Jan-26
—
100%
PK000I352K
SIS - Formal Award
20-Jan-26
10-Feb-26
—
100%
PK000I354K
ITCC - Formal Award
20-Jan-26
10-Feb-26
—
100%
PK000MJ38D
Receive Quotes MJ308
20-Jan-26
10-Feb-26
—
100%
EK000MU29D
Technical Evaluation - MU292
20-Jan-26
03-Mar-26
—
100%
PK000MB66K
MB660 - Fabricate/PO Promise 101-B Dampers & Air Doors
24-Jan-26
27-Dec-26
—
27%
PK000MB66P
Issue Formal P.O. for MB660
24-Jan-26
24-Jan-26
—
100%
PK000PS00A
000 SP Items - Issue RFQ
24-Jan-26
29-Jan-26
—
100%
PK000PTA0H
Engineered Pipe Supports - Production V. Data
24-Jan-26
29-Jan-26
—
100%
PK000MU11I
05B MU311 Eval Bids & Issue Recmd
24-Jan-26
31-Jan-26
—
100%
EK010I1241
Rotameters - Purchase ERW
28-Jan-26
27-Dec-26
—
26%
EK050PI014
Plot Plan - Dock/Storage Issue IFC
28-Jan-26
27-Dec-26
—
26%
PK01BMF02
01B MF302 2001-FA/FB Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK01BMF03
01B MF302 2001-FA/FB Water Tank - Piping Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK01BMF04
01B MF302 2001-FA/FB Water Tank - Civil Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK01BMF05
01B MF302 2001-FA/FB Water Tank - E&I Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK03DMF01
03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
EK000SY095
010 P&ID's - Tech Review
28-Jan-26
29-Jan-26
—
100%
PK01BMF01
01B MF302 2001-FA/FB Water Tank - Fdn. V. Data (Subcontract)
28-Jan-26
21-Feb-26
—
100%
EK000I3540
ITCC - Develop Final Design Basis
28-Jan-26
04-Mar-26
—
100%
EK000I3520
SIS - Develop Final Design Basis
28-Jan-26
12-Mar-26
—
100%
PK03DMF00
03D MF302 2002-F Demineralized Water Tank - Fdn. V. Data (Subcontract)
28-Jan-26
18-Mar-26
—
100%
EK010PI014
Plot Plan - Overall Site (Drwg 0101) Issue IFC
28-Jan-26
29-Mar-26
—
100%
EK010IC252
MOV Valves - Purchase ERW
28-Jan-26
15-Apr-26
—
100%
EK000MU25D
02G MU225 Technical Evaluation
28-Jan-26
21-Feb-26
—
100%
PK000I1220
Coriolis Meters - Fabricate/Exworks
29-Jan-26
27-Dec-26
—
26%
EK01YPI050
01Y Model Comment Resolution Approval
29-Jan-26
31-Jan-26
—
100%
PK000MD107
MD305 Merc. Removal Bed - Eval Bids & Issue Recmd
29-Jan-26
31-Jan-26
—
100%
EK000MD105
MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW
29-Jan-26
01-Feb-26
—
100%
PK000PS00B
000 SP Items - Receive Quotes
29-Jan-26
11-Feb-26
—
100%
PK000ML50N
Recv. Planning V. Data ML500
29-Jan-26
24-Feb-26
—
100%
PK000ML50P
Issue Formal P.O. for ML500
29-Jan-26
26-Mar-26
—
100%
PK000MB42S
MB420 - Marshaling 101-B Cast Peep Sites
30-Jan-26
27-Dec-26
—
25%
PK03AMLV01
03A ML500 2003-L - Piping Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK03AMLV02
03A ML500 2003-L - Civil Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK03AMLV03
03A ML500 2003-L - E&I Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK000MD108
MD305 Merc. Removal Bed - Final Negotiate/Interim Award
31-Jan-26
03-Feb-26
—
100%
PK000MU11J
05B MU311 Final Negotiate/Interim Award
31-Jan-26
13-Feb-26
—
100%
EK010E008A
540-SB Admin. Area Pwr Supply - ERW Package
01-Feb-26
14-Feb-26
—
100%
PK000I221H
000 Everest Control Valves - Fabricate/Exworks
03-Feb-26
30-Dec-26
504.0d
24%
PK000MD110
MD305 Merc. Removal Bed - Fabricate/PO Promise
03-Feb-26
28-Feb-27
157.0d
21%
EK01DPI021
01D Model Review Comment Resolution
03-Feb-26
07-Feb-26
—
100%
EK00012210
000 Everest Control Valves - D/S,Sizing,Tech Eval
03-Feb-26
05-Mar-26
—
100%
PK000MD109
MD305 Merc. Removal Bed - Issue Formal P.O.
03-Feb-26
11-Mar-26
—
100%
PK000ML52P
Issue Formal P.O. for ML501
03-Feb-26
26-Mar-26
—
100%
PK000ML50K
ML500 - Fabricate/PO Promise 2003-L PAI/IA
04-Feb-26
10-Feb-27
78.0d
21%
PK000MJ36K
MJ305 - Fabricate/PO Promise OSBL PUMPS
04-Feb-26
10-Jan-27
60.0d
23%
PK000MBP3U
MB311 - Shop Recv - 101-B Convection Tube & Pipe
07-Feb-26
22-Apr-26
—
100%
EK000YA822
(EP-22) Issue for Planning (IPL) >90% OSBL P&ID's
09-Feb-26
09-Feb-26
—
100%
EK000YA824
(EP-23) Issue For Planning (IPL) >90% ISBL P&ID's
09-Feb-26
09-Feb-26
—
100%
PK000I352H
SIS - Fabricate Hardware
10-Feb-26
27-Dec-26
—
23%
EK01BPI050
01B Model Comment Resolution Approval
10-Feb-26
14-Feb-26
—
100%
PK000MJ38E
Technical Evaluation - MJ308
10-Feb-26
27-Mar-26
—
100%
PK05AMF05
05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract)
11-Feb-26
27-Dec-26
—
23%
EK000MU11E
05B MU311 Prepare & Issue Purchase ERW
11-Feb-26
13-Feb-26
—
100%
EK01EIC120
01E Instrument Detail Model / Review
11-Feb-26
01-Mar-26
—
100%
PK000MF32D
05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK05AMF33
05A MF312 2105-F - Piping Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK05AMF34
05A MF312 2105-F - Civil Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK05AMF35
05A MF312 2105-F - E&I Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
—
100%
PK000PS00D
000 SP Items - Eval Bids / Issue Recmd
11-Feb-26
18-Feb-26
—
100%
EK000PS00C
000 SP Items - Technical Evaluation
11-Feb-26
01-Mar-26
—
100%
EK01DPI050
01D Model Comment Resolution Approval
12-Feb-26
13-Feb-26
—
100%
PK000I1100
020 Orific Plates - Fabricate/Exworks
13-Feb-26
27-Dec-26
—
22%
PK000MU11K
05B MU311 - Fabricate/PO Promise HYDROCHLORIC ACID STORAGE
13-Feb-26
27-Dec-26
—
22%
PK000MU11P
05B MU311 Issue Formal P.O.
13-Feb-26
13-Feb-26
—
100%
PK000MU11N
05B MU311 Recv. Planning V. Data
13-Feb-26
28-Feb-26
—
100%
PK000I444K
Issue Formal Purchase Order - Shelters/ Analyzers
17-Feb-26
17-Feb-26
—
100%
PK010E008B
540-SB Admin. Area Pwr Supply - Inquiry REQ/RFQ
17-Feb-26
20-Feb-26
—
100%
PK000MJ71G
Issue MJ731 RFQ
17-Feb-26
10-Mar-26
—
100%
EK000I444B
Develop Final Design Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
—
100%
EK000I444M
Develop Final Deign Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
—
100%
EK000E004A
UPS System - Issue ERW
17-Feb-26
28-Mar-26
—
100%
EK03DPI050
03D Model Comment Resolution Approval
18-Feb-26
06-Mar-26
—
100%
EK000E001D
Sub Stations - Tech Evaluation
19-Feb-26
27-Dec-26
—
21%
PK000PS00E
000 SP Items - Final Negotiation / Interim Award
19-Feb-26
27-Dec-26
—
21%
PK010E008C
540-SB Admin. Area Pwr Supply - Receive Bids
20-Feb-26
03-Apr-26
—
100%
PK000MU25I
02G MU225 Eval Bids & Issue Recmd
21-Feb-26
18-Mar-26
—
100%
EK000CS027
Turnover System Definition for OSBL
25-Feb-26
27-Dec-26
—
19%
EK000I444F
Planning V. Data - Shelters/ Analyzers
25-Feb-26
27-Dec-26
—
19%
PK000I352J
SIS - Planning V. Data
25-Feb-26
27-Dec-26
—
19%
PK000I354J
ITCC - Planning V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV04
05A ML501 2103-L - Piping Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV05
05A ML501 2103-L - Civil Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV06
05A ML501 2103-L - E&I Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
EK000MJ38T
Update/Issue Formal Inquiry for ERW - MJ308
25-Feb-26
03-Mar-26
—
100%
EK000ML50E
Prepare & Issue Purchase ERW - ML500
25-Feb-26
08-Mar-26
—
100%
EK000YA831
(EP-26) Complete Hazard Review Meeting on >90% ISBL P&ID's
25-Feb-26
25-Feb-26
—
100%
EK000MJ39E
Prepare & Issue Purchase ERW - MJ391
27-Feb-26
09-Apr-26
—
100%
PK000MB68J
Final Negotiate/Interim Award - MB692
27-Feb-26
03-Mar-26
—
100%
EK000I3541
ITCC - Develop Purchase T-Req
27-Feb-26
05-Mar-26
—
100%
PK000MB68K
MB692 - Fabricate/PO Promise 101-B Cat Vacuum Equip.
03-Mar-26
27-Dec-26
—
17%
PK000MB68P
Issue Formal P.O. for MB692
03-Mar-26
06-Mar-26
—
100%
PK000MU29I
Eval Bids & Issue Recmd MU292
03-Mar-26
19-Mar-26
—
100%
EK030I131A
Develop / Issue Purchase ERW -Transmitter OSBL
04-Mar-26
27-Dec-26
—
17%
EK000E002D
Transformer - Tech Evaluation
04-Mar-26
27-Dec-26
—
17%
PK000E002E
Transformer - Eval Bids/Issue Recmd
04-Mar-26
27-Dec-26
—
17%
PK000MB21F
Marshaling of Equip. 101-B Siding for MB212
04-Mar-26
27-Dec-26
—
17%
EK000YA826
(EP-27) Begin Issuing Area Line Installation Details (IDF Files)
04-Mar-26
04-Mar-26
—
100%
EK03CPI050
03C Model Comment Resolution Approval
05-Mar-26
07-Mar-26
—
100%
PK000I3540
ITCC - Vendor Update Pricing / Quote
06-Mar-26
29-Mar-26
—
100%
EK000I221F
000 Everest Control Valves - Purchase ERW
11-Mar-26
27-Dec-26
—
15%
EK010I1211
Vortex Meters - Purchase ERW
11-Mar-26
27-Dec-26
—
15%
PK000MJ71H
Receive Quotes MJ731
11-Mar-26
05-Apr-26
—
100%
PK000ML43S
ML430 - Marshaling 110-L BENFIELD MIXER
11-Mar-26
27-Dec-26
—
15%
PK05BMU06
05B MU311 2109-LA/LB, 2110-L - Piping Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
PK05BMU07
05B MU311 2109-LA/LB, 2110-L - Civil Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
PK000MJ39J
Final Negotiate/Interim Award - MJ391/MJ392
14-Mar-26
17-Mar-26
—
100%
PK03BMU100
03B Recv. Planning V. Data - Utility Equip. 2401-J/JA
15-Mar-26
31-Mar-26
—
100%
PK000MJ39P
Issue Formal P.O. for MJ391/MJ392
17-Mar-26
27-Dec-26
—
13%
EK050PI006
Site Data Needed - Loading Area (SPDC)
18-Mar-26
27-Dec-26
—
13%
PK000MJ39K
Fabricate/Exworks FIREWATER PUMPS
18-Mar-26
10-Jan-27
60.0d
12%
PK01BMJV04
01B MJ391 2204-J/JA - Piping Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK01BMJV05
01B MJ391 2204-J/JA - Civil Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK01BMJV06
01B MJ391 2204-J/JA - E&I Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV07
05A MJ392 2105-JA/JB - Piping Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV08
05A MJ392 2105-JA/JB - Civil Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV09
05A MJ392 2105-JA/JB - E&I Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK000MU25J
02G MU225 Final Negotiate/Interim Award
19-Mar-26
27-Dec-26
—
13%
PK000MU29K
MU292 - Fabricate/PO Promise 2404-L
19-Mar-26
27-Dec-26
—
13%
PK03BMUV04
03B MU292 2404-L - Piping Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
PK03BMUV05
03B MU292 2404-L - Civil Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
PK03BMUV06
03B MU292 2404-L - E&I Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
PK000MU29J
Final Negotiate/Interim Award - MU292
19-Mar-26
19-Mar-26
—
100%
PK000MU29P
Issue Formal P.O. for MU292
19-Mar-26
31-Mar-26
—
100%
PK000MU29N
Recv. Planning V. Data MU292
19-Mar-26
09-Apr-26
—
100%
EK030I616A
Develop / Issue Purchase ERW - Steam Drum Lvl Gauges - OSBL
22-Mar-26
27-Dec-26
—
12%
EK03CIC120
03C Instrument Detail Model / Review
22-Mar-26
18-Apr-26
—
100%
EK000MU29E
Prepare & Issue Purchase ERW - MU292
24-Mar-26
27-Mar-26
—
100%
PK000MU32J
01D MU322 Final Negotiate/Interim Award
24-Mar-26
31-Mar-26
—
100%
PK020IC210
020 Control Valves - Fabricate/Exworks
27-Mar-26
27-Dec-26
—
10%
PK000E004B
UPS System - Inquiry REQ/RFQ
27-Mar-26
08-Apr-26
—
100%
PK000MJ38B
Eval Bids & Issue Recmd MJ308
27-Mar-26
23-Apr-26
—
100%
PK010IC210
010 Control Valves - Fabricate/Exworks
28-Mar-26
27-Dec-26
—
10%
PK030IC210
030 Control Valves - Fabricate/Exworks
28-Mar-26
27-Dec-26
—
10%
EK020FP460
FP Electrical Area Classification OSBL - IFC
31-Mar-26
27-Dec-26
—
9%
PK01DMUV07
01D MU322 2210-L,2211-L - Piping Prod. V. Data
31-Mar-26
27-Dec-26
—
9%
PK01DMUV09
01D MU322 2210-L,2211-L - E&I Prod. V. Data
31-Mar-26
27-Dec-26
—
9%
EK000MU32E
01D MU322 Prepare & Issue Purchase ERW
31-Mar-26
31-Mar-26
—
100%
PK000MBP3Z
MB311 - Shop Recv - 101-B Radiant Tube & Pipe
31-Mar-26
31-Mar-26
—
100%
PK01DMUV08
01D MU322 2210-L,2211-L - Civil Prod. V. Data
31-Mar-26
01-Apr-26
—
100%
PK000ML90J
Final Negotiate/Interim Award - ML900
31-Mar-26
02-Apr-26
—
100%
EK000I3521
SIS - Develop Purchase T-Req
31-Mar-26
03-Apr-26
—
100%
PK000MU32P
01D MU322 Issue Formal P.O.
31-Mar-26
22-Apr-26
—
100%
EK000MU25E
02G MU225 Prepare & Issue Purchase ERW
01-Apr-26
27-Dec-26
—
9%
EK010I1151
Annubars - Purchase ERW
01-Apr-26
27-Dec-26
—
9%
EK030I623A
Develop / Issue Purchase ERW -Multi-Point Thermocouples - OSBL
01-Apr-26
27-Dec-26
—
9%
PK000ML42S
ML420 - Marshaling CARTRIDGE FILTERS
01-Apr-26
27-Dec-26
—
9%
PK05AMB46
05A MB710 2202-B/BL - Piping Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK05AMB47
05A MB710 2202-B/BL - Civil Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK05AMB48
05A MB710 2202-B/BL - E&I Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
EK000I3542
ITCC - Final Tech Evaluation for Purchase
01-Apr-26
03-Apr-26
—
100%
EK000I444C
Develop / Issue T-Req - Shelters/ Analyzers
01-Apr-26
03-Apr-26
—
100%
EK01YIC120
01Y Instrument Detail Model / Review
01-Apr-26
10-Apr-26
—
100%
PK000PIA1H
Bulk Piping A/G & U/G - Transport / Delivery (First CS,SS,U/G)
01-Apr-26
27-Dec-26
—
9%
PK000MB61L
Marshaling of 101-B Burners MB610
02-Apr-26
27-Dec-26
—
8%
PK000MU32K
01D MU322 - Fabricate/PO Promise COOLING WTR FILTER & CLARIFIER
02-Apr-26
27-Dec-26
—
8%
PK000ML90K
ML900 - Fabricate/PO Promise Evap. Pond Spray Nzl.
02-Apr-26
27-Dec-26
—
8%
PK01AMLV01
01A ML900 2408-LA,LB,LC,LD - Piping Prod. V. Data
02-Apr-26
27-Dec-26
—
8%
PK01AMLV02
01A ML900 2408-LA,LB,LC,LD - Civil Prod. V. Data
02-Apr-26
27-Dec-26
—
8%
PK01AMLV03
01A ML900 2408-LA,LB,LC,LD - E&I Prod. V. Data
02-Apr-26
27-Dec-26
—
8%
PK000ML90P
Issue Formal P.O. for ML900
02-Apr-26
15-Apr-26
—
100%
PK000MBP3X
MB311 - Shop Recv - 101-B Convection Fittings
02-Apr-26
15-Apr-26
—
100%
EK010E008D
540-SB Admin. Area Pwr Supply - Tech Evaluation
03-Apr-26
27-Dec-26
—
8%
EK05BEL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK05BEL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
PK000E00C
UPS System - Receive Bids
07-Apr-26
27-Dec-26
—
6%
EK030I621A
Develop / Issue Purchase ERW - Temperature Elements - OSBL
08-Apr-26
27-Dec-26
—
6%
EK01API050
01A Model Comment Resolution Approval
08-Apr-26
17-Apr-26
—
100%
PK000MC61F
MC610 - Marshaling DBL PIPE EXCH 161-C
10-Apr-26
27-Dec-26
—
5%
PK000I444D
Vendor Update Pricing - Shelters/ Analyzers
15-Apr-26
27-Dec-26
—
5%
PK000MB83S
MB630 - Marshaling 101-B Air Preheater
15-Apr-26
27-Dec-26
—
5%
PK000MU61S
MU611 - Marshaling 2101-U, 2101-UJA Thru UJG CW TWR & Fans
15-Apr-26
27-Dec-26
—
5%
PK000MU61U
MU611 - Marshaling 2101-UJA Thru UJGM CW Motors
15-Apr-26
27-Dec-26
—
5%
PK000I3521
SIS - Vendor Provides Software & Workstations
16-Apr-26
27-Dec-26
—
5%
PK010I1210
Vortex Meters - Fabricate/Exworks
16-Apr-26
27-Dec-26
—
5%
EK000I3523
SIS - Software Programming by KBR
18-Apr-26
27-Dec-26
—
5%
EK030I611A
Develop / Issue Purchase ERW - Pressure Gauges - OSBL
22-Apr-26
27-Dec-26
—
5%
EK05AIC120
05A Instrument Detail Model / Review
22-Apr-26
27-Dec-26
—
5%
PK000I3520
SIS - Vendor Update Pricing / Quote
22-Apr-26
27-Dec-26
—
5%
PK010I1100
010 Orific Plates - Fabricate/Exworks
22-Apr-26
27-Dec-26
—
5%
EK000MJ38C
Prepare & Issue Purchase ERW - MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38M
Final Negotiate/Interim Award - MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38R
Issue Formal P.O. for MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38T
Recv. Planning V. Data MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38U
MJ308 - Fabricate/PO Promisse ISBL ANSI/API PUMPS
23-Apr-26
10-Jan-27
198.0d
5%
PK01AMJV01
01A MJ308 2408-JA/JB - Piping Prod. V. Data
23-Apr-26
27-Dec-26
—
5%
PK01AMJV02
01A MJ308 2408-JA/JB - Civil Prod. V. Data
23-Apr-26
27-Dec-26
—
5%
PK01AMJV03
01A MJ308 2408-JA/JB - E&I Prod. V. Data
23-Apr-26
27-Dec-26
—
5%
PK000MU35S
MU350 - Marshaling 101-U DEAERATOR
24-Apr-26
27-Dec-26
—
5%
EK000CV146
Receive Site Survey Data Areas 04 & 05
27-Dec-26
27-Dec-26
—
0%
EK000E004D
UPS System - Tech Evaluation
27-Dec-26
27-Dec-26
—
0%
EK000ELEG0
Electrical Heat Tracing - ERW Package
27-Dec-26
27-Dec-26
—
0%
EK000FP060
FP Overall Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
—
0%
EK000FP065
FP Overall Firewater P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
—
0%
EK000GE030
Production Check Estimate
27-Dec-26
27-Dec-26
—
0%
EK000I3522
SIS - Final Tech Evaluation for Purchase
27-Dec-26
27-Dec-26
—
0%
EK000I352M
SIS - Review / Approve V. Data
27-Dec-26
27-Dec-26
—
0%
EK000I354M
ITCC - Review / Approve V. Data
27-Dec-26
27-Dec-26
—
0%
EK000I444E
Final Tech Evaluation - Shelters/ Analyzers
27-Dec-26
27-Dec-26
—
0%
EK000I444G
Review / Approve V. Data - Shelters/ Analyzers
27-Dec-26
27-Dec-26
—
0%
EK000YA832
(EP-32) Issue OSBL (Units01/03) found./UG pipe work package
27-Dec-26
27-Dec-26
—
0%
EK000YA833
(EP-33) Issue > 90% ISBL Civil Foundations
27-Dec-26
27-Dec-26
—
0%
EK000YA839
(EP-35) Issue >90% OSBL P&ID's For Construction (IFC)
27-Dec-26
27-Dec-26
—
0%
EK000YA841
(EP-29) Issue OSBL Plot Plan for Construction (IFC)
27-Dec-26
27-Dec-26
—
0%
EK000YA848
(EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC)
27-Dec-26
27-Dec-26
—
0%
EK000YA888
(TLA-02) Second TLA Payment
27-Dec-26
27-Dec-26
—
0%
EK010FP040
FP Firewater Pump P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
—
0%
EK01AIC120
01A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01API144
01A OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01BIC120
01B Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01BPI144
01B OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01CIC120
01C Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01CPI143
01C OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01DIC120
01D Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01DPI144
01D OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01HIC120
01H Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01JIC120
01J Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01JPI050
01J Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01JPI143
01J Op's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01YPI143
01Y OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK020ELEG5
Cathodic Protection - Design & Specs Package (By Consultant)
27-Dec-26
27-Dec-26
—
0%
EK03AIC120
03A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03API050
03A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03API143
03A OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03BIC120
03B Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03BPI050
03B Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03BPI143
03B OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03CPI143
03C OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03DIC120
03D Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03DPI145
03D OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03EIC120
03E Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03EPI050
03E Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03EPI144
03E OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03FIC120
03F Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03FPI050
03F Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03FPI144
03F OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03YIC120
03Y Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03YPI050
03Y Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03YPI144
03Y OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK04AIC120
04A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK05API050
05A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK05API144
05A OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK05BPI035
05B Plot Plan
27-Dec-26
27-Dec-26
—
0%
EM03YPI021
03Y Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
PK0003525
SIS - Ship to DCS Shop/ Setup
27-Dec-26
27-Dec-26
—
0%
PK0003526
SIS - Integrated FAT
27-Dec-26
27-Dec-26
—
0%
PK000E001E
Sub Stations - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
—
0%
PK000E001G
Sub Stations - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK000E001J
Sub Stations - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E001K
Sub Stations - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK000E001M
Sub Stations - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E002G
Transformer - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK000E002J
Transformer - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E002K
Transformer - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK000E002M
Transformer - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E004E
UPS System - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
—
0%
PK000E004G
UPS System - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK000E004J
UPS System - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E004K
UPS System - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK000E004M
UPS System - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK000I1103
020 Orific Plates - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK000I1161
020 Wedge Flow Meters - Fabricate/Exworks
27-Dec-26
27-Dec-26
—
0%
PK000I1162
020 Wedge Flow Meters - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK000I1221
Coriolis Meters - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK000I1270
Fabricate/Exworks Magnetic Flow Meters
27-Dec-26
27-Dec-26
—
0%
PK000I1271
Transport & Deliver Magnetic Flow Meters
27-Dec-26
27-Dec-26
—
0%
PK000I3522
SIS - FAT Test
27-Dec-26
27-Dec-26
—
0%
PK000I3523
SIS - Cleanup / Changes
27-Dec-26
27-Dec-26
—
0%
PK000I3542
ITCC - Software Programming by Vendor
27-Dec-26
27-Dec-26
—
0%
PK000I3543
ITCC - FAT Test
27-Dec-26
27-Dec-26
—
0%
PK000I3544
ITCC - Cleanup / Changes
27-Dec-26
27-Dec-26
—
0%
PK000I354P
ITCC - Ship to DCS Shop/ Setup
27-Dec-26
27-Dec-26
—
0%
PK000I354Q
ITCC - Integrated FAT
27-Dec-26
27-Dec-26
—
0%
PK000I444H
Fabricate - Shelters/ Analyzers
27-Dec-26
27-Dec-26
—
0%
PK000I611H
Fabricate / Exworks - Pressure Gauges - ISBL
27-Dec-26
27-Dec-26
—
0%
PK000I616H
Fabricate / Exworks - Steam Drum Lvl Gauges
27-Dec-26
27-Dec-26
—
0%
PK000I616N
Transport & Deliver - Steam Drum Lvl Gauges
27-Dec-26
27-Dec-26
—
0%
PK000I617H
Fabricate / Exworks - Magnetic Lvl Gauges
27-Dec-26
27-Dec-26
—
0%
PK000IC352
DCS - FAT Test
27-Dec-26
27-Dec-26
—
0%
PK000IC353
DCS - Cleanup / Changes
27-Dec-26
27-Dec-26
—
0%
PK000IC355
DCS - ITCC / SIS / DCS - Integrated FAT
27-Dec-26
27-Dec-26
—
0%
PK000IC35M
DCS - Review / Approve V. Data
27-Dec-26
27-Dec-26
—
0%
PK000MB21O
Transport & Deliver of Equip. 101-B Siding
27-Dec-26
27-Dec-26
—
0%
PK000MB33O
MB333 - Transport/Customes Equip. 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB33S
MB333 - Marshaling Riser Transition 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB34Z
Shop Recv.- 101-B Finned Convection Tubes & Pipe
27-Dec-26
27-Dec-26
—
0%
PK000MB41Z
Shop Recv. - 101-B Cast Tube Supports
27-Dec-26
27-Dec-26
—
0%
PK000MB42O
MB420 - Transport to Vendor 101-B Cast Peep Sites
27-Dec-26
27-Dec-26
—
0%
PK000MB61O
Transport & Deliver 101-B Burners
27-Dec-26
27-Dec-26
—
0%
PK000MB63O
MB630 - Transport/Customes 101-B Air Preheater
27-Dec-26
27-Dec-26
—
0%
PK000MB64O
MB640 - Transport/Customes 101-B Springs & Hangers
27-Dec-26
27-Dec-26
—
0%
PK000MB64S
MB640 - Marshaling 101-B Springs & Hangers
27-Dec-26
27-Dec-26
—
0%
PK000MB65O
MB622 - Transport/Customes 101-B Penthouse Circ Fans
27-Dec-26
27-Dec-26
—
0%
PK000MB65S
MB622 - Marshaling 101-B Penthouse Circ Fans
27-Dec-26
27-Dec-26
—
0%
PK000MB66O
MB660 - Transport/Customes 101-B Dampers & Air Doors
27-Dec-26
27-Dec-26
—
0%
PK000MB66S
MB660 - Marshaling 101-B Dampers & Air Doors
27-Dec-26
27-Dec-26
—
0%
PK000MB68O
MB692 - Transport/Customes 101-B Cat Vacuum Equip.
27-Dec-26
27-Dec-26
—
0%
PK000MB68S
MB692 - Marshaling 101-B Cat Vacuum Equip.
27-Dec-26
27-Dec-26
—
0%
PK000MB69O
MB691 - Transport/Customes of Equip. 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB69S
MB691 - Marshaling 101-B for MB691
27-Dec-26
27-Dec-26
—
0%
PK000MB81O
MB810 - Transport & Deliver of Equip. 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB81S
MB810 - Marshaling 102-B
27-Dec-26
27-Dec-26
—
0%
PK000MBP1C
MB221 - Marshaling 101-B Convection Modules
27-Dec-26
27-Dec-26
—
0%
PK000MBP1M
MB221 - Transport/Customes 101-B Radiant Steel Panels
27-Dec-26
27-Dec-26
—
0%
PK000MBP1T
MB221 - Fab/PO Promise 101-B Crossover Pipe
27-Dec-26
27-Dec-26
—
0%
PK000MBP1U
MB221 - Transport/Customes 101-B Radiant Harps
27-Dec-26
27-Dec-26
—
0%
PK000MBP1V
MB221 - Transport/Customes 101-B Convection Modules
27-Dec-26
27-Dec-26
—
0%
PK000MBP1X
MB221 - Transport/Customes 101-B Radiant Ducting
27-Dec-26
27-Dec-26
—
0%
PK000MBP1Y
MB221 - Transport/Customes 101-B Crossover
27-Dec-26
27-Dec-26
—
0%
PK000MBP2C
MB221 - Marshaling 101-B Crossover
27-Dec-26
27-Dec-26
—
0%
PK000MBP3C
MB221 - Marshaling 101-B Radiant Ducting
27-Dec-26
27-Dec-26
—
0%
PK000MBP3V
MB311 - Shop Recv - 101-B Crossover Tube & Pipe
27-Dec-26
27-Dec-26
—
0%
PK000MBP3W
MB311 - Shop Recv - 101-B Crossover Fittings
27-Dec-26
27-Dec-26
—
0%
PK000MBP4C
MB221 - Marshaling 101-B Radiant Coil/Harps
27-Dec-26
27-Dec-26
—
0%
PK000MBP4O
MB312 - Transport/Customes 101-B Radiant Cast Stringer Grids
27-Dec-26
27-Dec-26
—
0%
PK000MBP4S
MB312 - Transport/Customes 101-B Radiant Cast Tube/Riser/Manifold
27-Dec-26
27-Dec-26
—
0%
PK000MBP4T
MB312 - Shop Recv. 101-B Radiant Cast Stringer Grids
27-Dec-26
27-Dec-26
—
0%
PK000MBP4U
MB312 - Shop Recv. 101-B Radiant Cast Tube/Riser/Manifold
27-Dec-26
27-Dec-26
—
0%
PK000MBP5C
MB221 - Marshaling 101-B Radiant Steel Panels
27-Dec-26
27-Dec-26
—
0%
PK000MC21O
MC210 - Transport/Customes 110/115/124/128/130/133/134/160/167/173/174-C
27-Dec-26
27-Dec-26
—
0%
PK000MC21R
MC210 - Marshaling 127-C
27-Dec-26
27-Dec-26
—
0%
PK000MC21S
MC210 - Marshaling 110/115/124/128/130/133/134/160/167/173/174-C
27-Dec-26
27-Dec-26
—
0%
PK000MC21T
MC210 - Transport/Customes 127-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23B
MC230 - Marshaling 106-C & 109-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23C
MC230 - Transport/Customes 106-C & 109-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23O
MC230 - Transport/Customes 105/172/183-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23R
MC230 - Marshaling 111/114-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23S
MC230 - Marshaling 105/172/183-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23T
MC230 - Transport/Customes 114-C
27-Dec-26
27-Dec-26
—
0%
PK000MC61O
MC610 - Transport/Customes DBL PIPE EXCH 188-CA
27-Dec-26
27-Dec-26
—
0%
PK000MC61Q
MC610 - Transport/Customes DBL PIPE EXCH 161-C
27-Dec-26
27-Dec-26
—
0%
PK000MC61S
MC610 - Marshaling DBL PIPE EXCH 188-CA
27-Dec-26
27-Dec-26
—
0%
PK000MD22B
MD202 - Marshaling TOWERS 104-E
27-Dec-26
27-Dec-26
—
0%
PK000MD22C
MD202 - Transport/Customes TOWERS 104-E
27-Dec-26
27-Dec-26
—
0%
PK000MD22O
MD202 - Transport/Customes TOWERS 103/105-E
27-Dec-26
27-Dec-26
—
0%
PK000MD22S
MD202 - Marshaling TOWERS 103/105-E
27-Dec-26
27-Dec-26
—
0%
PK000MD42A
MD402 -Marshaling 144-F
27-Dec-26
27-Dec-26
—
0%
PK000MD42B
MD402 - Transport/Customes 144-F
27-Dec-26
27-Dec-26
—
0%
PK000MD42R
MD402 - Transport/Customes 104-F
27-Dec-26
27-Dec-26
—
0%
PK000MD42T
MD402 -Marshaling 104-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44M
MD404 - Marshaling 107-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44N
MD404 - Transport/Customes 107-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44O
MD404 - Transport/Customes 109-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44S
MD404 - Marshaling 109-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45B
MD405 - Marshaling ISBL DRUMS - 115-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45C
MD405 - Transport/Customes ISBL DRUMS - 115-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45O
MD405 - Transport/Customes ISBL DRUMS - 156-F & 157-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45S
MD405 - Marshaling ISBL DRUMS - 156-F & 157-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45T
MD405 - Transport/Customes ISBL DRUMS - 118-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46O
MD411 - Transport/Customes OSBL DRUMS - 2203-F & 2204-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46S
MD411 - Marshaling OSBL DRUMS - 2203-F & 2204-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46U
MD411 - Marshaling OSBL DRUMS - 2006-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46V
MD411 - Transport/Customes OSBL DRUMS - 2006-F
27-Dec-26
27-Dec-26
—
0%
PK000MD47O
MD406 - Transport/DCustomes ISBL DRUMS
27-Dec-26
27-Dec-26
—
0%
PK000MD47S
MD406 - Marshaling ISBL DRUMS 103-F
27-Dec-26
27-Dec-26
—
0%
PK000MD51O
MD501 - Transport/Customes 107-D
27-Dec-26
27-Dec-26
—
0%
PK000MD51S
MD501 - Marshaling 107-D
27-Dec-26
27-Dec-26
—
0%
PK000MDR
MD405 - Marshaling ISBL DRUMS - 118-F
27-Dec-26
27-Dec-26
—
0%
PK000MJ21O
MJ202 - Transport/Customes 102/3/5-J
27-Dec-26
27-Dec-26
—
0%
PK000MJ21S
MJ202 - Marshaling 102/3/5-J
27-Dec-26
27-Dec-26
—
0%
PK000MJ37O
MJ340 - Transport/Customes METERING PUMPS
27-Dec-26
27-Dec-26
—
0%
PK000MJ37S
MJ340 - Marshaling METERING PUMPS
27-Dec-26
27-Dec-26
—
0%
PK000MJ71I
Eval Bids & Issue Recmd MJ731
27-Dec-26
27-Dec-26
—
0%
PK000MJ71J
Final Negotiate/Interim Award - MJ731
27-Dec-26
27-Dec-26
—
0%
PK000MJ71P
Issue Formal P.O. for MJ731
27-Dec-26
27-Dec-26
—
0%
PK000MJ75O
MJ750 - Transport/Customes SURFACE CONDENSORS
27-Dec-26
27-Dec-26
—
0%
PK000MJ75S
MJ750 - Marshaling SURFACE CONDENSORS
27-Dec-26
27-Dec-26
—
0%
PK000ML33O
ML330 - Transport/Customes 2101-L
27-Dec-26
27-Dec-26
—
0%
PK000ML33S
ML330 - Marshaling 2101-L
27-Dec-26
27-Dec-26
—
0%
PK000ML42O
ML420 - Transpor/Customes CARTRIDGE FILTERS
27-Dec-26
27-Dec-26
—
0%
PK000ML43O
ML430 - Transport/Customes 110-L BENFIELD MIXER
27-Dec-26
27-Dec-26
—
0%
PK000ML51O
ML512 - Transport/Customs 2102-L LOADING ARM
27-Dec-26
27-Dec-26
—
0%
PK000ML51S
ML512 - Marshaling 2102-L LOADING ARM
27-Dec-26
27-Dec-26
—
0%
PK000MU11S
05B MU311 - Marshaling HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
—
0%
PK000MU21O
MU221 - Transport/Customs LIFT STATION
27-Dec-26
27-Dec-26
—
0%
PK000MU21S
MU221 - Marshaling LIFT STATION
27-Dec-26
27-Dec-26
—
0%
PK000MU22O
MU222 - Transport/Customes .2401-U
27-Dec-26
27-Dec-26
—
0%
PK000MU22S
MU222 - Marshaling 2401-U
27-Dec-26
27-Dec-26
—
0%
PK000MU25K
MU225 - 02G Fabricate/PO Promise LIFT STATION
27-Dec-26
27-Dec-26
—
0%
PK000MU25P
02G MU225 Issue Formal P.O.
27-Dec-26
27-Dec-26
—
0%
PK000MU311
05B MU311 Transport/Customes BULK CHEM. STORAGE TANKS
27-Dec-26
27-Dec-26
—
0%
PK000MU35O
MU350 - Transport/Customes 101-U DEAERATOR
27-Dec-26
27-Dec-26
—
0%
PK000MU41O
MU410 - Transport/Customes 2002-U PKG BOILER
27-Dec-26
27-Dec-26
—
0%
PK000MU41S
MU410 - Marshaling 2002-U PKG BOILER
27-Dec-26
27-Dec-26
—
0%
PK000MU61O
MU611 - Transport/Customes 2101-U, 2101-UJA Thru UJG CW TWR & Fans
27-Dec-26
27-Dec-26
—
0%
PK000PIA1J
Bulk Piping A/G & U/G - Receive at Site FIRST (CS,SS,U/G)
27-Dec-26
27-Dec-26
—
0%
PK000PIA1L
Bulk Piping A/G - Transport / Delivery (CROME)
27-Dec-26
27-Dec-26
—
0%
PK000PIA1M
Bulk Piping A/G - Receive at Site (CHROME)
27-Dec-26
27-Dec-26
—
0%
PK000PIA4H
Product Line Piping - Transport / Delivery to Insulation Shop
27-Dec-26
27-Dec-26
—
0%
PK000PIA4I
Product Line Piping - Insulation Fab/Exworks
27-Dec-26
27-Dec-26
—
0%
PK000PIA4J
Product Line Piping - Receive at Site
27-Dec-26
27-Dec-26
—
0%
PK000PIA4K
Product Line Piping - Transport / Delivery
27-Dec-26
27-Dec-26
—
0%
PK000PIA4L
Product Line Piping - Fab/Exworks Remaining +/- 1500 Mts.
27-Dec-26
27-Dec-26
—
0%
PK000PS00F
000 SP Items - Issue Formal Blanket P.O.
27-Dec-26
27-Dec-26
—
0%
PK010E008F
540-SG Admin. Area Pwr Supply - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
—
0%
PK010E008G
540-SG Admin. Area Pwr Supply - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK010E008H
540-SG Admin. Area Pwr Supply - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK010E008J
540-SG Admin. Area Pwr Supply - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK010E008L
540-SG Admin. Area Pwr Supply - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK010I1103
010 Orific Plates - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK010I1105
010 Orific Plates - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK01DMU61Z
01D Recv. at Site - 2101-U, 2101-UJA Thru UJG CW TWR & Fans
27-Dec-26
27-Dec-26
—
0%
PK01FMU21Z
01E Recv. at Site - 2402-L Lift Station
27-Dec-26
27-Dec-26
—
0%
PK01GMU21Z
01E Recv. at Site - Lift Station
27-Dec-26
27-Dec-26
—
0%
PK020I131H
Fabricate / Exworks - Transmitters -Press.
27-Dec-26
27-Dec-26
—
0%
PK020IC214
020 Control Valves - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK02FMU11Z
05B MU311 Recv. at Site - 2109-LA HYDROCHLORIC ACID STORAGE TANK A
27-Dec-26
27-Dec-26
—
0%
PK02GMU11Z
05B MU311 Recv. at Site - 2109-LB HYDROCHLORIC ACID STORAGE TANK B
27-Dec-26
27-Dec-26
—
0%
PK02LMU11Z
05B MU311 Recv. at Site - 2110-L SODIUM HYDROCHLORITE STORAGE
27-Dec-26
27-Dec-26
—
0%
PK030I1100
Orific Plates - Fabricate/Exworks
27-Dec-26
27-Dec-26
—
0%
PK030IC214
030 Control Valves - Transport & Delivery
27-Dec-26
27-Dec-26
—
0%
PK030IC220
030 Control Valves - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK03BMU22Z
03B Recv. at Site - 2401-U Sanitary Treatment Pkg
27-Dec-26
27-Dec-26
—
0%
PK03CMD46Z
03C Recv. at Site - 2203-F & 2204-F Caustic Tank/ Acid Drum
27-Dec-26
27-Dec-26
—
0%
PK03FMD46Z
03F Recv. at Site - 2006-F Boiler Blowdown Drum
27-Dec-26
27-Dec-26
—
0%
PK03FMU11Z
05B MU311 Recv. at Site - 2109-L HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
—
0%
PK03FMU41Z
03F Recv. at Site - 2002-U Package Boiler
27-Dec-26
27-Dec-26
—
0%
PK050I1105
050 Orfice Plates - Recv on Site Dock/Storage Area
27-Dec-26
27-Dec-26
—
0%
PK05AMF25
05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract)
27-Dec-26
27-Dec-26
—
0%
PK05AMJV10
05A MJ731 2108-J - Civil Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK05AMJV11
05A MJ731 2108-J - E&I Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK05AML33Z
05A Recv. at Site - 2101-L Ammonia Refrigeration Pkg
27-Dec-26
27-Dec-26
—
0%
PK05BML51Z
05B Recv. at Site - 2102-L Loading Arm
27-Dec-26
27-Dec-26
—
0%
ZZ1020
01D Recv. at Site - 2101-UJA Thru UJGM CW Motors
27-Dec-26
27-Dec-26
—
0%
ZZ1040
MU611 - Transport/Customes 2101-UJA Thru UJGM CW Motors
27-Dec-26
27-Dec-26
—
0%
EK000YA500
Issue ISBL Paint & Insulation Work Package
28-Dec-26
08-Mar-27
750.0d
0%
EK000ELEGP
Electrical Heat Tracing - Design & BOM by Consultant
30-Dec-26
30-Jan-27
91.0d
0%
EK000ELEN1
01,03,04 LV Wiring Diagrams - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN2
01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN3
01,03, Equipment Interconnection Diagrams - IFC
30-Dec-26
30-Jan-27
511.0d
0%
EK020ELEG6
Cathodic Protection - Material Supply (By Consultant)
30-Dec-26
02-May-27
6.0d
0%
EK05ACV200
05A Redesign Piling & Ammonia Tank Foundations
30-Dec-26
10-Jan-27
-44.0d
0%
EK05BIC120
05B Instrument Model
30-Dec-26
30-Dec-26
110.0d
0%
PK000E001H
Sub Stations - Fab / Exworks
30-Dec-26
28-Feb-27
62.0d
0%
PK000E002H
Transformer - Fab / Exworks
30-Dec-26
04-Feb-27
28.0d
0%
PK000E004H
UPS System - Fab / Exworks
30-Dec-26
05-Feb-27
27.0d
0%
PK000I1121
020 Venturis - Fabricate/Exworks
30-Dec-26
30-Dec-26
509.0d
0%
PK000I2300
On/Off Valves - Fabricate/Exworks
30-Dec-26
07-Feb-27
460.0d
0%
PK000I3524
SIS - Packing / Exworks
30-Dec-26
10-Jan-27
55.0d
0%
PK000I3545
ITCC - Packing / Exworks
30-Dec-26
10-Jan-27
55.0d
0%
PK000I4440
FAT Test - Shelters/ Analyzers
30-Dec-26
10-Jan-27
161.0d
0%
PK000I611N
Transport & Deliver - Pressure Gauges - ISBL
30-Dec-26
03-Jan-27
110.0d
0%
PK000I612H
Fabricate / Exworks - Differential Pressure Gauges
30-Dec-26
18-Feb-27
28.0d
0%
PK000I617N
Transport & Deliver - Magnetic Lvl Gauges
30-Dec-26
13-Jan-27
104.0d
0%
PK000I621H
Fabricate / Exworks - Temperature Elements
30-Dec-26
13-Mar-27
31.0d
0%
PK000I623H
Fabricate / Exworks - Multi-Point Thermocouples
30-Dec-26
30-Dec-26
84.0d
0%
PK000IC354
DCS - Packing / Exworks
30-Dec-26
30-Dec-26
85.0d
0%
PK000IC35N
DCS - Transport (Hold for Field Request)
30-Dec-26
07-Feb-27
85.0d
0%
PK000MB62S
MB621 - Marshaling 101-B ID & FD Fans
30-Dec-26
14-Feb-27
215.0d
0%
PK000MB71S
MB710 - Marshaling 2202-B/BL Storage Flare & Flame FRT Gen.
30-Dec-26
07-Feb-27
240.0d
0%
PK000MD34T
MD304 - Marshaling 108-DA/B
30-Dec-26
07-Feb-27
162.0d
0%
PK000MD41S
MD401 - Marshaling 101-F
30-Dec-26
07-Feb-27
175.0d
0%
PK000MD44U
MD404 - Marshaling 132-F
30-Dec-26
07-Feb-27
65.0d
0%
PK000MJ35S
MJ305 - Marshaling ISBL ANSI/API PUMPS
30-Dec-26
11-Feb-27
153.0d
0%
PK000MJ71K
MJ731 - Fabricate/PO Promise EMERG PWR GENERATOR
30-Dec-26
21-Feb-27
70.0d
0%
PK000ML31S
ML313 - Marshaling 160-L
30-Dec-26
30-Dec-26
261.0d
0%
PK000ML90S
01A ML900 - Marshaling Evap. Pond Spray Nzl.
30-Dec-26
10-Jan-27
103.0d
0%
PK000MU25S
02G MU225 - Marshaling LIFT STATION
30-Dec-26
07-Feb-27
215.0d
0%
PK000MU29S
MU292 - Marshaling 2404-L
30-Dec-26
07-Feb-27
195.0d
0%
PK000MU30S
MU300 - Marshaling 2102-U
30-Dec-26
07-Feb-27
76.0d
0%
PK000MU31S
MU310 - Marshaling Injection System & Chlorination Unit
30-Dec-26
07-Feb-27
59.0d
0%
PK000MU32S
MU322 - Marshaling COOLING WTR FILTER & CLARIFIER
30-Dec-26
07-Feb-27
71.0d
0%
PK000MU33S
MU330 - Marshaling 2001-U
30-Dec-26
07-Feb-27
111.0d
0%
PK000PIA1N
Bulk Piping A/G - Fab/Exworks (FINAL)
30-Dec-26
07-Mar-27
45.0d
0%
PK000PS00G
000 SP Items - Fabricate/Exworks
30-Dec-26
30-Dec-26
247.0d
0%
PK000PSA8H
000 Relief Valves - Transport & Deliver
30-Dec-26
24-Feb-27
257.0d
0%
PK000PTA0J
Engineered Pipe Supports - Transport
30-Dec-26
10-Feb-27
58.0d
0%
PK010E008K
540-SG Admin. Area Pwr Supply - Fab / Exworks
30-Dec-26
11-Feb-27
70.0d
0%
PK010I1211
Vortex Meters - Transport & Deliver
30-Dec-26
31-Dec-26
533.0d
0%
PK010I1241
Rotameters - Transport & Deliver
30-Dec-26
14-Jan-27
523.0d
0%
PK010IC214
010 Control Valves - Transport & Deliver
30-Dec-26
30-Dec-26
535.0d
0%
PK010IC220
010 Control Valves - Recv on Site
30-Dec-26
30-Dec-26
—
0%
PK010IC252
MOV Valves - Fabricate/Exworks
30-Dec-26
27-Jan-27
475.0d
0%
PK020I131N
Transport & Deliver - Transmitters -Press.
30-Dec-26
20-Feb-27
76.0d
0%
PK030I1103
Orific Plates -Transport & Deliver
30-Dec-26
27-Jan-27
514.0d
0%
PK030I131H
Fabricate / Exworks - Transmitters - Temp.
30-Dec-26
16-Jan-27
71.0d
0%
PK030I611H
Fabricate / Exworks - Pressure Gauges - OSBL
30-Dec-26
04-Feb-27
58.0d
0%
ZZ2080
MJ305 - Transport/Customes OSBL ANSI/API PUMPS
30-Dec-26
07-Feb-27
190.0d
0%
ZZ2090
MJ305 - Marshaling OSBL ANSI/API PUMPS
30-Dec-26
30-Dec-26
190.0d
0%
PK000I1131
Venturis - Transport & Deliver
31-Dec-26
03-Feb-27
509.0d
0%
PK000I221N
000 Everest Control Valves - Transport & Deliver
31-Dec-26
10-Feb-27
504.0d
0%
PK000MB51S
MB511 - Marshaling 101-B Insulation
31-Dec-26
20-Jan-27
204.0d
0%
PK000ML31O
ML313 - Transport/Customs 160-L
31-Dec-26
24-Jan-27
365.0d
0%
PK000PS00H
000 SP Items - Transport & Deliver
31-Dec-26
10-Mar-27
247.0d
0%
PK010I1151
Annubars - Transport & Deliver
31-Dec-26
03-Feb-27
509.0d
0%
PK010I1212
Vortex Meters - Recv on Site
31-Dec-26
31-Dec-26
615.0d
0%
PK000MD21S
MD201- Marshaling 101-E
02-Jan-27
07-Feb-27
93.0d
0%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
—
0%
EK000YA838
(EP-34) Issue >90% ISBL P&ID's For Construction (IFC)
03-Jan-27
03-Jan-27
—
0%
PK000I352N
SIS - Transport & Delivery
13-Jan-27
21-Mar-27
55.0d
0%
PK000I354N
ITCC - Transport & Delivery
13-Jan-27
21-Mar-27
55.0d
0%
PK000I4441
Cleanup / Changes - Shelters/ Analyzers
13-Jan-27
24-Jan-27
161.0d
0%
PK000MD32S
MD302 - Marshaling 104-D1/2
13-Jan-27
07-Feb-27
85.0d
0%
PK000MJ22S
MJ201 - Marshaling 101-J
13-Jan-27
31-Jan-27
86.0d
0%
PK000MJ36S
MJ305 - Marshaling OSBL PUMPS
13-Jan-27
31-Jan-27
60.0d
0%
PK000MJ38V
MJ308 - Marshaling ISBL ANSI/API PUMPS
13-Jan-27
31-Jan-27
198.0d
0%
PK000MJ39S
Marshaling FIREWATER PUMPS
13-Jan-27
31-Jan-27
60.0d
0%
PK000ML90O
01A ML900 - Transport/Customes Evap. Pond Spray Nzl.
13-Jan-27
21-Feb-27
103.0d
0%
PK010I1242
Rotameters - Recv on Site
14-Jan-27
14-Jan-27
—
0%
EK05BPI050
05B Model Comment Resolution Approval
15-Jan-27
17-Jan-27
75.0d
0%
PK000MC32S
MC311 - Marshaling KBR S&T EXCH
17-Jan-27
06-Mar-27
76.0d
0%
PK000MJ34S
MJ304 - Marshaling MP BFW PUMPS
17-Jan-27
06-Feb-27
186.0d
0%
PK030I131N
Transport & Deliver - Transmitters - Temp.
17-Jan-27
30-Jan-27
91.0d
0%
PK000MJ32S
MJ302 - Marshaling 107-JA/JB/JC
20-Jan-27
07-Feb-27
175.0d
0%
PK000MB51O
MB511 - Transport/Customes 101-B Insulation
21-Jan-27
03-Mar-27
204.0d
0%
PK000MJ37V
MJ307 - Marshaling ISBL ANSI/API PUMPS
21-Jan-27
10-Feb-27
192.0d
0%
EK000YA030
Last PDS Planning Release
24-Jan-27
24-Jan-27
515.0d
0%
EK05BEL165
Switchgear One line Diagrams - IFC
27-Jan-27
30-Jan-27
276.0d
0%
EK05BEL185
MCC One line Diagrams - IFC
27-Jan-27
30-Jan-27
286.0d
0%
PK000I4442
Packing / Exworks - Shelters/ Analyzers
27-Jan-27
31-Jan-27
161.0d
0%
PK030I1105
Orific Plates - Recv on Site
27-Jan-27
27-Jan-27
592.0d
0%
PK000MD34S
MD304 - Marshaling 106-D, 109-DA/B
30-Jan-27
07-Feb-27
200.0d
0%
EK000YA040
Engineering 95% Complete
30-Jan-27
30-Jan-27
—
0%
PK000I444N
Transport & Deliver - Shelters/ Analyzers
03-Feb-27
11-Apr-27
161.0d
0%
PK000MJ22O
MJ201 - Transport/Customs 101-J
03-Feb-27
07-Mar-27
86.0d
0%
PK000MJ31S
MJ301 - Marshaling 104-J
03-Feb-27
04-Mar-27
168.0d
0%
PK000MJ36O
MJ305 - Transport/Customes OSBL PUMPS
03-Feb-27
14-Mar-27
60.0d
0%
PK000MJ38W
MJ308 - Transport/Customes ISBL ANSI/API PUMP
03-Feb-27
14-Mar-27
198.0d
0%
PK000MJ39O
Transport/Customes FIREWATER PUMPS
03-Feb-27
14-Mar-27
60.0d
0%
PK010IC262
MOV Valves - Transport & Deliver
03-Feb-27
21-Mar-27
475.0d
0%
PK010I1152
Annubars - Recv on Site
03-Feb-27
03-Feb-27
586.0d
0%
PK000E002X
Transformer - Marshalling
05-Feb-27
01-Apr-27
28.0d
0%
PK030I611N
Transport & Deliver - Pressure Gauges - OSBL
05-Feb-27
25-Feb-27
73.0d
0%
PK000E004X
UPS System - Marshalling
06-Feb-27
02-Apr-27
27.0d
0%
PK000MJ34O
MJ304 - Transport/Customes MP BFW PUMPS
07-Feb-27
20-Mar-27
186.0d
0%
PK000MB71O
MB710 - Transport/Customes 2202-B/BL Storage Flare & Flame FRT Gen.
08-Feb-27
28-Feb-27
336.0d
0%
PK000MD21O
MD201 - Transport/Customes 101-E
08-Feb-27
28-Feb-27
131.0d
0%
PK000MD32O
MD302 - Transport/Customes 104-D1/2
08-Feb-27
28-Feb-27
120.0d
0%
PK000MD34O
MD304 - Transport/Customes 106-D, 109-DA/B
08-Feb-27
28-Feb-27
280.0d
0%
PK000MD41O
MD401 - Transport/Customes 101-F
08-Feb-27
28-Feb-27
246.0d
0%
PK000MD44V
MD404 - Transport/Customes 132-F
08-Feb-27
28-Feb-27
93.0d
0%
PK000MU225
02G MU225 Transport/Customes LIFT STATION
08-Feb-27
28-Feb-27
302.0d
0%
PK000MU29O
MU292 - Transport/Customes 2404-L
08-Feb-27
28-Feb-27
275.0d
0%
PK000MU30O
MU300 - Transport/Customes 2102-U
08-Feb-27
28-Feb-27
108.0d
0%
PK000MU31O
MU310 - Transport/Customes Injection System & Chlorination Unit
08-Feb-27
28-Feb-27
83.0d
0%
PK000MU322
MU322 Transport/Customes COOLING WTR FILTER & CLARIFIER
08-Feb-27
28-Feb-27
101.0d
0%
PK000MU33O
MU330 - Transport/Customes 2001-U
08-Feb-27
28-Feb-27
157.0d
0%
ZZ2100
MD304 - Transport/Customes 108-DA/B
08-Feb-27
28-Feb-27
228.0d
0%
PK01GIC35L
DCS - Receive at Site
08-Feb-27
08-Feb-27
104.0d
0%
PK000I2330
On/Off Valves - Transport & Deliver
10-Feb-27
11-Apr-27
460.0d
0%
PK000MJ32O
MJ302 - Transport/Customes 107-JA/JB/JC
10-Feb-27
28-Feb-27
175.0d
0%
ZZ2110
MC230 - Transport/Customes 107/111
10-Feb-27
28-Feb-27
93.0d
0%
PK000I221L
000 Everest Control Valves - Recv on Site
10-Feb-27
10-Feb-27
580.0d
0%
PK000PTA0K
Engineered Pipe Supports - Receive at Site
10-Feb-27
10-Feb-27
69.0d
0%
EK035BI145
05B OP's & Serv. Model Comments Resolution Approval
11-Feb-27
13-Feb-27
75.0d
0%
PK000MJ37W
MJ307 - Transport/Customes ISBL ANSI/API PUMP
11-Feb-27
24-Mar-27
192.0d
0%
PK000ML50S
ML500 - Marshaling 2003-L PAI/IA
11-Feb-27
07-Mar-27
78.0d
0%
PK000MJ35O
MJ305 - Transport/Customes ISBL ANSI/API PUMPS
12-Feb-27
25-Mar-27
153.0d
0%
PK010E008M
540-SG Admin. Area Pwr Supply - Marshalling
12-Feb-27
08-Apr-27
70.0d
0%
PK000MB62O
MB621 - Transport/Customes of 101-B ID & FD Fans
15-Feb-27
07-Mar-27
301.0d
0%
PK000E001Z
Sub Stations - FAT
17-Feb-27
28-Feb-27
62.0d
0%
PK000MD31S
MD301 - Marshaling 103-D
18-Feb-27
07-Mar-27
55.0d
0%
PK000I612N
Transport & Deliver - Differential Pressure Gauges
19-Feb-27
29-Apr-27
28.0d
0%
EK000YA835
(EP-36) Issue >90% Area Line Installation Details
21-Feb-27
21-Feb-27
—
0%
EK000YA847
(EP-39) Issue >90% OSBL Electrical Design Drawings
21-Feb-27
21-Feb-27
—
0%
PK000ML90Z
01A ML900 - Recv. at Site - Evap. Pond Spray Nzl.
22-Feb-27
22-Feb-27
125.0d
0%
PK000MJ71S
MJ731 - Marshaling EMERG PWR GENERATOR
24-Feb-27
07-Mar-27
70.0d
0%
PK000PSA8J
000 Relief Valves - Recv on Site
24-Feb-27
24-Feb-27
284.0d
0%
PK03FMU32Z
MU322 Recv. at Site - COOLING WTR FILTER & CLARIFIER
28-Feb-27
28-Feb-27
71.0d
0%
PK030I131L
Recv at Site - Transmitters -Temp.
01-Mar-27
01-Mar-27
86.0d
0%
PK000MB71Z
05A Recv. at Site - Storage Flare & Flame FRT Gen.
01-Mar-27
01-Mar-27
264.0d
0%
PK01BMU30Z
01C Recv. at Site - 2102-U EDR Unit
01-Mar-27
01-Mar-27
93.0d
0%
PK03BMU29Z
03B Recv. at Site - 2404-L Oil Skimmer
01-Mar-27
01-Mar-27
212.0d
0%
PK03EMU33Z
03E Recv. at Site - 2001-U Demineralizer Unit
01-Mar-27
01-Mar-27
135.0d
0%
PK000E001N
Sub Stations - Transport
03-Mar-27
11-Apr-27
62.0d
0%
PK000md113
MD305 Merc. Removal Bed 102-D - Marshaling
03-Mar-27
07-Mar-27
157.0d
0%
PK000MD22U
MD202 - Marshaling TOWERS 150-E
03-Mar-27
07-Mar-27
100.0d
0%
PK000MJ33S
MJ303 - Marshaling CW PUMPS
03-Mar-27
19-Mar-27
27.0d
0%
PK000MJ73S
MJ730 - Marshaling EMERG PWR GENERATOR
03-Mar-27
07-Mar-27
70.0d
0%
PK020MC31D
MC312 - Marshaling 121-C
03-Mar-27
07-Mar-27
90.0d
0%
PK020MC31S
MC312 - Marshaling 120-C
03-Mar-27
07-Mar-27
90.0d
0%
PK000MJ31O
MJ301 - Transport/Customes 104-J
05-Mar-27
15-Apr-27
168.0d
0%
PK000MD22N
MD201- Marshaling 102-E
06-Mar-27
07-Mar-27
62.0d
0%
PK000MC32O
MC311 - Transport/Customes KBR S&T EXCH
06-Mar-27
27-Mar-27
108.0d
0%
PK000ML50O
ML500 - Transport/Customes 2003-L PAI/IA
08-Mar-27
28-Mar-27
110.0d
0%
PK000MD111
MD305 Merc. Removal Bed - Transport & Deliver
10-Mar-27
02-May-27
157.0d
0%
PK000MD211
MD201 - Transport/Customes 102-E
10-Mar-27
18-Apr-27
62.0d
0%
PK000MD22V
MD202 - Transport/Customes TOWERS 150-E
10-Mar-27
02-May-27
100.0d
0%
PK000MD31O
MD301 - Transport/Customes 103-D
10-Mar-27
04-Apr-27
55.0d
0%
PK000MJ71O
MJ731 - Transport/Customes EMERG PWR GENERATOR
10-Mar-27
18-Apr-27
70.0d
0%
PK000MJ73O
MJ730 - Transport/Customes EMERG PWR GENERATOR
10-Mar-27
18-Apr-27
70.0d
0%
PK000PIA1O
Bulk Piping A/G - Transport / Delivery (FINAL)
10-Mar-27
11-Apr-27
45.0d
0%
PK020MC31J
MC312 - Transport/Customes 121-C
10-Mar-27
04-Apr-27
90.0d
0%
PK020MC31L
MC312 - Transport/Customes 120-C
10-Mar-27
04-Apr-27
90.0d
0%
PK000PS00J
000 SP Items - Recv on Site
10-Mar-27
10-Mar-27
272.0d
0%
PK000MD43S
MD403 - Marshaling 106-F
12-Mar-27
25-Apr-27
135.0d
0%
PK000I621N
Transport & Deliver - Temperature Elements
14-Mar-27
14-Apr-27
39.0d
0%
PK000MJ38A
05A Recv. at Site - 2100-JA Pumps - MJ308
15-Mar-27
15-Mar-27
215.0d
0%
PK01BMJ36Z
01B Recv. at Site - 2001-JA/JB/JC, 2004-J/JA, 2007J/JA
15-Mar-27
15-Mar-27
73.0d
0%
PK01BMJ39Z
Recv. at Site - Firewater Pumps
15-Mar-27
15-Mar-27
73.0d
0%
PK03CMJ36Z
03C Recv. at Site - 2205-J/JA, 2206-J/JA Pumps
15-Mar-27
15-Mar-27
146.0d
0%
PK03DMJ36Z
03D Recv. at Site - 2002-J/JA Demineralized Water Pumps
15-Mar-27
15-Mar-27
158.0d
0%
PK05AMJ36Z
05A Recv. at Site - 2203-J/JM, 2106-J, 2107-J Pumps
15-Mar-27
15-Mar-27
207.0d
0%
PK030I611L
Recv at Site - Pressure Gauges - OSBL
19-Mar-27
19-Mar-27
70.0d
0%
PK000MJ33O
MJ303 - Transport/Customes CW PUMPS
20-Mar-27
30-Apr-27
27.0d
0%
PK000MD33S
MD303 - Marshaling 105-D
21-Mar-27
11-Apr-27
50.0d
0%
PK010IC272
MOV Valves - Recv on Site
22-Mar-27
22-Mar-27
547.0d
0%
PK01GI352L
SIS - Receive at Site
22-Mar-27
22-Mar-27
68.0d
0%
PK01GI354L
ITCC - Receive at Site
22-Mar-27
22-Mar-27
68.0d
0%
PK000MD42S
MD402 -Marshaling 102-F1, 102-F2
24-Mar-27
28-Mar-27
130.0d
0%
PK05AMJ37A
05A Recv. at Site - 2100-JA Pumps - MJ307
24-Mar-27
24-Mar-27
206.0d
0%
PK03AML50Z
03A Recv. at Site - 2003-L PAI/IA Compressor Pkg
29-Mar-27
29-Mar-27
95.0d
0%
PK000MD42O
MD402 - Transport/Customes 102-F1, 102-F2
31-Mar-27
09-May-27
130.0d
0%
PK000E002N
Transformer - Transport
02-Apr-27
13-May-27
28.0d
0%
PK000E004N
UPS System - Transport
03-Apr-27
14-May-27
27.0d
0%
PK010E008N
540-SG Admin. Area Pwr Supply - Transport
09-Apr-27
20-May-27
70.0d
0%
PK000I444L
Recv at Site - Shelters/ Analyzers
12-Apr-27
12-Apr-27
171.0d
0%
PK000I9000
Receive Instruments at Site
12-Apr-27
12-Apr-27
529.0d
0%
PK000PIA1P
Bulk Piping A/G - Receive at Site (FINAL)
12-Apr-27
12-Apr-27
56.0d
0%
PK01HE001L
Sub Stations - Receive at Site
12-Apr-27
12-Apr-27
76.0d
0%
PK000MD33O
MD303 - Transport/Customes 105-D
14-Apr-27
09-May-27
50.0d
0%
PK000MJ71Z
05A Recv. at Site - 2108-J Emerg Power Generator
19-Apr-27
19-Apr-27
86.0d
0%
PK01HMJ73Z
01H Recv. at Site - 2303-J Emerg Power Generator
19-Apr-27
19-Apr-27
86.0d
0%
PK000MD43O
MD403 - Transport/Customs 106-F
28-Apr-27
23-May-27
135.0d
0%
PK01BMJ33Z
01B Recv. at Site - 2007-J/JA Cooling Wtr Makeup Pumps
30-Apr-27
30-Apr-27
32.0d
0%
PK01DMJ33Z
01D Recv. at Site - Equip. 2202-JA/B/C
30-Apr-27
30-Apr-27
28.0d
0%
EK000YA889
(TLA-03) Complete > TLA Payments
03-May-27
03-May-27
623.0d
0%
PK01HE002L
Transformer - Receive at Site
13-May-27
13-May-27
34.0d
0%
PK000E004L
UPS System - Receive at Site
14-May-27
14-May-27
33.0d
0%
PK010E008P
540-SG Admin. Area Pwr Supply - Receive at Site
20-May-27
20-May-27
78.0d
0%
PK000MC31S
MC310 - Marshaling 101-C & 102-C (Heavy Lift)
01-Jul-27
01-Jul-27
8.0d
0%
PK000MC31O
MC310 - Transport/Customes 101-C & 102-C (Heavy Lift)
02-Jul-27
29-Jul-27
8.0d
0%
PK000PR20J
PR201 KAAP Catalyst - Transport & Deliver
04-Nov-27
12-Jan-28
26.0d
0%