Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2035 activities in E2B2 All Other Areas (HOC) × clear
Code
Activity
Start
Finish
Flt
%
EK000CK085
Establish bank account in Egypt
02-Jul-24
24-Jan-26
100%
EK000SY005
Systems Work Plan & Project Setup
21-Jan-25
25-Mar-25
100%
EK000YA002
Start Project
22-Jan-25
22-Jan-25
100%
EK000PR025
Pressure Profile
22-Jan-25
01-Feb-25
100%
EK000PR050
Electrical Load Summary - Initial
22-Jan-25
01-Feb-25
100%
EK000MD005
Attend Alignment & strategy meetings
22-Jan-25
09-Feb-25
100%
EK000PR015
Process Configuration
22-Jan-25
13-Feb-25
100%
EK000PR030
Stream Summary
22-Jan-25
13-Feb-25
100%
EK000PR035
Process Flow Diagrams PFD's - EOR
22-Jan-25
13-Feb-25
100%
EK000PR040
Steam Balance Diagram - EOR
22-Jan-25
13-Feb-25
100%
EK000GE005
Estimate Escalation Check - Info to Estimating
22-Jan-25
14-Feb-25
100%
EK000PR045
Cooling Water Balance - EOR
22-Jan-25
15-Feb-25
100%
EK000PE025
Document Management Plan - Issue for Review
22-Jan-25
16-Feb-25
100%
EK000SY010
MEC Convert prelim P&ID's to Smart Plant P&ID's
22-Jan-25
16-Feb-25
100%
EK000MD015
Conversion of drawings to metric units
22-Jan-25
19-Feb-25
100%
EK000PM015
Project Coordination Procedure - IFA
22-Jan-25
23-Feb-25
100%
EK000PR020
Heat & Material Balances (SOR & EOR)
22-Jan-25
23-Feb-25
100%
EK000PE085
Participate in Escalation confirmation effort
22-Jan-25
01-Mar-25
100%
EK000IM030
Project Portal & Dashboard
22-Jan-25
06-Mar-25
100%
EK000IC030
Develop & Issue FieldBus Main Instr Vendor ERW
22-Jan-25
08-Mar-25
100%
EK000PR055
Feed & Fuel Summary
22-Jan-25
09-Mar-25
100%
EK000IM020
IM Strategy plan
22-Jan-25
12-Mar-25
100%
EK000IM025
IM Execution plan
22-Jan-25
12-Mar-25
100%
EK000PR010
Process Work Plan
22-Jan-25
23-Mar-25
100%
EK000AR020
Gather Bldg Requirements & Coordinate w/ Constr
22-Jan-25
12-Apr-25
100%
EK000IM010
Object Engineering set-up & procedures
22-Jan-25
13-Apr-25
100%
EK000CV005
Identify scope / Project set-up
23-Jan-25
23-Feb-25
100%
PK000PK005
Implement use of Procuri and funct'nality (Req?)
29-Jan-25
02-Feb-25
100%
EK000PE125
Preliminary Issue - Equipment List
29-Jan-25
12-Feb-25
100%
EK000CV020
Review FMCL documents - Specs & Drawings
29-Jan-25
16-Feb-25
100%
EK000IM040
Establish Citrix for Test of PDS (HOC-MEC)
29-Jan-25
23-Feb-25
100%
EK000PI080
Develop Split of work
29-Jan-25
23-Feb-25
100%
PK000MM020
Project requisition matrix
29-Jan-25
02-Mar-25
100%
EK000IM005
Equipment List (MEL) Definition
29-Jan-25
30-Mar-25
100%
PK000MM010
Project material responsibility matrix
29-Jan-25
04-May-25
100%
EK000PE050
Confirm of Split of Work for MEC
02-Feb-25
23-Feb-25
100%
PK000PK035
Review ITP as with eng.
02-Feb-25
16-Mar-25
100%
EK000IC35A
DCS - Engr ERW Issued
04-Feb-25
12-Feb-25
100%
EK000IM035
Establish Documentum
05-Feb-25
16-Feb-25
100%
EK000PE010
Publish Unit conversion standard
05-Feb-25
16-Feb-25
100%
EK000PE040
Devlop & Issue List of Project Specs & Standards
05-Feb-25
16-Feb-25
100%
EK000CV025
Review SEGAS Wind & Earthquake Specs
05-Feb-25
19-Feb-25
100%
EK000PI120
Identify priority pipe classes
05-Feb-25
20-Feb-25
100%
EK000PS015
Issue 90 Day look ahead schedule
05-Feb-25
21-Feb-25
100%
EK000MJ005
Prepare Machinery Specs (Motors, Pkg Equipment)
05-Feb-25
25-Feb-25
100%
EK000IC015
Modify Package Equipment Spec for IEC basis
05-Feb-25
05-Mar-25
100%
EK000PE110
Issue Draft Project Design Data
05-Feb-25
06-Mar-25
100%
EK000MC010
Develop & Issue Exchanger Work Plan
05-Feb-25
09-Mar-25
100%
EK000PI115
Develop Piping Class Index (IOPMC)
05-Feb-25
13-Mar-25
100%
EK000SY015
Develop Utility & offsite block flow diagrams
05-Feb-25
16-Mar-25
100%
EK000PI132
Develop Early Tech P-Class specs for Procurement
05-Feb-25
22-Mar-25
100%
EK000SY065
Complete Utility Flow Diagrams
05-Feb-25
03-Apr-25
100%
PK000MM025
Piping Bulk Quanities for Mill Run Commitment
05-Feb-25
06-May-25
100%
EK000CV010
HOC / MEC split of Work
07-Feb-25
16-Feb-25
100%
EK000CV030
Prepare EBIC Wind & EarthquakeSpecs
07-Feb-25
26-Feb-25
100%
EK000QM010
Training - Export Compliance
08-Feb-25
08-Feb-25
100%
PK000I354H
ITCC - Fabricate Hardware
11-Feb-25
27-Dec-26
64%
PK000I210B
000 Control Valves - Issue RFQ
11-Feb-25
18-Feb-25
100%
EK000ELZE0
Area Classification
11-Feb-25
30-Dec-25
100%
EK000MD31C
Prepare & Issue Prelim. RFQ - MD301 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD32C
Prepare & Issue Prelim. RFQ - MD302 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD34C
Prepare & Issue Prelim. RFQ - MD304 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD51C
Prepare & Issue Prelim. RFQ - MD501 to Proc.
12-Feb-25
16-Feb-25
100%
EK000CV040
Prepare Topo Survey S/C Pkg
12-Feb-25
23-Feb-25
100%
EK000PE090
Develop & Issue Engineering Plan
12-Feb-25
02-Mar-25
100%
EK000EL005
Electrical Work Plans
12-Feb-25
09-Mar-25
100%
EK000PI040
Prepare technology work plan - Piping Engr.
12-Feb-25
09-Mar-25
100%
EK000PI060
Prepare Other Project Documentation
12-Feb-25
09-Mar-25
100%
PK000PK01C
Prepare/Issue Critical & Prelim. ERW's to Proc.
12-Feb-25
09-Mar-25
100%
EK000PI051
Prepare P/Mech Support Details
12-Feb-25
15-Mar-25
100%
EK000CV015
Civil work Plan & Safety check list
12-Feb-25
16-Mar-25
100%
EK000CV050
Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis
12-Feb-25
16-Mar-25
100%
EK000MB005
Develop & Issue Furnance Job Plan
12-Feb-25
16-Mar-25
100%
EK05BEL150
Switchgear One line diagrams - ICA Dock
12-Feb-25
15-Nov-25
100%
EK05BEL170
MCC One line diagrams - ICA Dock
12-Feb-25
22-Nov-25
100%
EK000MJ31C
Prepare & Issue Prelim. RFQ - MJ301 to Proc.
13-Feb-25
13-Feb-25
100%
EK000MJ32C
Prepare & Issue Prelim. RFQ - MJ302 to Proc.
13-Feb-25
13-Feb-25
100%
PK000IC35B
DCS - Inquiry REQ/RFQ
13-Feb-25
14-Feb-25
100%
EK000MB33A
101-B Develop & Issue Load Sheet
14-Feb-25
16-Feb-25
100%
EK000MD33A
Develop & Issue Load Sheets for ERW - MD303
14-Feb-25
16-Feb-25
100%
EK000MJ22A
Develop & Issue Load Sheets for ERW - MJ201
14-Feb-25
16-Feb-25
100%
EK000MJ21A
Develop & Issue Load Sheets for ERW - MJ202
14-Feb-25
21-Feb-25
100%
PK000MJ31G
Issue MJ301 RFQ
14-Feb-25
21-Feb-25
100%
PK000MJ32G
Issue MJ302 RFQ
14-Feb-25
21-Feb-25
100%
EK000PI110
Locate FMCL Documents
14-Feb-25
23-Feb-25
100%
EK000PR060
Process Load Sheets
14-Feb-25
22-Mar-25
100%
EK000PC005
Prepare Estimate for Escalation Check
15-Feb-25
23-Feb-25
100%
EK000PE015
MSD (From Metallurgy) - ISBL
15-Feb-25
27-Feb-25
100%
PK000IC35C
DCS - Receive Bids
15-Feb-25
13-Mar-25
100%
EK000MC31C
Prepare & Issue Prelim. RFQ - MC310 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MC61C
Prepare & Issue Prelim. RFQ - MC610 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MBP1C
101-B Prepare & Issue Prelim. Shop Fab to Proc.
16-Feb-25
20-Feb-25
100%
EK000QM015
Develop & Issue Quality Plan
16-Feb-25
16-Mar-25
100%
EK000MC32C
Issue Prelim. RFQ - MC311
19-Feb-25
19-Feb-25
100%
EK000MJ22C
Prepare & Issue Prelim. RFQ - MJ201 to Proc.
19-Feb-25
19-Feb-25
100%
EK020MC31A
MC312 - (120,121-C) - Issue Prelim. RFQ
19-Feb-25
19-Feb-25
100%
PK000MJ22G
Issue MJ201 RFQ
19-Feb-25
19-Feb-25
100%
EK000MD21A
Develop & Issue Load Sheets for ERW - MD201
19-Feb-25
20-Feb-25
100%
EK000MD41C
Prepare & Issue Prelim. RFQ - MD401 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD43C
Prepare & Issue Prelim. RFQ - MD403 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD43A
Develop & Issue Load Sheets for ERW - MD403
19-Feb-25
21-Feb-25
100%
EK000MJ31A
Develop & Issue Load Sheets for ERW - MJ301
19-Feb-25
21-Feb-25
100%
EK010SY010
010 Issue Marked up FMCL U&O / Dock P&ID's
19-Feb-25
21-Feb-25
100%
EK000MD33C
Prepare & Issue Prelim. RFQ - MD303 to Proc.
19-Feb-25
22-Feb-25
100%
PK000MD32G
Issue MD302 RFQ
19-Feb-25
22-Feb-25
100%
EK000EL020
Define bulk material requirements
19-Feb-25
23-Feb-25
100%
EK000MJ22B
Develop & Issue Design Data for ERW - MJ201
19-Feb-25
23-Feb-25
100%
EK000ML31C
Prepare & Issue Prelim. RFQ - ML313 to Proc.
19-Feb-25
23-Feb-25
100%
EK000PR115
Issue Prelim Load Sht for Air Cooling Study
19-Feb-25
23-Feb-25
100%
PK000MD31G
Issue MD301 RFQ
19-Feb-25
23-Feb-25
100%
PK000MD34G
Issue MD304 RFQ
19-Feb-25
23-Feb-25
100%
PK000MD42G
Issue MD402 RFQ
19-Feb-25
23-Feb-25
100%
PK000MD51G
Issue MD501 RFQ
19-Feb-25
23-Feb-25
100%
EK000MC210
Cooling Water Balance Review
19-Feb-25
26-Feb-25
100%
PK000MC31G
Issue MC310 RFQ
19-Feb-25
26-Feb-25
100%
PK000MC61G
Issue MC610 RFQ
19-Feb-25
26-Feb-25
100%
PK000PK020
Meeting w/ doc mngmnt & eng. (work process) TREQ
19-Feb-25
28-Feb-25
100%
EK000IM045
Establish IPMS
19-Feb-25
01-Mar-25
100%
EK000IC005
Develop Typical SIL Values Worksheet
19-Feb-25
02-Mar-25
100%
EK000MJ35C
Prepare & Issue Prelim. RFQ - MJ305 to Proc.
19-Feb-25
02-Mar-25
100%
EK000MJ36C
Prepare & Issue Prelim. RFQ - MJ306 to Proc.
19-Feb-25
02-Mar-25
100%
EK000PK030
Provide Job Specific SDR2 Priorities to Purch.
19-Feb-25
02-Mar-25
100%
EK000PI160
P&ID Area Break Mark-up
19-Feb-25
08-Mar-25
100%
EK000MJ39C
Prepare & Issue Prelim. RFQ - MJ391 to Proc.
19-Feb-25
09-Mar-25
100%
EK000PR076
Identify Risk of Equipment Changes
19-Feb-25
09-Mar-25
100%
EK000PE035
Rvw Lesson Learn w/Prj. Team&Develop Action List
19-Feb-25
16-Mar-25
100%
PK000MM015
IPMS Initial Setup
19-Feb-25
16-Mar-25
100%
EK000EV005
Conceptual Design of Wastewater Systems
19-Feb-25
23-Mar-25
100%
EK000PR145
Eng. Studies - Ammonia Product Line U/G vs. A/G
19-Feb-25
29-Mar-25
100%
EK000MB010
101-B Furnance Analytical - Convection Design
19-Feb-25
30-Mar-25
100%
EK000CV070
Validate Concrete & Steel by Planning Areas
19-Feb-25
15-Apr-25
100%
EK000MD33P
Develop Analytical Sketches for ERW - MD303
19-Feb-25
04-May-25
100%
EK000PM055
Complete EPC Insurance Forms
19-Feb-25
04-May-25
100%
PK000PE030
Coating Supplier of Choice Selection
19-Feb-25
04-May-25
100%
EK000PI020
Develop Piping Specs (Paper)
19-Feb-25
28-May-25
100%
PK000I210C
000 Control Valves - Receive Quotes
19-Feb-25
19-Mar-25
100%
EK000MJ21C
Prepare & Issue Prelim. RFQ - MJ202 to Proc.
20-Feb-25
20-Feb-25
100%
PK000MJ21G
Issue MJ202 RFQ
20-Feb-25
20-Feb-25
100%
EK000ML50C
Prepare & Issue Prelim. RFQ - ML500 to Proc.
20-Feb-25
26-Feb-25
100%
PK000MC32G
Issue MC311 RFQ
20-Feb-25
26-Feb-25
100%
PK020MC31B
MC312 - (120,121-C) - Issue RFQ
20-Feb-25
26-Feb-25
100%
PK000MJ22H
Receive Quotes MJ201
20-Feb-25
15-Mar-25
100%
EK000MD44A
Develop & Issue Load Sheets for ERW - MD404
20-Feb-25
20-Mar-25
100%
EK000MB61C
Prepare & Issue Prelim. RFQ - MB610 to Proc.
21-Feb-25
23-Feb-25
100%
EK000MB62C
Prepare & Issue Prelim. RFQ - MB621 to Proc.
21-Feb-25
23-Feb-25
100%
PK000MBP1G
101-B Prepare & Issue Shop Fab RFQ to Vendors
21-Feb-25
23-Feb-25
100%
PK000MD41G
Issue MD401 RFQ
21-Feb-25
23-Feb-25
100%
PK000MD43G
Issue MD403 RFQ
21-Feb-25
23-Feb-25
100%
EK000MD34A
Develop & Issue Load Sheets for ERW - MD304
21-Feb-25
26-Feb-25
100%
PK000MJ21H
Receive Quotes MJ202
21-Feb-25
26-Mar-25
100%
EK000MJ21B
Develop & Issue Design Data for ERW - MJ202
22-Feb-25
07-Mar-25
100%
EK000MD21P
Develop Prelim Analytical Sktch for ERW - MD201
22-Feb-25
22-Mar-25
100%
PK000MJ31H
Receive Quotes MJ301
22-Feb-25
11-Apr-25
100%
PK000MJ32H
Receive Quotes MJ302
22-Feb-25
12-Apr-25
100%
EK000MD21Q
Develop Final Analytical Sktch for ERW - MD201
22-Feb-25
26-Apr-25
100%
EK000YA804
(EP-05) Issue Heat and Material Balance for Process Release
22-Feb-25
22-Feb-25
100%
EK000YA805
(EP-06) Issue Equipment List for review
22-Feb-25
22-Feb-25
100%
EK000YA807
(EP-08) Issue Utility Balances for Initial Release
22-Feb-25
22-Feb-25
100%
EK000FP025
FP Gas Detection Location Plans - Not Required
22-Feb-25
23-Aug-25
100%
PK000MD33G
Issue MD303 RFQ
23-Feb-25
23-Feb-25
100%
PK000ML31G
Issue ML313 RFQ
23-Feb-25
23-Feb-25
100%
EK000MC32A
Develop & Issue Load Sheets for ERW - MC311
23-Feb-25
28-Feb-25
100%
PK000MD32H
Receive Quotes MD302
23-Feb-25
01-Apr-25
100%
EK000CK080
Expedite legal issues associated w/ KBRII
23-Feb-25
28-Feb-26
100%
PK000I131B
Issue RFQ - Transmitters
25-Feb-25
28-Feb-25
100%
EK000MB060
101-B General Arrangement Drawing
25-Feb-25
08-Mar-25
100%
EK000MF31A
Develop & Issue Load Sheets for ERW - MF301
26-Feb-25
26-Feb-25
100%
PK000MB61G
Issue MB610 RFQ
26-Feb-25
26-Feb-25
100%
EK000MB41C
Prepare & Issue Prelim. RFQ - MB410 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC21C
Prepare & Issue Prelim. RFQ - MC210 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC23C
Prepare & Issue Prelim. RFQ - MC230 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MD31A
Develop & Issue Load Sheets for ERW - MD301
26-Feb-25
27-Feb-25
100%
EK000MD32A
Develop & Issue Load Sheets for ERW - MD302
26-Feb-25
27-Feb-25
100%
EK000MD41A
Develop & Issue Load Sheets for ERW - MD401
26-Feb-25
27-Feb-25
100%
EK000EL015
Split of work with MEC and Other Discipline
26-Feb-25
28-Feb-25
100%
EK000MB63C
Prepare & Issue Prelim. RFQ - MB630 to Proc.
26-Feb-25
28-Feb-25
100%
EK000MBP4C
Prepare & Issue Prelim. RFQ Cast Material
26-Feb-25
28-Feb-25
100%
EK000PE060
Define Task Force Area in MEC
26-Feb-25
28-Feb-25
100%
EK000PE075
MEC Organization Chart
26-Feb-25
28-Feb-25
100%
PK000MB81G
Issue MB810 RFQ
26-Feb-25
28-Feb-25
100%
EK000PM030
Estimate Escalation Check - IRC Approvals
26-Feb-25
01-Mar-25
100%
PK000MB62G
Issue MB621 RFQ
26-Feb-25
01-Mar-25
100%
EK000PR095
Steam Balance - Startup, 103-J, Etc
26-Feb-25
02-Mar-25
100%
EK000MBP3C
Prepare & Issue Prelim. RFQ Pressure Parts
26-Feb-25
05-Mar-25
100%
PK000MBP1H
101-B Receive Quotes Shop Fab
26-Feb-25
05-Mar-25
100%
EK000MD33B
Develop & Issue Design Data for ERW - MD303
26-Feb-25
08-Mar-25
100%
EK000EV025
Develop & Issue Enviromental Work Plan
26-Feb-25
09-Mar-25
100%
EK000IC020
Establlish data warehouse - Intools Basic Setup
26-Feb-25
09-Mar-25
100%
EK000IC025
Review Instr. & Installation Details - ID Change
26-Feb-25
09-Mar-25
100%
EK000MJ22F
Update/Issue Formal Inquiry for ERW - MJ201
26-Feb-25
09-Mar-25
100%
EK000PK010
Issue critical req'n submittal sched to Procmnt
26-Feb-25
09-Mar-25
100%
EK000GE010
Eng. Studies - Air Coolers vs. Cooling Water
26-Feb-25
12-Mar-25
100%
PK000MD34H
Receive Quotes MD304
26-Feb-25
15-Mar-25
100%
PK000MD41H
Receive Quotes MD401
26-Feb-25
15-Mar-25
100%
EK000CV060
Civil project highlights
26-Feb-25
16-Mar-25
100%
EK000PI005
Locate Permanent Tie in pnts Gas, Wtr, Storm wtr
26-Feb-25
16-Mar-25
100%
PK000MD42H
Receive Quotes MD402
26-Feb-25
21-Mar-25
100%
PK000MD51H
Receive Quotes MD501
26-Feb-25
21-Mar-25
100%
EK000PE065
Develop & Issue HOC - MEC Coordination Plan
26-Feb-25
23-Mar-25
100%
PK000MD43H
Receive Quotes MD403
26-Feb-25
01-Apr-25
100%
PK000ML31H
Receive Quotes ML313
26-Feb-25
04-Apr-25
100%
EK000PI133
Dvlp/Issue V-class specs & Standads for Procurmt
26-Feb-25
09-Apr-25
100%
EK000MB085
101-B Radiant Detail Drawings - IFF
26-Feb-25
12-Apr-25
100%
EK000MB090
101-B Convection Detail Drawings - IFF
26-Feb-25
12-Apr-25
100%
PK000MD31H
Receive Quotes MD301
26-Feb-25
13-Apr-25
100%
PK000MD33H
Receive Quotes MD303
26-Feb-25
13-Apr-25
100%
EK000CV035
Prepare Geotech S/C Pkgs
26-Feb-25
27-Apr-25
100%
EK000EL025
Develop installation details
26-Feb-25
07-May-25
100%
EK000IC045
Develop & Issue CSE Work Plan
26-Feb-25
08-May-25
100%
EK000PM045
Issue Execution Strategy /Project Execution Plan
26-Feb-25
24-May-25
100%
EK000MC31A
Develop & Issue Load Sheets for ERW - MC310
27-Feb-25
01-Mar-25
100%
PK000ML50G
Issue ML500 RFQ
27-Feb-25
01-Mar-25
100%
EK000ML50B
Develop/Issue Load Sht & Design Data ERW - ML500
27-Feb-25
05-Mar-25
100%
PK000MB61H
Receive Quotes for MB610
27-Feb-25
13-Mar-25
100%
PK000MC61H
Receive Quotes MC610
27-Feb-25
16-Mar-25
100%
PK000MC31H
Receive Quotes for MC310
27-Feb-25
04-May-25
100%
PK000MC32H
Receive Quotes for MC311
27-Feb-25
04-May-25
100%
PK020MC3C
MC312 - (120,121-C) - Receive Quotes
27-Feb-25
04-May-25
100%
PK000MC21G
Issue MC210 RFQ
28-Feb-25
28-Feb-25
100%
PK000MC23G
Issue MC230 RFQ
28-Feb-25
28-Feb-25
100%
EK000MD42A
Develop & Issue Load Sheets for ERW - MD402
28-Feb-25
01-Mar-25
100%
PK000MB41G
Issue MB410 RFQ
28-Feb-25
01-Mar-25
100%
EK000MD51A
Develop & Issue Load Sheets for ERW - MD501
28-Feb-25
05-Mar-25
100%
EK000MJ35A
Develop & Issue Load Sheets for ERW - MJ305
28-Feb-25
23-Mar-25
100%
PK000MD22G
Issue MD202 RFQ
01-Mar-25
01-Mar-25
100%
PK000MD44G
Issue MD404 RFQ
01-Mar-25
01-Mar-25
100%
PK000MD45G
Issue MD405 RFQ
01-Mar-25
01-Mar-25
100%
PK000MD46G
Issue MD411 RFQ
01-Mar-25
01-Mar-25
100%
PK000MB63G
Issue MB630 RFQ
01-Mar-25
05-Mar-25
100%
PK000MBP4G
Issue 101-B Cast Material RFQ
01-Mar-25
05-Mar-25
100%
PK000MC21H
Receive Quotes for MC210
01-Mar-25
26-Mar-25
100%
PK000MC23H
Receive Quotes for MC230
01-Mar-25
02-Apr-25
100%
EK000YA808
(EP-09) Issue Engineering Plan
01-Mar-25
01-Mar-25
100%
PK000I131C
Receive Quotes - Transmitters
01-Mar-25
25-Mar-25
100%
EK000MD060
Prepare Vessel work plan & other quality documents
02-Mar-25
02-Mar-25
100%
EK010PI005
Develop Plot Plan & ID Areas - Overall Site IFI
02-Mar-25
09-Mar-25
100%
EK030PI005
Develop Plot Plan & ID Areas - Utility Plant IFI
02-Mar-25
09-Mar-25
100%
EK050PI005
Develop Plot Plan & ID Areas - Dock/Storage IFI
02-Mar-25
09-Mar-25
100%
EK000MC31B
Develop & Issue Design Data for ERW - MC310
02-Mar-25
13-Mar-25
100%
PK000MD22H
Receive Quotes for MD202
02-Mar-25
21-Mar-25
100%
PK000MD44H
Receive Quotes MD404
02-Mar-25
21-Mar-25
100%
PK000MD45H
Receive Quotes MD405
02-Mar-25
21-Mar-25
100%
PK000MD46H
Receive Quotes MD411
02-Mar-25
21-Mar-25
100%
PK000ML50H
Receive Quotes ML500
02-Mar-25
22-Mar-25
100%
PK000MB81H
Receive Quotes for MB810
02-Mar-25
28-Mar-25
100%
PK000MB62H
Receive Quotes for MB621
02-Mar-25
29-Mar-25
100%
EK000MC31F
Finalize Equip. Data Sheets for ERW - MC310
02-Mar-25
12-Apr-25
100%
PK000MB41H
Receive Quotes for MB410
02-Mar-25
20-Apr-25
100%
EK000PI125
Validate new plot layout (impacts on pipe stress
02-Mar-25
21-May-25
100%
EK000MJ21D
Technical Evaluation - MJ202
05-Mar-25
05-Mar-25
100%
EK000MJ75A
Develop & Issue Load Sheets for ERW - MJ750
05-Mar-25
05-Mar-25
100%
EK000ML31A
Develop & Issue Load Sheets for ERW - ML313
05-Mar-25
05-Mar-25
100%
EK000MB51C
Prepare & Issue Prelim. RFQ - MB511 to Proc.
05-Mar-25
07-Mar-25
100%
EK000CV075
Egyptian Professional Engineer - Define Reqmnts
05-Mar-25
08-Mar-25
100%
EK000MC21A
Develop & Issue Load Sheets for ERW - MC210
05-Mar-25
08-Mar-25
100%
EK000EL035
Voltage drop table
05-Mar-25
09-Mar-25
100%
EK000ML42C
Prepare & Issue Prelim. RFQ - ML420 to Proc.
05-Mar-25
09-Mar-25
100%
EK000MU33C
Prepare & Issue Prelim. RFQ - MU330 to Proc.
05-Mar-25
09-Mar-25
100%
EK000PI140
Eqvlnt Line Counts / Planning Area-Utility Plant
05-Mar-25
09-Mar-25
100%
PK000MJ35G
Issue MJ305 RFQ
05-Mar-25
12-Mar-25
100%
PK000MJ36G
Issue MJ306 RFQ
05-Mar-25
12-Mar-25
100%
EK000CS030
Start-up Schedule (Prelim for 1st Planner)
05-Mar-25
14-Mar-25
100%
EK000MC32B
Develop & Issue Design Data for ERW - MC311
05-Mar-25
19-Mar-25
100%
EK000MC23A
Develop & Issue Load Sheets for ERW - MC230
05-Mar-25
22-Mar-25
100%
EK000MC32F
Finalize Equip. Data Sheets for ERW - MC311
05-Mar-25
24-May-25
100%
EK000MD22A
Develop & Issue Load Sheets for ERW - MD202
06-Mar-25
06-Mar-25
100%
PK000MJ21I
Eval Bids & Issue Recmd MJ202
06-Mar-25
06-Mar-25
100%
PK000MBP3G
Issue 101-B Pressure Parts RFQ
06-Mar-25
07-Mar-25
100%
EK000MBP1D
101-B Technical Bid Evaluation Shop Fab
06-Mar-25
09-Mar-25
100%
EK000MJ37A
Develop & Issue Load Sheets for ERW - MJ340
06-Mar-25
09-Mar-25
100%
EK000ML31B
Develop & Issue Design Data for ERW - ML313
06-Mar-25
15-Mar-25
100%
EK000MD42P
Confirm Analytical Design for ERW - MD402
06-Mar-25
21-Mar-25
100%
PK000MB63H
Receive Quotes for MB630
06-Mar-25
29-Mar-25
100%
PK000MBP4H
Receive Quotes for 101-B Cast Material
06-Mar-25
03-Apr-25
100%
EK000ML50F
Update/Issue Formal Inquiry for ERW - ML500
06-Mar-25
27-Apr-25
100%
EK000PE020
WMS Setup & Development
07-Mar-25
15-Mar-25
100%
EK000CV080
Egyptian Professional Eng. - Issue P.O/Subc. Pkg
08-Mar-25
09-Mar-25
100%
PK000MB51G
Issue MB511 RFQ
08-Mar-25
09-Mar-25
100%
EK000MJ21F
Update/Issue Formal Inquiry for ERW - MJ202
08-Mar-25
13-Mar-25
100%
EK000MC21B
Develop & Issue Design Data for ERW - MC210
08-Mar-25
01-Apr-25
100%
EK000MJ31B
Develop & Issue Design Data for ERW - MJ301
08-Mar-25
12-Apr-25
100%
PK000MBP3H
Receive Quotes for 101-B Pressure Part
08-Mar-25
15-Apr-25
100%
EK000PI055
Prepare Object Engineering Work Instruction
08-Mar-25
15-Mar-25
100%
PK000MJ39G
Issue MJ391/MJ392 RFQ
09-Mar-25
09-Mar-25
100%
EK000PC010
Estimate Turnover to Project Team
09-Mar-25
15-Mar-25
100%
EK000PI085
Estimate/Schedule Review
09-Mar-25
15-Mar-25
100%
EK000MD34R
Develop Final Analytical Sktch for ERW - MD304
09-Mar-25
16-Mar-25
100%
EK000MD43P
Confirm Analytical Design for ERW - MD403
09-Mar-25
16-Mar-25
100%
EK000MC61A
Develop & Issue Load Sheets for ERW - MC610
09-Mar-25
20-Mar-25
100%
PK000IC36B
DCS (MIV) - Inquiry REQ/RFQ
09-Mar-25
21-Mar-25
100%
EK000PC015
Estimate Recast & Develop Project Control Budget
09-Mar-25
23-Apr-25
100%
EK000PI105
Performance Test of Citrix for PDS w/MEC
12-Mar-25
12-Mar-25
100%
PK000MU35G
Issue MU350 RFQ
12-Mar-25
13-Mar-25
100%
PK000ML42G
Issue ML420 RFQ
12-Mar-25
15-Mar-25
100%
EK000MU41F
Develop & Issue Inquiry for ERW - MU410
12-Mar-25
16-Mar-25
100%
PK000PK045
Review ISSP work process with eng.
12-Mar-25
16-Mar-25
100%
PK000PK050
Est Preselect low cost redundent bid items
12-Mar-25
16-Mar-25
100%
EK000SY060
010 Util & Offsites Conceptual Design revw mtngs
12-Mar-25
19-Mar-25
100%
EK000MD34P
Confirm Analytical Design for ERW - MD304
12-Mar-25
20-Mar-25
100%
EK000MU41A
Develop & Issue Load Sheets for ERW - MU410
12-Mar-25
20-Mar-25
100%
EK000MD31P
Confirm Analytical Design for ERW - MD301
12-Mar-25
29-Mar-25
100%
PK000MB51H
Receive Quotes for MB511
12-Mar-25
02-Apr-25
100%
EK000MD32P
Confirm Analytical Design for ERW - MD302
12-Mar-25
02-Apr-25
100%
EK000PI100
Critical Line List
12-Mar-25
06-Apr-25
100%
PK000MJ39H
Receive Quotes MJ391/MJ392
12-Mar-25
09-Apr-25
100%
EK000EV020
Develop Preliminary noise model
12-Mar-25
20-Apr-25
100%
PK000MJ22M
Requote/Bid Condition/Final Tab - MJ201
12-Mar-25
18-May-25
100%
EK000MC21F
Finalize Equip. Data Sheets for ERW - MC210
12-Mar-25
13-Jun-25
100%
EK000SY075
010 OSBL Hydraulic Calculations
12-Mar-25
30-Jul-25
100%
PK000MBP1I
Eval Bids & Issue Recmd 101-B Shop Fab
13-Mar-25
13-Mar-25
100%
PK000MJ35H
Receive Quotes MJ305
13-Mar-25
26-Mar-25
100%
PK000MJ36H
Receive Quotes MJ306
13-Mar-25
26-Mar-25
100%
EK000MD020
Equipment Modeling for Vessel - MEC
13-Mar-25
25-Mar-26
100%
EK000MB61D
Technical Evaluation - MB610
14-Mar-25
20-Mar-25
100%
PK000MU35H
Receive Quotes MU350
14-Mar-25
06-Apr-25
100%
PK000MJ21M
Requote/Bid Condition/Final Tab - MJ202
14-Mar-25
01-May-25
100%
EK000PR080
Input to Process Guarantees
14-Mar-25
03-May-25
100%
EK000IC35D
DCS - Tech Evaluation
14-Mar-25
14-May-25
100%
EK000MJ32A
Develop & Issue Load Sheets for ERW - MJ302
15-Mar-25
20-Mar-25
100%
PK000MBP1J
Final Negotiate/Interim Award - 101-B Shop Fab
15-Mar-25
09-Aug-25
100%
EK000ML31F
Update/Issue Formal Inquiry for ERW - ML313
16-Mar-25
16-Mar-25
100%
EK000MD31B
Develop & Issue Design Data for ERW - MD301
16-Mar-25
19-Mar-25
100%
EK000MD32B
Develop & Issue Design Data for ERW - MD302
16-Mar-25
19-Mar-25
100%
EK000MD34B
Develop & Issue Design Data for ERW - MD304
16-Mar-25
19-Mar-25
100%
EK000MJ22D
Technical Evaluation - MJ201
16-Mar-25
19-Mar-25
100%
EK000MD45A
Develop & Issue Load Sheets for ERW - MD405
16-Mar-25
20-Mar-25
100%
EK000ML43A
Develop & Issue Load Sheets for ERW - ML430
16-Mar-25
20-Mar-25
100%
EK000ML44A
Develop & Issue Load Sheets for ERW - ML440
16-Mar-25
20-Mar-25
100%
PK000ML42H
Receive Quotes ML420
16-Mar-25
08-Apr-25
100%
EK000PE095
Disciplines Load WMS with Budgets & Deliverables
16-Mar-25
20-Apr-25
100%
EK000MD34D
Technical Evaluation - MD304
16-Mar-25
23-Apr-25
100%
EK000MD41D
Technical Evaluation - MD401
16-Mar-25
23-Apr-25
100%
PK000PIA1A
Bulk Piping A/G & U/G - Issue REQ/RFQ to Vend
18-Mar-25
20-Mar-25
100%
EK000ML42A
Develop & Issue Load Sheets for ERW - ML420
19-Mar-25
20-Mar-25
100%
EK000MU35A
Develop & Issue Load Sheets for ERW - MU350
19-Mar-25
20-Mar-25
100%
EK000MU41B
Develop & Issue Design Data for ERW - MU410
19-Mar-25
21-Mar-25
100%
EK000MU30F
Develop & Issue Inquiry for ERW - MU300
19-Mar-25
26-Mar-25
100%
EK000MF32A
05A MF312 2105-F Water Tank - Process Load Sht.
19-Mar-25
26-Mar-25
100%
EK000MF33B
Develop/Issue Load Sht & Design Data ERW - MF311
19-Mar-25
26-Mar-25
100%
EK000MF32B
Develop/Issue Load Sht & Design Data ERW - MF302
19-Mar-25
06-Apr-25
100%
EK000MD21B
Develop & Issue Design Data for ERW - MD201
19-Mar-25
08-May-25
100%
PK000ML31M
Requote/Bid Condition/Final Tab - ML313
19-Mar-25
30-Jul-25
100%
EK000ML42F
Update/Issue Formal Inquiry for ERW - ML420
19-Mar-25
24-Apr-25
100%
PK000MJ22I
Eval Bids & Issue Recmd MJ201
20-Mar-25
22-Mar-25
100%
EK000MC63A
Develop & Issue Load Sheets for ERW - MC630
20-Mar-25
22-Mar-25
100%
PK000MU41G
Issue MU410 RFQ
20-Mar-25
21-Mar-25
100%
EK000MU61F
Develop & Issue Inquiry for ERW - MU611
20-Mar-25
25-Mar-25
100%
EK000I210D
000 Control Valves - Technical Evaluation
20-Mar-25
23-May-25
100%
EK000MU35F
Update/Issue Formal Inquiry for ERW - MU350
21-Mar-25
22-Mar-25
100%
EK000MD47A
Develop & Issue Load Sheets for ERW - MD406
21-Mar-25
23-Mar-25
100%
EK000MD51B
Develop & Issue Design Data for ERW - MD501
21-Mar-25
28-Mar-25
100%
EK000MC61D
Technical Evaluation - MC610
21-Mar-25
01-Apr-25
100%
EK000MC61F
Finalize Equip. Data Sheets for ERW - MC610
21-Mar-25
10-Apr-25
100%
EK000MJ32B
Develop & Issue Design Data for ERW - MJ302
21-Mar-25
13-Apr-25
100%
EK000MD34F
Update/Issue Formal Inquiry for ERW - MD304
21-Mar-25
20-Apr-25
100%
PK000MB61I
Eval Bids & Issue Recmd MB610
21-Mar-25
25-Apr-25
100%
PK000PIA1B
Bulk Piping A/G & U/G - Receive Bids
21-Mar-25
04-May-25
100%
PK000IC36C
DCS (MIV) - Receive Bids
22-Mar-25
12-Apr-25
100%
EK000EV010
Develop design basis for evaporation pond
22-Mar-25
11-May-25
100%
EK000YA802
(EP-03) Issue Process Plan
22-Mar-25
22-Mar-25
100%
EK000MB51F
Prepare & Issue Purchase ERW - MB511
23-Mar-25
17-Apr-25
100%
EK010PI010
Develop Plot Plan & ID Areas - Overall Site (Drwg 0101) ICA
23-Mar-25
31-Aug-25
100%
EK030PI010
Develop Plot Plan & ID Areas - Utility Plant ICA
23-Mar-25
11-Oct-25
100%
EK050PI010
Develop Plot Plan & ID Areas - Dock/Storage ICA
23-Mar-25
11-Oct-25
100%
PK000MU41H
Receive Quotes MU410
23-Mar-25
25-Apr-25
100%
EK000MJ39B
Develop/Issue Load Sht & Design Data ERW - MJ391
25-Mar-25
29-Mar-25
100%
EK000ML50D
Technical Evaluation - ML500
25-Mar-25
27-Apr-25
100%
EK000MD025
Prepare job quality drawings for ERW
25-Mar-25
28-May-25
100%
EK000ML44B
Develop & Issue Design Data for ERW - ML440
26-Mar-25
27-Mar-25
100%
EK000MF31P
Confirm Analytical Design for ERW - MF301
26-Mar-25
29-Mar-25
100%
EK000PR070
Effluent Summary
26-Mar-25
30-Mar-25
100%
EK000MD51D
Technical Evaluation - MD501
26-Mar-25
03-Apr-25
100%
EK000MU33F
Update/Issue Formal Inquiry for ERW - MU330
26-Mar-25
04-Apr-25
100%
EK000MD33F
Update/Issue Formal Inquiry for ERW - MD303
26-Mar-25
11-May-25
100%
PK000MU30G
Issue MU300 RFQ
26-Mar-25
28-Mar-25
100%
PK000MU61G
Issue MU611 RFQ
26-Mar-25
04-Apr-25
100%
EK000MF32F
Develop & Issue Design Data for Tank Subcontract - MF302
26-Mar-25
08-Apr-25
100%
PK000MJ35I
Eval Bids & Issue Recmd MJ305
26-Mar-25
02-May-25
100%
EK000I131D
Technical Evaluation - Transmitters
26-Mar-25
23-May-25
100%
EK000MJ35D
Technical Evaluation - MJ305
27-Mar-25
02-Apr-25
100%
EK000MJ36D
Technical Evaluation - MJ306
27-Mar-25
02-Apr-25
100%
EK000MF32C
05A MF312 2105-F Water Tank - Issue Data for Subcontract
27-Mar-25
09-Apr-25
100%
EK000MF33F
Develop & Issue Design Data for Tank Subcontract - MF311
27-Mar-25
09-Apr-25
100%
EK000CVK35
OSBL Rough Grading/Road
27-Mar-25
23-May-25
100%
EK000MD51F
Update/Issue Formal Inquiry for ERW - MD501
29-Mar-25
08-Apr-25
100%
EK000MD45P
Confirm Analytical Design for ERW - MD405
29-Mar-25
25-Apr-25
100%
PK000MU30H
Receive Quotes MU300
29-Mar-25
10-May-25
100%
EK000MB62D
Technical Evaluation - MB621
30-Mar-25
18-Apr-25
100%
EK000MB63D
Technical Evaluation - MB630
30-Mar-25
24-Jun-25
100%
EK000MF31B
Develop & Issue Design Data for Tank Subcontrac - MF301
01-Apr-25
08-Apr-25
100%
EK000MJ34B
Develop/Issue Load Sht & Design Data ERW - MJ304
01-Apr-25
08-Apr-25
100%
EK000PR065
Catalyst and Chemical Specs
01-Apr-25
09-Apr-25
100%
EK000MB070
101-B Foundation Loads
01-Apr-25
19-Apr-25
100%
EK000PR075
Process Description
01-Apr-25
25-Apr-25
100%
EK000MJ39F
Update/Issue Formal Inquiry for ERW - MJ391
01-Apr-25
27-Apr-25
100%
EK000QM020
Develop/ Issue/ Approval of QA/QC Manual (EBIC/EXIM Verification)
01-Apr-25
31-Oct-25
100%
EK000MD44P
Confirm Analytical Design for ERW - MD404
02-Apr-25
03-Apr-25
100%
EK000MD31F
Update/Issue Formal Inquiry for ERW - MD301
02-Apr-25
16-Apr-25
100%
EK000MU61B
Develop/Issue Load Sht & Design Data ERW - MU611
02-Apr-25
14-May-25
100%
EK000MB51D
Technical Evaluation - MB511
02-Apr-25
16-Apr-25
100%
EK000MD32F
Update/Issue Formal Inquiry for ERW - MD302
02-Apr-25
20-Apr-25
100%
EK000MD43D
Technical Evaluation - MD403
02-Apr-25
25-Apr-25
100%
PK000MC61I
Eval Bids & Issue Recmd MC610
03-Apr-25
05-Apr-25
100%
EK000MC61B
Develop & Issue Design Data for ERW - MC610
04-Apr-25
20-Apr-25
100%
PK000PSA8A
000 Relief Valves - Issue RFQ
04-Apr-25
10-Apr-25
100%
EK000MJ35B
Develop & Issue Design Data for ERW - MJ305
05-Apr-25
09-May-25
100%
EK000MB080
101-B Convection Coil Design
05-Apr-25
12-Apr-25
100%
EK000ML31D
Technical Evaluation - ML313
05-Apr-25
19-Apr-25
100%
PK000MJ36I
Eval Bids & Issue Recmd MJ306
06-Apr-25
12-Apr-25
100%
PK000PK040
Establish Project Warranty Criteria
06-Apr-25
12-Apr-25
100%
EK000MB050
101-B Radiant coil design
06-Apr-25
12-Apr-25
100%
EK000MD22P
Confirm Analytical Design for ERW - MD202
06-Apr-25
15-Apr-25
100%
EK000MB33F
MB333 - Develop & Issue Purchase ERW 101-B
06-Apr-25
23-Apr-25
100%
EK010SY020
010 CW Twr & FW Tanks P&ID development IDR Issue
06-Apr-25
25-Apr-25
100%
EK030SY020
030 Utility Plant P&ID development IDR Issue
06-Apr-25
25-Apr-25
100%
EK050SY020
050 Dock/Storage P&ID development IDR Issue
06-Apr-25
25-Apr-25
100%
EK000MBP4D
Technical Evaluation - 101-B Cast Material
06-Apr-25
01-May-25
100%
PK000MU61H
Receive Quotes MU611
06-Apr-25
02-May-25
100%
PK000MD51I
Eval Bids & Issue Recmd MD501
06-Apr-25
24-May-25
100%
EK000PI131
Devlop Balance Tech P-Class specs for Procuremnt
06-Apr-25
25-May-25
100%
EK000FP050
FP Overall Firewater P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK010FP011
FP Firewater Pump P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK010FP050
FP Deluge P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
PK000MU33G
Issue MU330 RFQ
08-Apr-25
09-Apr-25
100%
EK000MD43B
Develop & Issue Design Data for ERW - MD403
08-Apr-25
12-Apr-25
100%
EK000MU35D
Technical Evaluation - MU350
08-Apr-25
19-Apr-25
100%
EK000MC21D
Technical Evaluation - MC210
08-Apr-25
23-Apr-25
100%
EK000MC23D
Technical Evaluation - MC230
08-Apr-25
23-Apr-25
100%
EK000MD45B
Develop & Issue Design Data for ERW - MD405
08-Apr-25
08-May-25
100%
PK000MC61M
Requote/Bid Condition/Final Tab - MC610
08-Apr-25
04-Sep-25
100%
EK000MC23B
Develop & Issue Design Data for ERW - MC230
09-Apr-25
13-Apr-25
100%
EK000MD42B
Develop & Issue Design Data for ERW - MD402
09-Apr-25
13-Apr-25
100%
EK000MD41B
Develop & Issue Design Data for ERW - MD401
09-Apr-25
18-Apr-25
100%
EK000MU30B
Develop/Issue Load Sht & Design Data ERW - MU300
09-Apr-25
25-Apr-25
100%
EK000PS010
Level III CPM Schedule / First Planner
09-Apr-25
24-May-25
100%
PK000IC35E
DCS - Eval Bids/Issue Recmd
09-Apr-25
31-May-25
100%
EK000ML42D
Technical Evaluation - ML420
09-Apr-25
19-Apr-25
100%
EK000MJ34F
Update/Issue Formal Inquiry for ERW - MJ304
09-Apr-25
26-Apr-25
100%
PK000MD51M
Requote/Bid Condition/Final Tab - MD501
09-Apr-25
03-May-25
100%
EK000MB41D
Technical Evaluation - MB410
10-Apr-25
01-May-25
100%
PK000MU33H
Receive Quotes MU330
10-Apr-25
20-May-25
100%
PK000PSA8B
000 Relief Valves - Receive Quotes
10-Apr-25
20-Jun-25
100%
EK000MJ33B
Develop/Issue Load Sht & Design Data ERW - MJ303
11-Apr-25
23-May-25
100%
EK000MJ32D
Technical Evaluation - MJ302
12-Apr-25
19-Apr-25
100%
EK000MJ31D
Technical Evaluation - MJ301
12-Apr-25
25-Apr-25
100%
EK000MB055
101-B Radiant coil BOM
15-Apr-25
19-Apr-25
100%
EK000MB075
101-B Convection Coil BOM
15-Apr-25
19-Apr-25
100%
EK000ML51B
Develop/Issue Load Sht & Design Data ERW - ML512
15-Apr-25
19-Apr-25
100%
EK000MC63B
Develop & Issue Design Data for ERW - MC630
15-Apr-25
20-Apr-25
100%
EK000MB61E
Prepare & Issue Purchase ERW - MB610
15-Apr-25
22-Apr-25
100%
EK000MD43F
Update/Issue Formal Inquiry for ERW - MD403
15-Apr-25
25-Apr-25
100%
EK000MD32D
Technical Evaluation - MD302
15-Apr-25
04-May-25
100%
EK000IC36D
DCS (MIV) - Tech Evaluation
15-Apr-25
17-May-25
100%
EK000MC31P
Develop & Issue Setting Plans for ERW - MC310
15-Apr-25
28-May-25
100%
EK000MC21P
Develop & Issue Setting Plans for ERW - MC210
15-Apr-25
20-Jun-25
100%
EK000CS025
Turnover System Definition for ISBL
15-Apr-25
31-Jan-26
100%
EK000MD42F
Update/Issue Formal Inquiry for ERW - MD402
16-Apr-25
19-Apr-25
100%
EK000ML42B
Develop & Issue Design Data for ERW - ML420
16-Apr-25
20-Apr-25
100%
EK000MD31D
Technical Evaluation - MD301
16-Apr-25
25-Apr-25
100%
EK000ML33B
Develop/Issue Load Sht & Design Data ERW - ML330
16-Apr-25
25-Apr-25
100%
EK000MD33D
Technical Evaluation - MD303
16-Apr-25
04-May-25
100%
EK000MBP3D
Technical Evaluation - 101-B Pressure Parts
16-Apr-25
10-May-25
100%
EK000MD21F
Develop & Issue Inquiry ERW - MD201
17-Apr-25
17-Jun-25
100%
EK000PR140
Formal Issue of Process Release
18-Apr-25
08-May-25
100%
PK000MD31M
Final Tab/Recmd - MD301
18-Apr-25
24-Jul-25
100%
EK000MD47P
Confirm Analytical Design for ERW - MD406
18-Apr-25
22-Apr-25
100%
PK000MD45I
Eval Bids & Issue Recmd MD405
19-Apr-25
01-May-25
100%
PK000MJ36J
Final Negotiate/Interim Award - MJ306
19-Apr-25
02-May-25
100%
PK000MD22I
Eval Bids & Issue Recmd MD202
19-Apr-25
03-May-25
100%
PK000MD42I
Eval Bids & Issue Recmd MD402
19-Apr-25
04-May-25
100%
PK000MD44I
Eval Bids & Issue Recmd MD404
19-Apr-25
04-May-25
100%
EK000MJ37B
Develop & Issue Design Data for ERW - MJ340
19-Apr-25
09-May-25
100%
EK000MD41F
Update/Issue Formal Inquiry for ERW - MD401
20-Apr-25
26-Apr-25
100%
EK000MD44Q
Develop Analytical Sketches for ERW - MD404
20-Apr-25
27-Apr-25
100%
EK000MJ73B
Develop/Issue Load Sht & Design Data ERW - MJ730
20-Apr-25
30-Apr-25
100%
EK000EV015
Issue load sheets for wastewater systems
20-Apr-25
31-May-25
100%
EK000MD44B
Develop & Issue Design Data for ERW - MD404
22-Apr-25
25-Apr-25
100%
EK000MD47B
Develop & Issue Design Data for ERW - MD406
22-Apr-25
25-Apr-25
100%
PK000I110B
Issue RFQ - Orific Plates
22-Apr-25
25-Apr-25
100%
PK000I112B
Issue RFQ - Venturis
22-Apr-25
25-Apr-25
100%
PK000I115B
Issue RFQ - Annubars
22-Apr-25
25-Apr-25
100%
PK000I116B
Issue RFQ - Wedge Flow Meters
22-Apr-25
25-Apr-25
100%
PK000I616B
Issue RFQ - Steam Drum Lvl Gauges
22-Apr-25
25-Apr-25
100%
PK000I623B
Issue RFQ - Multi-Point Thermocouples
22-Apr-25
25-Apr-25
100%
PK000MB81I
Eval Bids & Issue Recmd MB810
22-Apr-25
25-Apr-25
100%
PK000ML31I
Eval Bids & Issue Recmd ML313
22-Apr-25
26-Apr-25
100%
PK000ML42I
Eval Bids & Issue Recmd ML420
22-Apr-25
26-Apr-25
100%
PK000MU35I
Eval Bids & Issue Recmd MU350
22-Apr-25
26-Apr-25
100%
PK000MD42M
Requote/Bid Condition/Final Tab - MD402
22-Apr-25
30-Apr-25
100%
EK000MD46B
Develop/Issue Load Sht & Design Data ERW - MD411
22-Apr-25
03-May-25
100%
PK000MJ32I
Eval Bids & Issue Recmd MJ302
22-Apr-25
03-May-25
100%
PK000MD34M
Requote/Bid Condition/Final Tab - MD304
22-Apr-25
04-May-25
100%
PK000MD46I
Eval Bids & Issue Recmd MD411
22-Apr-25
04-May-25
100%
EK000MU11B
05B MU311 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU25B
02G MU225 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU32B
01D MU322 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MD22B
Develop & Issue Design Data for ERW - MD202
23-Apr-25
01-May-25
100%
PK000MD32M
Requote/Bid Condition/Final Tab - MD302
23-Apr-25
10-May-25
100%
EK000MU31B
Develop/Issue Load Sht & Design Data ERW - MU310
23-Apr-25
16-May-25
100%
EK000MC23F
Finalize Equip. Data Sheets for ERW - MC230
23-Apr-25
13-Jun-25
100%
PK000MD41I
Eval Bids & Issue Recmd MD401
23-Apr-25
02-May-25
100%
PK000MD34I
Eval Bids & Issue Recmd MD304
24-Apr-25
11-May-25
100%
PK000MC21I
Eval Bids & Issue Recmd MC210
24-Apr-25
24-May-25
100%
PK000MC23I
Eval Bids & Issue Recmd MC230
24-Apr-25
24-May-25
100%
PK000I611B
Issue RFQ - Pressure Gauges
24-Apr-25
30-Apr-25
100%
PK000I612B
Issue RFQ - Differential Pressure Gauges
25-Apr-25
30-Apr-25
100%
PK000I618B
Issue RFQ - Temperature Gauges
25-Apr-25
30-Apr-25
100%
PK000I621B
Issue RFQ - Temperature Elements
25-Apr-25
30-Apr-25
100%
PK000I121B
Issue RFQ - Vortex Meters
25-Apr-25
01-May-25
100%
PK000I122B
Issue RFQ - Coriolis Meters
25-Apr-25
01-May-25
100%
PK000I124B
Issue RFQ - Rotameters
25-Apr-25
01-May-25
100%
PK000I127B
Magnetic Flow Meters - Issue RFQ
25-Apr-25
01-May-25
100%
PK000ML42M
Requote/Bid Condition/Final Tab - ML420
25-Apr-25
18-Oct-25
100%
PK000I617B
Issue RFQ - Magnetic Lvl Gauges
26-Apr-25
01-May-25
100%
+
MB333 - Issue RFQ 101-B
26-Apr-25
02-May-25
100%
EK000CV036
Issue Geotech S/C PKG
26-Apr-25
02-May-25
100%
PK000MJ31I
Eval Bids & Issue Recmd MJ301
26-Apr-25
03-May-25
100%
EK000CV140
Issue Site Survey S/C PKG
26-Apr-25
14-May-25
100%
PK000I115C
Receive Quotes - Annubars
26-Apr-25
14-May-25
100%
PK000I116C
Receive Quotes - Wedge Flow Meters
26-Apr-25
15-May-25
100%
EK000CV145
Issue Site Leveling PKG
26-Apr-25
16-May-25
100%
PK000I616C
Receive Quotes - Steam Drum Lvl Gauges
26-Apr-25
17-May-25
100%
PK000I110C
Receive Quotes - Orific Plates
26-Apr-25
20-May-25
100%
PK000I112C
Receive Quotes - Venturis
26-Apr-25
13-Jun-25
100%
PK000I623C
Receive Quotes - Multi-Point Thermocouples
26-Apr-25
15-Jul-25
100%
PK000MB62I
Eval Bids & Issue Recmd MB621
27-Apr-25
29-Apr-25
100%
PK000MJ34G
Issue MJ304 RFQ
27-Apr-25
30-Apr-25
100%
EK000MD44F
Update/Issue Formal Inquiry for ERW - MD404
27-Apr-25
01-May-25
100%
EK000ML51F
Develop & Issue Inquiry for ERW - ML512
27-Apr-25
01-May-25
100%
PK000MD43I
Eval Bids & Issue Recmd MD403
27-Apr-25
04-May-25
100%
PK000MD43M
Requote/Bid Condition/Final Tab - MD403
27-Apr-25
04-May-25
100%
PK000ML50I
Eval Bids & Issue Recmd ML500
27-Apr-25
04-May-25
100%
EK000MJ31F
Update/Issue Formal Inquiry for ERW - MJ301
27-Apr-25
08-May-25
100%
EK000MBP1E
Prepare & Issue Purchase ERW 101-B Shop Fab
27-Apr-25
10-May-25
100%
EK000ML33F
Develop & Issue Inquiry for ERW - ML330
27-Apr-25
13-May-25
100%
PK000MB51I
Eval Bids & Issue Recmd MB511
27-Apr-25
14-May-25
100%
EK000MJ32F
Update/Issue Formal Inquiry for ERW - MJ302
27-Apr-25
29-May-25
100%
EK000MB63F
Prepare & Issue Purchase ERW - MB630
27-Apr-25
29-May-25
100%
EK000MJ36B
Develop/Issue Load Sht & Design Data ERW - MJ306
27-Apr-25
08-Jun-25
100%
PK000MU35M
Requote/Bid Condition/Final Tab - MU350
27-Apr-25
15-Jul-25
100%
PK000MD41M
Final Tab/Recmd - MD401
27-Apr-25
23-Jul-25
100%
PK000ML50M
Requote/Bid Condition/Final Tab - ML500
29-Apr-25
08-Aug-25
100%
PK000MJ39M
Requote/Bid Condition/Final Tab - MJ391/MJ392
29-Apr-25
20-Dec-25
100%
EK000MU35B
Develop & Issue Design Data for ERW - MU350
01-May-25
14-May-25
100%
EK000IC010
Make decision of FF vs. Traditional DCS system
01-May-25
17-May-25
100%
EK000MJ75B
Develop & Issue Design Data for ERW - MJ750
01-May-25
20-May-25
100%
EK000CV136
Issue Rough Grade (Ammonia) S/C PKG
01-May-25
27-May-25
100%
EK000MJ73F
Develop & Issue Inquiry for ERW - MJ730
01-May-25
12-Jun-25
100%
PK000MJ34H
Receive Quotes MJ304
01-May-25
01-May-25
100%
PK000ML51G
Issue ML512 RFQ
01-May-25
01-May-25
100%
EK000MD22F
Update/Issue Formal Inquiry for ERW - MD202
01-May-25
17-May-25
100%
PK000I611C
Receive Quotes - Pressure Gauges
01-May-25
22-May-25
100%
PK000I612C
Receive Quotes - Differential Pressure Gauges
01-May-25
22-May-25
100%
EK000MC23P
Develop & Issue Setting Plans for ERW - MC230
01-May-25
21-Jun-25
100%
PK000I621C
Receive Quotes - Temperature Elements
01-May-25
10-Jul-25
100%
PK000I618C
Receive Quotes - Temperature Gauges
01-May-25
11-Jul-25
100%
EK000MU11O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU25O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU310
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU32O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK010SY030
010 CW Twr & FW Tanks P&ID IDR Meeting milestone
02-May-25
03-May-25
100%
EK030SY030
030 Utility Plant P&ID IDR Meeting milestone
02-May-25
03-May-25
100%
EK050SY030
050 Dock/Storage P&ID IDR Meeting milestone
02-May-25
03-May-25
100%
PK000MBP4I
Eval Bids & Issue Recmd 101-B Cast Material
02-May-25
10-May-25
100%
EK000MD46P
Confirm Analytical Design for ERW - MD411
02-May-25
11-May-25
100%
PK000MB41I
Eval Bids & Issue Recmd MB410
02-May-25
20-May-25
100%
EK000MJ34D
Technical Evaluation - MJ304
02-May-25
03-May-25
100%
PK000I121C
Receive Quotes - Vortex Meters
02-May-25
20-May-25
100%
PK000I122C
Receive Quotes - Coriolis Meters
02-May-25
20-May-25
100%
PK000I124C
Receive Quotes - Rotameters
02-May-25
20-May-25
100%
PK000I127C
Magnetic Flow Meters - Receive Quotes
02-May-25
20-May-25
100%
PK000I617C
Receive Quotes - Magnetic Lvl Gauges
02-May-25
22-May-25
100%
PK000ML51H
Receive Quotes ML512
02-May-25
17-Jun-25
100%
EK000MC32P
Develop & Issue Setting Plans for ERW - MC311
02-May-25
20-Jun-25
100%
PK000MJ35J
Final Negotiate/Interim Award - MJ305
02-May-25
23-Aug-25
100%
EK000MU41D
Technical Evaluation - MU410
03-May-25
28-Jun-25
100%
PK000MU61I
Eval Bids & Issue Recmd MU611
03-May-25
25-Jul-25
100%
PK000MD33I
Eval Bids & Issue Recmd MD303
04-May-25
10-May-25
100%
EK000MD31E
Prepare & Issue Purchase ERW - MD301
04-May-25
11-May-25
100%
EK000MD34E
Prepare & Issue Purchase ERW - MD304
04-May-25
11-May-25
100%
EK000MBP4E
Prepare & Issue Purchase ERW 101-B Cast Material
04-May-25
17-May-25
100%
EK000PC020
Load PCMS & Issue First Cost Report
04-May-25
18-May-25
100%
EK000MB41E
Prepare & Issue Purchase ERW - MB410
04-May-25
20-May-25
100%
EK010SY040
010 CW Twr & FW Tanks P&IDs - ICA Issue development
04-May-25
20-Jun-25
100%
EK030SY040
030 Utility Plant P&IDs - ICA Issue development
04-May-25
20-Jun-25
100%
EK050SY040
050 Dock/Storage P&IDs - ICA Issue development
04-May-25
20-Jun-25
100%
EK000MD32E
Prepare & Issue Purchase ERW - MD302
06-May-25
10-May-25
100%
PK000MD32I
Eval Bids & Issue Recmd MD302
06-May-25
10-May-25
100%
PK000MJ34I
Eval Bids & Issue Recmd MJ304
06-May-25
10-May-25
100%
EK000MD43E
Prepare & Issue Purchase ERW - MD403
06-May-25
11-May-25
100%
PK000PIA4A
Product Line Piping - Issue REQ/RFQ to Vend
06-May-25
15-May-25
100%
EK05BPI030
05B Conceptual Layout - Supersketches
07-May-25
27-Dec-26
59%
PK000MD31I
Eval Bids & Issue Recmd MD301
07-May-25
11-May-25
100%
EK000MU33B
Develop/Issue Load Sht & Design Data ERW - MU330
07-May-25
20-May-25
100%
EK000MC31D
Technical Evaluation - MC310
07-May-25
24-May-25
100%
EK000MC32D
Technical Evaluation - MC311
07-May-25
24-May-25
100%
EK020MC31D
MC312 - (120,121-C) - Technical Evaluation
07-May-25
24-May-25
100%
PK000MB33H
MB333 - Receive Quotes 101-B
07-May-25
08-Jun-25
100%
EK000MU61D
Technical Evaluation - MU611
07-May-25
20-Jun-25
100%
PK000PIA1C
Bulk Piping A/G & U/G - Tech Evaluation
07-May-25
21-Jun-25
100%
PK000PIA1D
Bulk Piping A/G & U/G - Eval Bids/Issue Recmd
07-May-25
01-Jul-25
100%
PK000PTA0A
Engineered Pipe Supports - Inquiry REQ/RFQ
07-May-25
04-Jun-25
100%
EK000MU21B
Develop/Issue Load Sht & Design Data ERW - MU221
08-May-25
10-May-25
100%
EK000MU22B
Develop/Issue Load Sht & Design Data ERW - MU222
08-May-25
20-May-25
100%
EK000MU29B
Develop/Issue Load Sht & Design Data ERW - MU292
08-May-25
20-May-25
100%
EK000YA005
Process Release
08-May-25
08-May-25
100%
EK000YA811
(EP-12) Issue Process Release
08-May-25
08-May-25
100%
EK000MD51E
Prepare & Issue Purchase ERW - MD501
09-May-25
11-May-25
100%
EK000MJ37F
Develop & Issue Inquiry for ERW - MJ340
09-May-25
05-Jun-25
100%
PK000MJ32M
Requote/Bid Condition/Final Tab - MJ302
09-May-25
16-Jul-25
100%
PK000MJ31M
Requote/Bid Condition/Final Tab - MJ301
09-May-25
25-Jul-25
100%
EK000MJ35F
Update/Issue Formal Inquiry for ERW - MJ305
10-May-25
24-May-25
100%
PK000MU30I
Eval Bids & Issue Recmd MU300
10-May-25
29-Oct-25
100%
PK000MD47G
Issue MD406 RFQ
13-May-25
13-May-25
100%
EK000MBP3E
Prepare & Issue Purchase ERW 101-B Pressure Part
13-May-25
16-May-25
100%
PK000MBP3I
Eval Bids & Issue Recmd 101-B Pressure Parts
13-May-25
18-May-25
100%
EK000I220A
Issue Preliminary ERW Pkg - MOV Valves
13-May-25
31-May-25
100%
EK000MD45F
Update/Issue Formal Inquiry for ERW - MD405
13-May-25
31-May-25
100%
PK000MB63I
Eval Bids & Issue Recmd MB630
13-May-25
11-Jul-25
100%
EK000I354A
ITCC - Engr ERW Issued
13-May-25
23-Jul-25
100%
EK000MU30D
Technical Evaluation - MU300
13-May-25
27-Sep-25
100%
EK000MD46F
Update/Issue Formal Inquiry for ERW - MD411
14-May-25
31-May-25
100%
EK000MB62F
Prepare & Issue Purchase ERW - MB621
14-May-25
05-Jun-25
100%
PK000MD33M
Final Tab/Recmd - MD303
14-May-25
23-Jul-25
100%
PK000ML33G
Issue ML330 RFQ
14-May-25
15-May-25
100%
PK000MD47H
Receive Quotes MD406
14-May-25
06-Jun-25
100%
PK000I115E
Eval Bids / Issue Recmd - Annubars
15-May-25
31-Jul-25
100%
PK000PIA4B
Product Line Piping - Receive Bids
16-May-25
06-Jun-25
100%
PK000ML33H
Receive Quotes ML330
16-May-25
10-Jul-25
100%
PK000I116E
Eval Bids / Issue Recmd - Wedge Flow Meters
16-May-25
31-Jul-25
100%
EK000MB045
Catalyst Vac data sheets
20-May-25
28-May-25
100%
EK000CV065
Review Perimeter Wall Design - IFC (by OCI)
20-May-25
14-Jun-25
100%
PK000MU33I
Eval Bids & Issue Recmd MU330
20-May-25
09-Sep-25
100%
EK000MJ75F
Develop & Issue Inquiry for ERW - MJ750
21-May-25
28-May-25
100%
PK000I110E
Eval Bids / Issue Recmd - Orific Plates
21-May-25
31-Jul-25
100%
PK000I121E
Eval Bids / Issue Recmd - Vortex Meters
21-May-25
31-Jul-25
100%
PK000I122E
Eval Bids / Issue Recmd - Coriolis Meters
21-May-25
31-Jul-25
100%
PK000I124E
Eval Bids / Issue Recmd - Rotameters
21-May-25
31-Jul-25
100%
PK000I616E
Eval Bids / Issue Recmd - Steam Drum Lvl Gauges
21-May-25
31-Jul-25
100%
PK000I621E
Eval Bids / Issue Recmd - Temperature Elements
21-May-25
31-Jul-25
100%
PK000I611E
Eval Bids / Issue Recmd - Pressure Gauges
22-May-25
31-Jul-25
100%
PK000I617E
Eval Bids / Issue Recmd - Magnetic Lvl Gauges
22-May-25
31-Jul-25
100%
EK000YA806
(EP-07) Issue Project Plan
24-May-25
24-May-25
100%
PK000I131E
Eval Bids / Issue Recmd - Transmitters
24-May-25
31-May-25
100%
PK000I210E
000 Control Valves - Eval Bids / Issue Recmd
24-May-25
31-May-25
100%
PK000MJ75G
Issue MJ750 RFQ
27-May-25
28-May-25
100%
EK000MBG10
General & Administrative
28-May-25
27-Dec-26
57%
EK000I110D
Technical Evaluation - Orific Plates
28-May-25
10-Jun-25
100%
EK000I115D
Technical Evaluation - Annubars
28-May-25
10-Jun-25
100%
EK000I116D
Technical Evaluation - Wedge Flow Meters
28-May-25
10-Jun-25
100%
EK000I121D
Technical Evaluation - Vortex Meters
28-May-25
10-Jun-25
100%
EK000I122D
Technical Evaluation - Coriolis Meters
28-May-25
10-Jun-25
100%
EK000I124D
Technical Evaluation - Rotameters
28-May-25
10-Jun-25
100%
EK000I611D
Technical Evaluation - Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I612D
Technical Evaluation - Differential Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I616D
Technical Evaluation - Steam Drum Lvl Gauges
28-May-25
10-Jun-25
100%
EK000I617D
Technical Evaluation - Magnetic Lvl Gauges
28-May-25
10-Jun-25
100%
EK000MJ33F
Develop & Issue Inquiry for ERW - MJ303
28-May-25
18-Jun-25
100%
EK000MJ36F
Update/Issue Formal Inquiry for ERW - MJ306
28-May-25
19-Jun-25
100%
EK000I127D
Magnetic Flow Meters - Technical Evaluation
28-May-25
26-Jun-25
100%
EK000MB33D
MB333 - Technical Evaluation 101-B
28-May-25
01-Jul-25
100%
PK000I612E
Eval Bids / Issue Recmd - Differential Pressure Gauges
28-May-25
31-Jul-25
100%
EK000YA801
(EP-02) Issue 30 day Look Ahead Schedule
28-May-25
28-May-25
100%
PK000MJ75H
Receive Quotes MJ750
28-May-25
29-May-25
100%
EK000MJ75D
Technical Evaluation - MJ750
29-May-25
30-May-25
100%
PK000MJ75I
Eval Bids & Issue Recmd MJ750
29-May-25
30-May-25
100%
PK000MJ37G
Issue MJ340 RFQ
31-May-25
11-Jun-25
100%
EK000ML43F
Develop & Issue Inquiry for ERW - ML430
31-May-25
06-Jun-25
100%
PK000MJ37Q
Prepare & Issue Prelim. RFQ - MJ307 to Proc.
31-May-25
12-Jun-25
100%
EK000MB69F
Prepare & IssuePurchase ERW - MB691
03-Jun-25
17-Jun-25
100%
PK000I230B
Issue RFQ - On/Off Valves
04-Jun-25
06-Jun-25
100%
PK000PTA0B
Engineered Pipe Supports - Receive Bids
04-Jun-25
25-Jun-25
100%
EK000MU33D
Technical Evaluation - MU330
04-Jun-25
01-Jul-25
100%
EK000QM025
Training - Management System
05-Jun-25
05-Jun-25
100%
PK000I220B
Issue RFQ - MOV's
05-Jun-25
06-Jun-25
100%
EK000I230A
Issue Preliminary ERW Pkg - On/Off Valves
05-Jun-25
15-Jun-25
100%
EK000PS040
Incorporate Comments / Issue Baseline Schedule
05-Jun-25
15-Jun-25
100%
EK000MU22F
Develop & Issue Inquiry for ERW - MU222
05-Jun-25
26-Jun-25
100%
EK000MB65F
Develop & Issue Purchase ERW - MB622
06-Jun-25
17-Jun-25
100%
PK000I221B
000 Everest Control Valves - Issue RFQ
06-Jun-25
06-Jun-25
100%
PK000I221C
000 Everest Control Valves - Receive Quotes
06-Jun-25
25-Jun-25
100%
PK000I230C
Receive Quotes -On/Off Valves
07-Jun-25
02-Jul-25
100%
PK000I220C
Receive Quotes - MOV's
07-Jun-25
02-Jul-25
100%
PK000PIA4C
Product Line Piping - Tech Evaluation
07-Jun-25
04-Jul-25
100%
PK000MB33I
MB333 - Eval Bids & Issue Recmd 101-B
07-Jun-25
25-Jul-25
100%
PK000MD47I
Eval Bids & Issue Recmd MD406
07-Jun-25
19-Sep-25
100%
EK000I112D
Technical Evaluation - Venturis
10-Jun-25
14-Jun-25
100%
PK000MJ73G
Issue MJ730 RFQ
10-Jun-25
17-Jun-25
100%
EK000PS030
Schedule Risk Analysis
10-Jun-25
20-Jun-25
100%
EK000MB66F
Prepare & IssuePurchase ERW - MB660
10-Jun-25
21-Jun-25
100%
EK000MU34B
Develop/Issue Load Sht & Design Data ERW - Chlorination Unit
11-Jun-25
15-Jun-25
100%
PK000MJ37F
Issue MJ307 RFQ
12-Jun-25
21-Jun-25
100%
PK000MJ37H
Receive Quotes MJ340
12-Jun-25
18-Jul-25
100%
EK000MB68F
Prepare & Issue Purchase ERW - MB692
13-Jun-25
26-Jun-25
100%
PK000MD21G
Issue MD201 RFQ
17-Jun-25
20-Jun-25
100%
EK000MB21F
Prepare & Issue Purchase ERW - MB212
17-Jun-25
25-Jun-25
100%
EK000MB42F
Prepare & Issue Purchase ERW - MB420
17-Jun-25
26-Jun-25
100%
PK000ML43G
Issue ML430 RFQ
18-Jun-25
22-Jun-25
100%
PK000MB69G
Issue MB691 RFQ
18-Jun-25
25-Jun-25
100%
PK000MJ73H
Receive Quotes MJ730
18-Jun-25
06-Aug-25
100%
PK000MJ33G
Issue MJ303 RFQ
19-Jun-25
21-Jun-25
100%
EK000FP055
FP Overall Firewater P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK010FP020
FP Firewater Pump P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK010FP060
FP Deluge P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK000MB34F
Prepare & Issue Purchase ERW - MB340
20-Jun-25
21-Jun-25
100%
PK000MB65G
Issue MB622 RFQ
20-Jun-25
25-Jun-25
100%
EK010SY050
010 Twr & FW Tanks P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
100%
EK030SY050
030 Utility Plant P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
100%
EK050SY050
050 Dock/Storage P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
100%
PK000PSA8D
000 Relief Valves - Eval Bids / Issue Recmd
20-Jun-25
26-Sep-25
100%
PK000ML43H
Receive Quotes ML430
21-Jun-25
10-Jul-25
100%
PK000MJ37D
Receive Quotes MJ307
21-Jun-25
19-Jul-25
100%
PK000MU41I
Eval Bids & Issue Recmd MU410
21-Jun-25
24-Jul-25
100%
EK030SY135
030 Utility Plant CV & FE Process Data
21-Jun-25
07-Sep-25
100%
PK000MC21M
Requote/Bid Condition/Final Tab - MC210
21-Jun-25
27-Sep-25
100%
PK000MC23M
Requote/Bid Condition/Final Tab - MC230
21-Jun-25
27-Sep-25
100%
PK000MJ33H
Receive Quotes MJ303
22-Jun-25
29-Aug-25
100%
PK000MB68G
Issue MB692 RFQ
24-Jun-25
26-Jun-25
100%
PK000PIA1E
Bulk Piping A/G & U/G - Reconfirm Pricing
24-Jun-25
01-Jul-25
100%
PK000MD21H
Receive Quotes for MD201
24-Jun-25
11-Jul-25
100%
EK050SY060
050 Dock/Storage P&ID's - IPL Issue Development
25-Jun-25
11-Oct-25
100%
EK010SY060
010 CW Twr & FW Tanks P&ID's - IPL Issue Development
25-Jun-25
31-Oct-25
100%
EK030SY060
030 Utility Plant P&ID's - IPL Issue Development
25-Jun-25
19-Nov-25
100%
PK000MB66G
Issue MB660 RFQ
25-Jun-25
25-Jun-25
100%
EK000I221D
000 Everest Control Valves - Technical Evaluation
25-Jun-25
10-Jul-25
100%
PK000MB66H
Receive Quotes for MB660
25-Jun-25
27-Jul-25
100%
PK000PTA0C
Engineered Pipe Supports - Eval Bids/Issue Recmd
25-Jun-25
08-Aug-25
100%
EK000YA809
(EP-10) Locate Utility Tie-Ins
26-Jun-25
26-Jun-25
100%
EK000MU21F
Develop & Issue Inquiry for ERW - MU221
26-Jun-25
03-Jul-25
100%
PK000MB65H
Receive Quotes for MB622
26-Jun-25
18-Jul-25
100%
PK000MB21G
Issue MB212 RFQ
26-Jun-25
22-Jul-25
100%
PK000MB69H
Receive Quotes for MB691
26-Jun-25
22-Jul-25
100%
PK000MB68H
Receive Quotes for MB692
27-Jun-25
26-Jul-25
100%
PK000I127E
Magnetic Flow Meters - Eval Bids / Issue Recmd
27-Jun-25
31-Jul-25
100%
EK000MD33E
Prepare & Issue Purchase ERW - MD303
01-Jul-25
04-Jul-25
100%
EK000MD41E
Prepare & Issue Purchase ERW - MD401
01-Jul-25
04-Jul-25
100%
PK000MB42G
Issue MB420 RFQ
02-Jul-25
05-Jul-25
100%
EK000MB64F
Prepare & Issue Purchase ERW - MB640
02-Jul-25
11-Jul-25
100%
PK000MU22G
Issue MU222 RFQ
02-Jul-25
02-Jul-25
100%
PK000I220E
Eval Bids / Issue Recmd - MOV's
02-Jul-25
27-Aug-25
100%
PK000I230E
Eval Bids / Issue Recmd - On/Off Valves
02-Jul-25
28-Aug-25
100%
PK000MB34G
Issue MB340 RFQ
03-Jul-25
03-Jul-25
100%
EK03FPI000
03F Preliminary Drawings for Supersketch U-2002
03-Jul-25
04-Jul-25
100%
PK000MU21G
Issue MU221 RFQ
03-Jul-25
05-Jul-25
100%
PK000MU22H
Receive Quotes MU222
03-Jul-25
22-Jul-25
100%
PK000MB34H
Receive Quotes for MB340
03-Jul-25
24-Jul-25
100%
PK000PIA4D
Product Line Piping - Eval Bids/Issue Recmd
05-Jul-25
18-Jul-25
100%
PK000MB42H
Receive Quotes for MB420
05-Jul-25
20-Sep-25
100%
PK000MJ34X
Eval Bids & Issue Recmd MJ304
06-Jul-25
09-Sep-25
100%
PK000MU21H
Receive Quotes MU221
08-Jul-25
25-Jul-25
100%
PK000MB64G
Issue MB640 RFQ
09-Jul-25
11-Jul-25
100%
PK000I221E
000 Everest Control Valves - Eval Bids / Issue Recmd
10-Jul-25
31-Jul-25
100%
EK000ML33D
Technical Evaluation - ML330
10-Jul-25
23-Aug-25
100%
EK000ML43D
Technical Evaluation - ML430
10-Jul-25
06-Sep-25
100%
PK000I618E
Eval Bids / Issue Recmd - Temperature Gauges
11-Jul-25
31-Jul-25
100%
PK000MB64H
Receive Quotes for MB640
12-Jul-25
09-Aug-25
100%
EK03API000
03A Preliminary Drawings for Supersketch L-2003
13-Jul-25
13-Jul-25
100%
PK020MC31E
MC312 - (120,121-C) - Eval Bids & Issue Recmd
13-Jul-25
19-Aug-25
100%
PK000MC32I
Eval Bids & Issue Recmd MC311
13-Jul-25
14-Oct-25
100%
PK000MC31I
Eval Bids & Issue Recmd MC310
13-Jul-25
20-Dec-25
100%
EK03API030
03A Conceptual Layout - Supersketches
15-Jul-25
22-Jul-25
100%
PK000MD21I
Eval Bids & Issue Recmd MD201
15-Jul-25
17-Aug-25
100%
PK000I623E
Eval Bids / Issue Recmd - Multi-Point Thermocouples
16-Jul-25
31-Jul-25
100%
EK000I220D
Technical Evaluation - MOV's
16-Jul-25
23-Jul-25
100%
EK000MD21D
Technical Evaluation - MD201
16-Jul-25
10-Aug-25
100%
EK000I230D
Technical Evaluation - On/Off Valves
17-Jul-25
24-Jul-25
100%
PK000I444B
Issue RFQ - Analyzer Shelter
19-Jul-25
25-Jul-25
100%
EK000MB65D
Technical Evaluation - MB622
19-Jul-25
02-Aug-25
100%
PK000MJ37E
Technical Evaluation - MJ307
19-Jul-25
06-Dec-25
100%
EK01UPICWA
01U Plant Layout Model - Cooling Water
20-Jul-25
23-Aug-25
100%
EK000I618D
Technical Evaluation - Temperature Gauges
22-Jul-25
26-Jul-25
100%
EK000I621D
Technical Evaluation - Temperature Elements
22-Jul-25
26-Jul-25
100%
EK000I623D
Technical Evaluation - Multi-Point Thermocouples
22-Jul-25
26-Jul-25
100%
PK000MB33J
MB333 - Final Negotiate/Interim Award 101-B
22-Jul-25
26-Jul-25
100%
EK000I352A
SIS - Engr ERW Issued
22-Jul-25
02-Aug-25
100%
EK000MB69D
Technical Evaluation - MB691
22-Jul-25
07-Aug-25
100%
PK000MB21H
Receive Quotes for MB212
22-Jul-25
28-Aug-25
100%
EK000MU22D
Technical Evaluation - MU222
22-Jul-25
06-Sep-25
100%
PK000MU41J
Final Negotiate/Interim Award - MU410
24-Jul-25
24-Jul-25
100%
PK000I354B
ITCC - Inquiry REQ/RFQ
24-Jul-25
01-Aug-25
100%
PK000MB34I
Eval Bids & Issue Recmd MB340
24-Jul-25
14-Aug-25
100%
EK000MJ37D
Technical Evaluation - MJ340
24-Jul-25
28-Aug-25
100%
PK000MU41P
Issue Formal P.O. for MU410
24-Jul-25
05-Sep-25
100%
EK000MJ39D
Technical Evaluation - MJ391
25-Jul-25
21-Dec-25
100%
EK000MJ31X
Technical Evaluation - MJ301
25-Jul-25
10-Aug-25
100%
PK000MJ32X
Technical Evaluation - MJ302
25-Jul-25
10-Aug-25
100%
PK000I444C
Receive Quotes - Analyzer Shelter
25-Jul-25
13-Sep-25
100%
PK000MU61J
Final Negotiate/Interim Award - MU611
26-Jul-25
29-Jul-25
100%
PK000MB33K
MB333 - Fab/PO Promise 101-B Riser Transition 101-B
29-Jul-25
27-Dec-26
52%
PK000I112E
Eval Bids / Issue Recmd - Venturis
29-Jul-25
31-Jul-25
100%
EK000MU11L
05B MU311 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MU25L
02G MU225 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MU32L
01D MU322 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
100%
EK000MB68D
Technical Evaluation - MB692
29-Jul-25
30-Aug-25
100%
PK000MU61P
Issue Formal P.O. for MU611
29-Jul-25
03-Sep-25
100%
EK01BPI000
01B Preliminary Drawings for Supersketch J-2001,2003,2004,2007
30-Jul-25
30-Jul-25
100%
EK01DPI000
01D Preliminary Drawings for Supersketch J-2202
30-Jul-25
30-Jul-25
100%
PK000MD33J
Final Negotiate/Interim Award - MD303
30-Jul-25
09-Aug-25
100%
EK000MU31L
Define Chemical Treatment Requirements - MU310
30-Jul-25
10-Aug-25
100%
PK000MU35J
Final Negotiate/Interim Award - MU350
30-Jul-25
10-Aug-25
100%
EK000MB66D
Technical Evaluation - MB660
30-Jul-25
13-Aug-25
100%
EK000MB34D
Technical Evaluation - MB340
30-Jul-25
13-Aug-25
100%
EK010SY135
010 CW Twr & FW Tanks CV & FE Process Data
30-Jul-25
17-Aug-25
100%
EK000ML51D
Technical Evaluation - ML512
30-Jul-25
19-Aug-25
100%
PK000MBP3J
Final Negotiate/Interim Award - Pressure Parts
30-Jul-25
30-Aug-25
100%
EK000MU21D
Technical Evaluation - MU221
30-Jul-25
14-Sep-25
100%
PK000I110G
Final Negotiation / Interim Award - Orific Plates
31-Jul-25
01-Aug-25
100%
PK000I112G
Final Negotiation / Interim Award - Venturis
31-Jul-25
01-Aug-25
100%
PK000I115G
Final Negotiation / Interim Award - Annubars
31-Jul-25
01-Aug-25
100%
PK000I121G
Final Negotiation / Interim Award - Vortex Meters
31-Jul-25
01-Aug-25
100%
PK000I122G
Final Negotiation / Interim Award - Coriolis Meters
31-Jul-25
01-Aug-25
100%
PK000I124G
Final Negotiation / Interim Award - Rotameters
31-Jul-25
01-Aug-25
100%
PK000I127G
Final Negotiation / Interim Award - Magnetic Flow Meters
31-Jul-25
01-Aug-25
100%
PK000I612G
Final Negotiation / Interim Award - Differential Pressure Gauges
31-Jul-25
01-Aug-25
100%
PK000I616G
Final Negotiation / Interim Award - Steam Drum Lvl Gauges
31-Jul-25
01-Aug-25
100%
PK000I116G
Final Negotiation / Interim Award - Wedge Flow Meters
31-Jul-25
06-Aug-25
100%
PK000I611G
Final Negotiation / Interim Award - Pressure Gauges
31-Jul-25
06-Aug-25
100%
PK000I617G
Final Negotiation / Interim Award - Magnetic Lvl Gauges
31-Jul-25
06-Aug-25
100%
PK000I621G
Final Negotiation / Interim Award - Temperature Elements
31-Jul-25
06-Aug-25
100%
PK000I623G
Final Negotiation / Interim Award - Multi-Point Thermocouples
31-Jul-25
06-Aug-25
100%
PK000I221G
Final Negotiation / Interim Award - Everest Control Valves
31-Jul-25
14-Aug-25
100%
EK03DPI030
03D Conceptual Layout - Supersketches
01-Aug-25
07-Aug-25
100%
EK01DPI030
01D Conceptual Layout - Supersketches
01-Aug-25
15-Aug-25
100%
PK000I131G
Final Negotiation / Interim Award - Transmitters
01-Aug-25
06-Aug-25
100%
PK000MBP4J
Final Negotiate/Interim Award - Cast Material
01-Aug-25
09-Aug-25
100%
EK000MU35E
Prepare & Issue Purchase ERW - MU350
01-Aug-25
13-Aug-25
100%
EK050SY135
050 Dock/Storage CV & FE Process Data
01-Aug-25
15-Aug-25
100%
PK000I354C
ITCC - Receive Bids
01-Aug-25
28-Aug-25
100%
EK020FP490
FP OSBL Fire Protection Eqmt. Location Plans - ICA
01-Aug-25
02-Sep-25
100%
PK000I115K
Issue Formal Purchase Agreement - Annubars
01-Aug-25
31-Oct-25
100%
PK000I121K
Issue Formal Purchase Agreement - Vortex Meters
01-Aug-25
31-Oct-25
100%
PK000I122K
Issue Formal Purchase Agreement - Coriolis Meters
01-Aug-25
31-Oct-25
100%
PK000I124K
Issue Formal Purchase Agreement - Rotameters
01-Aug-25
31-Oct-25
100%
PK000I127K
Magnetic Flow Meters - Issue Formal Purchase Agreement
01-Aug-25
31-Oct-25
100%
PK000I110K
Issue Formal Purchase Agreement. - Orific Plates
01-Aug-25
14-Nov-25
100%
PK000I112K
Issue Formal Purchase Agreement - Venturis
01-Aug-25
14-Nov-25
100%
PK000I616K
Issue Formal Purchase Agreement. - Steam Drum Lvl Gauges
01-Aug-25
30-Dec-25
100%
PK000I612K
Issue Formal Purchase Agreement - Differential Pressure Gauges
01-Aug-25
06-Feb-26
100%
PK000I352B
SIS - Inquiry REQ/RFQ
02-Aug-25
07-Aug-25
100%
EK000YA810
(EP-11) Issue Level 3 CPM Schedule
03-Aug-25
03-Aug-25
100%
PK000MB61J
Final Negotiate/Interim Award - MB610
05-Aug-25
09-Aug-25
100%
PK000MB62J
Final Negotiate/Interim Award - MB621
05-Aug-25
09-Aug-25
100%
PK000MB63J
Final Negotiate/Interim Award - MB630
05-Aug-25
09-Aug-25
100%
PK000MB81J
Final Negotiate/Interim Award - MB810
05-Aug-25
09-Aug-25
100%
EK000QM005
Training - Object Engineering
06-Aug-25
13-Aug-25
100%
EK000I444A
Develop & Issue Inquiry ERW - Analyzer Shelter
06-Aug-25
17-Aug-25
100%
EK000MJ73D
Technical Evaluation - MJ730
06-Aug-25
16-Sep-25
100%
PK000MJ73I
Eval Bids & Issue Recmd MJ730
06-Aug-25
19-Oct-25
100%
PK000MB69I
Eval Bids & Issue Recmd MB691
06-Aug-25
29-Oct-25
100%
PK000I131K
Issue Formal Purchase Agreement - Transmitters
06-Aug-25
02-Dec-25
100%
PK000I621K
Issue Formal Purchase Agreement - Temperature Elements
06-Aug-25
30-Dec-25
100%
PK000I623K
Issue Formal Purchase Agreement - Multi-Point Thermocouples
06-Aug-25
30-Dec-25
100%
PK000I617K
Issue Formal Purchase Agreement - Magnetic Lvl Gauges
06-Aug-25
20-Jan-26
100%
PK000I611K
Issue Formal Purchase Agreement - Pressure Gauges
06-Aug-25
06-Feb-26
100%
PK000I116K
Issue Formal Purchase Agreement - Wedge Flow Meters
06-Aug-25
07-Feb-26
100%
PK000I352C
SIS - Receive Bids
07-Aug-25
21-Aug-25
100%
PK000PTA0D
Engineered Pipe Supports - Interim Award
08-Aug-25
14-Aug-25
100%
EK000CV165
Issue ISBL Rough Grade Design Pkg.
09-Aug-25
04-Oct-25
100%
PK000MBP1K
MB221 - Fab/PO Promise 101-B Radiant Steel Panels
09-Aug-25
27-Dec-26
51%
PK000MBP1Q
MB221 - Fab/PO Promise 101-B Radiant Coil/Harps
09-Aug-25
27-Dec-26
51%
PK000MBP1R
MB221 - Fab/PO Promise 101-B Convection Modules
09-Aug-25
27-Dec-26
51%
PK000MBP1S
MB221 - Fabr/PO Promise 101-B Radiant Ducting
09-Aug-25
27-Dec-26
51%
PK000MD31K
MD301 - Fabricate/PO Promise 103-D
09-Aug-25
17-Feb-27
55.0d
46%
PK000MD33K
MD303 - Fabricate/PO Promise 105-D
09-Aug-25
20-Mar-27
50.0d
44%
PK000MJ21K
MJ202 - Fabricate/PO Promise 102/3/5-J
09-Aug-25
27-Dec-26
51%
PK000I210G
Final Negotiation / Interim Award - Control Valves
09-Aug-25
09-Aug-25
100%
PK000MB41J
Final Negotiate/Interim Award - MB410
09-Aug-25
09-Aug-25
100%
PK000MD31J
Final Negotiate/Interim Award - MD301
09-Aug-25
09-Aug-25
100%
PK000MJ21J
Final Negotiate/Interim Award - MJ202
09-Aug-25
09-Aug-25
100%
PK000MJ75J
Final Negotiate/Interim Award - MJ750
09-Aug-25
12-Aug-25
100%
PK000PR20B
PR201 KAAP Catalyst - Issue RFQ
09-Aug-25
12-Aug-25
100%
PK000MD34J
Final Negotiate/Interim Award - MD304
09-Aug-25
16-Aug-25
100%
PK000MD42J
Final Negotiate/Interim Award - MD402
09-Aug-25
16-Aug-25
100%
PK000MD44J
Final Negotiate/Interim Award - MD404
09-Aug-25
16-Aug-25
100%
PK000MD45J
Final Negotiate/Interim Award - MD405
09-Aug-25
16-Aug-25
100%
PK000MD46J
Final Negotiate/Interim Award - MD411
09-Aug-25
16-Aug-25
100%
PK000MD22J
Final Negotiate/Interim Award - MD202
09-Aug-25
17-Aug-25
100%
PK000MD32J
Final Negotiate/Interim Award - MD302
09-Aug-25
17-Aug-25
100%
PK000MD33P
Issue Formal P.O. for MD303
09-Aug-25
19-Aug-25
100%
PK000MD41J
Final Negotiate/Interim Award - MD401
09-Aug-25
23-Aug-25
100%
PK000MD43J
Final Negotiate/Interim Award - MD403
09-Aug-25
23-Aug-25
100%
PK000MD51J
Final Negotiate/Interim Award - MD501
09-Aug-25
27-Aug-25
100%
PK000MJ21N
Recv. Planning V. Data MJ202
09-Aug-25
30-Aug-25
100%
PK000MJ22J
Final Negotiate/Interim Award - MJ201
09-Aug-25
30-Aug-25
100%
PK000MJ75N
Recv. Planning V. Data MJ750
09-Aug-25
30-Aug-25
100%
PK000ML31J
Final Negotiate/Interim Award - ML313
09-Aug-25
31-Aug-25
100%
PK000MD21J
Final Negotiate/Interim Award - MD201
09-Aug-25
02-Sep-25
100%
PK000MB63P
Issue Formal P.O. for MB630
09-Aug-25
09-Sep-25
100%
PK000MD31N
Recv. Planning V. Data MD301
09-Aug-25
09-Sep-25
100%
PK000MB41P
Issue Formal P.O. for MB410
09-Aug-25
10-Sep-25
100%
PK000ML31N
Recv. Planning V. Data ML313
09-Aug-25
12-Sep-25
100%
PK000PIA4E
Product Line Piping - Final Negotiation/Interim Award
09-Aug-25
13-Sep-25
100%
PK000MD41N
Recv. Planning V. Data MD401
09-Aug-25
17-Sep-25
100%
PK000MJ21P
Issue Formal P.O. for MJ202
09-Aug-25
19-Sep-25
100%
PK000MBP1P
Issue Formal P.O. for 101-B Shop Fab
09-Aug-25
20-Sep-25
100%
PK000MBP4P
Issue Formal P.O. for 101-B Cast Material
09-Aug-25
20-Sep-25
100%
PK000MB81P
Issue Formal P.O. for MB810
09-Aug-25
21-Sep-25
100%
PK000MU35P
Issue Formal P.O. for MU350
09-Aug-25
23-Sep-25
100%
PK000MD33N
Recv. Planning V. Data MD303
09-Aug-25
25-Sep-25
100%
PK000MB61P
Issue Formal P.O. for MB610
09-Aug-25
30-Sep-25
100%
PK000IC35G
DCS - Interim Award
09-Aug-25
12-Oct-25
100%
PK000MD43N
Recv. Planning V. Data MD403
09-Aug-25
14-Oct-25
100%
EK000MB64D
Technical Evaluation - MB640
09-Aug-25
17-Oct-25
100%
PK000MJ32J
Final Negotiate/Interim Award - MJ302
09-Aug-25
20-Nov-25
100%
PK000MJ31J
Final Negotiate/Interim Award - MJ301
09-Aug-25
21-Nov-25
100%
PK000MB62P
Issue Formal P.O. for MB621
09-Aug-25
09-Dec-25
100%
PK000I210K
000 Control Valves - Issue Formal Purchase Agreement
09-Aug-25
03-Feb-26
100%
PK000PIA1G
Bulk Piping A/G & U/G - Fab/Exworks (CS, SS, U/G)
09-Aug-25
31-Mar-26
100%
PK000MU35K
MU350 - Fabricate/PO Promise 101-U DEAERATOR
09-Aug-25
23-Apr-26
100%
EK000EB015
Notice to Proceed (Eng. & Procurement Only)
10-Aug-25
10-Aug-25
100%
EK030SY150
030 Relief Valve Calculations - Utility Plant
10-Aug-25
26-Sep-25
100%
PK000MB62K
MB621 - Fabricate/PO Promise 101-B ID & FD Fans
12-Aug-25
27-Dec-26
51%
PK000MB81K
MB810 - Fabricate/PO Promise 102-B
12-Aug-25
27-Dec-26
51%
EK000I221A
000 Everest Control Valves - Issue Inquiry Req
12-Aug-25
16-Aug-25
100%
PK000MJ75P
Issue Formal P.O. for MJ750
12-Aug-25
23-Aug-25
100%
EK000MJ21E
Prepare & Issue Purchase ERW - MJ202
12-Aug-25
30-Aug-25
100%
PK000PR20C
PR201 KAAP Catalyst - Receive Quotes
12-Aug-25
17-Sep-25
100%
PK000MU35N
Recv. Planning V. Data MU350
12-Aug-25
27-Sep-25
100%
EK05API030
05A Conceptual Layout - Supersketches
12-Aug-25
28-Sep-25
100%
EK000IC350
DCS - Develop Design Basis
12-Aug-25
04-Oct-25
100%
PK000IC35K
DCS - Formal Award
12-Aug-25
17-Oct-25
100%
PK000MB66I
Eval Bids & Issue Recmd MB660
12-Aug-25
20-Jan-26
100%
PK000MB41K
MB410 - Fabricate/PO Promise 101-B Cast Tube Supports
12-Aug-25
27-Feb-26
100%
PK000MB61K
MB610 - Fabricate/PO Promise 101-B Burners
12-Aug-25
01-Apr-26
100%
PK000MB63K
MB630 - Fabricate/PO Promise 101-B Air Preheater
12-Aug-25
14-Apr-26
100%
PK000MD32K
MD302 - Fabricate/PO Promise 104-D1/2
13-Aug-25
10-Jan-27
85.0d
49%
PK000MJ75K
MJ750 - Fabricate/PO Promise SURFACE CONDENSORS
13-Aug-25
27-Dec-26
51%
EK000MU61E
Prepare & Issue Purchase ERW - MU611
13-Aug-25
16-Aug-25
100%
PK000MD41P
Issue Formal P.O. for MD401
13-Aug-25
20-Aug-25
100%
PK000MB34J
Final Negotiate/Interim Award - MB340
13-Aug-25
14-Aug-25
100%
EK010SY150
010 Relief Valve Calculations - CW Twr & FW Tanks
14-Aug-25
26-Sep-25
100%
PK000MB34K
MB340 - Fabricate/PO Promise 101-B Finning
14-Aug-25
27-Dec-26
51%
PK000PTA0G
Engineered Pipe Supports - Fab / Exworks
14-Aug-25
27-Dec-26
51%
PK000MB34P
Issue Formal P.O. for MB340
14-Aug-25
10-Sep-25
100%
PK000PTA0E
Engineered Pipe Supports - Formal Award
14-Aug-25
30-Dec-25
100%
PK000PTA0F
Engineered Pipe Supports - Planning V. Data
14-Aug-25
24-Jan-26
100%
PK000I221K
000 Everest Control Valves - Issue Formal Purchase Agreement
14-Aug-25
03-Feb-26
100%
EK01BPI030
01B Conceptual Layout - Supersketches
15-Aug-25
31-Aug-25
100%
PK000MD22A
MD202 - Fabricate/PO Promise TOWERS 104-E
16-Aug-25
27-Dec-26
50%
PK000MD22K
MD202 - Fabricate/PO Promise TOWERS 103/105-E
16-Aug-25
27-Dec-26
50%
PK000MD22T
MD202 - Fabricate/PO Promise TOWERS 150-E
16-Aug-25
28-Feb-27
100.0d
45%
PK000MD34K
MD304 - Fabricate/PO Promise 106-D, 109-DA/B
16-Aug-25
29-Jan-27
200.0d
47%
PK000MD34Z
MD304 - Fabricate/PO Promise 108-DA/B
16-Aug-25
27-Dec-26
50%
PK000MD42K
MD402 - Fabricate/PO Promise 102-F1, 102-F2
16-Aug-25
21-Mar-27
130.0d
43%
PK000MD42N
MD402 - Fabricate/PO Promise 104-F, 144-F
16-Aug-25
27-Dec-26
50%
PK000MD44K
MD404 - Fabricate/PO Promise 109-F
16-Aug-25
27-Dec-26
50%
PK000MD44L
MD404 - Fabricate/PO Promise 107-F
16-Aug-25
27-Dec-26
50%
PK000MD44T
MD404 - Fabricate/PO Promise 132-F
16-Aug-25
27-Dec-26
50%
PK000MD45A
MD405 - Fabricate/PO Promise ISBL DRUMS - 115-F
16-Aug-25
27-Dec-26
50%
PK000MD45K
MD405 - Fabricate/PO Promise ISBL DRUMS - 156-F & 157-F
16-Aug-25
27-Dec-26
50%
PK000MD46K
MD411 - Fabricate/PO Promise OSBL DRUMS - 2203-F & 2204-F
16-Aug-25
27-Dec-26
50%
PK000MD46T
MD411 - Fabricate/PO Promise OSBL DRUMS - 2006-F
16-Aug-25
27-Dec-26
50%
PK000MD4Q
MD405 - Fabricate/PO Promise ISBL DRUMS - 118-F
16-Aug-25
27-Dec-26
50%
PK000MD42P
Issue Formal P.O. for MD402
16-Aug-25
02-Sep-25
100%
PK000MD44P
Issue Formal P.O. for MD404
16-Aug-25
02-Sep-25
100%
PK000MD45P
Issue Formal P.O. for MD405
16-Aug-25
02-Sep-25
100%
PK000MD46P
Issue Formal P.O. for MD411
16-Aug-25
02-Sep-25
100%
PK000MD32P
Issue Formal P.O. for MD302
16-Aug-25
07-Sep-25
100%
PK03FMD03
03F MD411 2006-F Boiler Blowdown Drum - Prod. V. Data
16-Aug-25
13-Sep-25
100%
PK000MD34P
Issue Formal P.O. for MD304
16-Aug-25
18-Sep-25
100%
PK000MD32N
Recv. Planning V. Data MD302
16-Aug-25
02-Oct-25
100%
PK000MD34N
Recv. Planning V. Data MD304
16-Aug-25
12-Nov-25
100%
PK020MC31G
MC312 - (120,121-C) - Final Negotiate/Interim Award
19-Aug-25
21-Aug-25
100%
PK000MBP3M
Requote/Bid Condition/Final Tab - Pressure Parts
19-Aug-25
28-Aug-25
100%
PK000ML51I
Eval Bids & Issue Recmd ML512
19-Aug-25
06-Sep-25
100%
PK000ML33I
Eval Bids & Issue Recmd ML330
19-Aug-25
13-Sep-25
100%
EK000MJ75E
Prepare & Issue Purchase ERW - MJ750
19-Aug-25
28-Sep-25
100%
EK050SY150
050 Relief Valve Calculations - Dock/Storage
20-Aug-25
25-Sep-25
100%
PK000PIA1F
Bulk Piping A/G & U/G - Formal Award
20-Aug-25
03-Sep-25
100%
PK020MC31C
MC312 - Fabricate/PO Promise 121-C
21-Aug-25
28-Feb-27
90.0d
44%
PK020MC31K
MC312 - Fabricate/PO Promise 120-C
21-Aug-25
28-Feb-27
90.0d
44%
EK000PE070
Kick-off meeting at MEC
22-Aug-25
23-Aug-25
100%
PK020MC31H
MC312 - (120,121-C) - Issue Formal P.O.
22-Aug-25
19-Sep-25
100%
EK03UPIFWA
03U Plant Layout Model - Firewater
22-Aug-25
05-Oct-25
100%
EK01UPIFWA
01U Plant Layout Model - Firewater
22-Aug-25
08-Oct-25
100%
PK000MJ35P
Issue Formal P.O. for MJ305
22-Aug-25
04-Feb-26
100%
PK000MJ36P
Issue Formal P.O. for MJ306
22-Aug-25
04-Feb-26
100%
PK000MD41K
MD401 - Fabricate/PO Promise 101-F
23-Aug-25
27-Dec-26
50%
PK000MD43K
MD403 - Fabricate/PO Promise 106-F
23-Aug-25
11-Mar-27
135.0d
43%
PK000MJ35K
MJ305 - Fabricate/PO Promise ISBL ANSI/API PUMPS
23-Aug-25
27-Dec-26
50%
ZZ2070
MJ305 - Fabricate/PO Promise OSBL ANSI/API PUMPS
23-Aug-25
27-Dec-26
50%
PK000MD43P
Issue Formal P.O. for MD403
23-Aug-25
07-Sep-25
100%
PK000ML43I
Eval Bids & Issue Recmd ML430
23-Aug-25
12-Sep-25
100%
PK000MJ35N
Recv. Planning V. Data MJ305
23-Aug-25
27-Sep-25
100%
PK000MJ36N
Recv. Planning V. Data MJ306
23-Aug-25
27-Sep-25
100%
PK000MD51P
Issue Formal P.O. for MD501
26-Aug-25
06-Sep-25
100%
EK01PIBSA
01U Plant Layout Model - Benfield Sewer
26-Aug-25
05-Oct-25
100%
EK01UPISSA
01U Plant Layout Model - Sanitary Sewer
26-Aug-25
05-Oct-25
100%
EK000MD21E
Prepare & Issue Purchase ERW - MD201
27-Aug-25
29-Aug-25
100%
PK000MB51J
Final Negotiate/Interim Award - MB511
27-Aug-25
02-Sep-25
100%
PK000MD22P
Issue Formal P.O. for MD202
27-Aug-25
02-Sep-25
100%
PK000MB65I
Eval Bids & Issue Recmd MB622
27-Aug-25
20-Nov-25
100%
PK000MD51K
MD501 - Fabricate/PO Promise 107-D
27-Aug-25
27-Dec-26
49%
PK000I220G
Final Negotiation / Interim Award - MOV's
27-Aug-25
02-Sep-25
100%
PK000MD51N
Recv. Planning V. Data MD501
27-Aug-25
01-Nov-25
100%
PK000MBP3P
Issue Formal P.O. for 101-B Pressure Parts
28-Aug-25
16-Oct-25
100%
PK000MU31G
Issue MU310 RFQ
28-Aug-25
30-Aug-25
100%
PK000I230G
Final Negotiation / Interim Award - On/Off Valves
28-Aug-25
02-Sep-25
100%
PK000MJ37I
Eval Bids & Issue Recmd MJ340
28-Aug-25
19-Oct-25
100%
PK000MBP3T
MB311 - Shop Recv - 101-B Radiant Fittings
28-Aug-25
03-Mar-26
100%
EK000MB21D
Technical Evaluation - MB212
29-Aug-25
01-Nov-25
100%
PK000MJ22K
MJ201 - Fabricate/PO Promise 101-J
30-Aug-25
10-Jan-27
86.0d
48%
PK000ML31K
ML313 - Fabricate/PO Promise 160-L
30-Aug-25
27-Dec-26
49%
PK000MD31P
Issue Formal P.O. for MD301
30-Aug-25
12-Sep-25
100%
PK000ML31P
Issue Formal P.O. for ML313
30-Aug-25
24-Sep-25
100%
PK000MJ22P
Issue Formal P.O. for MJ201
30-Aug-25
15-Oct-25
100%
EK000MJ33D
Technical Evaluation - MJ303
30-Aug-25
19-Dec-25
100%
PK000MB68I
Eval Bids & Issue Recmd MB692
30-Aug-25
27-Feb-26
100%
PK000MU21N
Recv. Planning V. Data MU221
01-Sep-25
27-Sep-25
100%
PK000MBP3R
MB311 - Fab/Exworks 101-B Crossover Tube & Pipe
02-Sep-25
27-Dec-26
49%
PK000MBP3S
MB311 - Fab/Exworks 101-B Crossover Fittings
02-Sep-25
27-Dec-26
49%
EK010PI011
Plot Plan - Overall Site (Drwg 0101) Client ICA Approval
02-Sep-25
14-Sep-25
100%
PK000MU31H
Receive Quotes MU310
02-Sep-25
23-Sep-25
100%
PK000ML42N
Recv. Planning V. Data ML420
02-Sep-25
26-Sep-25
100%
PK000MJ32N
Recv. Planning V. Data MJ302
02-Sep-25
27-Sep-25
100%
PK000MJ34N
Recv. Planning V. Data MJ304
02-Sep-25
27-Sep-25
100%
PK000MJ37N
Recv. Planning V. Data MJ340
02-Sep-25
27-Sep-25
100%
PK000MJ39N
Recv. Planning V. Data MJ391
02-Sep-25
27-Sep-25
100%
PK000MJ73N
Recv. Planning V. Data MJ730
02-Sep-25
27-Sep-25
100%
PK000MU22N
Recv. Planning V. Data MU222
02-Sep-25
27-Sep-25
100%
PK000MB51P
Issue Formal P.O. for MB511
02-Sep-25
06-Dec-25
100%
PK000MBP3K
MB311 - Fab/Exworks 101-B Radiant Tube & Pipe
02-Sep-25
31-Mar-26
100%
EK000MB095
101-B Ducting Detail Drawings - IFF
02-Sep-25
05-Apr-26
100%
PK000MBP3O
MB311 - Fab/Exworks 101-B Convection Tube & Pipe
02-Sep-25
15-Apr-26
100%
PK000MBP3Q
MB311 - Fab/Exworks 101-B Convection Fittings
02-Sep-25
15-Apr-26
100%
EK000MD055
Pre-qualification trip to vendors shop (105-D)
03-Sep-25
05-Sep-25
100%
EK000MU41E
Prepare & Issue Purchase ERW - MU410
03-Sep-25
05-Sep-25
100%
PK000MD21P
Issue Formal P.O. for MD201
03-Sep-25
18-Sep-25
100%
PK000MU61N
Recv. Planning V. Data MU611
03-Sep-25
26-Sep-25
100%
PK000MB51K
MB511 - Fabricate/PO Promise 101-B Insulation
03-Sep-25
30-Dec-26
204.0d
48%
PK01DMUV04
01D MU611 2101-U - Piping Prod. V. Data
03-Sep-25
03-Mar-26
100%
PK01DMUV05
01D MU611 2101-U - Civil Prod. V. Data
03-Sep-25
03-Mar-26
100%
PK01DMUV06
01D MU611 2101-U - E&I Prod. V. Data
03-Sep-25
03-Mar-26
100%
PK000MB33P
MB333 - Issue Formal P.O. 101-B
04-Sep-25
06-Sep-25
100%
PK000MC61J
Final Negotiate/Interim Award - MC610
05-Sep-25
09-Sep-25
100%
PK000MJ22N
Recv. Planning V. Data MJ201
05-Sep-25
27-Sep-25
100%
PK000MU41K
MU410 - Fabricate/PO Promise 2002-U PKG BOILER
06-Sep-25
27-Dec-26
48%
PK000MU22I
Eval Bids & Issue Recmd MU222
06-Sep-25
19-Sep-25
100%
PK000MJ31N
Recv. Planning V. Data MJ301
06-Sep-25
27-Sep-25
100%
PK000ML51J
Final Negotiate/Interim Award - ML512
09-Sep-25
11-Sep-25
100%
EK030PI011
Plot Plan - Utility Plant Client ICA Approval
09-Sep-25
27-Sep-25
100%
PK000MJ34J
Final Negotiate/Interim Award - MJ304
09-Sep-25
14-Oct-25
100%
PK000MU33J
Final Negotiate/Interim Award - MU330
09-Sep-25
29-Oct-25
100%
PK000MU61K
MU611 - Fabricate/PO Promise 2101-U, 2101-UJA Thru UJG CW TWR & Fans
09-Sep-25
14-Apr-26
100%
PK000MU61T
MU611 - Fabricate/PO Promise 2101-UJA Thru UJGM CW Motors
09-Sep-25
14-Apr-26
100%
PK000MC61K
MC610 - Fabricate/PO Promise DBL PIPE EXCH 188-CA
10-Sep-25
27-Dec-26
48%
PK000MC61P
Issue Formal P.O. for MC610
10-Sep-25
12-Oct-25
100%
PK000MC61N
Recv. Planning V. Data MC610
10-Sep-25
03-Dec-25
100%
PK000MC61L
MC610 - Fabricate/PO Promise DBL PIPE EXCH 161-C
10-Sep-25
09-Apr-26
100%
EK000CV137
Issue OSBL Rough Grade Design Pkg.
11-Sep-25
26-Nov-25
100%
PK000MBP4K
MB312 - Fab/PO Promise 101-B Radiant Cast Fittings
11-Sep-25
27-Dec-26
48%
PK000MBP4Q
MB312 - Fab/PO Promise 101-B Radiant Cast Stringer Grids
11-Sep-25
27-Dec-26
48%
PK000MBP4R
MB312 - Fab/PO Promise 101-B Radiant Cast Tube/Riser/Manifold
11-Sep-25
27-Dec-26
48%
PK000ML51K
ML512 - Fabricate/PO Promise 2102-L LOADING ARM
11-Sep-25
27-Dec-26
48%
PK000MBP4M
Requote/Bid Condition/Final Tab - Cast Material
11-Sep-25
16-Sep-25
100%
EK000ML51E
Prepare & Issue Purchase ERW - ML512
11-Sep-25
25-Sep-25
100%
PK000ML51N
Recv. Planning V. Data ML512
11-Sep-25
27-Sep-25
100%
PK000ML51P
Issue Formal P.O. for ML512
11-Sep-25
27-Sep-25
100%
PK000ML43J
Final Negotiate/Interim Award - ML430
12-Sep-25
14-Oct-25
100%
PK000MB71G
Issue MB710 RFQ
13-Sep-25
17-Sep-25
100%
PK000ML33J
Final Negotiate/Interim Award - ML330
13-Sep-25
20-Sep-25
100%
EK000MJ36E
Prepare & Issue Purchase ERW - MJ306
13-Sep-25
25-Sep-25
100%
EK000MJ35E
Prepare & Issue Purchase ERW - MJ305
13-Sep-25
25-Sep-25
100%
PK000PIA4F
Product Line Piping - Formal Award
13-Sep-25
02-Oct-25
100%
EK000MJ22E
Prepare & Issue Purchase ERW - MJ201
13-Sep-25
13-Nov-25
100%
PK03EMU100
03E Recv. Planning V. Data - Utility Equip.
16-Sep-25
16-Sep-25
100%
EK050PI012
Plot Plan - Dock/Storage Issue IPL
16-Sep-25
26-Oct-25
100%
EK000I444D
Technical Evaluation - Analyzer Shelter
16-Sep-25
11-Dec-25
100%
PK000MD21K
MD201 - Fabricate/PO Promise 101-E
17-Sep-25
01-Jan-27
93.0d
46%
PK000MD21M
MD201 - Fabricate/PO Promise 102-E
17-Sep-25
05-Mar-27
62.0d
41%
PK03BMJ154
03B Recv. Planning V. Data - Pumps 2401-J, 2401-JA
17-Sep-25
17-Sep-25
100%
PK03CMJ154
03C Recv. Planning V. Data - Pumps 2205-J/JA, 2206-J/JA
17-Sep-25
17-Sep-25
100%
PK03DMJ154
03D Recv. Planning V. Data - Pumps 2202-J/JA
17-Sep-25
17-Sep-25
100%
PK05AMJ154
05A Recv. Planning V. Data - Pumps 2106/7-J
17-Sep-25
17-Sep-25
100%
PK000MU21I
Eval Bids & Issue Recmd MU221
17-Sep-25
19-Sep-25
100%
EK000ML33E
Prepare & Issue Purchase ERW - ML330
17-Sep-25
25-Sep-25
100%
EK03UPIOSA
03U Plant Layout Model - Outfall Sewer
17-Sep-25
26-Sep-25
100%
PK000MU41N
Recv. Planning V. Data MU410
17-Sep-25
27-Sep-25
100%
PK000I220K
Issue Formal Purchase Agreement. - MOV's
17-Sep-25
13-Dec-25
100%
PK000I230K
Issue Formal Purchase Agreement. - On/Off Valves
17-Sep-25
13-Dec-25
100%
EK000FP012
FP Electrical Area Classification OSBL - ICA
17-Sep-25
10-Oct-25
100%
PK000MB71H
Receive Quotes for MB710
17-Sep-25
14-Oct-25
100%
EK020PR20D
PR201 KAAP Catalyst - Technical Evaluation
17-Sep-25
01-Nov-25
100%
PK000MBP4Z
MB312 - Shop Recv. 101-B Radiant Cast Fittings
17-Sep-25
03-Mar-26
100%
EK000MC61E
Prepare & Issue Purchase ERW - MC610
18-Sep-25
25-Sep-25
100%
PK000MU21J
Final Negotiate/Interim Award - MU221
19-Sep-25
04-Nov-25
100%
PK000MU22J
Final Negotiate/Interim Award - MU222
19-Sep-25
04-Nov-25
100%
EK000MJ32E
Prepare & Issue Purchase ERW - MJ302
20-Sep-25
13-Nov-25
100%
PK000ML33K
ML330 - Fabricate/Po Promise 2101-L
20-Sep-25
27-Dec-26
47%
PK000MD47J
Final Negotiate/Interim Award - MD406
20-Sep-25
25-Sep-25
100%
PK000ML33N
Recv. Planning V. Data ML330
20-Sep-25
27-Sep-25
100%
EK03UPIASA
03U Plant Layout Model - Acid Sewer
20-Sep-25
08-Oct-25
100%
EK03UPICSA
03U Plant Layout Model - Caustic Sewer
20-Sep-25
08-Oct-25
100%
PK000ML33P
Issue Formal P.O. for ML330
20-Sep-25
31-Oct-25
100%
PK000ML43N
Recv. Planning V. Data ML430
20-Sep-25
01-Nov-25
100%
EK000MJ34E
Prepare & Issue Final Data Shts - MJ304
21-Sep-25
08-Nov-25
100%
EK000MU33E
Prepare & Issue Purchase ERW - MU330
21-Sep-25
26-Sep-25
100%
EK020MC31C
MC312 - (120,121-C) - Prepare & Issue Purchase ERW
23-Sep-25
27-Sep-25
100%
EK03CPI030
03C Conceptual Layout - Supersketches
23-Sep-25
27-Sep-25
100%
PK020MC31F
MC312 - (120,121-C) - Planning V. Data (Setting Plans)
23-Sep-25
08-Oct-25
100%
EK010I1240
Rotameters - D/S,Sizing,Tech Eval
23-Sep-25
15-Nov-25
100%
EK030I1100
030 Orific Plates - D/S Utility Plant
24-Sep-25
05-Nov-25
100%
EK030IC210
030 Control Valves - D/S, Sizing,Tech Eval
24-Sep-25
21-Dec-25
100%
EK000MU31D
Technical Evaluation - MU310
24-Sep-25
30-Sep-25
100%
PK000MD47P
Issue Formal P.O. for MD406
24-Sep-25
03-Oct-25
100%
EK010IC242
MOV Valves - D/S,Sizing,Tech Eval
25-Sep-25
15-Nov-25
100%
EK050SY185
050 SP Item Data Sheets - Dock/Storage
25-Sep-25
24-Dec-25
100%
EK01JPI030
01J Conceptual Layout - Supersketches
25-Sep-25
03-Oct-25
100%
EK010SY185
010 SP Item Data Sheets - CW Twr & FW Tanks
25-Sep-25
24-Dec-25
100%
PK000PSA8E
000 Relief Valves - Final Negotiation / Interim Award
26-Sep-25
27-Sep-25
100%
EK01UPIPWA
01U Plant Layout Model - Potable Water
26-Sep-25
05-Oct-25
100%
PK000MU33P
Issue Formal P.O. for MU330
26-Sep-25
20-Feb-26
100%
EK030SY185
030 SP Item Data Sheets - Utiliy Plant
27-Sep-25
24-Dec-25
100%
EK04API030
04A Conceptual Layout - Supersketches
27-Sep-25
27-Dec-26
46%
PK000PSA8G
000 Relief Valves - Fabricate/Exworks
27-Sep-25
30-Dec-26
257.0d
46%
PK01BMJ154
01B Recv. Planning V. Data - Pumps (2001,4,7,2203,4)
27-Sep-25
27-Sep-25
100%
PK000PSA8F
000 Relief Valves - Issue Formal Blanket P.O.
27-Sep-25
20-Dec-25
100%
EK01UPIPAA
01U Plant Layout Model - Plant Air
30-Sep-25
30-Sep-25
100%
EK01UPIWWA
01U Plant Layout Model - Waste Water
30-Sep-25
05-Oct-25
100%
EK000MC23E
Prepare & Issue Purchase ERW - MC230
30-Sep-25
15-Oct-25
100%
EK000I352D
SIS - Tech Evaluation
30-Sep-25
07-Nov-25
100%
EK000MC21E
Prepare & Issue Purchase ERW - MC210
30-Sep-25
07-Nov-25
100%
PK000MD47K
MD406 - Fabricate/PO Promise ISBL DRUMS
01-Oct-25
27-Dec-26
45%
PK000MU33K
MU330 - Fabricate/PO Promise 2001-U
01-Oct-25
27-Dec-26
45%
PK000PIA1K
Bulk Piping A/G - Fab/Exworks (CROME)
01-Oct-25
27-Dec-26
45%
PK000PIA4G
Product Line Piping - Fab/Exworks +/- 5700 Mts.
01-Oct-25
27-Dec-26
45%
PK01HMJ135
01H Recv. Planning V.Data - Emerg Pwr Generator
01-Oct-25
01-Oct-25
100%
PK05AML100
05A Recv. Planning V. Data - Special Equip.
01-Oct-25
01-Oct-25
100%
PK05BML100
05B Recv. Planning V. Data - Special Equip. 2102-L
01-Oct-25
01-Oct-25
100%
EK000MU30E
Prepare & Issue Purchase ERW - MU300
01-Oct-25
14-Oct-25
100%
EK01API030
01A Conceptual Layout - Supersketches
01-Oct-25
08-Oct-25
100%
PK000MC21J
Final Negotiate/Interim Award - MC210
01-Oct-25
09-Oct-25
100%
PK000MC23J
Final Negotiate/Interim Award - MC230
01-Oct-25
09-Oct-25
100%
EK000ML42E
Prepare & Issue Purchase ERW - ML420
01-Oct-25
10-Oct-25
100%
EK000MJ37E
Prepare & Issue Purchase ERW - MJ340
01-Oct-25
16-Oct-25
100%
PK000MB42J
Final Negotiate/Interim Award - MB420
01-Oct-25
07-Nov-25
100%
PK000PR20E
PR201 KAAP Catalyst - Eval Bids & Issue Recmd
02-Oct-25
17-Oct-25
100%
EK03BPI030
03B Conceptual Layout - Supersketches
03-Oct-25
07-Oct-25
100%
PK000I352E
SIS - Eval Bids/Issue Recmd
03-Oct-25
28-Dec-25
100%
EK010I1100
010 Orific Plates - D/S,Sizing,Tech Eval
04-Oct-25
24-Oct-25
100%
EK010I1150
Annubars - D/S,Sizing,Tech Eval
04-Oct-25
02-Nov-25
100%
EK010I1210
Vortex Meters - D/S,Sizing,Tech Eval
04-Oct-25
02-Nov-25
100%
EK050I1100
050 Orific Plates - D/S Dock/Storage Area
04-Oct-25
05-Nov-25
100%
EK010IC210
010 Control Valves - D/S,Sizing,Tech Eval
04-Oct-25
21-Dec-25
100%
EK000MU31E
Prepare & Issue Purchase ERW - MU310
04-Oct-25
08-Oct-25
100%
EK000IC351
DCS - Develop Purchase T-Req
05-Oct-25
07-Nov-25
100%
EK010SY155
010 Issue Requisition - PSA08 Relief Valves - CW Twr & FW Tanks
05-Oct-25
19-Nov-25
100%
EK030SY155
030 Issue Requisition - PSA08 Relief Valves - Utility PLant
05-Oct-25
19-Nov-25
100%
EK050SY155
050 Issue Requisition - PSA08 Relief Valves - Dock/Storage
05-Oct-25
19-Nov-25
100%
PK000IC350
DCS - Vendor Update Pricing / Quote
07-Oct-25
11-Oct-25
100%
EK000PR600
MD305 Merc. Removal Bed - Develop & Issue Load Sheets for ERW
08-Oct-25
09-Oct-25
100%
EK000MJ31E
Prepare & Issue Purchase ERW - MJ301
08-Oct-25
13-Nov-25
100%
PK000MJ33N
Recv. Planning V. Data MJ303
08-Oct-25
26-Dec-25
100%
PK000MU31I
Eval Bids & Issue Recmd MU310
08-Oct-25
04-Jan-26
100%
EK000ML31E
Prepare & Issue Purchase ERW - ML313
08-Oct-25
09-Jan-26
100%
PK000ML42J
Final Negotiate/Interim Award - ML420
09-Oct-25
12-Oct-25
100%
PK000MC21K
MC210 - Fabricate/PO Promise 110/115/124/128/130/133/134/160/167/173/174-C
09-Oct-25
27-Dec-26
44%
PK000MC21N
MC210 - Fabricate/PO Promise 127-C
09-Oct-25
27-Dec-26
44%
PK000MC23A
MC230 - Fabricate/PO Promise 106-C & 109-C
09-Oct-25
27-Dec-26
44%
PK000MC23K
MC230 - Fabricate/PO Promise 105/107/172/183-C
09-Oct-25
27-Dec-26
44%
PK000MC23N
MC230 - Fabricate/PO Promise 111/114-C
09-Oct-25
27-Dec-26
44%
PK000MC23P
Issue Formal P.O. for MC230
09-Oct-25
09-Nov-25
100%
PK000MC21P
Issue Formal P.O. for MC210
09-Oct-25
04-Dec-25
100%
EK020ELEG2
Cathodic Protection - Subcontract Consultant ERW Package
09-Oct-25
01-Mar-26
100%
EK000MC32E
Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4)
10-Oct-25
15-Nov-25
100%
EK000MD103
MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW
10-Oct-25
26-Nov-25
100%
EK000PR610
MD305 Merc. Removal Bed - Analytical Design
10-Oct-25
26-Nov-25
100%
EK000YA813
(EP-14) Issue Plot Plans for Client Approval
11-Oct-25
11-Oct-25
100%
EK04ASY170
04A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
100%
EK050SY090
050 Dock/Storage P&IDs IPL Issue Milestone
11-Oct-25
11-Oct-25
100%
EK05ASY170
05A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
100%
EK05BSY170
05B OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
100%
EK050PI011
Plot Plan - Dock/Storage Client ICA Approval
11-Oct-25
26-Oct-25
100%
PK000ML42P
Issue Formal P.O. for ML420
11-Oct-25
30-Oct-25
100%
PK000ML42K
ML420 - Fabricate/PO Promise CARTRIDGE FILTERS
11-Oct-25
28-Mar-26
100%
PK000MC32J
Final Negotiate/Interim Award - MC311
14-Oct-25
16-Oct-25
100%
PK000ML43P
Issue Formal P.O. for ML430
14-Oct-25
06-Nov-25
100%
PK000ML43K
ML430 - Fabricate/PO Promise 110-L BENFIELD MIXER
14-Oct-25
11-Mar-26
100%
PK000MJ34K
MJ304 - Fabricate/PO Promise MP BFW PUMPS
15-Oct-25
16-Jan-27
186.0d
42%
EK000I354D
ITCC - Tech Evaluation
15-Oct-25
12-Dec-25
100%
EK000MB42D
Technical Evaluation - MB420
16-Oct-25
30-Oct-25
100%
PK000MC32K
MC311 - Fabricate/PO Promise KBR S&T EXCH
16-Oct-25
16-Jan-27
76.0d
42%
PK000MC32P
Issue Formal P.O. for MC311
16-Oct-25
13-Dec-25
100%
PK000IC35J
DCS - Planning V. Data
17-Oct-25
27-Dec-26
43%
PK000MB64I
Eval Bids & Issue Recmd MB640
18-Oct-25
11-Nov-25
100%
PK000MJ73J
Final Negotiate/Interim Award - MJ730
18-Oct-25
11-Nov-25
100%
PK000MJ37J
Final Negotiate/Interim Award - MJ340
18-Oct-25
13-Dec-25
100%
PK000MB71I
Eval Bids & Issue Recmd MB710
18-Oct-25
31-Dec-25
100%
PK000IC35H
DCS - Fabricate Hardware
21-Oct-25
27-Dec-26
43%
PK000MU30J
Final Negotiate/Interim Award - MU300
25-Oct-25
29-Oct-25
100%
PK000MJ34P
Issue Formal P.O. for MJ304
30-Oct-25
22-Nov-25
100%
PK010I1240
Rotameters - Fabricate/Exworks
30-Oct-25
27-Dec-26
42%
PK000MB42I
Eval Bids & Issue Recmd MB420
30-Oct-25
31-Oct-25
100%
PK000MB69J
Final Negotiate/Interim Award - MB691
30-Oct-25
02-Nov-25
100%
PK000MU32G
01D MU322 Issue RFQ
30-Oct-25
11-Nov-25
100%
PK000MU33N
03E MU330 2001-U - Piping Conceptual V. Data
30-Oct-25
02-Feb-26
100%
PK010I1150
Annubars - Fabricate/Exworks
31-Oct-25
30-Dec-26
509.0d
41%
EK010SY090
010 CW Twr & FW Tanks P&IDs IPL Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01ASY170
01A OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01BSY170
01B OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01CSY170
01C OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01DSY170
01D OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01ESY170
01E OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01FSY170
01F OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01HSY170
01H OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01JSY170
01J OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01YSY170
01Y OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK010FP031
FP Firewater Pump P&IDs - Development & Issue IFD
01-Nov-25
27-Dec-26
41%
EK000ML43E
Prepare & Issue Purchase ERW - ML430
01-Nov-25
07-Nov-25
100%
PK01FMU100
01F Recv. Planning V. Data - Utility Equip. 2603-K, 2607-K
01-Nov-25
15-Nov-25
100%
PK000MB69K
MB691 - Fabricate/PO Promise 101-B
04-Nov-25
27-Dec-26
41%
PK000MU21K
MU221 - Fabricate/PO Promise LIFT STATION
04-Nov-25
27-Dec-26
41%
PK000MU22K
MU222 - Fabricate/PO Promise 2401-U
04-Nov-25
27-Dec-26
41%
PK000MB69P
Issue Formal P.O. for MB691
04-Nov-25
04-Nov-25
100%
EK000MJ37R
Develop & Issue Load Sheets for ERW - MJ307
04-Nov-25
08-Nov-25
100%
EK000MJ38R
Develop & Issue Load Sheets for ERW - MJ308
04-Nov-25
08-Nov-25
100%
PK000PR20F
PR201 KAAP Catalyst - Final Negotiate/Interim Award
04-Nov-25
09-Dec-25
100%
PK000MU21P
Issue Formal P.O. for MU221
04-Nov-25
11-Dec-25
100%
PK000MU22P
Issue Formal P.O. for MU222
04-Nov-25
11-Dec-25
100%
PK000MB21I
Eval Bids & Issue Recmd MB212
05-Nov-25
06-Nov-25
100%
EK000MU21E
Prepare & Issue Purchase ERW - MU221
05-Nov-25
22-Nov-25
100%
EK000MU22E
Prepare & Issue Purchase ERW - MU222
05-Nov-25
22-Nov-25
100%
EK000MU29F
Develop & Issue Inquiry for ERW - MU292
05-Nov-25
23-Nov-25
100%
PK000MJ32P
Issue Formal P.O. for MJ302
05-Nov-25
27-Nov-25
100%
PK000MB21J
Final Negotiate/Interim Award - MB212
06-Nov-25
07-Nov-25
100%
PK000MB21P
Issue Formal P.O. for MB212
07-Nov-25
21-Nov-25
100%
PK000MB42K
MB420 - Fabricate/PO Promise 101-B Cast Peep Sites
07-Nov-25
29-Jan-26
100%
EK03FPI030
03F Conceptual Layout - Supersketches (Need Dwgs)
07-Nov-25
01-Feb-26
100%
PK000MB21K
MB212 - Fabricate/PO Promise Equip. 101-B Siding
07-Nov-25
03-Mar-26
100%
PK000MB42P
Issue Formal P.O. for MB420
08-Nov-25
21-Nov-25
100%
PK000MJ73P
Issue Formal P.O. for MJ730
11-Nov-25
11-Nov-25
100%
EK000MJ37S
Develop & Issue Design Data for ERW - MJ307
11-Nov-25
15-Nov-25
100%
EK000MJ38S
Develop & Issue Design Data for ERW - MJ308
11-Nov-25
15-Nov-25
100%
EK05BEL175
Client Review of MCC Oneline Diagrams
11-Nov-25
22-Nov-25
100%
PK000MU32H
01D MU322 Receive Quotes
11-Nov-25
23-Dec-25
100%
PK000MB64J
Final Negotiate/Interim Award - MB640
11-Nov-25
06-Jan-26
100%
EK000IC352
DCS - Final Tech Evaluation for Purchase
13-Nov-25
15-Nov-25
100%
EK05BEL155
Client Review of Switchgear Oneline Diagrams
14-Nov-25
22-Nov-25
100%
PK000IC351
DCS - Vendor Provides Software & Workstations
14-Nov-25
29-Nov-25
100%
EK000MJ37T
Update/Issue Formal Inquiry for ERW - MJ307
18-Nov-25
26-Nov-25
100%
EK000MJ73E
Prepare & Issue Purchase ERW - MJ730
19-Nov-25
05-Dec-25
100%
EK000FA005
Issue First Invoice to EBIC
19-Nov-25
19-Nov-25
100%
PK000MU30K
MU300 - Fabricate/PO Promise 2102-U
19-Nov-25
27-Dec-26
39%
EK030SY090
030 Utility Plant P&IDs IPL Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03ASY170
03A OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03BSY170
03B OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03CSY170
03C OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03DSY170
03D OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03ESY170
03E OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03FSY170
03F OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03YSY170
03Y OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
PK000MU30N
Recv. Planning V. Data MU300 - EDR Unit
19-Nov-25
10-Jan-26
100%
PK000MU30P
Issue Formal P.O. for MU300
19-Nov-25
16-Jan-26
100%
PK000MJ31K
MJ301 - Fabricate/ PO Promise 104-J
20-Nov-25
31-Jan-27
168.0d
35%
PK000MJ32K
MJ302 - Fabricate/PO Promise 107-JA/JB/JC
20-Nov-25
17-Jan-27
175.0d
37%
PK000MU11G
05B MU311 Issue RFQ
20-Nov-25
26-Nov-25
100%
PK000MJ31P
Issue Formal P.O. for MJ301
20-Nov-25
27-Nov-25
100%
PK000MB65J
Final Negotiate/Interim Award - MB622
20-Nov-25
06-Jan-26
100%
EK000E001A
Sub Stations - Issue ERW
22-Nov-25
31-Dec-25
100%
EK000MD102
MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur.
26-Nov-25
05-Dec-25
100%
PK000MU29G
Issue MU292 RFQ
26-Nov-25
06-Dec-25
100%
PK000ML50Y
Requote - ML500
26-Nov-25
10-Dec-25
100%
PK000MU11H
05B MU311 Receive Quotes
26-Nov-25
03-Jan-26
100%
EK010PI012
Plot Plan - Overall Site (Drwg 0101) Issue IPL
28-Nov-25
20-Dec-25
100%
EK030PI012
Plot Plan - Utility Plant Issue IPL
28-Nov-25
20-Dec-25
100%
PK000MD104
MD305 Merc. Removal Bed - Issue RFQ
05-Dec-25
10-Dec-25
100%
PK000MU29H
Receive Quotes MU292
05-Dec-25
20-Jan-26
100%
PK000MJ37B
Eval Bids & Issue Recmd MJ307
06-Dec-25
21-Dec-25
100%
PK000PR20G
PR201 KAAP Catalyst - Issue Formal P.O.
09-Dec-25
09-Dec-25
100%
PK000ML52G
Issue ML501 RFQ
09-Dec-25
31-Dec-25
100%
PK000PR20H
PR201 KAAP Catalyst - Fabricate/Exworks
10-Dec-25
03-Nov-27
26.0d
19%
PK000ML90G
Issue ML900 RFQ
10-Dec-25
16-Dec-25
100%
EK000ML50Z
Technical Evaluation - ML500
10-Dec-25
31-Dec-25
100%
PK000MD106
MD305 Merc. Removal Bed - Receive Quotes
11-Dec-25
10-Jan-26
100%
PK000MJ37K
MJ340 - Fabricate/PO Promise METERING PUMPS
13-Dec-25
27-Dec-26
35%
PK000MJ37P
Issue Formal P.O. for MJ340
13-Dec-25
20-Jan-26
100%
PK000I354E
ITCC - Eval Bids/Issue Recmd
16-Dec-25
28-Dec-25
100%
PK000ML90H
Receive Quotes ML900
16-Dec-25
20-Jan-26
100%
PK000I444E
Eval Bids / Issue Recmd - Analyzer Shelter
17-Dec-25
20-Dec-25
100%
EK03EPI030
03E Conceptual Layout - Supersketches
17-Dec-25
31-Mar-26
100%
EK000E002A
Transformer - Issue ERW
18-Dec-25
30-Dec-25
100%
PK000MJ33I
Eval Bids & Issue Recmd MJ303
19-Dec-25
24-Dec-25
100%
EK000MJ33E
Prepare & Issue Purchase ERW - MJ303
19-Dec-25
27-Dec-25
100%
PK000MC31J
Final Negotiate/Interim Award - MC310
20-Dec-25
03-Jan-26
100%
PK000I352G
SIS - Interim Award
20-Dec-25
20-Jan-26
100%
PK000I354G
ITCC - Interim Award
20-Dec-25
20-Jan-26
100%
PK000MJ37M
Final Negotiate/Interim Award - MJ307
20-Dec-25
20-Jan-26
100%
PK000MJ39I
Eval Bids & Issue Recmd MJ391/MJ392
20-Dec-25
14-Mar-26
100%
PK000PSA8C
000 Relief Valves - Technical Evaluation
23-Dec-25
27-Dec-25
100%
EK010PI013
Plot Plan - Overall Site (Drwg 0101) Issue IPL
23-Dec-25
23-Jan-26
100%
EK000MU32D
01D MU322 Technical Evaluation
23-Dec-25
31-Jan-26
100%
PK000MU32I
01D MU322 Eval Bids & Issue Recmd
23-Dec-25
01-Apr-26
100%
PK000MJ33J
Final Negotiate/Interim Award - MJ303
24-Dec-25
03-Jan-26
100%
PK000MJ73K
MJ730 - Fabricate/PO Promise EMERG PWR GENERATOR
25-Dec-25
28-Feb-27
70.0d
28%
EK010IC213
010 Control Valves - Purchase ERW
25-Dec-25
27-Dec-26
33%
PK01DMJ154
01D Recv. Planning V. Data - Pumps 2210-J
26-Dec-25
26-Dec-25
100%
PK03DMJV02
03D MJ305 2002-J/JA - Civil Prod. V. Data
27-Dec-25
27-Dec-26
32%
PK000I444G
Final Negotiation / Interim Award - Shelters/ Analyzers
28-Dec-25
17-Feb-26
100%
EK000ELEJ1
Lighting, Installation Details
28-Dec-25
31-Dec-25
100%
EK000ELEK1
A/G Power & Control, Details
28-Dec-25
31-Dec-25
100%
EK05BELED0
Substation Building Layout
28-Dec-25
31-Dec-25
100%
PK000EL000
OSBL Motors & Drivers - Prod. V. Data (Information Only)
30-Dec-25
30-Dec-26
32%
PK03DMJV01
03D MJ305 2002-J/JA - Piping Prod. V. Data
30-Dec-25
27-Dec-26
32%
PK03DMJV03
03D MJ305 2002-J/JA - E&I Prod. V. Data
30-Dec-25
27-Dec-26
32%
PK000MU25G
02G MU225 Issue RFQ
30-Dec-25
31-Dec-25
100%
EK000GE025
First Check Estimate
30-Dec-25
27-Feb-26
100%
PK01BMJV03
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK01HMJV01
01H MJ730 2303-J - Civil Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK01HMJV02
01H MJ730 2303-J - E&I Prod. V. Data
31-Dec-25
30-Dec-26
511.0d
31%
PK03BMUV03
03B MU222,MJ305 2401-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03CMJV03
03C MJ305 2205-J/JA,2206-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03EMUV01
03E MU330 2001-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03EMUV02
03E MU330 2001-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03EMUV03
03E MU330 2001-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03FMUV03
03F MU222 2401-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03FMUV04
03F MU410 2002-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03FMUV05
03F MU410 2002-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK03FMUV06
03F MU410 2002-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK05AMLV01
05A ML330 2101-L - Piping Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK05AMLV02
05A ML330 2101-L - Civil Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK05AMLV03
05A ML330 2101-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK05BMLV03
05B ML512 2102-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK01EMUV01
01E MU221 Warehouse / Maintenance Area - Piping Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK01EMUV02
01E MU221 Warehouse / Maintenance Area - Civil Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK01EMUV03
01E MU221 Warehouse / Maintenance Area - E&I Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK03CMD06
03C MD411 2203-F 50% Caustic Storage Tank - Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK03CMD07
03C MD411 2204-F 98% Sulfuric Acid Drum - Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK000E002B
Transformer - Inquiry REQ/RFQ
31-Dec-25
16-Jan-26
100%
PK03CMJV01
03C MJ305 2205-J/JA,2206-J/JA - Piping Prod. V. Data
31-Dec-25
03-Mar-26
100%
PK05AMJV01
05A MJ305 2106-J,2107-J - Piping Prod. V. Data
31-Dec-25
03-Mar-26
100%
PK03FMUV01
03F MU222 2401-U - Piping Prod. V. Data
31-Dec-25
05-Mar-26
100%
PK03FMUV02
03F MU222 2401-U - Civil Prod. V. Data
31-Dec-25
05-Mar-26
100%
PK03BMUV01
03B MU222 2401-J/JA - Piping Prod. V. Data
31-Dec-25
08-Mar-26
100%
PK03BMUV02
03B MU222 2401-J/JA - Civil Prod. V. Data
31-Dec-25
08-Mar-26
100%
EK010I1105
010 Orific Plates - Purchase ERW
31-Dec-25
11-Mar-26
100%
EK030I1105
030 Orific Plates - Purchase ERW Utility Plant
31-Dec-25
11-Mar-26
100%
EK050I1105
050 Orific Plates - Purchase ERW Dock/Storage Area
31-Dec-25
11-Mar-26
100%
PK05AMJV02
05A MJ305 2106-J,2107-J - Civil Prod. V. Data
31-Dec-25
20-Mar-26
100%
PK01BMJV02
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Civil Prod. V. Data
31-Dec-25
21-Mar-26
100%
PK03CMJV02
03C MJ305 2205-J/JA,2206-J/JA - Civil Prod. V. Data
31-Dec-25
21-Mar-26
100%
PK05AMJV03
05A MJ305 2106-J,2107-J - E&I Prod. V. Data
31-Dec-25
21-Mar-26
100%
PK05BMLV01
05B ML512 2102-L - Piping Prod. V. Data
31-Dec-25
21-Mar-26
100%
PK05BMLV02
05B ML512 2102-L - Civil Prod. V. Data
31-Dec-25
21-Mar-26
100%
PK01BMJV01
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Piping Prod. V. Data
31-Dec-25
31-Mar-26
100%
PK000E001B
Sub Stations - Inquiry REQ/RFQ
31-Dec-25
31-Dec-25
100%
PK000MB71J
Final Negotiate/Interim Award - MB710
31-Dec-25
06-Jan-26
100%
PK000MU25H
02G MU225 Receive Quotes
31-Dec-25
29-Jan-26
100%
PK000E001C
Sub Stations - Receive Bids
31-Dec-25
19-Feb-26
100%
EK030IC213
030 Control Valves - Purchase ERW
01-Jan-26
27-Dec-26
31%
EK01AIC300
01A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK01BIC300
01B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK01CIC300
01C In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK01DIC300
01D In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK01YIC300
01Y In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03AIC300
03A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03BIC300
03B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03DIC300
03D In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03EIC300
03E In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03FIC300
03F In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03YIC300
03Y In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK05AIC300
05A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK05BIC300
05B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
PK000MJ38Q
Prepare & Issue Prelim. RFQ - MJ308 to Proc.
01-Jan-26
13-Jan-26
100%
EK050PI013
Plot Plan - Dock/Storage Issue IPL
01-Jan-26
23-Jan-26
100%
EK01JIC300
01J In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
100%
EK03CIC300
03C In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
100%
EK04AIC300
04A In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
100%
PK000MC31K
MC310 - Fabricate/PO Promise 101-C & 102-C (Heavy Lift)
03-Jan-26
30-Jun-27
8.0d
20%
PK000MJ33K
MJ303 - Fabricate/PO Promise CW PUMPS
03-Jan-26
28-Feb-27
27.0d
26%
EK000MU11D
05B MU311 Technical Evaluation
03-Jan-26
01-Feb-26
100%
PK000MJ33P
Issue Formal P.O. for MJ303
03-Jan-26
03-Feb-26
100%
EK000MC31E
Prepare & Issue Purchase ERW - MC310
03-Jan-26
12-Feb-26
100%
PK000MC31P
Issue Formal P.O. for MC310
03-Jan-26
19-Feb-26
100%
PK01DMJV01
01D MJ303 2202-JA/JB/JC - Civil Prod. V. Data
03-Jan-26
07-Mar-26
100%
PK01DMJV02
01D MJ303 2202-JA/JB/JC - Piping Prod. V. Data
03-Jan-26
07-Mar-26
100%
PK000ML90I
Eval Bids & Issue Recmd ML900
03-Jan-26
01-Apr-26
100%
PK01DMJV03
01D MJ303 2202-JA/JB/JC - E&I Prod. V. Data
04-Jan-26
27-Dec-26
31%
PK000MB64K
MB640 - Fabricate/PO Promise 101-B Springs & Hangers
06-Jan-26
27-Dec-26
30%
PK000MB71K
MB710 - Fabricate/PO Promise 2202-B/BL Storage Flare & Flame FRT Gen.
06-Jan-26
27-Dec-26
30%
PK000MB64P
Issue Formal P.O. for MB640
06-Jan-26
20-Jan-26
100%
PK000MB71P
Issue Formal P.O. for MB710
06-Jan-26
21-Jan-26
100%
PK000ML52I
Eval Bids & Issue Recmd ML501
06-Jan-26
01-Feb-26
100%
PK000MB65K
MB622 - Fab/PO Promise 101-B Penthouse Circ Fans
07-Jan-26
27-Dec-26
30%
PK000MB65P
Issue Formal P.O. for MB622
07-Jan-26
20-Jan-26
100%
PK000MU31J
Final Negotiate/Interim Award - MU310
07-Jan-26
14-Jan-26
100%
PK01BMU100
01B Recv. Planning V. Data - 2007-L (No Req.)
10-Jan-26
10-Jan-26
100%
PK000MJ38F
Issue MJ308 RFQ
13-Jan-26
17-Jan-26
100%
EK000MD104
MD305 Merc. Removal Bed - Technical Evaluation
13-Jan-26
29-Jan-26
100%
PK000MU31K
MU310 - Fabricate/PO Promise Injection System & Chlorination Unit
14-Jan-26
27-Dec-26
29%
PK01DMUV01
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L-Piping Prod. V. Data
14-Jan-26
27-Dec-26
29%
PK01DMUV03
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L- E&I Prod. V. Data
14-Jan-26
27-Dec-26
29%
PK000MU31P
Issue Formal P.O. for MU310
14-Jan-26
14-Jan-26
100%
PK01DMUV02
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L - Civil Prod. V. Data
14-Jan-26
31-Mar-26
100%
PK03FMUV07
03F MU310 2001-L - Piping Prod. V. Data
15-Jan-26
27-Dec-26
29%
PK03FMUV08
03F MU310 2001-L - Civil Prod. V. Data
15-Jan-26
27-Dec-26
29%
PK03FMUV09
03F MU310 2001-L - E&I Prod. V. Data
15-Jan-26
27-Dec-26
29%
EK000IC353
DCS - Software Programming by KBR
15-Jan-26
27-Dec-26
29%
PK01CMUV01
01C MU300 2102-U - Piping Prod. V. Data
16-Jan-26
27-Dec-26
28%
PK01CMUV02
01C MU300 2102-U - Civil Prod. V. Data
16-Jan-26
27-Dec-26
28%
PK01CMUV03
01C MU300 2102-U - E&I Prod. V. Data
16-Jan-26
27-Dec-26
28%
PK000ML52J
Final Negotiate/Interim Award - ML501
16-Jan-26
31-Jan-26
100%
PK000ML50J
Final Negotiate/Interim Award - ML500
16-Jan-26
01-Feb-26
100%
PK000E002C
Transformer - Receive Bids
16-Jan-26
04-Mar-26
100%
EK000CV045
Prepare Foundation Design Criteria
16-Jan-26
14-Mar-26
100%
EK000MJ37C
Prepare & Issue Purchase ERW - MJ307
17-Jan-26
20-Jan-26
100%
PK000MJ37U
MJ307 - Fabricate/PO Promise ISBL ANSI/API PUMPS
20-Jan-26
20-Jan-27
192.0d
26%
PK05AMJV04
05A MJ307 2100-JA/JB - Piping Prod. V. Data
20-Jan-26
27-Dec-26
28%
PK05AMJV05
05A MJ307 2100-JA/JB - Civil Prod. V. Data
20-Jan-26
27-Dec-26
28%
PK05AMJV06
05A MJ307 2100-JA/JB - E&I Prod. V. Data
20-Jan-26
27-Dec-26
28%
PK000MJ37T
Recv. Planning V. Data MJ307
20-Jan-26
23-Jan-26
100%
PK000MB66J
Final Negotiate/Interim Award - MB660
20-Jan-26
24-Jan-26
100%
PK000MJ37R
Issue Formal P.O. for MJ307
20-Jan-26
31-Jan-26
100%
PK000I352K
SIS - Formal Award
20-Jan-26
10-Feb-26
100%
PK000I354K
ITCC - Formal Award
20-Jan-26
10-Feb-26
100%
PK000MJ38D
Receive Quotes MJ308
20-Jan-26
10-Feb-26
100%
EK000MU29D
Technical Evaluation - MU292
20-Jan-26
03-Mar-26
100%
PK000MB66K
MB660 - Fabricate/PO Promise 101-B Dampers & Air Doors
24-Jan-26
27-Dec-26
27%
PK000MB66P
Issue Formal P.O. for MB660
24-Jan-26
24-Jan-26
100%
PK000PS00A
000 SP Items - Issue RFQ
24-Jan-26
29-Jan-26
100%
PK000PTA0H
Engineered Pipe Supports - Production V. Data
24-Jan-26
29-Jan-26
100%
PK000MU11I
05B MU311 Eval Bids & Issue Recmd
24-Jan-26
31-Jan-26
100%
EK010I1241
Rotameters - Purchase ERW
28-Jan-26
27-Dec-26
26%
EK050PI014
Plot Plan - Dock/Storage Issue IFC
28-Jan-26
27-Dec-26
26%
PK01BMF02
01B MF302 2001-FA/FB Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK01BMF03
01B MF302 2001-FA/FB Water Tank - Piping Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK01BMF04
01B MF302 2001-FA/FB Water Tank - Civil Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK01BMF05
01B MF302 2001-FA/FB Water Tank - E&I Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK03DMF01
03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
EK000SY095
010 P&ID's - Tech Review
28-Jan-26
29-Jan-26
100%
PK01BMF01
01B MF302 2001-FA/FB Water Tank - Fdn. V. Data (Subcontract)
28-Jan-26
21-Feb-26
100%
EK000I3540
ITCC - Develop Final Design Basis
28-Jan-26
04-Mar-26
100%
EK000I3520
SIS - Develop Final Design Basis
28-Jan-26
12-Mar-26
100%
PK03DMF00
03D MF302 2002-F Demineralized Water Tank - Fdn. V. Data (Subcontract)
28-Jan-26
18-Mar-26
100%
EK010PI014
Plot Plan - Overall Site (Drwg 0101) Issue IFC
28-Jan-26
29-Mar-26
100%
EK010IC252
MOV Valves - Purchase ERW
28-Jan-26
15-Apr-26
100%
EK000MU25D
02G MU225 Technical Evaluation
28-Jan-26
21-Feb-26
100%
PK000I1220
Coriolis Meters - Fabricate/Exworks
29-Jan-26
27-Dec-26
26%
EK01YPI050
01Y Model Comment Resolution Approval
29-Jan-26
31-Jan-26
100%
PK000MD107
MD305 Merc. Removal Bed - Eval Bids & Issue Recmd
29-Jan-26
31-Jan-26
100%
EK000MD105
MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW
29-Jan-26
01-Feb-26
100%
PK000PS00B
000 SP Items - Receive Quotes
29-Jan-26
11-Feb-26
100%
PK000ML50N
Recv. Planning V. Data ML500
29-Jan-26
24-Feb-26
100%
PK000ML50P
Issue Formal P.O. for ML500
29-Jan-26
26-Mar-26
100%
PK000MB42S
MB420 - Marshaling 101-B Cast Peep Sites
30-Jan-26
27-Dec-26
25%
PK03AMLV01
03A ML500 2003-L - Piping Prod. V. Data
31-Jan-26
27-Dec-26
25%
PK03AMLV02
03A ML500 2003-L - Civil Prod. V. Data
31-Jan-26
27-Dec-26
25%
PK03AMLV03
03A ML500 2003-L - E&I Prod. V. Data
31-Jan-26
27-Dec-26
25%
PK000MD108
MD305 Merc. Removal Bed - Final Negotiate/Interim Award
31-Jan-26
03-Feb-26
100%
PK000MU11J
05B MU311 Final Negotiate/Interim Award
31-Jan-26
13-Feb-26
100%
EK010E008A
540-SB Admin. Area Pwr Supply - ERW Package
01-Feb-26
14-Feb-26
100%
PK000I221H
000 Everest Control Valves - Fabricate/Exworks
03-Feb-26
30-Dec-26
504.0d
24%
PK000MD110
MD305 Merc. Removal Bed - Fabricate/PO Promise
03-Feb-26
28-Feb-27
157.0d
21%
EK01DPI021
01D Model Review Comment Resolution
03-Feb-26
07-Feb-26
100%
EK00012210
000 Everest Control Valves - D/S,Sizing,Tech Eval
03-Feb-26
05-Mar-26
100%
PK000MD109
MD305 Merc. Removal Bed - Issue Formal P.O.
03-Feb-26
11-Mar-26
100%
PK000ML52P
Issue Formal P.O. for ML501
03-Feb-26
26-Mar-26
100%
PK000ML50K
ML500 - Fabricate/PO Promise 2003-L PAI/IA
04-Feb-26
10-Feb-27
78.0d
21%
PK000MJ36K
MJ305 - Fabricate/PO Promise OSBL PUMPS
04-Feb-26
10-Jan-27
60.0d
23%
PK000MBP3U
MB311 - Shop Recv - 101-B Convection Tube & Pipe
07-Feb-26
22-Apr-26
100%
EK000YA822
(EP-22) Issue for Planning (IPL) >90% OSBL P&ID's
09-Feb-26
09-Feb-26
100%
EK000YA824
(EP-23) Issue For Planning (IPL) >90% ISBL P&ID's
09-Feb-26
09-Feb-26
100%
PK000I352H
SIS - Fabricate Hardware
10-Feb-26
27-Dec-26
23%
EK01BPI050
01B Model Comment Resolution Approval
10-Feb-26
14-Feb-26
100%
PK000MJ38E
Technical Evaluation - MJ308
10-Feb-26
27-Mar-26
100%
PK05AMF05
05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract)
11-Feb-26
27-Dec-26
23%
EK000MU11E
05B MU311 Prepare & Issue Purchase ERW
11-Feb-26
13-Feb-26
100%
EK01EIC120
01E Instrument Detail Model / Review
11-Feb-26
01-Mar-26
100%
PK000MF32D
05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF33
05A MF312 2105-F - Piping Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF34
05A MF312 2105-F - Civil Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF35
05A MF312 2105-F - E&I Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK000PS00D
000 SP Items - Eval Bids / Issue Recmd
11-Feb-26
18-Feb-26
100%
EK000PS00C
000 SP Items - Technical Evaluation
11-Feb-26
01-Mar-26
100%
EK01DPI050
01D Model Comment Resolution Approval
12-Feb-26
13-Feb-26
100%
PK000I1100
020 Orific Plates - Fabricate/Exworks
13-Feb-26
27-Dec-26
22%
PK000MU11K
05B MU311 - Fabricate/PO Promise HYDROCHLORIC ACID STORAGE
13-Feb-26
27-Dec-26
22%
PK000MU11P
05B MU311 Issue Formal P.O.
13-Feb-26
13-Feb-26
100%
PK000MU11N
05B MU311 Recv. Planning V. Data
13-Feb-26
28-Feb-26
100%
PK000I444K
Issue Formal Purchase Order - Shelters/ Analyzers
17-Feb-26
17-Feb-26
100%
PK010E008B
540-SB Admin. Area Pwr Supply - Inquiry REQ/RFQ
17-Feb-26
20-Feb-26
100%
PK000MJ71G
Issue MJ731 RFQ
17-Feb-26
10-Mar-26
100%
EK000I444B
Develop Final Design Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000I444M
Develop Final Deign Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000E004A
UPS System - Issue ERW
17-Feb-26
28-Mar-26
100%
EK03DPI050
03D Model Comment Resolution Approval
18-Feb-26
06-Mar-26
100%
EK000E001D
Sub Stations - Tech Evaluation
19-Feb-26
27-Dec-26
21%
PK000PS00E
000 SP Items - Final Negotiation / Interim Award
19-Feb-26
27-Dec-26
21%
PK010E008C
540-SB Admin. Area Pwr Supply - Receive Bids
20-Feb-26
03-Apr-26
100%
PK000MU25I
02G MU225 Eval Bids & Issue Recmd
21-Feb-26
18-Mar-26
100%
EK000CS027
Turnover System Definition for OSBL
25-Feb-26
27-Dec-26
19%
EK000I444F
Planning V. Data - Shelters/ Analyzers
25-Feb-26
27-Dec-26
19%
PK000I352J
SIS - Planning V. Data
25-Feb-26
27-Dec-26
19%
PK000I354J
ITCC - Planning V. Data
25-Feb-26
27-Dec-26
19%
PK05AMLV04
05A ML501 2103-L - Piping Prod. V. Data
25-Feb-26
27-Dec-26
19%
PK05AMLV05
05A ML501 2103-L - Civil Prod. V. Data
25-Feb-26
27-Dec-26
19%
PK05AMLV06
05A ML501 2103-L - E&I Prod. V. Data
25-Feb-26
27-Dec-26
19%
EK000MJ38T
Update/Issue Formal Inquiry for ERW - MJ308
25-Feb-26
03-Mar-26
100%
EK000ML50E
Prepare & Issue Purchase ERW - ML500
25-Feb-26
08-Mar-26
100%
EK000YA831
(EP-26) Complete Hazard Review Meeting on >90% ISBL P&ID's
25-Feb-26
25-Feb-26
100%
EK000MJ39E
Prepare & Issue Purchase ERW - MJ391
27-Feb-26
09-Apr-26
100%
PK000MB68J
Final Negotiate/Interim Award - MB692
27-Feb-26
03-Mar-26
100%
EK000I3541
ITCC - Develop Purchase T-Req
27-Feb-26
05-Mar-26
100%
PK000MB68K
MB692 - Fabricate/PO Promise 101-B Cat Vacuum Equip.
03-Mar-26
27-Dec-26
17%
PK000MB68P
Issue Formal P.O. for MB692
03-Mar-26
06-Mar-26
100%
PK000MU29I
Eval Bids & Issue Recmd MU292
03-Mar-26
19-Mar-26
100%
EK030I131A
Develop / Issue Purchase ERW -Transmitter OSBL
04-Mar-26
27-Dec-26
17%
EK000E002D
Transformer - Tech Evaluation
04-Mar-26
27-Dec-26
17%
PK000E002E
Transformer - Eval Bids/Issue Recmd
04-Mar-26
27-Dec-26
17%
PK000MB21F
Marshaling of Equip. 101-B Siding for MB212
04-Mar-26
27-Dec-26
17%
EK000YA826
(EP-27) Begin Issuing Area Line Installation Details (IDF Files)
04-Mar-26
04-Mar-26
100%
EK03CPI050
03C Model Comment Resolution Approval
05-Mar-26
07-Mar-26
100%
PK000I3540
ITCC - Vendor Update Pricing / Quote
06-Mar-26
29-Mar-26
100%
EK000I221F
000 Everest Control Valves - Purchase ERW
11-Mar-26
27-Dec-26
15%
EK010I1211
Vortex Meters - Purchase ERW
11-Mar-26
27-Dec-26
15%
PK000MJ71H
Receive Quotes MJ731
11-Mar-26
05-Apr-26
100%
PK000ML43S
ML430 - Marshaling 110-L BENFIELD MIXER
11-Mar-26
27-Dec-26
15%
PK05BMU06
05B MU311 2109-LA/LB, 2110-L - Piping Prod. V. Data
14-Mar-26
27-Dec-26
14%
PK05BMU07
05B MU311 2109-LA/LB, 2110-L - Civil Prod. V. Data
14-Mar-26
27-Dec-26
14%
PK000MJ39J
Final Negotiate/Interim Award - MJ391/MJ392
14-Mar-26
17-Mar-26
100%
PK03BMU100
03B Recv. Planning V. Data - Utility Equip. 2401-J/JA
15-Mar-26
31-Mar-26
100%
PK000MJ39P
Issue Formal P.O. for MJ391/MJ392
17-Mar-26
27-Dec-26
13%
EK050PI006
Site Data Needed - Loading Area (SPDC)
18-Mar-26
27-Dec-26
13%
PK000MJ39K
Fabricate/Exworks FIREWATER PUMPS
18-Mar-26
10-Jan-27
60.0d
12%
PK01BMJV04
01B MJ391 2204-J/JA - Piping Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK01BMJV05
01B MJ391 2204-J/JA - Civil Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK01BMJV06
01B MJ391 2204-J/JA - E&I Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK05AMJV07
05A MJ392 2105-JA/JB - Piping Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK05AMJV08
05A MJ392 2105-JA/JB - Civil Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK05AMJV09
05A MJ392 2105-JA/JB - E&I Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK000MU25J
02G MU225 Final Negotiate/Interim Award
19-Mar-26
27-Dec-26
13%
PK000MU29K
MU292 - Fabricate/PO Promise 2404-L
19-Mar-26
27-Dec-26
13%
PK03BMUV04
03B MU292 2404-L - Piping Prod. V. Data
19-Mar-26
27-Dec-26
13%
PK03BMUV05
03B MU292 2404-L - Civil Prod. V. Data
19-Mar-26
27-Dec-26
13%
PK03BMUV06
03B MU292 2404-L - E&I Prod. V. Data
19-Mar-26
27-Dec-26
13%
PK000MU29J
Final Negotiate/Interim Award - MU292
19-Mar-26
19-Mar-26
100%
PK000MU29P
Issue Formal P.O. for MU292
19-Mar-26
31-Mar-26
100%
PK000MU29N
Recv. Planning V. Data MU292
19-Mar-26
09-Apr-26
100%
EK030I616A
Develop / Issue Purchase ERW - Steam Drum Lvl Gauges - OSBL
22-Mar-26
27-Dec-26
12%
EK03CIC120
03C Instrument Detail Model / Review
22-Mar-26
18-Apr-26
100%
EK000MU29E
Prepare & Issue Purchase ERW - MU292
24-Mar-26
27-Mar-26
100%
PK000MU32J
01D MU322 Final Negotiate/Interim Award
24-Mar-26
31-Mar-26
100%
PK020IC210
020 Control Valves - Fabricate/Exworks
27-Mar-26
27-Dec-26
10%
PK000E004B
UPS System - Inquiry REQ/RFQ
27-Mar-26
08-Apr-26
100%
PK000MJ38B
Eval Bids & Issue Recmd MJ308
27-Mar-26
23-Apr-26
100%
PK010IC210
010 Control Valves - Fabricate/Exworks
28-Mar-26
27-Dec-26
10%
PK030IC210
030 Control Valves - Fabricate/Exworks
28-Mar-26
27-Dec-26
10%
EK020FP460
FP Electrical Area Classification OSBL - IFC
31-Mar-26
27-Dec-26
9%
PK01DMUV07
01D MU322 2210-L,2211-L - Piping Prod. V. Data
31-Mar-26
27-Dec-26
9%
PK01DMUV09
01D MU322 2210-L,2211-L - E&I Prod. V. Data
31-Mar-26
27-Dec-26
9%
EK000MU32E
01D MU322 Prepare & Issue Purchase ERW
31-Mar-26
31-Mar-26
100%
PK000MBP3Z
MB311 - Shop Recv - 101-B Radiant Tube & Pipe
31-Mar-26
31-Mar-26
100%
PK01DMUV08
01D MU322 2210-L,2211-L - Civil Prod. V. Data
31-Mar-26
01-Apr-26
100%
PK000ML90J
Final Negotiate/Interim Award - ML900
31-Mar-26
02-Apr-26
100%
EK000I3521
SIS - Develop Purchase T-Req
31-Mar-26
03-Apr-26
100%
PK000MU32P
01D MU322 Issue Formal P.O.
31-Mar-26
22-Apr-26
100%
EK000MU25E
02G MU225 Prepare & Issue Purchase ERW
01-Apr-26
27-Dec-26
9%
EK010I1151
Annubars - Purchase ERW
01-Apr-26
27-Dec-26
9%
EK030I623A
Develop / Issue Purchase ERW -Multi-Point Thermocouples - OSBL
01-Apr-26
27-Dec-26
9%
PK000ML42S
ML420 - Marshaling CARTRIDGE FILTERS
01-Apr-26
27-Dec-26
9%
PK05AMB46
05A MB710 2202-B/BL - Piping Prod. V. Data
01-Apr-26
27-Dec-26
9%
PK05AMB47
05A MB710 2202-B/BL - Civil Prod. V. Data
01-Apr-26
27-Dec-26
9%
PK05AMB48
05A MB710 2202-B/BL - E&I Prod. V. Data
01-Apr-26
27-Dec-26
9%
EK000I3542
ITCC - Final Tech Evaluation for Purchase
01-Apr-26
03-Apr-26
100%
EK000I444C
Develop / Issue T-Req - Shelters/ Analyzers
01-Apr-26
03-Apr-26
100%
EK01YIC120
01Y Instrument Detail Model / Review
01-Apr-26
10-Apr-26
100%
PK000PIA1H
Bulk Piping A/G & U/G - Transport / Delivery (First CS,SS,U/G)
01-Apr-26
27-Dec-26
9%
PK000MB61L
Marshaling of 101-B Burners MB610
02-Apr-26
27-Dec-26
8%
PK000MU32K
01D MU322 - Fabricate/PO Promise COOLING WTR FILTER & CLARIFIER
02-Apr-26
27-Dec-26
8%
PK000ML90K
ML900 - Fabricate/PO Promise Evap. Pond Spray Nzl.
02-Apr-26
27-Dec-26
8%
PK01AMLV01
01A ML900 2408-LA,LB,LC,LD - Piping Prod. V. Data
02-Apr-26
27-Dec-26
8%
PK01AMLV02
01A ML900 2408-LA,LB,LC,LD - Civil Prod. V. Data
02-Apr-26
27-Dec-26
8%
PK01AMLV03
01A ML900 2408-LA,LB,LC,LD - E&I Prod. V. Data
02-Apr-26
27-Dec-26
8%
PK000ML90P
Issue Formal P.O. for ML900
02-Apr-26
15-Apr-26
100%
PK000MBP3X
MB311 - Shop Recv - 101-B Convection Fittings
02-Apr-26
15-Apr-26
100%
EK010E008D
540-SB Admin. Area Pwr Supply - Tech Evaluation
03-Apr-26
27-Dec-26
8%
EK05BEL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
7%
EK05BEL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
7%
PK000E00C
UPS System - Receive Bids
07-Apr-26
27-Dec-26
6%
EK030I621A
Develop / Issue Purchase ERW - Temperature Elements - OSBL
08-Apr-26
27-Dec-26
6%
EK01API050
01A Model Comment Resolution Approval
08-Apr-26
17-Apr-26
100%
PK000MC61F
MC610 - Marshaling DBL PIPE EXCH 161-C
10-Apr-26
27-Dec-26
5%
PK000I444D
Vendor Update Pricing - Shelters/ Analyzers
15-Apr-26
27-Dec-26
5%
PK000MB83S
MB630 - Marshaling 101-B Air Preheater
15-Apr-26
27-Dec-26
5%
PK000MU61S
MU611 - Marshaling 2101-U, 2101-UJA Thru UJG CW TWR & Fans
15-Apr-26
27-Dec-26
5%
PK000MU61U
MU611 - Marshaling 2101-UJA Thru UJGM CW Motors
15-Apr-26
27-Dec-26
5%
PK000I3521
SIS - Vendor Provides Software & Workstations
16-Apr-26
27-Dec-26
5%
PK010I1210
Vortex Meters - Fabricate/Exworks
16-Apr-26
27-Dec-26
5%
EK000I3523
SIS - Software Programming by KBR
18-Apr-26
27-Dec-26
5%
EK030I611A
Develop / Issue Purchase ERW - Pressure Gauges - OSBL
22-Apr-26
27-Dec-26
5%
EK05AIC120
05A Instrument Detail Model / Review
22-Apr-26
27-Dec-26
5%
PK000I3520
SIS - Vendor Update Pricing / Quote
22-Apr-26
27-Dec-26
5%
PK010I1100
010 Orific Plates - Fabricate/Exworks
22-Apr-26
27-Dec-26
5%
EK000MJ38C
Prepare & Issue Purchase ERW - MJ308
23-Apr-26
27-Dec-26
5%
PK000MJ38M
Final Negotiate/Interim Award - MJ308
23-Apr-26
27-Dec-26
5%
PK000MJ38R
Issue Formal P.O. for MJ308
23-Apr-26
27-Dec-26
5%
PK000MJ38T
Recv. Planning V. Data MJ308
23-Apr-26
27-Dec-26
5%
PK000MJ38U
MJ308 - Fabricate/PO Promisse ISBL ANSI/API PUMPS
23-Apr-26
10-Jan-27
198.0d
5%
PK01AMJV01
01A MJ308 2408-JA/JB - Piping Prod. V. Data
23-Apr-26
27-Dec-26
5%
PK01AMJV02
01A MJ308 2408-JA/JB - Civil Prod. V. Data
23-Apr-26
27-Dec-26
5%
PK01AMJV03
01A MJ308 2408-JA/JB - E&I Prod. V. Data
23-Apr-26
27-Dec-26
5%
PK000MU35S
MU350 - Marshaling 101-U DEAERATOR
24-Apr-26
27-Dec-26
5%
EK000CV146
Receive Site Survey Data Areas 04 & 05
27-Dec-26
27-Dec-26
0%
EK000E004D
UPS System - Tech Evaluation
27-Dec-26
27-Dec-26
0%
EK000ELEG0
Electrical Heat Tracing - ERW Package
27-Dec-26
27-Dec-26
0%
EK000FP060
FP Overall Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
0%
EK000FP065
FP Overall Firewater P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
0%
EK000GE030
Production Check Estimate
27-Dec-26
27-Dec-26
0%
EK000I3522
SIS - Final Tech Evaluation for Purchase
27-Dec-26
27-Dec-26
0%
EK000I352M
SIS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I354M
ITCC - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I444E
Final Tech Evaluation - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
EK000I444G
Review / Approve V. Data - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
EK000YA832
(EP-32) Issue OSBL (Units01/03) found./UG pipe work package
27-Dec-26
27-Dec-26
0%
EK000YA833
(EP-33) Issue > 90% ISBL Civil Foundations
27-Dec-26
27-Dec-26
0%
EK000YA839
(EP-35) Issue >90% OSBL P&ID's For Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA841
(EP-29) Issue OSBL Plot Plan for Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA848
(EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC)
27-Dec-26
27-Dec-26
0%
EK000YA888
(TLA-02) Second TLA Payment
27-Dec-26
27-Dec-26
0%
EK010FP040
FP Firewater Pump P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
0%
EK01AIC120
01A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK01API144
01A OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK01BIC120
01B Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK01BPI144
01B OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK01CIC120
01C Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK01CPI143
01C OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK01DIC120
01D Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK01DPI144
01D OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK01HIC120
01H Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK01JIC120
01J Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK01JPI050
01J Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK01JPI143
01J Op's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK01YPI143
01Y OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK020ELEG5
Cathodic Protection - Design & Specs Package (By Consultant)
27-Dec-26
27-Dec-26
0%
EK03AIC120
03A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03API050
03A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03API143
03A OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03BIC120
03B Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03BPI050
03B Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03BPI143
03B OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03CPI143
03C OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03DIC120
03D Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03DPI145
03D OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03EIC120
03E Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03EPI050
03E Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03EPI144
03E OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03FIC120
03F Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03FPI050
03F Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03FPI144
03F OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03YIC120
03Y Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03YPI050
03Y Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03YPI144
03Y OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK04AIC120
04A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK05API050
05A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK05API144
05A OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK05BPI035
05B Plot Plan
27-Dec-26
27-Dec-26
0%
EM03YPI021
03Y Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
PK0003525
SIS - Ship to DCS Shop/ Setup
27-Dec-26
27-Dec-26
0%
PK0003526
SIS - Integrated FAT
27-Dec-26
27-Dec-26
0%
PK000E001E
Sub Stations - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
0%
PK000E001G
Sub Stations - Interim Award
27-Dec-26
27-Dec-26
0%
PK000E001J
Sub Stations - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E001K
Sub Stations - Formal Award
27-Dec-26
27-Dec-26
0%
PK000E001M
Sub Stations - Production V. Data
27-Dec-26
27-Dec-26
0%
PK000E002G
Transformer - Interim Award
27-Dec-26
27-Dec-26
0%
PK000E002J
Transformer - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E002K
Transformer - Formal Award
27-Dec-26
27-Dec-26
0%
PK000E002M
Transformer - Production V. Data
27-Dec-26
27-Dec-26
0%
PK000E004E
UPS System - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
0%
PK000E004G
UPS System - Interim Award
27-Dec-26
27-Dec-26
0%
PK000E004J
UPS System - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E004K
UPS System - Formal Award
27-Dec-26
27-Dec-26
0%
PK000E004M
UPS System - Production V. Data
27-Dec-26
27-Dec-26
0%
PK000I1103
020 Orific Plates - Transport & Deliver
27-Dec-26
27-Dec-26
0%
PK000I1161
020 Wedge Flow Meters - Fabricate/Exworks
27-Dec-26
27-Dec-26
0%
PK000I1162
020 Wedge Flow Meters - Transport & Deliver
27-Dec-26
27-Dec-26
0%
PK000I1221
Coriolis Meters - Transport & Deliver
27-Dec-26
27-Dec-26
0%
PK000I1270
Fabricate/Exworks Magnetic Flow Meters
27-Dec-26
27-Dec-26
0%
PK000I1271
Transport & Deliver Magnetic Flow Meters
27-Dec-26
27-Dec-26
0%
PK000I3522
SIS - FAT Test
27-Dec-26
27-Dec-26
0%
PK000I3523
SIS - Cleanup / Changes
27-Dec-26
27-Dec-26
0%
PK000I3542
ITCC - Software Programming by Vendor
27-Dec-26
27-Dec-26
0%
PK000I3543
ITCC - FAT Test
27-Dec-26
27-Dec-26
0%
PK000I3544
ITCC - Cleanup / Changes
27-Dec-26
27-Dec-26
0%
PK000I354P
ITCC - Ship to DCS Shop/ Setup
27-Dec-26
27-Dec-26
0%
PK000I354Q
ITCC - Integrated FAT
27-Dec-26
27-Dec-26
0%
PK000I444H
Fabricate - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
PK000I611H
Fabricate / Exworks - Pressure Gauges - ISBL
27-Dec-26
27-Dec-26
0%
PK000I616H
Fabricate / Exworks - Steam Drum Lvl Gauges
27-Dec-26
27-Dec-26
0%
PK000I616N
Transport & Deliver - Steam Drum Lvl Gauges
27-Dec-26
27-Dec-26
0%
PK000I617H
Fabricate / Exworks - Magnetic Lvl Gauges
27-Dec-26
27-Dec-26
0%
PK000IC352
DCS - FAT Test
27-Dec-26
27-Dec-26
0%
PK000IC353
DCS - Cleanup / Changes
27-Dec-26
27-Dec-26
0%
PK000IC355
DCS - ITCC / SIS / DCS - Integrated FAT
27-Dec-26
27-Dec-26
0%
PK000IC35M
DCS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
PK000MB21O
Transport & Deliver of Equip. 101-B Siding
27-Dec-26
27-Dec-26
0%
PK000MB33O
MB333 - Transport/Customes Equip. 101-B
27-Dec-26
27-Dec-26
0%
PK000MB33S
MB333 - Marshaling Riser Transition 101-B
27-Dec-26
27-Dec-26
0%
PK000MB34Z
Shop Recv.- 101-B Finned Convection Tubes & Pipe
27-Dec-26
27-Dec-26
0%
PK000MB41Z
Shop Recv. - 101-B Cast Tube Supports
27-Dec-26
27-Dec-26
0%
PK000MB42O
MB420 - Transport to Vendor 101-B Cast Peep Sites
27-Dec-26
27-Dec-26
0%
PK000MB61O
Transport & Deliver 101-B Burners
27-Dec-26
27-Dec-26
0%
PK000MB63O
MB630 - Transport/Customes 101-B Air Preheater
27-Dec-26
27-Dec-26
0%
PK000MB64O
MB640 - Transport/Customes 101-B Springs & Hangers
27-Dec-26
27-Dec-26
0%
PK000MB64S
MB640 - Marshaling 101-B Springs & Hangers
27-Dec-26
27-Dec-26
0%
PK000MB65O
MB622 - Transport/Customes 101-B Penthouse Circ Fans
27-Dec-26
27-Dec-26
0%
PK000MB65S
MB622 - Marshaling 101-B Penthouse Circ Fans
27-Dec-26
27-Dec-26
0%
PK000MB66O
MB660 - Transport/Customes 101-B Dampers & Air Doors
27-Dec-26
27-Dec-26
0%
PK000MB66S
MB660 - Marshaling 101-B Dampers & Air Doors
27-Dec-26
27-Dec-26
0%
PK000MB68O
MB692 - Transport/Customes 101-B Cat Vacuum Equip.
27-Dec-26
27-Dec-26
0%
PK000MB68S
MB692 - Marshaling 101-B Cat Vacuum Equip.
27-Dec-26
27-Dec-26
0%
PK000MB69O
MB691 - Transport/Customes of Equip. 101-B
27-Dec-26
27-Dec-26
0%
PK000MB69S
MB691 - Marshaling 101-B for MB691
27-Dec-26
27-Dec-26
0%
PK000MB81O
MB810 - Transport & Deliver of Equip. 101-B
27-Dec-26
27-Dec-26
0%
PK000MB81S
MB810 - Marshaling 102-B
27-Dec-26
27-Dec-26
0%
PK000MBP1C
MB221 - Marshaling 101-B Convection Modules
27-Dec-26
27-Dec-26
0%
PK000MBP1M
MB221 - Transport/Customes 101-B Radiant Steel Panels
27-Dec-26
27-Dec-26
0%
PK000MBP1T
MB221 - Fab/PO Promise 101-B Crossover Pipe
27-Dec-26
27-Dec-26
0%
PK000MBP1U
MB221 - Transport/Customes 101-B Radiant Harps
27-Dec-26
27-Dec-26
0%
PK000MBP1V
MB221 - Transport/Customes 101-B Convection Modules
27-Dec-26
27-Dec-26
0%
PK000MBP1X
MB221 - Transport/Customes 101-B Radiant Ducting
27-Dec-26
27-Dec-26
0%
PK000MBP1Y
MB221 - Transport/Customes 101-B Crossover
27-Dec-26
27-Dec-26
0%
PK000MBP2C
MB221 - Marshaling 101-B Crossover
27-Dec-26
27-Dec-26
0%
PK000MBP3C
MB221 - Marshaling 101-B Radiant Ducting
27-Dec-26
27-Dec-26
0%
PK000MBP3V
MB311 - Shop Recv - 101-B Crossover Tube & Pipe
27-Dec-26
27-Dec-26
0%
PK000MBP3W
MB311 - Shop Recv - 101-B Crossover Fittings
27-Dec-26
27-Dec-26
0%
PK000MBP4C
MB221 - Marshaling 101-B Radiant Coil/Harps
27-Dec-26
27-Dec-26
0%
PK000MBP4O
MB312 - Transport/Customes 101-B Radiant Cast Stringer Grids
27-Dec-26
27-Dec-26
0%
PK000MBP4S
MB312 - Transport/Customes 101-B Radiant Cast Tube/Riser/Manifold
27-Dec-26
27-Dec-26
0%
PK000MBP4T
MB312 - Shop Recv. 101-B Radiant Cast Stringer Grids
27-Dec-26
27-Dec-26
0%
PK000MBP4U
MB312 - Shop Recv. 101-B Radiant Cast Tube/Riser/Manifold
27-Dec-26
27-Dec-26
0%
PK000MBP5C
MB221 - Marshaling 101-B Radiant Steel Panels
27-Dec-26
27-Dec-26
0%
PK000MC21O
MC210 - Transport/Customes 110/115/124/128/130/133/134/160/167/173/174-C
27-Dec-26
27-Dec-26
0%
PK000MC21R
MC210 - Marshaling 127-C
27-Dec-26
27-Dec-26
0%
PK000MC21S
MC210 - Marshaling 110/115/124/128/130/133/134/160/167/173/174-C
27-Dec-26
27-Dec-26
0%
PK000MC21T
MC210 - Transport/Customes 127-C
27-Dec-26
27-Dec-26
0%
PK000MC23B
MC230 - Marshaling 106-C & 109-C
27-Dec-26
27-Dec-26
0%
PK000MC23C
MC230 - Transport/Customes 106-C & 109-C
27-Dec-26
27-Dec-26
0%
PK000MC23O
MC230 - Transport/Customes 105/172/183-C
27-Dec-26
27-Dec-26
0%
PK000MC23R
MC230 - Marshaling 111/114-C
27-Dec-26
27-Dec-26
0%
PK000MC23S
MC230 - Marshaling 105/172/183-C
27-Dec-26
27-Dec-26
0%
PK000MC23T
MC230 - Transport/Customes 114-C
27-Dec-26
27-Dec-26
0%
PK000MC61O
MC610 - Transport/Customes DBL PIPE EXCH 188-CA
27-Dec-26
27-Dec-26
0%
PK000MC61Q
MC610 - Transport/Customes DBL PIPE EXCH 161-C
27-Dec-26
27-Dec-26
0%
PK000MC61S
MC610 - Marshaling DBL PIPE EXCH 188-CA
27-Dec-26
27-Dec-26
0%
PK000MD22B
MD202 - Marshaling TOWERS 104-E
27-Dec-26
27-Dec-26
0%
PK000MD22C
MD202 - Transport/Customes TOWERS 104-E
27-Dec-26
27-Dec-26
0%
PK000MD22O
MD202 - Transport/Customes TOWERS 103/105-E
27-Dec-26
27-Dec-26
0%
PK000MD22S
MD202 - Marshaling TOWERS 103/105-E
27-Dec-26
27-Dec-26
0%
PK000MD42A
MD402 -Marshaling 144-F
27-Dec-26
27-Dec-26
0%
PK000MD42B
MD402 - Transport/Customes 144-F
27-Dec-26
27-Dec-26
0%
PK000MD42R
MD402 - Transport/Customes 104-F
27-Dec-26
27-Dec-26
0%
PK000MD42T
MD402 -Marshaling 104-F
27-Dec-26
27-Dec-26
0%
PK000MD44M
MD404 - Marshaling 107-F
27-Dec-26
27-Dec-26
0%
PK000MD44N
MD404 - Transport/Customes 107-F
27-Dec-26
27-Dec-26
0%
PK000MD44O
MD404 - Transport/Customes 109-F
27-Dec-26
27-Dec-26
0%
PK000MD44S
MD404 - Marshaling 109-F
27-Dec-26
27-Dec-26
0%
PK000MD45B
MD405 - Marshaling ISBL DRUMS - 115-F
27-Dec-26
27-Dec-26
0%
PK000MD45C
MD405 - Transport/Customes ISBL DRUMS - 115-F
27-Dec-26
27-Dec-26
0%
PK000MD45O
MD405 - Transport/Customes ISBL DRUMS - 156-F & 157-F
27-Dec-26
27-Dec-26
0%
PK000MD45S
MD405 - Marshaling ISBL DRUMS - 156-F & 157-F
27-Dec-26
27-Dec-26
0%
PK000MD45T
MD405 - Transport/Customes ISBL DRUMS - 118-F
27-Dec-26
27-Dec-26
0%
PK000MD46O
MD411 - Transport/Customes OSBL DRUMS - 2203-F & 2204-F
27-Dec-26
27-Dec-26
0%
PK000MD46S
MD411 - Marshaling OSBL DRUMS - 2203-F & 2204-F
27-Dec-26
27-Dec-26
0%
PK000MD46U
MD411 - Marshaling OSBL DRUMS - 2006-F
27-Dec-26
27-Dec-26
0%
PK000MD46V
MD411 - Transport/Customes OSBL DRUMS - 2006-F
27-Dec-26
27-Dec-26
0%
PK000MD47O
MD406 - Transport/DCustomes ISBL DRUMS
27-Dec-26
27-Dec-26
0%
PK000MD47S
MD406 - Marshaling ISBL DRUMS 103-F
27-Dec-26
27-Dec-26
0%
PK000MD51O
MD501 - Transport/Customes 107-D
27-Dec-26
27-Dec-26
0%
PK000MD51S
MD501 - Marshaling 107-D
27-Dec-26
27-Dec-26
0%
PK000MDR
MD405 - Marshaling ISBL DRUMS - 118-F
27-Dec-26
27-Dec-26
0%
PK000MJ21O
MJ202 - Transport/Customes 102/3/5-J
27-Dec-26
27-Dec-26
0%
PK000MJ21S
MJ202 - Marshaling 102/3/5-J
27-Dec-26
27-Dec-26
0%
PK000MJ37O
MJ340 - Transport/Customes METERING PUMPS
27-Dec-26
27-Dec-26
0%
PK000MJ37S
MJ340 - Marshaling METERING PUMPS
27-Dec-26
27-Dec-26
0%
PK000MJ71I
Eval Bids & Issue Recmd MJ731
27-Dec-26
27-Dec-26
0%
PK000MJ71J
Final Negotiate/Interim Award - MJ731
27-Dec-26
27-Dec-26
0%
PK000MJ71P
Issue Formal P.O. for MJ731
27-Dec-26
27-Dec-26
0%
PK000MJ75O
MJ750 - Transport/Customes SURFACE CONDENSORS
27-Dec-26
27-Dec-26
0%
PK000MJ75S
MJ750 - Marshaling SURFACE CONDENSORS
27-Dec-26
27-Dec-26
0%
PK000ML33O
ML330 - Transport/Customes 2101-L
27-Dec-26
27-Dec-26
0%
PK000ML33S
ML330 - Marshaling 2101-L
27-Dec-26
27-Dec-26
0%
PK000ML42O
ML420 - Transpor/Customes CARTRIDGE FILTERS
27-Dec-26
27-Dec-26
0%
PK000ML43O
ML430 - Transport/Customes 110-L BENFIELD MIXER
27-Dec-26
27-Dec-26
0%
PK000ML51O
ML512 - Transport/Customs 2102-L LOADING ARM
27-Dec-26
27-Dec-26
0%
PK000ML51S
ML512 - Marshaling 2102-L LOADING ARM
27-Dec-26
27-Dec-26
0%
PK000MU11S
05B MU311 - Marshaling HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
0%
PK000MU21O
MU221 - Transport/Customs LIFT STATION
27-Dec-26
27-Dec-26
0%
PK000MU21S
MU221 - Marshaling LIFT STATION
27-Dec-26
27-Dec-26
0%
PK000MU22O
MU222 - Transport/Customes .2401-U
27-Dec-26
27-Dec-26
0%
PK000MU22S
MU222 - Marshaling 2401-U
27-Dec-26
27-Dec-26
0%
PK000MU25K
MU225 - 02G Fabricate/PO Promise LIFT STATION
27-Dec-26
27-Dec-26
0%
PK000MU25P
02G MU225 Issue Formal P.O.
27-Dec-26
27-Dec-26
0%
PK000MU311
05B MU311 Transport/Customes BULK CHEM. STORAGE TANKS
27-Dec-26
27-Dec-26
0%
PK000MU35O
MU350 - Transport/Customes 101-U DEAERATOR
27-Dec-26
27-Dec-26
0%
PK000MU41O
MU410 - Transport/Customes 2002-U PKG BOILER
27-Dec-26
27-Dec-26
0%
PK000MU41S
MU410 - Marshaling 2002-U PKG BOILER
27-Dec-26
27-Dec-26
0%
PK000MU61O
MU611 - Transport/Customes 2101-U, 2101-UJA Thru UJG CW TWR & Fans
27-Dec-26
27-Dec-26
0%
PK000PIA1J
Bulk Piping A/G & U/G - Receive at Site FIRST (CS,SS,U/G)
27-Dec-26
27-Dec-26
0%
PK000PIA1L
Bulk Piping A/G - Transport / Delivery (CROME)
27-Dec-26
27-Dec-26
0%
PK000PIA1M
Bulk Piping A/G - Receive at Site (CHROME)
27-Dec-26
27-Dec-26
0%
PK000PIA4H
Product Line Piping - Transport / Delivery to Insulation Shop
27-Dec-26
27-Dec-26
0%
PK000PIA4I
Product Line Piping - Insulation Fab/Exworks
27-Dec-26
27-Dec-26
0%
PK000PIA4J
Product Line Piping - Receive at Site
27-Dec-26
27-Dec-26
0%
PK000PIA4K
Product Line Piping - Transport / Delivery
27-Dec-26
27-Dec-26
0%
PK000PIA4L
Product Line Piping - Fab/Exworks Remaining +/- 1500 Mts.
27-Dec-26
27-Dec-26
0%
PK000PS00F
000 SP Items - Issue Formal Blanket P.O.
27-Dec-26
27-Dec-26
0%
PK010E008F
540-SG Admin. Area Pwr Supply - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
0%
PK010E008G
540-SG Admin. Area Pwr Supply - Interim Award
27-Dec-26
27-Dec-26
0%
PK010E008H
540-SG Admin. Area Pwr Supply - Formal Award
27-Dec-26
27-Dec-26
0%
PK010E008J
540-SG Admin. Area Pwr Supply - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK010E008L
540-SG Admin. Area Pwr Supply - Production V. Data
27-Dec-26
27-Dec-26
0%
PK010I1103
010 Orific Plates - Transport & Deliver
27-Dec-26
27-Dec-26
0%
PK010I1105
010 Orific Plates - Recv on Site
27-Dec-26
27-Dec-26
0%
PK01DMU61Z
01D Recv. at Site - 2101-U, 2101-UJA Thru UJG CW TWR & Fans
27-Dec-26
27-Dec-26
0%
PK01FMU21Z
01E Recv. at Site - 2402-L Lift Station
27-Dec-26
27-Dec-26
0%
PK01GMU21Z
01E Recv. at Site - Lift Station
27-Dec-26
27-Dec-26
0%
PK020I131H
Fabricate / Exworks - Transmitters -Press.
27-Dec-26
27-Dec-26
0%
PK020IC214
020 Control Valves - Transport & Deliver
27-Dec-26
27-Dec-26
0%
PK02FMU11Z
05B MU311 Recv. at Site - 2109-LA HYDROCHLORIC ACID STORAGE TANK A
27-Dec-26
27-Dec-26
0%
PK02GMU11Z
05B MU311 Recv. at Site - 2109-LB HYDROCHLORIC ACID STORAGE TANK B
27-Dec-26
27-Dec-26
0%
PK02LMU11Z
05B MU311 Recv. at Site - 2110-L SODIUM HYDROCHLORITE STORAGE
27-Dec-26
27-Dec-26
0%
PK030I1100
Orific Plates - Fabricate/Exworks
27-Dec-26
27-Dec-26
0%
PK030IC214
030 Control Valves - Transport & Delivery
27-Dec-26
27-Dec-26
0%
PK030IC220
030 Control Valves - Recv on Site
27-Dec-26
27-Dec-26
0%
PK03BMU22Z
03B Recv. at Site - 2401-U Sanitary Treatment Pkg
27-Dec-26
27-Dec-26
0%
PK03CMD46Z
03C Recv. at Site - 2203-F & 2204-F Caustic Tank/ Acid Drum
27-Dec-26
27-Dec-26
0%
PK03FMD46Z
03F Recv. at Site - 2006-F Boiler Blowdown Drum
27-Dec-26
27-Dec-26
0%
PK03FMU11Z
05B MU311 Recv. at Site - 2109-L HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
0%
PK03FMU41Z
03F Recv. at Site - 2002-U Package Boiler
27-Dec-26
27-Dec-26
0%
PK050I1105
050 Orfice Plates - Recv on Site Dock/Storage Area
27-Dec-26
27-Dec-26
0%
PK05AMF25
05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract)
27-Dec-26
27-Dec-26
0%
PK05AMJV10
05A MJ731 2108-J - Civil Prod. V. Data
27-Dec-26
27-Dec-26
0%
PK05AMJV11
05A MJ731 2108-J - E&I Prod. V. Data
27-Dec-26
27-Dec-26
0%
PK05AML33Z
05A Recv. at Site - 2101-L Ammonia Refrigeration Pkg
27-Dec-26
27-Dec-26
0%
PK05BML51Z
05B Recv. at Site - 2102-L Loading Arm
27-Dec-26
27-Dec-26
0%
ZZ1020
01D Recv. at Site - 2101-UJA Thru UJGM CW Motors
27-Dec-26
27-Dec-26
0%
ZZ1040
MU611 - Transport/Customes 2101-UJA Thru UJGM CW Motors
27-Dec-26
27-Dec-26
0%
EK000YA500
Issue ISBL Paint & Insulation Work Package
28-Dec-26
08-Mar-27
750.0d
0%
EK000ELEGP
Electrical Heat Tracing - Design & BOM by Consultant
30-Dec-26
30-Jan-27
91.0d
0%
EK000ELEN1
01,03,04 LV Wiring Diagrams - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN2
01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN3
01,03, Equipment Interconnection Diagrams - IFC
30-Dec-26
30-Jan-27
511.0d
0%
EK020ELEG6
Cathodic Protection - Material Supply (By Consultant)
30-Dec-26
02-May-27
6.0d
0%
EK05ACV200
05A Redesign Piling & Ammonia Tank Foundations
30-Dec-26
10-Jan-27
-44.0d
0%
EK05BIC120
05B Instrument Model
30-Dec-26
30-Dec-26
110.0d
0%
PK000E001H
Sub Stations - Fab / Exworks
30-Dec-26
28-Feb-27
62.0d
0%
PK000E002H
Transformer - Fab / Exworks
30-Dec-26
04-Feb-27
28.0d
0%
PK000E004H
UPS System - Fab / Exworks
30-Dec-26
05-Feb-27
27.0d
0%
PK000I1121
020 Venturis - Fabricate/Exworks
30-Dec-26
30-Dec-26
509.0d
0%
PK000I2300
On/Off Valves - Fabricate/Exworks
30-Dec-26
07-Feb-27
460.0d
0%
PK000I3524
SIS - Packing / Exworks
30-Dec-26
10-Jan-27
55.0d
0%
PK000I3545
ITCC - Packing / Exworks
30-Dec-26
10-Jan-27
55.0d
0%
PK000I4440
FAT Test - Shelters/ Analyzers
30-Dec-26
10-Jan-27
161.0d
0%
PK000I611N
Transport & Deliver - Pressure Gauges - ISBL
30-Dec-26
03-Jan-27
110.0d
0%
PK000I612H
Fabricate / Exworks - Differential Pressure Gauges
30-Dec-26
18-Feb-27
28.0d
0%
PK000I617N
Transport & Deliver - Magnetic Lvl Gauges
30-Dec-26
13-Jan-27
104.0d
0%
PK000I621H
Fabricate / Exworks - Temperature Elements
30-Dec-26
13-Mar-27
31.0d
0%
PK000I623H
Fabricate / Exworks - Multi-Point Thermocouples
30-Dec-26
30-Dec-26
84.0d
0%
PK000IC354
DCS - Packing / Exworks
30-Dec-26
30-Dec-26
85.0d
0%
PK000IC35N
DCS - Transport (Hold for Field Request)
30-Dec-26
07-Feb-27
85.0d
0%
PK000MB62S
MB621 - Marshaling 101-B ID & FD Fans
30-Dec-26
14-Feb-27
215.0d
0%
PK000MB71S
MB710 - Marshaling 2202-B/BL Storage Flare & Flame FRT Gen.
30-Dec-26
07-Feb-27
240.0d
0%
PK000MD34T
MD304 - Marshaling 108-DA/B
30-Dec-26
07-Feb-27
162.0d
0%
PK000MD41S
MD401 - Marshaling 101-F
30-Dec-26
07-Feb-27
175.0d
0%
PK000MD44U
MD404 - Marshaling 132-F
30-Dec-26
07-Feb-27
65.0d
0%
PK000MJ35S
MJ305 - Marshaling ISBL ANSI/API PUMPS
30-Dec-26
11-Feb-27
153.0d
0%
PK000MJ71K
MJ731 - Fabricate/PO Promise EMERG PWR GENERATOR
30-Dec-26
21-Feb-27
70.0d
0%
PK000ML31S
ML313 - Marshaling 160-L
30-Dec-26
30-Dec-26
261.0d
0%
PK000ML90S
01A ML900 - Marshaling Evap. Pond Spray Nzl.
30-Dec-26
10-Jan-27
103.0d
0%
PK000MU25S
02G MU225 - Marshaling LIFT STATION
30-Dec-26
07-Feb-27
215.0d
0%
PK000MU29S
MU292 - Marshaling 2404-L
30-Dec-26
07-Feb-27
195.0d
0%
PK000MU30S
MU300 - Marshaling 2102-U
30-Dec-26
07-Feb-27
76.0d
0%
PK000MU31S
MU310 - Marshaling Injection System & Chlorination Unit
30-Dec-26
07-Feb-27
59.0d
0%
PK000MU32S
MU322 - Marshaling COOLING WTR FILTER & CLARIFIER
30-Dec-26
07-Feb-27
71.0d
0%
PK000MU33S
MU330 - Marshaling 2001-U
30-Dec-26
07-Feb-27
111.0d
0%
PK000PIA1N
Bulk Piping A/G - Fab/Exworks (FINAL)
30-Dec-26
07-Mar-27
45.0d
0%
PK000PS00G
000 SP Items - Fabricate/Exworks
30-Dec-26
30-Dec-26
247.0d
0%
PK000PSA8H
000 Relief Valves - Transport & Deliver
30-Dec-26
24-Feb-27
257.0d
0%
PK000PTA0J
Engineered Pipe Supports - Transport
30-Dec-26
10-Feb-27
58.0d
0%
PK010E008K
540-SG Admin. Area Pwr Supply - Fab / Exworks
30-Dec-26
11-Feb-27
70.0d
0%
PK010I1211
Vortex Meters - Transport & Deliver
30-Dec-26
31-Dec-26
533.0d
0%
PK010I1241
Rotameters - Transport & Deliver
30-Dec-26
14-Jan-27
523.0d
0%
PK010IC214
010 Control Valves - Transport & Deliver
30-Dec-26
30-Dec-26
535.0d
0%
PK010IC220
010 Control Valves - Recv on Site
30-Dec-26
30-Dec-26
0%
PK010IC252
MOV Valves - Fabricate/Exworks
30-Dec-26
27-Jan-27
475.0d
0%
PK020I131N
Transport & Deliver - Transmitters -Press.
30-Dec-26
20-Feb-27
76.0d
0%
PK030I1103
Orific Plates -Transport & Deliver
30-Dec-26
27-Jan-27
514.0d
0%
PK030I131H
Fabricate / Exworks - Transmitters - Temp.
30-Dec-26
16-Jan-27
71.0d
0%
PK030I611H
Fabricate / Exworks - Pressure Gauges - OSBL
30-Dec-26
04-Feb-27
58.0d
0%
ZZ2080
MJ305 - Transport/Customes OSBL ANSI/API PUMPS
30-Dec-26
07-Feb-27
190.0d
0%
ZZ2090
MJ305 - Marshaling OSBL ANSI/API PUMPS
30-Dec-26
30-Dec-26
190.0d
0%
PK000I1131
Venturis - Transport & Deliver
31-Dec-26
03-Feb-27
509.0d
0%
PK000I221N
000 Everest Control Valves - Transport & Deliver
31-Dec-26
10-Feb-27
504.0d
0%
PK000MB51S
MB511 - Marshaling 101-B Insulation
31-Dec-26
20-Jan-27
204.0d
0%
PK000ML31O
ML313 - Transport/Customs 160-L
31-Dec-26
24-Jan-27
365.0d
0%
PK000PS00H
000 SP Items - Transport & Deliver
31-Dec-26
10-Mar-27
247.0d
0%
PK010I1151
Annubars - Transport & Deliver
31-Dec-26
03-Feb-27
509.0d
0%
PK010I1212
Vortex Meters - Recv on Site
31-Dec-26
31-Dec-26
615.0d
0%
PK000MD21S
MD201- Marshaling 101-E
02-Jan-27
07-Feb-27
93.0d
0%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
0%
EK000YA838
(EP-34) Issue >90% ISBL P&ID's For Construction (IFC)
03-Jan-27
03-Jan-27
0%
PK000I352N
SIS - Transport & Delivery
13-Jan-27
21-Mar-27
55.0d
0%
PK000I354N
ITCC - Transport & Delivery
13-Jan-27
21-Mar-27
55.0d
0%
PK000I4441
Cleanup / Changes - Shelters/ Analyzers
13-Jan-27
24-Jan-27
161.0d
0%
PK000MD32S
MD302 - Marshaling 104-D1/2
13-Jan-27
07-Feb-27
85.0d
0%
PK000MJ22S
MJ201 - Marshaling 101-J
13-Jan-27
31-Jan-27
86.0d
0%
PK000MJ36S
MJ305 - Marshaling OSBL PUMPS
13-Jan-27
31-Jan-27
60.0d
0%
PK000MJ38V
MJ308 - Marshaling ISBL ANSI/API PUMPS
13-Jan-27
31-Jan-27
198.0d
0%
PK000MJ39S
Marshaling FIREWATER PUMPS
13-Jan-27
31-Jan-27
60.0d
0%
PK000ML90O
01A ML900 - Transport/Customes Evap. Pond Spray Nzl.
13-Jan-27
21-Feb-27
103.0d
0%
PK010I1242
Rotameters - Recv on Site
14-Jan-27
14-Jan-27
0%
EK05BPI050
05B Model Comment Resolution Approval
15-Jan-27
17-Jan-27
75.0d
0%
PK000MC32S
MC311 - Marshaling KBR S&T EXCH
17-Jan-27
06-Mar-27
76.0d
0%
PK000MJ34S
MJ304 - Marshaling MP BFW PUMPS
17-Jan-27
06-Feb-27
186.0d
0%
PK030I131N
Transport & Deliver - Transmitters - Temp.
17-Jan-27
30-Jan-27
91.0d
0%
PK000MJ32S
MJ302 - Marshaling 107-JA/JB/JC
20-Jan-27
07-Feb-27
175.0d
0%
PK000MB51O
MB511 - Transport/Customes 101-B Insulation
21-Jan-27
03-Mar-27
204.0d
0%
PK000MJ37V
MJ307 - Marshaling ISBL ANSI/API PUMPS
21-Jan-27
10-Feb-27
192.0d
0%
EK000YA030
Last PDS Planning Release
24-Jan-27
24-Jan-27
515.0d
0%
EK05BEL165
Switchgear One line Diagrams - IFC
27-Jan-27
30-Jan-27
276.0d
0%
EK05BEL185
MCC One line Diagrams - IFC
27-Jan-27
30-Jan-27
286.0d
0%
PK000I4442
Packing / Exworks - Shelters/ Analyzers
27-Jan-27
31-Jan-27
161.0d
0%
PK030I1105
Orific Plates - Recv on Site
27-Jan-27
27-Jan-27
592.0d
0%
PK000MD34S
MD304 - Marshaling 106-D, 109-DA/B
30-Jan-27
07-Feb-27
200.0d
0%
EK000YA040
Engineering 95% Complete
30-Jan-27
30-Jan-27
0%
PK000I444N
Transport & Deliver - Shelters/ Analyzers
03-Feb-27
11-Apr-27
161.0d
0%
PK000MJ22O
MJ201 - Transport/Customs 101-J
03-Feb-27
07-Mar-27
86.0d
0%
PK000MJ31S
MJ301 - Marshaling 104-J
03-Feb-27
04-Mar-27
168.0d
0%
PK000MJ36O
MJ305 - Transport/Customes OSBL PUMPS
03-Feb-27
14-Mar-27
60.0d
0%
PK000MJ38W
MJ308 - Transport/Customes ISBL ANSI/API PUMP
03-Feb-27
14-Mar-27
198.0d
0%
PK000MJ39O
Transport/Customes FIREWATER PUMPS
03-Feb-27
14-Mar-27
60.0d
0%
PK010IC262
MOV Valves - Transport & Deliver
03-Feb-27
21-Mar-27
475.0d
0%
PK010I1152
Annubars - Recv on Site
03-Feb-27
03-Feb-27
586.0d
0%
PK000E002X
Transformer - Marshalling
05-Feb-27
01-Apr-27
28.0d
0%
PK030I611N
Transport & Deliver - Pressure Gauges - OSBL
05-Feb-27
25-Feb-27
73.0d
0%
PK000E004X
UPS System - Marshalling
06-Feb-27
02-Apr-27
27.0d
0%
PK000MJ34O
MJ304 - Transport/Customes MP BFW PUMPS
07-Feb-27
20-Mar-27
186.0d
0%
PK000MB71O
MB710 - Transport/Customes 2202-B/BL Storage Flare & Flame FRT Gen.
08-Feb-27
28-Feb-27
336.0d
0%
PK000MD21O
MD201 - Transport/Customes 101-E
08-Feb-27
28-Feb-27
131.0d
0%
PK000MD32O
MD302 - Transport/Customes 104-D1/2
08-Feb-27
28-Feb-27
120.0d
0%
PK000MD34O
MD304 - Transport/Customes 106-D, 109-DA/B
08-Feb-27
28-Feb-27
280.0d
0%
PK000MD41O
MD401 - Transport/Customes 101-F
08-Feb-27
28-Feb-27
246.0d
0%
PK000MD44V
MD404 - Transport/Customes 132-F
08-Feb-27
28-Feb-27
93.0d
0%
PK000MU225
02G MU225 Transport/Customes LIFT STATION
08-Feb-27
28-Feb-27
302.0d
0%
PK000MU29O
MU292 - Transport/Customes 2404-L
08-Feb-27
28-Feb-27
275.0d
0%
PK000MU30O
MU300 - Transport/Customes 2102-U
08-Feb-27
28-Feb-27
108.0d
0%
PK000MU31O
MU310 - Transport/Customes Injection System & Chlorination Unit
08-Feb-27
28-Feb-27
83.0d
0%
PK000MU322
MU322 Transport/Customes COOLING WTR FILTER & CLARIFIER
08-Feb-27
28-Feb-27
101.0d
0%
PK000MU33O
MU330 - Transport/Customes 2001-U
08-Feb-27
28-Feb-27
157.0d
0%
ZZ2100
MD304 - Transport/Customes 108-DA/B
08-Feb-27
28-Feb-27
228.0d
0%
PK01GIC35L
DCS - Receive at Site
08-Feb-27
08-Feb-27
104.0d
0%
PK000I2330
On/Off Valves - Transport & Deliver
10-Feb-27
11-Apr-27
460.0d
0%
PK000MJ32O
MJ302 - Transport/Customes 107-JA/JB/JC
10-Feb-27
28-Feb-27
175.0d
0%
ZZ2110
MC230 - Transport/Customes 107/111
10-Feb-27
28-Feb-27
93.0d
0%
PK000I221L
000 Everest Control Valves - Recv on Site
10-Feb-27
10-Feb-27
580.0d
0%
PK000PTA0K
Engineered Pipe Supports - Receive at Site
10-Feb-27
10-Feb-27
69.0d
0%
EK035BI145
05B OP's & Serv. Model Comments Resolution Approval
11-Feb-27
13-Feb-27
75.0d
0%
PK000MJ37W
MJ307 - Transport/Customes ISBL ANSI/API PUMP
11-Feb-27
24-Mar-27
192.0d
0%
PK000ML50S
ML500 - Marshaling 2003-L PAI/IA
11-Feb-27
07-Mar-27
78.0d
0%
PK000MJ35O
MJ305 - Transport/Customes ISBL ANSI/API PUMPS
12-Feb-27
25-Mar-27
153.0d
0%
PK010E008M
540-SG Admin. Area Pwr Supply - Marshalling
12-Feb-27
08-Apr-27
70.0d
0%
PK000MB62O
MB621 - Transport/Customes of 101-B ID & FD Fans
15-Feb-27
07-Mar-27
301.0d
0%
PK000E001Z
Sub Stations - FAT
17-Feb-27
28-Feb-27
62.0d
0%
PK000MD31S
MD301 - Marshaling 103-D
18-Feb-27
07-Mar-27
55.0d
0%
PK000I612N
Transport & Deliver - Differential Pressure Gauges
19-Feb-27
29-Apr-27
28.0d
0%
EK000YA835
(EP-36) Issue >90% Area Line Installation Details
21-Feb-27
21-Feb-27
0%
EK000YA847
(EP-39) Issue >90% OSBL Electrical Design Drawings
21-Feb-27
21-Feb-27
0%
PK000ML90Z
01A ML900 - Recv. at Site - Evap. Pond Spray Nzl.
22-Feb-27
22-Feb-27
125.0d
0%
PK000MJ71S
MJ731 - Marshaling EMERG PWR GENERATOR
24-Feb-27
07-Mar-27
70.0d
0%
PK000PSA8J
000 Relief Valves - Recv on Site
24-Feb-27
24-Feb-27
284.0d
0%
PK03FMU32Z
MU322 Recv. at Site - COOLING WTR FILTER & CLARIFIER
28-Feb-27
28-Feb-27
71.0d
0%
PK030I131L
Recv at Site - Transmitters -Temp.
01-Mar-27
01-Mar-27
86.0d
0%
PK000MB71Z
05A Recv. at Site - Storage Flare & Flame FRT Gen.
01-Mar-27
01-Mar-27
264.0d
0%
PK01BMU30Z
01C Recv. at Site - 2102-U EDR Unit
01-Mar-27
01-Mar-27
93.0d
0%
PK03BMU29Z
03B Recv. at Site - 2404-L Oil Skimmer
01-Mar-27
01-Mar-27
212.0d
0%
PK03EMU33Z
03E Recv. at Site - 2001-U Demineralizer Unit
01-Mar-27
01-Mar-27
135.0d
0%
PK000E001N
Sub Stations - Transport
03-Mar-27
11-Apr-27
62.0d
0%
PK000md113
MD305 Merc. Removal Bed 102-D - Marshaling
03-Mar-27
07-Mar-27
157.0d
0%
PK000MD22U
MD202 - Marshaling TOWERS 150-E
03-Mar-27
07-Mar-27
100.0d
0%
PK000MJ33S
MJ303 - Marshaling CW PUMPS
03-Mar-27
19-Mar-27
27.0d
0%
PK000MJ73S
MJ730 - Marshaling EMERG PWR GENERATOR
03-Mar-27
07-Mar-27
70.0d
0%
PK020MC31D
MC312 - Marshaling 121-C
03-Mar-27
07-Mar-27
90.0d
0%
PK020MC31S
MC312 - Marshaling 120-C
03-Mar-27
07-Mar-27
90.0d
0%
PK000MJ31O
MJ301 - Transport/Customes 104-J
05-Mar-27
15-Apr-27
168.0d
0%
PK000MD22N
MD201- Marshaling 102-E
06-Mar-27
07-Mar-27
62.0d
0%
PK000MC32O
MC311 - Transport/Customes KBR S&T EXCH
06-Mar-27
27-Mar-27
108.0d
0%
PK000ML50O
ML500 - Transport/Customes 2003-L PAI/IA
08-Mar-27
28-Mar-27
110.0d
0%
PK000MD111
MD305 Merc. Removal Bed - Transport & Deliver
10-Mar-27
02-May-27
157.0d
0%
PK000MD211
MD201 - Transport/Customes 102-E
10-Mar-27
18-Apr-27
62.0d
0%
PK000MD22V
MD202 - Transport/Customes TOWERS 150-E
10-Mar-27
02-May-27
100.0d
0%
PK000MD31O
MD301 - Transport/Customes 103-D
10-Mar-27
04-Apr-27
55.0d
0%
PK000MJ71O
MJ731 - Transport/Customes EMERG PWR GENERATOR
10-Mar-27
18-Apr-27
70.0d
0%
PK000MJ73O
MJ730 - Transport/Customes EMERG PWR GENERATOR
10-Mar-27
18-Apr-27
70.0d
0%
PK000PIA1O
Bulk Piping A/G - Transport / Delivery (FINAL)
10-Mar-27
11-Apr-27
45.0d
0%
PK020MC31J
MC312 - Transport/Customes 121-C
10-Mar-27
04-Apr-27
90.0d
0%
PK020MC31L
MC312 - Transport/Customes 120-C
10-Mar-27
04-Apr-27
90.0d
0%
PK000PS00J
000 SP Items - Recv on Site
10-Mar-27
10-Mar-27
272.0d
0%
PK000MD43S
MD403 - Marshaling 106-F
12-Mar-27
25-Apr-27
135.0d
0%
PK000I621N
Transport & Deliver - Temperature Elements
14-Mar-27
14-Apr-27
39.0d
0%
PK000MJ38A
05A Recv. at Site - 2100-JA Pumps - MJ308
15-Mar-27
15-Mar-27
215.0d
0%
PK01BMJ36Z
01B Recv. at Site - 2001-JA/JB/JC, 2004-J/JA, 2007J/JA
15-Mar-27
15-Mar-27
73.0d
0%
PK01BMJ39Z
Recv. at Site - Firewater Pumps
15-Mar-27
15-Mar-27
73.0d
0%
PK03CMJ36Z
03C Recv. at Site - 2205-J/JA, 2206-J/JA Pumps
15-Mar-27
15-Mar-27
146.0d
0%
PK03DMJ36Z
03D Recv. at Site - 2002-J/JA Demineralized Water Pumps
15-Mar-27
15-Mar-27
158.0d
0%
PK05AMJ36Z
05A Recv. at Site - 2203-J/JM, 2106-J, 2107-J Pumps
15-Mar-27
15-Mar-27
207.0d
0%
PK030I611L
Recv at Site - Pressure Gauges - OSBL
19-Mar-27
19-Mar-27
70.0d
0%
PK000MJ33O
MJ303 - Transport/Customes CW PUMPS
20-Mar-27
30-Apr-27
27.0d
0%
PK000MD33S
MD303 - Marshaling 105-D
21-Mar-27
11-Apr-27
50.0d
0%
PK010IC272
MOV Valves - Recv on Site
22-Mar-27
22-Mar-27
547.0d
0%
PK01GI352L
SIS - Receive at Site
22-Mar-27
22-Mar-27
68.0d
0%
PK01GI354L
ITCC - Receive at Site
22-Mar-27
22-Mar-27
68.0d
0%
PK000MD42S
MD402 -Marshaling 102-F1, 102-F2
24-Mar-27
28-Mar-27
130.0d
0%
PK05AMJ37A
05A Recv. at Site - 2100-JA Pumps - MJ307
24-Mar-27
24-Mar-27
206.0d
0%
PK03AML50Z
03A Recv. at Site - 2003-L PAI/IA Compressor Pkg
29-Mar-27
29-Mar-27
95.0d
0%
PK000MD42O
MD402 - Transport/Customes 102-F1, 102-F2
31-Mar-27
09-May-27
130.0d
0%
PK000E002N
Transformer - Transport
02-Apr-27
13-May-27
28.0d
0%
PK000E004N
UPS System - Transport
03-Apr-27
14-May-27
27.0d
0%
PK010E008N
540-SG Admin. Area Pwr Supply - Transport
09-Apr-27
20-May-27
70.0d
0%
PK000I444L
Recv at Site - Shelters/ Analyzers
12-Apr-27
12-Apr-27
171.0d
0%
PK000I9000
Receive Instruments at Site
12-Apr-27
12-Apr-27
529.0d
0%
PK000PIA1P
Bulk Piping A/G - Receive at Site (FINAL)
12-Apr-27
12-Apr-27
56.0d
0%
PK01HE001L
Sub Stations - Receive at Site
12-Apr-27
12-Apr-27
76.0d
0%
PK000MD33O
MD303 - Transport/Customes 105-D
14-Apr-27
09-May-27
50.0d
0%
PK000MJ71Z
05A Recv. at Site - 2108-J Emerg Power Generator
19-Apr-27
19-Apr-27
86.0d
0%
PK01HMJ73Z
01H Recv. at Site - 2303-J Emerg Power Generator
19-Apr-27
19-Apr-27
86.0d
0%
PK000MD43O
MD403 - Transport/Customs 106-F
28-Apr-27
23-May-27
135.0d
0%
PK01BMJ33Z
01B Recv. at Site - 2007-J/JA Cooling Wtr Makeup Pumps
30-Apr-27
30-Apr-27
32.0d
0%
PK01DMJ33Z
01D Recv. at Site - Equip. 2202-JA/B/C
30-Apr-27
30-Apr-27
28.0d
0%
EK000YA889
(TLA-03) Complete > TLA Payments
03-May-27
03-May-27
623.0d
0%
PK01HE002L
Transformer - Receive at Site
13-May-27
13-May-27
34.0d
0%
PK000E004L
UPS System - Receive at Site
14-May-27
14-May-27
33.0d
0%
PK010E008P
540-SG Admin. Area Pwr Supply - Receive at Site
20-May-27
20-May-27
78.0d
0%
PK000MC31S
MC310 - Marshaling 101-C & 102-C (Heavy Lift)
01-Jul-27
01-Jul-27
8.0d
0%
PK000MC31O
MC310 - Transport/Customes 101-C & 102-C (Heavy Lift)
02-Jul-27
29-Jul-27
8.0d
0%
PK000PR20J
PR201 KAAP Catalyst - Transport & Deliver
04-Nov-27
12-Jan-28
26.0d
0%
Q3 2024 Q4 2024 Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Q2 2027 Q3 2027 Q4 2027 Q1 2028 Data Date
EK000CK085 — Establish bank account in Egypt | 02-Jul-24 → 24-Jan-26 | Complete 100% | float — EK000CK085 EK000SY005 — Systems Work Plan & Project Setup | 21-Jan-25 → 25-Mar-25 | Complete 100% | float — EK000SY005 EK000YA002 — Start Project | 22-Jan-25 | Complete EK000PR025 — Pressure Profile | 22-Jan-25 → 01-Feb-25 | Complete 100% | float — EK000PR050 — Electrical Load Summary - Initial | 22-Jan-25 → 01-Feb-25 | Complete 100% | float — EK000MD005 — Attend Alignment & strategy meetings | 22-Jan-25 → 09-Feb-25 | Complete 100% | float — EK000PR015 — Process Configuration | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR030 — Stream Summary | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR035 — Process Flow Diagrams PFD's - EOR | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000PR040 — Steam Balance Diagram - EOR | 22-Jan-25 → 13-Feb-25 | Complete 100% | float — EK000GE005 — Estimate Escalation Check - Info to Estimating | 22-Jan-25 → 14-Feb-25 | Complete 100% | float — EK000PR045 — Cooling Water Balance - EOR | 22-Jan-25 → 15-Feb-25 | Complete 100% | float — EK000PE025 — Document Management Plan - Issue for Review | 22-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000SY010 — MEC Convert prelim P&ID's to Smart Plant P&ID's | 22-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000MD015 — Conversion of drawings to metric units | 22-Jan-25 → 19-Feb-25 | Complete 100% | float — EK000PM015 — Project Coordination Procedure - IFA | 22-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PR020 — Heat & Material Balances (SOR & EOR) | 22-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PE085 — Participate in Escalation confirmation effort | 22-Jan-25 → 01-Mar-25 | Complete 100% | float — EK000PE085 EK000IM030 — Project Portal & Dashboard | 22-Jan-25 → 06-Mar-25 | Complete 100% | float — EK000IM030 EK000IC030 — Develop & Issue FieldBus Main Instr Vendor ERW | 22-Jan-25 → 08-Mar-25 | Complete 100% | float — EK000IC030 EK000PR055 — Feed & Fuel Summary | 22-Jan-25 → 09-Mar-25 | Complete 100% | float — EK000PR055 EK000IM020 — IM Strategy plan | 22-Jan-25 → 12-Mar-25 | Complete 100% | float — EK000IM020 EK000IM025 — IM Execution plan | 22-Jan-25 → 12-Mar-25 | Complete 100% | float — EK000IM025 EK000PR010 — Process Work Plan | 22-Jan-25 → 23-Mar-25 | Complete 100% | float — EK000PR010 EK000AR020 — Gather Bldg Requirements & Coordinate w/ Constr | 22-Jan-25 → 12-Apr-25 | Complete 100% | float — EK000AR020 EK000IM010 — Object Engineering set-up & procedures | 22-Jan-25 → 13-Apr-25 | Complete 100% | float — EK000IM010 EK000CV005 — Identify scope / Project set-up | 23-Jan-25 → 23-Feb-25 | Complete 100% | float — PK000PK005 — Implement use of Procuri and funct'nality (Req?) | 29-Jan-25 → 02-Feb-25 | Complete 100% | float — EK000PE125 — Preliminary Issue - Equipment List | 29-Jan-25 → 12-Feb-25 | Complete 100% | float — EK000CV020 — Review FMCL documents - Specs & Drawings | 29-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000IM040 — Establish Citrix for Test of PDS (HOC-MEC) | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PI080 — Develop Split of work | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — PK000MM020 — Project requisition matrix | 29-Jan-25 → 02-Mar-25 | Complete 100% | float — EK000IM005 — Equipment List (MEL) Definition | 29-Jan-25 → 30-Mar-25 | Complete 100% | float — EK000IM005 PK000MM010 — Project material responsibility matrix | 29-Jan-25 → 04-May-25 | Complete 100% | float — PK000MM010 EK000PE050 — Confirm of Split of Work for MEC | 02-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000PK035 — Review ITP as with eng. | 02-Feb-25 → 16-Mar-25 | Complete 100% | float — PK000PK035 EK000IC35A — DCS - Engr ERW Issued | 04-Feb-25 → 12-Feb-25 | Complete 100% | float — EK000IM035 — Establish Documentum | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE010 — Publish Unit conversion standard | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE040 — Devlop & Issue List of Project Specs & Standards | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV025 — Review SEGAS Wind & Earthquake Specs | 05-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000PI120 — Identify priority pipe classes | 05-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000PS015 — Issue 90 Day look ahead schedule | 05-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MJ005 — Prepare Machinery Specs (Motors, Pkg Equipment) | 05-Feb-25 → 25-Feb-25 | Complete 100% | float — EK000IC015 — Modify Package Equipment Spec for IEC basis | 05-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000PE110 — Issue Draft Project Design Data | 05-Feb-25 → 06-Mar-25 | Complete 100% | float — EK000MC010 — Develop & Issue Exchanger Work Plan | 05-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI115 — Develop Piping Class Index (IOPMC) | 05-Feb-25 → 13-Mar-25 | Complete 100% | float — EK000SY015 — Develop Utility & offsite block flow diagrams | 05-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000SY015 EK000PI132 — Develop Early Tech P-Class specs for Procurement | 05-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PI132 EK000SY065 — Complete Utility Flow Diagrams | 05-Feb-25 → 03-Apr-25 | Complete 100% | float — EK000SY065 PK000MM025 — Piping Bulk Quanities for Mill Run Commitment | 05-Feb-25 → 06-May-25 | Complete 100% | float — PK000MM025 EK000CV010 — HOC / MEC split of Work | 07-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV030 — Prepare EBIC Wind & EarthquakeSpecs | 07-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000QM010 — Training - Export Compliance | 08-Feb-25 → 08-Feb-25 | Complete 100% | float — PK000I354H — ITCC - Fabricate Hardware | 11-Feb-25 → 27-Dec-26 | In Progress 64% | float — PK000I354H PK000I210B — 000 Control Valves - Issue RFQ | 11-Feb-25 → 18-Feb-25 | Complete 100% | float — EK000ELZE0 — Area Classification | 11-Feb-25 → 30-Dec-25 | Complete 100% | float — EK000ELZE0 EK000MD31C — Prepare & Issue Prelim. RFQ - MD301 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD32C — Prepare & Issue Prelim. RFQ - MD302 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD34C — Prepare & Issue Prelim. RFQ - MD304 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD51C — Prepare & Issue Prelim. RFQ - MD501 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV040 — Prepare Topo Survey S/C Pkg | 12-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PE090 — Develop & Issue Engineering Plan | 12-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000EL005 — Electrical Work Plans | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI040 — Prepare technology work plan - Piping Engr. | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI060 — Prepare Other Project Documentation | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — PK000PK01C — Prepare/Issue Critical & Prelim. ERW's to Proc. | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI051 — Prepare P/Mech Support Details | 12-Feb-25 → 15-Mar-25 | Complete 100% | float — EK000CV015 — Civil work Plan & Safety check list | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV050 — Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000MB005 — Develop & Issue Furnance Job Plan | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK05BEL150 — Switchgear One line diagrams - ICA Dock | 12-Feb-25 → 15-Nov-25 | Complete 100% | float — EK05BEL150 EK05BEL170 — MCC One line diagrams - ICA Dock | 12-Feb-25 → 22-Nov-25 | Complete 100% | float — EK05BEL170 EK000MJ31C — Prepare & Issue Prelim. RFQ - MJ301 to Proc. | 13-Feb-25 → 13-Feb-25 | Complete 100% | float — EK000MJ32C — Prepare & Issue Prelim. RFQ - MJ302 to Proc. | 13-Feb-25 → 13-Feb-25 | Complete 100% | float — PK000IC35B — DCS - Inquiry REQ/RFQ | 13-Feb-25 → 14-Feb-25 | Complete 100% | float — EK000MB33A — 101-B Develop & Issue Load Sheet | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD33A — Develop & Issue Load Sheets for ERW - MD303 | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MJ22A — Develop & Issue Load Sheets for ERW - MJ201 | 14-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MJ21A — Develop & Issue Load Sheets for ERW - MJ202 | 14-Feb-25 → 21-Feb-25 | Complete 100% | float — PK000MJ31G — Issue MJ301 RFQ | 14-Feb-25 → 21-Feb-25 | Complete 100% | float — PK000MJ32G — Issue MJ302 RFQ | 14-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000PI110 — Locate FMCL Documents | 14-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PR060 — Process Load Sheets | 14-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PC005 — Prepare Estimate for Escalation Check | 15-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PE015 — MSD (From Metallurgy) - ISBL | 15-Feb-25 → 27-Feb-25 | Complete 100% | float — PK000IC35C — DCS - Receive Bids | 15-Feb-25 → 13-Mar-25 | Complete 100% | float — EK000MC31C — Prepare & Issue Prelim. RFQ - MC310 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MC61C — Prepare & Issue Prelim. RFQ - MC610 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MBP1C — 101-B Prepare & Issue Prelim. Shop Fab to Proc. | 16-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000QM015 — Develop & Issue Quality Plan | 16-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000MC32C — Issue Prelim. RFQ - MC311 | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000MJ22C — Prepare & Issue Prelim. RFQ - MJ201 to Proc. | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK020MC31A — MC312 - (120,121-C) - Issue Prelim. RFQ | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — PK000MJ22G — Issue MJ201 RFQ | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000MD21A — Develop & Issue Load Sheets for ERW - MD201 | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD41C — Prepare & Issue Prelim. RFQ - MD401 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD43C — Prepare & Issue Prelim. RFQ - MD403 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD43A — Develop & Issue Load Sheets for ERW - MD403 | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MJ31A — Develop & Issue Load Sheets for ERW - MJ301 | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK010SY010 — 010 Issue Marked up FMCL U&O / Dock P&ID's | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000MD33C — Prepare & Issue Prelim. RFQ - MD303 to Proc. | 19-Feb-25 → 22-Feb-25 | Complete 100% | float — PK000MD32G — Issue MD302 RFQ | 19-Feb-25 → 22-Feb-25 | Complete 100% | float — EK000EL020 — Define bulk material requirements | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MJ22B — Develop & Issue Design Data for ERW - MJ201 | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000ML31C — Prepare & Issue Prelim. RFQ - ML313 to Proc. | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PR115 — Issue Prelim Load Sht for Air Cooling Study | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000MD31G — Issue MD301 RFQ | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000MD34G — Issue MD304 RFQ | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000MD42G — Issue MD402 RFQ | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000MD51G — Issue MD501 RFQ | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MC210 — Cooling Water Balance Review | 19-Feb-25 → 26-Feb-25 | Complete 100% | float — PK000MC31G — Issue MC310 RFQ | 19-Feb-25 → 26-Feb-25 | Complete 100% | float — PK000MC61G — Issue MC610 RFQ | 19-Feb-25 → 26-Feb-25 | Complete 100% | float — PK000PK020 — Meeting w/ doc mngmnt & eng. (work process) TREQ | 19-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000IM045 — Establish IPMS | 19-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000IC005 — Develop Typical SIL Values Worksheet | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MJ35C — Prepare & Issue Prelim. RFQ - MJ305 to Proc. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MJ36C — Prepare & Issue Prelim. RFQ - MJ306 to Proc. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PK030 — Provide Job Specific SDR2 Priorities to Purch. | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PI160 — P&ID Area Break Mark-up | 19-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000MJ39C — Prepare & Issue Prelim. RFQ - MJ391 to Proc. | 19-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PR076 — Identify Risk of Equipment Changes | 19-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PE035 — Rvw Lesson Learn w/Prj. Team&Develop Action List | 19-Feb-25 → 16-Mar-25 | Complete 100% | float — PK000MM015 — IPMS Initial Setup | 19-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000EV005 — Conceptual Design of Wastewater Systems | 19-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000PR145 — Eng. Studies - Ammonia Product Line U/G vs. A/G | 19-Feb-25 → 29-Mar-25 | Complete 100% | float — EK000PR145 EK000MB010 — 101-B Furnance Analytical - Convection Design | 19-Feb-25 → 30-Mar-25 | Complete 100% | float — EK000MB010 EK000CV070 — Validate Concrete & Steel by Planning Areas | 19-Feb-25 → 15-Apr-25 | Complete 100% | float — EK000CV070 EK000MD33P — Develop Analytical Sketches for ERW - MD303 | 19-Feb-25 → 04-May-25 | Complete 100% | float — EK000MD33P EK000PM055 — Complete EPC Insurance Forms | 19-Feb-25 → 04-May-25 | Complete 100% | float — EK000PM055 PK000PE030 — Coating Supplier of Choice Selection | 19-Feb-25 → 04-May-25 | Complete 100% | float — PK000PE030 EK000PI020 — Develop Piping Specs (Paper) | 19-Feb-25 → 28-May-25 | Complete 100% | float — EK000PI020 PK000I210C — 000 Control Valves - Receive Quotes | 19-Feb-25 → 19-Mar-25 | Complete 100% | float — EK000MJ21C — Prepare & Issue Prelim. RFQ - MJ202 to Proc. | 20-Feb-25 → 20-Feb-25 | Complete 100% | float — PK000MJ21G — Issue MJ202 RFQ | 20-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000ML50C — Prepare & Issue Prelim. RFQ - ML500 to Proc. | 20-Feb-25 → 26-Feb-25 | Complete 100% | float — PK000MC32G — Issue MC311 RFQ | 20-Feb-25 → 26-Feb-25 | Complete 100% | float — PK020MC31B — MC312 - (120,121-C) - Issue RFQ | 20-Feb-25 → 26-Feb-25 | Complete 100% | float — PK000MJ22H — Receive Quotes MJ201 | 20-Feb-25 → 15-Mar-25 | Complete 100% | float — EK000MD44A — Develop & Issue Load Sheets for ERW - MD404 | 20-Feb-25 → 20-Mar-25 | Complete 100% | float — EK000MB61C — Prepare & Issue Prelim. RFQ - MB610 to Proc. | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MB62C — Prepare & Issue Prelim. RFQ - MB621 to Proc. | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000MBP1G — 101-B Prepare & Issue Shop Fab RFQ to Vendors | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000MD41G — Issue MD401 RFQ | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000MD43G — Issue MD403 RFQ | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MD34A — Develop & Issue Load Sheets for ERW - MD304 | 21-Feb-25 → 26-Feb-25 | Complete 100% | float — PK000MJ21H — Receive Quotes MJ202 | 21-Feb-25 → 26-Mar-25 | Complete 100% | float — EK000MJ21B — Develop & Issue Design Data for ERW - MJ202 | 22-Feb-25 → 07-Mar-25 | Complete 100% | float — EK000MD21P — Develop Prelim Analytical Sktch for ERW - MD201 | 22-Feb-25 → 22-Mar-25 | Complete 100% | float — PK000MJ31H — Receive Quotes MJ301 | 22-Feb-25 → 11-Apr-25 | Complete 100% | float — PK000MJ31H PK000MJ32H — Receive Quotes MJ302 | 22-Feb-25 → 12-Apr-25 | Complete 100% | float — PK000MJ32H EK000MD21Q — Develop Final Analytical Sktch for ERW - MD201 | 22-Feb-25 → 26-Apr-25 | Complete 100% | float — EK000MD21Q EK000YA804 — (EP-05) Issue Heat and Material Balance for Process Release | 22-Feb-25 | Complete EK000YA805 — (EP-06) Issue Equipment List for review | 22-Feb-25 | Complete EK000YA807 — (EP-08) Issue Utility Balances for Initial Release | 22-Feb-25 | Complete EK000FP025 — FP Gas Detection Location Plans - Not Required | 22-Feb-25 → 23-Aug-25 | Complete 100% | float — EK000FP025 PK000MD33G — Issue MD303 RFQ | 23-Feb-25 → 23-Feb-25 | Complete 100% | float — PK000ML31G — Issue ML313 RFQ | 23-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MC32A — Develop & Issue Load Sheets for ERW - MC311 | 23-Feb-25 → 28-Feb-25 | Complete 100% | float — PK000MD32H — Receive Quotes MD302 | 23-Feb-25 → 01-Apr-25 | Complete 100% | float — EK000CK080 — Expedite legal issues associated w/ KBRII | 23-Feb-25 → 28-Feb-26 | Complete 100% | float — EK000CK080 PK000I131B — Issue RFQ - Transmitters | 25-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MB060 — 101-B General Arrangement Drawing | 25-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000MF31A — Develop & Issue Load Sheets for ERW - MF301 | 26-Feb-25 → 26-Feb-25 | Complete 100% | float — PK000MB61G — Issue MB610 RFQ | 26-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MB41C — Prepare & Issue Prelim. RFQ - MB410 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC21C — Prepare & Issue Prelim. RFQ - MC210 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC23C — Prepare & Issue Prelim. RFQ - MC230 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD31A — Develop & Issue Load Sheets for ERW - MD301 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD32A — Develop & Issue Load Sheets for ERW - MD302 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MD41A — Develop & Issue Load Sheets for ERW - MD401 | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000EL015 — Split of work with MEC and Other Discipline | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MB63C — Prepare & Issue Prelim. RFQ - MB630 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MBP4C — Prepare & Issue Prelim. RFQ Cast Material | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE060 — Define Task Force Area in MEC | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE075 — MEC Organization Chart | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — PK000MB81G — Issue MB810 RFQ | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PM030 — Estimate Escalation Check - IRC Approvals | 26-Feb-25 → 01-Mar-25 | Complete 100% | float — PK000MB62G — Issue MB621 RFQ | 26-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000PR095 — Steam Balance - Startup, 103-J, Etc | 26-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000MBP3C — Prepare & Issue Prelim. RFQ Pressure Parts | 26-Feb-25 → 05-Mar-25 | Complete 100% | float — PK000MBP1H — 101-B Receive Quotes Shop Fab | 26-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000MD33B — Develop & Issue Design Data for ERW - MD303 | 26-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000EV025 — Develop & Issue Enviromental Work Plan | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC020 — Establlish data warehouse - Intools Basic Setup | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC025 — Review Instr. & Installation Details - ID Change | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000MJ22F — Update/Issue Formal Inquiry for ERW - MJ201 | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PK010 — Issue critical req'n submittal sched to Procmnt | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000GE010 — Eng. Studies - Air Coolers vs. Cooling Water | 26-Feb-25 → 12-Mar-25 | Complete 100% | float — PK000MD34H — Receive Quotes MD304 | 26-Feb-25 → 15-Mar-25 | Complete 100% | float — PK000MD41H — Receive Quotes MD401 | 26-Feb-25 → 15-Mar-25 | Complete 100% | float — EK000CV060 — Civil project highlights | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000PI005 — Locate Permanent Tie in pnts Gas, Wtr, Storm wtr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — PK000MD42H — Receive Quotes MD402 | 26-Feb-25 → 21-Mar-25 | Complete 100% | float — PK000MD51H — Receive Quotes MD501 | 26-Feb-25 → 21-Mar-25 | Complete 100% | float — EK000PE065 — Develop & Issue HOC - MEC Coordination Plan | 26-Feb-25 → 23-Mar-25 | Complete 100% | float — PK000MD43H — Receive Quotes MD403 | 26-Feb-25 → 01-Apr-25 | Complete 100% | float — PK000ML31H — Receive Quotes ML313 | 26-Feb-25 → 04-Apr-25 | Complete 100% | float — EK000PI133 — Dvlp/Issue V-class specs & Standads for Procurmt | 26-Feb-25 → 09-Apr-25 | Complete 100% | float — EK000PI133 EK000MB085 — 101-B Radiant Detail Drawings - IFF | 26-Feb-25 → 12-Apr-25 | Complete 100% | float — EK000MB085 EK000MB090 — 101-B Convection Detail Drawings - IFF | 26-Feb-25 → 12-Apr-25 | Complete 100% | float — EK000MB090 PK000MD31H — Receive Quotes MD301 | 26-Feb-25 → 13-Apr-25 | Complete 100% | float — PK000MD31H PK000MD33H — Receive Quotes MD303 | 26-Feb-25 → 13-Apr-25 | Complete 100% | float — PK000MD33H EK000CV035 — Prepare Geotech S/C Pkgs | 26-Feb-25 → 27-Apr-25 | Complete 100% | float — EK000CV035 EK000EL025 — Develop installation details | 26-Feb-25 → 07-May-25 | Complete 100% | float — EK000EL025 EK000IC045 — Develop & Issue CSE Work Plan | 26-Feb-25 → 08-May-25 | Complete 100% | float — EK000IC045 EK000PM045 — Issue Execution Strategy /Project Execution Plan | 26-Feb-25 → 24-May-25 | Complete 100% | float — EK000PM045 EK000MC31A — Develop & Issue Load Sheets for ERW - MC310 | 27-Feb-25 → 01-Mar-25 | Complete 100% | float — PK000ML50G — Issue ML500 RFQ | 27-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000ML50B — Develop/Issue Load Sht & Design Data ERW - ML500 | 27-Feb-25 → 05-Mar-25 | Complete 100% | float — PK000MB61H — Receive Quotes for MB610 | 27-Feb-25 → 13-Mar-25 | Complete 100% | float — PK000MC61H — Receive Quotes MC610 | 27-Feb-25 → 16-Mar-25 | Complete 100% | float — PK000MC31H — Receive Quotes for MC310 | 27-Feb-25 → 04-May-25 | Complete 100% | float — PK000MC31H PK000MC32H — Receive Quotes for MC311 | 27-Feb-25 → 04-May-25 | Complete 100% | float — PK000MC32H PK020MC3C — MC312 - (120,121-C) - Receive Quotes | 27-Feb-25 → 04-May-25 | Complete 100% | float — PK020MC3C PK000MC21G — Issue MC210 RFQ | 28-Feb-25 → 28-Feb-25 | Complete 100% | float — PK000MC23G — Issue MC230 RFQ | 28-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000MD42A — Develop & Issue Load Sheets for ERW - MD402 | 28-Feb-25 → 01-Mar-25 | Complete 100% | float — PK000MB41G — Issue MB410 RFQ | 28-Feb-25 → 01-Mar-25 | Complete 100% | float — EK000MD51A — Develop & Issue Load Sheets for ERW - MD501 | 28-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000MJ35A — Develop & Issue Load Sheets for ERW - MJ305 | 28-Feb-25 → 23-Mar-25 | Complete 100% | float — PK000MD22G — Issue MD202 RFQ | 01-Mar-25 → 01-Mar-25 | Complete 100% | float — PK000MD44G — Issue MD404 RFQ | 01-Mar-25 → 01-Mar-25 | Complete 100% | float — PK000MD45G — Issue MD405 RFQ | 01-Mar-25 → 01-Mar-25 | Complete 100% | float — PK000MD46G — Issue MD411 RFQ | 01-Mar-25 → 01-Mar-25 | Complete 100% | float — PK000MB63G — Issue MB630 RFQ | 01-Mar-25 → 05-Mar-25 | Complete 100% | float — PK000MBP4G — Issue 101-B Cast Material RFQ | 01-Mar-25 → 05-Mar-25 | Complete 100% | float — PK000MC21H — Receive Quotes for MC210 | 01-Mar-25 → 26-Mar-25 | Complete 100% | float — PK000MC23H — Receive Quotes for MC230 | 01-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000YA808 — (EP-09) Issue Engineering Plan | 01-Mar-25 | Complete PK000I131C — Receive Quotes - Transmitters | 01-Mar-25 → 25-Mar-25 | Complete 100% | float — EK000MD060 — Prepare Vessel work plan & other quality documents | 02-Mar-25 → 02-Mar-25 | Complete 100% | float — EK010PI005 — Develop Plot Plan & ID Areas - Overall Site IFI | 02-Mar-25 → 09-Mar-25 | Complete 100% | float — EK030PI005 — Develop Plot Plan & ID Areas - Utility Plant IFI | 02-Mar-25 → 09-Mar-25 | Complete 100% | float — EK050PI005 — Develop Plot Plan & ID Areas - Dock/Storage IFI | 02-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MC31B — Develop & Issue Design Data for ERW - MC310 | 02-Mar-25 → 13-Mar-25 | Complete 100% | float — PK000MD22H — Receive Quotes for MD202 | 02-Mar-25 → 21-Mar-25 | Complete 100% | float — PK000MD44H — Receive Quotes MD404 | 02-Mar-25 → 21-Mar-25 | Complete 100% | float — PK000MD45H — Receive Quotes MD405 | 02-Mar-25 → 21-Mar-25 | Complete 100% | float — PK000MD46H — Receive Quotes MD411 | 02-Mar-25 → 21-Mar-25 | Complete 100% | float — PK000ML50H — Receive Quotes ML500 | 02-Mar-25 → 22-Mar-25 | Complete 100% | float — PK000MB81H — Receive Quotes for MB810 | 02-Mar-25 → 28-Mar-25 | Complete 100% | float — PK000MB62H — Receive Quotes for MB621 | 02-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000MC31F — Finalize Equip. Data Sheets for ERW - MC310 | 02-Mar-25 → 12-Apr-25 | Complete 100% | float — EK000MC31F PK000MB41H — Receive Quotes for MB410 | 02-Mar-25 → 20-Apr-25 | Complete 100% | float — PK000MB41H EK000PI125 — Validate new plot layout (impacts on pipe stress | 02-Mar-25 → 21-May-25 | Complete 100% | float — EK000PI125 EK000MJ21D — Technical Evaluation - MJ202 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000MJ75A — Develop & Issue Load Sheets for ERW - MJ750 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000ML31A — Develop & Issue Load Sheets for ERW - ML313 | 05-Mar-25 → 05-Mar-25 | Complete 100% | float — EK000MB51C — Prepare & Issue Prelim. RFQ - MB511 to Proc. | 05-Mar-25 → 07-Mar-25 | Complete 100% | float — EK000CV075 — Egyptian Professional Engineer - Define Reqmnts | 05-Mar-25 → 08-Mar-25 | Complete 100% | float — EK000MC21A — Develop & Issue Load Sheets for ERW - MC210 | 05-Mar-25 → 08-Mar-25 | Complete 100% | float — EK000EL035 — Voltage drop table | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000ML42C — Prepare & Issue Prelim. RFQ - ML420 to Proc. | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MU33C — Prepare & Issue Prelim. RFQ - MU330 to Proc. | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000PI140 — Eqvlnt Line Counts / Planning Area-Utility Plant | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — PK000MJ35G — Issue MJ305 RFQ | 05-Mar-25 → 12-Mar-25 | Complete 100% | float — PK000MJ36G — Issue MJ306 RFQ | 05-Mar-25 → 12-Mar-25 | Complete 100% | float — EK000CS030 — Start-up Schedule (Prelim for 1st Planner) | 05-Mar-25 → 14-Mar-25 | Complete 100% | float — EK000MC32B — Develop & Issue Design Data for ERW - MC311 | 05-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MC23A — Develop & Issue Load Sheets for ERW - MC230 | 05-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MC32F — Finalize Equip. Data Sheets for ERW - MC311 | 05-Mar-25 → 24-May-25 | Complete 100% | float — EK000MC32F EK000MD22A — Develop & Issue Load Sheets for ERW - MD202 | 06-Mar-25 → 06-Mar-25 | Complete 100% | float — PK000MJ21I — Eval Bids & Issue Recmd MJ202 | 06-Mar-25 → 06-Mar-25 | Complete 100% | float — PK000MBP3G — Issue 101-B Pressure Parts RFQ | 06-Mar-25 → 07-Mar-25 | Complete 100% | float — EK000MBP1D — 101-B Technical Bid Evaluation Shop Fab | 06-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MJ37A — Develop & Issue Load Sheets for ERW - MJ340 | 06-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000ML31B — Develop & Issue Design Data for ERW - ML313 | 06-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000MD42P — Confirm Analytical Design for ERW - MD402 | 06-Mar-25 → 21-Mar-25 | Complete 100% | float — PK000MB63H — Receive Quotes for MB630 | 06-Mar-25 → 29-Mar-25 | Complete 100% | float — PK000MBP4H — Receive Quotes for 101-B Cast Material | 06-Mar-25 → 03-Apr-25 | Complete 100% | float — EK000ML50F — Update/Issue Formal Inquiry for ERW - ML500 | 06-Mar-25 → 27-Apr-25 | Complete 100% | float — EK000ML50F EK000PE020 — WMS Setup & Development | 07-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000CV080 — Egyptian Professional Eng. - Issue P.O/Subc. Pkg | 08-Mar-25 → 09-Mar-25 | Complete 100% | float — PK000MB51G — Issue MB511 RFQ | 08-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000MJ21F — Update/Issue Formal Inquiry for ERW - MJ202 | 08-Mar-25 → 13-Mar-25 | Complete 100% | float — EK000MC21B — Develop & Issue Design Data for ERW - MC210 | 08-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MJ31B — Develop & Issue Design Data for ERW - MJ301 | 08-Mar-25 → 12-Apr-25 | Complete 100% | float — PK000MBP3H — Receive Quotes for 101-B Pressure Part | 08-Mar-25 → 15-Apr-25 | Complete 100% | float — PK000MBP3H EK000PI055 — Prepare Object Engineering Work Instruction | 08-Mar-25 → 15-Mar-25 | Complete 100% | float — PK000MJ39G — Issue MJ391/MJ392 RFQ | 09-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000PC010 — Estimate Turnover to Project Team | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI085 — Estimate/Schedule Review | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000MD34R — Develop Final Analytical Sktch for ERW - MD304 | 09-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD43P — Confirm Analytical Design for ERW - MD403 | 09-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MC61A — Develop & Issue Load Sheets for ERW - MC610 | 09-Mar-25 → 20-Mar-25 | Complete 100% | float — PK000IC36B — DCS (MIV) - Inquiry REQ/RFQ | 09-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000PC015 — Estimate Recast & Develop Project Control Budget | 09-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000PC015 EK000PI105 — Performance Test of Citrix for PDS w/MEC | 12-Mar-25 → 12-Mar-25 | Complete 100% | float — PK000MU35G — Issue MU350 RFQ | 12-Mar-25 → 13-Mar-25 | Complete 100% | float — PK000ML42G — Issue ML420 RFQ | 12-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000MU41F — Develop & Issue Inquiry for ERW - MU410 | 12-Mar-25 → 16-Mar-25 | Complete 100% | float — PK000PK045 — Review ISSP work process with eng. | 12-Mar-25 → 16-Mar-25 | Complete 100% | float — PK000PK050 — Est Preselect low cost redundent bid items | 12-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000SY060 — 010 Util & Offsites Conceptual Design revw mtngs | 12-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD34P — Confirm Analytical Design for ERW - MD304 | 12-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU41A — Develop & Issue Load Sheets for ERW - MU410 | 12-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MD31P — Confirm Analytical Design for ERW - MD301 | 12-Mar-25 → 29-Mar-25 | Complete 100% | float — PK000MB51H — Receive Quotes for MB511 | 12-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MD32P — Confirm Analytical Design for ERW - MD302 | 12-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000PI100 — Critical Line List | 12-Mar-25 → 06-Apr-25 | Complete 100% | float — PK000MJ39H — Receive Quotes MJ391/MJ392 | 12-Mar-25 → 09-Apr-25 | Complete 100% | float — EK000EV020 — Develop Preliminary noise model | 12-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000EV020 PK000MJ22M — Requote/Bid Condition/Final Tab - MJ201 | 12-Mar-25 → 18-May-25 | Complete 100% | float — PK000MJ22M EK000MC21F — Finalize Equip. Data Sheets for ERW - MC210 | 12-Mar-25 → 13-Jun-25 | Complete 100% | float — EK000MC21F EK000SY075 — 010 OSBL Hydraulic Calculations | 12-Mar-25 → 30-Jul-25 | Complete 100% | float — EK000SY075 PK000MBP1I — Eval Bids & Issue Recmd 101-B Shop Fab | 13-Mar-25 → 13-Mar-25 | Complete 100% | float — PK000MJ35H — Receive Quotes MJ305 | 13-Mar-25 → 26-Mar-25 | Complete 100% | float — PK000MJ36H — Receive Quotes MJ306 | 13-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MD020 — Equipment Modeling for Vessel - MEC | 13-Mar-25 → 25-Mar-26 | Complete 100% | float — EK000MD020 EK000MB61D — Technical Evaluation - MB610 | 14-Mar-25 → 20-Mar-25 | Complete 100% | float — PK000MU35H — Receive Quotes MU350 | 14-Mar-25 → 06-Apr-25 | Complete 100% | float — PK000MJ21M — Requote/Bid Condition/Final Tab - MJ202 | 14-Mar-25 → 01-May-25 | Complete 100% | float — PK000MJ21M EK000PR080 — Input to Process Guarantees | 14-Mar-25 → 03-May-25 | Complete 100% | float — EK000PR080 EK000IC35D — DCS - Tech Evaluation | 14-Mar-25 → 14-May-25 | Complete 100% | float — EK000IC35D EK000MJ32A — Develop & Issue Load Sheets for ERW - MJ302 | 15-Mar-25 → 20-Mar-25 | Complete 100% | float — PK000MBP1J — Final Negotiate/Interim Award - 101-B Shop Fab | 15-Mar-25 → 09-Aug-25 | Complete 100% | float — PK000MBP1J EK000ML31F — Update/Issue Formal Inquiry for ERW - ML313 | 16-Mar-25 → 16-Mar-25 | Complete 100% | float — EK000MD31B — Develop & Issue Design Data for ERW - MD301 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD32B — Develop & Issue Design Data for ERW - MD302 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD34B — Develop & Issue Design Data for ERW - MD304 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MJ22D — Technical Evaluation - MJ201 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD45A — Develop & Issue Load Sheets for ERW - MD405 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML43A — Develop & Issue Load Sheets for ERW - ML430 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML44A — Develop & Issue Load Sheets for ERW - ML440 | 16-Mar-25 → 20-Mar-25 | Complete 100% | float — PK000ML42H — Receive Quotes ML420 | 16-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000PE095 — Disciplines Load WMS with Budgets & Deliverables | 16-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000MD34D — Technical Evaluation - MD304 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD34D EK000MD41D — Technical Evaluation - MD401 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD41D PK000PIA1A — Bulk Piping A/G & U/G - Issue REQ/RFQ to Vend | 18-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000ML42A — Develop & Issue Load Sheets for ERW - ML420 | 19-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU35A — Develop & Issue Load Sheets for ERW - MU350 | 19-Mar-25 → 20-Mar-25 | Complete 100% | float — EK000MU41B — Develop & Issue Design Data for ERW - MU410 | 19-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MU30F — Develop & Issue Inquiry for ERW - MU300 | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MF32A — 05A MF312 2105-F Water Tank - Process Load Sht. | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MF33B — Develop/Issue Load Sht & Design Data ERW - MF311 | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MF32B — Develop/Issue Load Sht & Design Data ERW - MF302 | 19-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000MD21B — Develop & Issue Design Data for ERW - MD201 | 19-Mar-25 → 08-May-25 | Complete 100% | float — EK000MD21B PK000ML31M — Requote/Bid Condition/Final Tab - ML313 | 19-Mar-25 → 30-Jul-25 | Complete 100% | float — PK000ML31M EK000ML42F — Update/Issue Formal Inquiry for ERW - ML420 | 19-Mar-25 → 24-Apr-25 | Complete 100% | float — PK000MJ22I — Eval Bids & Issue Recmd MJ201 | 20-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MC63A — Develop & Issue Load Sheets for ERW - MC630 | 20-Mar-25 → 22-Mar-25 | Complete 100% | float — PK000MU41G — Issue MU410 RFQ | 20-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MU61F — Develop & Issue Inquiry for ERW - MU611 | 20-Mar-25 → 25-Mar-25 | Complete 100% | float — EK000I210D — 000 Control Valves - Technical Evaluation | 20-Mar-25 → 23-May-25 | Complete 100% | float — EK000I210D EK000MU35F — Update/Issue Formal Inquiry for ERW - MU350 | 21-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MD47A — Develop & Issue Load Sheets for ERW - MD406 | 21-Mar-25 → 23-Mar-25 | Complete 100% | float — EK000MD51B — Develop & Issue Design Data for ERW - MD501 | 21-Mar-25 → 28-Mar-25 | Complete 100% | float — EK000MC61D — Technical Evaluation - MC610 | 21-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MC61F — Finalize Equip. Data Sheets for ERW - MC610 | 21-Mar-25 → 10-Apr-25 | Complete 100% | float — EK000MJ32B — Develop & Issue Design Data for ERW - MJ302 | 21-Mar-25 → 13-Apr-25 | Complete 100% | float — EK000MD34F — Update/Issue Formal Inquiry for ERW - MD304 | 21-Mar-25 → 20-Apr-25 | Complete 100% | float — PK000MB61I — Eval Bids & Issue Recmd MB610 | 21-Mar-25 → 25-Apr-25 | Complete 100% | float — PK000PIA1B — Bulk Piping A/G & U/G - Receive Bids | 21-Mar-25 → 04-May-25 | Complete 100% | float — PK000PIA1B PK000IC36C — DCS (MIV) - Receive Bids | 22-Mar-25 → 12-Apr-25 | Complete 100% | float — EK000EV010 — Develop design basis for evaporation pond | 22-Mar-25 → 11-May-25 | Complete 100% | float — EK000EV010 EK000YA802 — (EP-03) Issue Process Plan | 22-Mar-25 | Complete EK000MB51F — Prepare & Issue Purchase ERW - MB511 | 23-Mar-25 → 17-Apr-25 | Complete 100% | float — EK010PI010 — Develop Plot Plan & ID Areas - Overall Site (Drwg 0101) ICA | 23-Mar-25 → 31-Aug-25 | Complete 100% | float — EK010PI010 EK030PI010 — Develop Plot Plan & ID Areas - Utility Plant ICA | 23-Mar-25 → 11-Oct-25 | Complete 100% | float — EK030PI010 EK050PI010 — Develop Plot Plan & ID Areas - Dock/Storage ICA | 23-Mar-25 → 11-Oct-25 | Complete 100% | float — EK050PI010 PK000MU41H — Receive Quotes MU410 | 23-Mar-25 → 25-Apr-25 | Complete 100% | float — EK000MJ39B — Develop/Issue Load Sht & Design Data ERW - MJ391 | 25-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000ML50D — Technical Evaluation - ML500 | 25-Mar-25 → 27-Apr-25 | Complete 100% | float — EK000MD025 — Prepare job quality drawings for ERW | 25-Mar-25 → 28-May-25 | Complete 100% | float — EK000MD025 EK000ML44B — Develop & Issue Design Data for ERW - ML440 | 26-Mar-25 → 27-Mar-25 | Complete 100% | float — EK000MF31P — Confirm Analytical Design for ERW - MF301 | 26-Mar-25 → 29-Mar-25 | Complete 100% | float — EK000PR070 — Effluent Summary | 26-Mar-25 → 30-Mar-25 | Complete 100% | float — EK000MD51D — Technical Evaluation - MD501 | 26-Mar-25 → 03-Apr-25 | Complete 100% | float — EK000MU33F — Update/Issue Formal Inquiry for ERW - MU330 | 26-Mar-25 → 04-Apr-25 | Complete 100% | float — EK000MD33F — Update/Issue Formal Inquiry for ERW - MD303 | 26-Mar-25 → 11-May-25 | Complete 100% | float — EK000MD33F PK000MU30G — Issue MU300 RFQ | 26-Mar-25 → 28-Mar-25 | Complete 100% | float — PK000MU61G — Issue MU611 RFQ | 26-Mar-25 → 04-Apr-25 | Complete 100% | float — EK000MF32F — Develop & Issue Design Data for Tank Subcontract - MF302 | 26-Mar-25 → 08-Apr-25 | Complete 100% | float — PK000MJ35I — Eval Bids & Issue Recmd MJ305 | 26-Mar-25 → 02-May-25 | Complete 100% | float — EK000I131D — Technical Evaluation - Transmitters | 26-Mar-25 → 23-May-25 | Complete 100% | float — EK000I131D EK000MJ35D — Technical Evaluation - MJ305 | 27-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MJ36D — Technical Evaluation - MJ306 | 27-Mar-25 → 02-Apr-25 | Complete 100% | float — EK000MF32C — 05A MF312 2105-F Water Tank - Issue Data for Subcontract | 27-Mar-25 → 09-Apr-25 | Complete 100% | float — EK000MF33F — Develop & Issue Design Data for Tank Subcontract - MF311 | 27-Mar-25 → 09-Apr-25 | Complete 100% | float — EK000CVK35 — OSBL Rough Grading/Road | 27-Mar-25 → 23-May-25 | Complete 100% | float — EK000CVK35 EK000MD51F — Update/Issue Formal Inquiry for ERW - MD501 | 29-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000MD45P — Confirm Analytical Design for ERW - MD405 | 29-Mar-25 → 25-Apr-25 | Complete 100% | float — PK000MU30H — Receive Quotes MU300 | 29-Mar-25 → 10-May-25 | Complete 100% | float — PK000MU30H EK000MB62D — Technical Evaluation - MB621 | 30-Mar-25 → 18-Apr-25 | Complete 100% | float — EK000MB63D — Technical Evaluation - MB630 | 30-Mar-25 → 24-Jun-25 | Complete 100% | float — EK000MB63D EK000MF31B — Develop & Issue Design Data for Tank Subcontrac - MF301 | 01-Apr-25 → 08-Apr-25 | Complete 100% | float — EK000MJ34B — Develop/Issue Load Sht & Design Data ERW - MJ304 | 01-Apr-25 → 08-Apr-25 | Complete 100% | float — EK000PR065 — Catalyst and Chemical Specs | 01-Apr-25 → 09-Apr-25 | Complete 100% | float — EK000MB070 — 101-B Foundation Loads | 01-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000PR075 — Process Description | 01-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MJ39F — Update/Issue Formal Inquiry for ERW - MJ391 | 01-Apr-25 → 27-Apr-25 | Complete 100% | float — EK000QM020 — Develop/ Issue/ Approval of QA/QC Manual (EBIC/EXIM Verification) | 01-Apr-25 → 31-Oct-25 | Complete 100% | float — EK000QM020 EK000MD44P — Confirm Analytical Design for ERW - MD404 | 02-Apr-25 → 03-Apr-25 | Complete 100% | float — EK000MD31F — Update/Issue Formal Inquiry for ERW - MD301 | 02-Apr-25 → 16-Apr-25 | Complete 100% | float — EK000MU61B — Develop/Issue Load Sht & Design Data ERW - MU611 | 02-Apr-25 → 14-May-25 | Complete 100% | float — EK000MU61B EK000MB51D — Technical Evaluation - MB511 | 02-Apr-25 → 16-Apr-25 | Complete 100% | float — EK000MD32F — Update/Issue Formal Inquiry for ERW - MD302 | 02-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MD43D — Technical Evaluation - MD403 | 02-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000MC61I — Eval Bids & Issue Recmd MC610 | 03-Apr-25 → 05-Apr-25 | Complete 100% | float — EK000MC61B — Develop & Issue Design Data for ERW - MC610 | 04-Apr-25 → 20-Apr-25 | Complete 100% | float — PK000PSA8A — 000 Relief Valves - Issue RFQ | 04-Apr-25 → 10-Apr-25 | Complete 100% | float — EK000MJ35B — Develop & Issue Design Data for ERW - MJ305 | 05-Apr-25 → 09-May-25 | Complete 100% | float — EK000MB080 — 101-B Convection Coil Design | 05-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000ML31D — Technical Evaluation - ML313 | 05-Apr-25 → 19-Apr-25 | Complete 100% | float — PK000MJ36I — Eval Bids & Issue Recmd MJ306 | 06-Apr-25 → 12-Apr-25 | Complete 100% | float — PK000PK040 — Establish Project Warranty Criteria | 06-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MB050 — 101-B Radiant coil design | 06-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MD22P — Confirm Analytical Design for ERW - MD202 | 06-Apr-25 → 15-Apr-25 | Complete 100% | float — EK000MB33F — MB333 - Develop & Issue Purchase ERW 101-B | 06-Apr-25 → 23-Apr-25 | Complete 100% | float — EK010SY020 — 010 CW Twr & FW Tanks P&ID development IDR Issue | 06-Apr-25 → 25-Apr-25 | Complete 100% | float — EK030SY020 — 030 Utility Plant P&ID development IDR Issue | 06-Apr-25 → 25-Apr-25 | Complete 100% | float — EK050SY020 — 050 Dock/Storage P&ID development IDR Issue | 06-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MBP4D — Technical Evaluation - 101-B Cast Material | 06-Apr-25 → 01-May-25 | Complete 100% | float — PK000MU61H — Receive Quotes MU611 | 06-Apr-25 → 02-May-25 | Complete 100% | float — PK000MD51I — Eval Bids & Issue Recmd MD501 | 06-Apr-25 → 24-May-25 | Complete 100% | float — PK000MD51I EK000PI131 — Devlop Balance Tech P-Class specs for Procuremnt | 06-Apr-25 → 25-May-25 | Complete 100% | float — EK000PI131 EK000FP050 — FP Overall Firewater P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK000FP050 EK010FP011 — FP Firewater Pump P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK010FP011 EK010FP050 — FP Deluge P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK010FP050 PK000MU33G — Issue MU330 RFQ | 08-Apr-25 → 09-Apr-25 | Complete 100% | float — EK000MD43B — Develop & Issue Design Data for ERW - MD403 | 08-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MU35D — Technical Evaluation - MU350 | 08-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MC21D — Technical Evaluation - MC210 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MC23D — Technical Evaluation - MC230 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MD45B — Develop & Issue Design Data for ERW - MD405 | 08-Apr-25 → 08-May-25 | Complete 100% | float — PK000MC61M — Requote/Bid Condition/Final Tab - MC610 | 08-Apr-25 → 04-Sep-25 | Complete 100% | float — PK000MC61M EK000MC23B — Develop & Issue Design Data for ERW - MC230 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MD42B — Develop & Issue Design Data for ERW - MD402 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MD41B — Develop & Issue Design Data for ERW - MD401 | 09-Apr-25 → 18-Apr-25 | Complete 100% | float — EK000MU30B — Develop/Issue Load Sht & Design Data ERW - MU300 | 09-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000PS010 — Level III CPM Schedule / First Planner | 09-Apr-25 → 24-May-25 | Complete 100% | float — EK000PS010 PK000IC35E — DCS - Eval Bids/Issue Recmd | 09-Apr-25 → 31-May-25 | Complete 100% | float — PK000IC35E EK000ML42D — Technical Evaluation - ML420 | 09-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MJ34F — Update/Issue Formal Inquiry for ERW - MJ304 | 09-Apr-25 → 26-Apr-25 | Complete 100% | float — PK000MD51M — Requote/Bid Condition/Final Tab - MD501 | 09-Apr-25 → 03-May-25 | Complete 100% | float — EK000MB41D — Technical Evaluation - MB410 | 10-Apr-25 → 01-May-25 | Complete 100% | float — PK000MU33H — Receive Quotes MU330 | 10-Apr-25 → 20-May-25 | Complete 100% | float — PK000MU33H PK000PSA8B — 000 Relief Valves - Receive Quotes | 10-Apr-25 → 20-Jun-25 | Complete 100% | float — PK000PSA8B EK000MJ33B — Develop/Issue Load Sht & Design Data ERW - MJ303 | 11-Apr-25 → 23-May-25 | Complete 100% | float — EK000MJ33B EK000MJ32D — Technical Evaluation - MJ302 | 12-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MJ31D — Technical Evaluation - MJ301 | 12-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MB055 — 101-B Radiant coil BOM | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MB075 — 101-B Convection Coil BOM | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML51B — Develop/Issue Load Sht & Design Data ERW - ML512 | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MC63B — Develop & Issue Design Data for ERW - MC630 | 15-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MB61E — Prepare & Issue Purchase ERW - MB610 | 15-Apr-25 → 22-Apr-25 | Complete 100% | float — EK000MD43F — Update/Issue Formal Inquiry for ERW - MD403 | 15-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD32D — Technical Evaluation - MD302 | 15-Apr-25 → 04-May-25 | Complete 100% | float — EK000IC36D — DCS (MIV) - Tech Evaluation | 15-Apr-25 → 17-May-25 | Complete 100% | float — EK000MC31P — Develop & Issue Setting Plans for ERW - MC310 | 15-Apr-25 → 28-May-25 | Complete 100% | float — EK000MC31P EK000MC21P — Develop & Issue Setting Plans for ERW - MC210 | 15-Apr-25 → 20-Jun-25 | Complete 100% | float — EK000MC21P EK000CS025 — Turnover System Definition for ISBL | 15-Apr-25 → 31-Jan-26 | Complete 100% | float — EK000CS025 EK000MD42F — Update/Issue Formal Inquiry for ERW - MD402 | 16-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML42B — Develop & Issue Design Data for ERW - ML420 | 16-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MD31D — Technical Evaluation - MD301 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000ML33B — Develop/Issue Load Sht & Design Data ERW - ML330 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD33D — Technical Evaluation - MD303 | 16-Apr-25 → 04-May-25 | Complete 100% | float — EK000MBP3D — Technical Evaluation - 101-B Pressure Parts | 16-Apr-25 → 10-May-25 | Complete 100% | float — EK000MD21F — Develop & Issue Inquiry ERW - MD201 | 17-Apr-25 → 17-Jun-25 | Complete 100% | float — EK000MD21F EK000PR140 — Formal Issue of Process Release | 18-Apr-25 → 08-May-25 | Complete 100% | float — PK000MD31M — Final Tab/Recmd - MD301 | 18-Apr-25 → 24-Jul-25 | Complete 100% | float — PK000MD31M EK000MD47P — Confirm Analytical Design for ERW - MD406 | 18-Apr-25 → 22-Apr-25 | Complete 100% | float — PK000MD45I — Eval Bids & Issue Recmd MD405 | 19-Apr-25 → 01-May-25 | Complete 100% | float — PK000MJ36J — Final Negotiate/Interim Award - MJ306 | 19-Apr-25 → 02-May-25 | Complete 100% | float — PK000MD22I — Eval Bids & Issue Recmd MD202 | 19-Apr-25 → 03-May-25 | Complete 100% | float — PK000MD42I — Eval Bids & Issue Recmd MD402 | 19-Apr-25 → 04-May-25 | Complete 100% | float — PK000MD44I — Eval Bids & Issue Recmd MD404 | 19-Apr-25 → 04-May-25 | Complete 100% | float — EK000MJ37B — Develop & Issue Design Data for ERW - MJ340 | 19-Apr-25 → 09-May-25 | Complete 100% | float — EK000MD41F — Update/Issue Formal Inquiry for ERW - MD401 | 20-Apr-25 → 26-Apr-25 | Complete 100% | float — EK000MD44Q — Develop Analytical Sketches for ERW - MD404 | 20-Apr-25 → 27-Apr-25 | Complete 100% | float — EK000MJ73B — Develop/Issue Load Sht & Design Data ERW - MJ730 | 20-Apr-25 → 30-Apr-25 | Complete 100% | float — EK000EV015 — Issue load sheets for wastewater systems | 20-Apr-25 → 31-May-25 | Complete 100% | float — EK000EV015 EK000MD44B — Develop & Issue Design Data for ERW - MD404 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD47B — Develop & Issue Design Data for ERW - MD406 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000I110B — Issue RFQ - Orific Plates | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000I112B — Issue RFQ - Venturis | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000I115B — Issue RFQ - Annubars | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000I116B — Issue RFQ - Wedge Flow Meters | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000I616B — Issue RFQ - Steam Drum Lvl Gauges | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000I623B — Issue RFQ - Multi-Point Thermocouples | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000MB81I — Eval Bids & Issue Recmd MB810 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — PK000ML31I — Eval Bids & Issue Recmd ML313 | 22-Apr-25 → 26-Apr-25 | Complete 100% | float — PK000ML42I — Eval Bids & Issue Recmd ML420 | 22-Apr-25 → 26-Apr-25 | Complete 100% | float — PK000MU35I — Eval Bids & Issue Recmd MU350 | 22-Apr-25 → 26-Apr-25 | Complete 100% | float — PK000MD42M — Requote/Bid Condition/Final Tab - MD402 | 22-Apr-25 → 30-Apr-25 | Complete 100% | float — EK000MD46B — Develop/Issue Load Sht & Design Data ERW - MD411 | 22-Apr-25 → 03-May-25 | Complete 100% | float — PK000MJ32I — Eval Bids & Issue Recmd MJ302 | 22-Apr-25 → 03-May-25 | Complete 100% | float — PK000MD34M — Requote/Bid Condition/Final Tab - MD304 | 22-Apr-25 → 04-May-25 | Complete 100% | float — PK000MD46I — Eval Bids & Issue Recmd MD411 | 22-Apr-25 → 04-May-25 | Complete 100% | float — EK000MU11B — 05B MU311 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU25B — 02G MU225 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU32B — 01D MU322 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MD22B — Develop & Issue Design Data for ERW - MD202 | 23-Apr-25 → 01-May-25 | Complete 100% | float — PK000MD32M — Requote/Bid Condition/Final Tab - MD302 | 23-Apr-25 → 10-May-25 | Complete 100% | float — EK000MU31B — Develop/Issue Load Sht & Design Data ERW - MU310 | 23-Apr-25 → 16-May-25 | Complete 100% | float — EK000MC23F — Finalize Equip. Data Sheets for ERW - MC230 | 23-Apr-25 → 13-Jun-25 | Complete 100% | float — EK000MC23F PK000MD41I — Eval Bids & Issue Recmd MD401 | 23-Apr-25 → 02-May-25 | Complete 100% | float — PK000MD34I — Eval Bids & Issue Recmd MD304 | 24-Apr-25 → 11-May-25 | Complete 100% | float — PK000MC21I — Eval Bids & Issue Recmd MC210 | 24-Apr-25 → 24-May-25 | Complete 100% | float — PK000MC23I — Eval Bids & Issue Recmd MC230 | 24-Apr-25 → 24-May-25 | Complete 100% | float — PK000I611B — Issue RFQ - Pressure Gauges | 24-Apr-25 → 30-Apr-25 | Complete 100% | float — PK000I612B — Issue RFQ - Differential Pressure Gauges | 25-Apr-25 → 30-Apr-25 | Complete 100% | float — PK000I618B — Issue RFQ - Temperature Gauges | 25-Apr-25 → 30-Apr-25 | Complete 100% | float — PK000I621B — Issue RFQ - Temperature Elements | 25-Apr-25 → 30-Apr-25 | Complete 100% | float — PK000I121B — Issue RFQ - Vortex Meters | 25-Apr-25 → 01-May-25 | Complete 100% | float — PK000I122B — Issue RFQ - Coriolis Meters | 25-Apr-25 → 01-May-25 | Complete 100% | float — PK000I124B — Issue RFQ - Rotameters | 25-Apr-25 → 01-May-25 | Complete 100% | float — PK000I127B — Magnetic Flow Meters - Issue RFQ | 25-Apr-25 → 01-May-25 | Complete 100% | float — PK000ML42M — Requote/Bid Condition/Final Tab - ML420 | 25-Apr-25 → 18-Oct-25 | Complete 100% | float — PK000ML42M PK000I617B — Issue RFQ - Magnetic Lvl Gauges | 26-Apr-25 → 01-May-25 | Complete 100% | float — + — MB333 - Issue RFQ 101-B | 26-Apr-25 → 02-May-25 | Complete 100% | float — EK000CV036 — Issue Geotech S/C PKG | 26-Apr-25 → 02-May-25 | Complete 100% | float — PK000MJ31I — Eval Bids & Issue Recmd MJ301 | 26-Apr-25 → 03-May-25 | Complete 100% | float — EK000CV140 — Issue Site Survey S/C PKG | 26-Apr-25 → 14-May-25 | Complete 100% | float — PK000I115C — Receive Quotes - Annubars | 26-Apr-25 → 14-May-25 | Complete 100% | float — PK000I116C — Receive Quotes - Wedge Flow Meters | 26-Apr-25 → 15-May-25 | Complete 100% | float — EK000CV145 — Issue Site Leveling PKG | 26-Apr-25 → 16-May-25 | Complete 100% | float — PK000I616C — Receive Quotes - Steam Drum Lvl Gauges | 26-Apr-25 → 17-May-25 | Complete 100% | float — PK000I110C — Receive Quotes - Orific Plates | 26-Apr-25 → 20-May-25 | Complete 100% | float — PK000I112C — Receive Quotes - Venturis | 26-Apr-25 → 13-Jun-25 | Complete 100% | float — PK000I112C PK000I623C — Receive Quotes - Multi-Point Thermocouples | 26-Apr-25 → 15-Jul-25 | Complete 100% | float — PK000I623C PK000MB62I — Eval Bids & Issue Recmd MB621 | 27-Apr-25 → 29-Apr-25 | Complete 100% | float — PK000MJ34G — Issue MJ304 RFQ | 27-Apr-25 → 30-Apr-25 | Complete 100% | float — EK000MD44F — Update/Issue Formal Inquiry for ERW - MD404 | 27-Apr-25 → 01-May-25 | Complete 100% | float — EK000ML51F — Develop & Issue Inquiry for ERW - ML512 | 27-Apr-25 → 01-May-25 | Complete 100% | float — PK000MD43I — Eval Bids & Issue Recmd MD403 | 27-Apr-25 → 04-May-25 | Complete 100% | float — PK000MD43M — Requote/Bid Condition/Final Tab - MD403 | 27-Apr-25 → 04-May-25 | Complete 100% | float — PK000ML50I — Eval Bids & Issue Recmd ML500 | 27-Apr-25 → 04-May-25 | Complete 100% | float — EK000MJ31F — Update/Issue Formal Inquiry for ERW - MJ301 | 27-Apr-25 → 08-May-25 | Complete 100% | float — EK000MBP1E — Prepare & Issue Purchase ERW 101-B Shop Fab | 27-Apr-25 → 10-May-25 | Complete 100% | float — EK000ML33F — Develop & Issue Inquiry for ERW - ML330 | 27-Apr-25 → 13-May-25 | Complete 100% | float — PK000MB51I — Eval Bids & Issue Recmd MB511 | 27-Apr-25 → 14-May-25 | Complete 100% | float — EK000MJ32F — Update/Issue Formal Inquiry for ERW - MJ302 | 27-Apr-25 → 29-May-25 | Complete 100% | float — EK000MB63F — Prepare & Issue Purchase ERW - MB630 | 27-Apr-25 → 29-May-25 | Complete 100% | float — EK000MJ36B — Develop/Issue Load Sht & Design Data ERW - MJ306 | 27-Apr-25 → 08-Jun-25 | Complete 100% | float — EK000MJ36B PK000MU35M — Requote/Bid Condition/Final Tab - MU350 | 27-Apr-25 → 15-Jul-25 | Complete 100% | float — PK000MU35M PK000MD41M — Final Tab/Recmd - MD401 | 27-Apr-25 → 23-Jul-25 | Complete 100% | float — PK000MD41M PK000ML50M — Requote/Bid Condition/Final Tab - ML500 | 29-Apr-25 → 08-Aug-25 | Complete 100% | float — PK000ML50M PK000MJ39M — Requote/Bid Condition/Final Tab - MJ391/MJ392 | 29-Apr-25 → 20-Dec-25 | Complete 100% | float — PK000MJ39M EK000MU35B — Develop & Issue Design Data for ERW - MU350 | 01-May-25 → 14-May-25 | Complete 100% | float — EK000IC010 — Make decision of FF vs. Traditional DCS system | 01-May-25 → 17-May-25 | Complete 100% | float — EK000MJ75B — Develop & Issue Design Data for ERW - MJ750 | 01-May-25 → 20-May-25 | Complete 100% | float — EK000CV136 — Issue Rough Grade (Ammonia) S/C PKG | 01-May-25 → 27-May-25 | Complete 100% | float — EK000MJ73F — Develop & Issue Inquiry for ERW - MJ730 | 01-May-25 → 12-Jun-25 | Complete 100% | float — EK000MJ73F PK000MJ34H — Receive Quotes MJ304 | 01-May-25 → 01-May-25 | Complete 100% | float — PK000ML51G — Issue ML512 RFQ | 01-May-25 → 01-May-25 | Complete 100% | float — EK000MD22F — Update/Issue Formal Inquiry for ERW - MD202 | 01-May-25 → 17-May-25 | Complete 100% | float — PK000I611C — Receive Quotes - Pressure Gauges | 01-May-25 → 22-May-25 | Complete 100% | float — PK000I612C — Receive Quotes - Differential Pressure Gauges | 01-May-25 → 22-May-25 | Complete 100% | float — EK000MC23P — Develop & Issue Setting Plans for ERW - MC230 | 01-May-25 → 21-Jun-25 | Complete 100% | float — EK000MC23P PK000I621C — Receive Quotes - Temperature Elements | 01-May-25 → 10-Jul-25 | Complete 100% | float — PK000I621C PK000I618C — Receive Quotes - Temperature Gauges | 01-May-25 → 11-Jul-25 | Complete 100% | float — PK000I618C EK000MU11O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU11O EK000MU25O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU25O EK000MU310 — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU310 EK000MU32O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU32O EK010SY030 — 010 CW Twr & FW Tanks P&ID IDR Meeting milestone | 02-May-25 → 03-May-25 | Complete 100% | float — EK030SY030 — 030 Utility Plant P&ID IDR Meeting milestone | 02-May-25 → 03-May-25 | Complete 100% | float — EK050SY030 — 050 Dock/Storage P&ID IDR Meeting milestone | 02-May-25 → 03-May-25 | Complete 100% | float — PK000MBP4I — Eval Bids & Issue Recmd 101-B Cast Material | 02-May-25 → 10-May-25 | Complete 100% | float — EK000MD46P — Confirm Analytical Design for ERW - MD411 | 02-May-25 → 11-May-25 | Complete 100% | float — PK000MB41I — Eval Bids & Issue Recmd MB410 | 02-May-25 → 20-May-25 | Complete 100% | float — EK000MJ34D — Technical Evaluation - MJ304 | 02-May-25 → 03-May-25 | Complete 100% | float — PK000I121C — Receive Quotes - Vortex Meters | 02-May-25 → 20-May-25 | Complete 100% | float — PK000I122C — Receive Quotes - Coriolis Meters | 02-May-25 → 20-May-25 | Complete 100% | float — PK000I124C — Receive Quotes - Rotameters | 02-May-25 → 20-May-25 | Complete 100% | float — PK000I127C — Magnetic Flow Meters - Receive Quotes | 02-May-25 → 20-May-25 | Complete 100% | float — PK000I617C — Receive Quotes - Magnetic Lvl Gauges | 02-May-25 → 22-May-25 | Complete 100% | float — PK000ML51H — Receive Quotes ML512 | 02-May-25 → 17-Jun-25 | Complete 100% | float — PK000ML51H EK000MC32P — Develop & Issue Setting Plans for ERW - MC311 | 02-May-25 → 20-Jun-25 | Complete 100% | float — EK000MC32P PK000MJ35J — Final Negotiate/Interim Award - MJ305 | 02-May-25 → 23-Aug-25 | Complete 100% | float — PK000MJ35J EK000MU41D — Technical Evaluation - MU410 | 03-May-25 → 28-Jun-25 | Complete 100% | float — EK000MU41D PK000MU61I — Eval Bids & Issue Recmd MU611 | 03-May-25 → 25-Jul-25 | Complete 100% | float — PK000MU61I PK000MD33I — Eval Bids & Issue Recmd MD303 | 04-May-25 → 10-May-25 | Complete 100% | float — EK000MD31E — Prepare & Issue Purchase ERW - MD301 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MD34E — Prepare & Issue Purchase ERW - MD304 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MBP4E — Prepare & Issue Purchase ERW 101-B Cast Material | 04-May-25 → 17-May-25 | Complete 100% | float — EK000PC020 — Load PCMS & Issue First Cost Report | 04-May-25 → 18-May-25 | Complete 100% | float — EK000MB41E — Prepare & Issue Purchase ERW - MB410 | 04-May-25 → 20-May-25 | Complete 100% | float — EK010SY040 — 010 CW Twr & FW Tanks P&IDs - ICA Issue development | 04-May-25 → 20-Jun-25 | Complete 100% | float — EK010SY040 EK030SY040 — 030 Utility Plant P&IDs - ICA Issue development | 04-May-25 → 20-Jun-25 | Complete 100% | float — EK030SY040 EK050SY040 — 050 Dock/Storage P&IDs - ICA Issue development | 04-May-25 → 20-Jun-25 | Complete 100% | float — EK050SY040 EK000MD32E — Prepare & Issue Purchase ERW - MD302 | 06-May-25 → 10-May-25 | Complete 100% | float — PK000MD32I — Eval Bids & Issue Recmd MD302 | 06-May-25 → 10-May-25 | Complete 100% | float — PK000MJ34I — Eval Bids & Issue Recmd MJ304 | 06-May-25 → 10-May-25 | Complete 100% | float — EK000MD43E — Prepare & Issue Purchase ERW - MD403 | 06-May-25 → 11-May-25 | Complete 100% | float — PK000PIA4A — Product Line Piping - Issue REQ/RFQ to Vend | 06-May-25 → 15-May-25 | Complete 100% | float — EK05BPI030 — 05B Conceptual Layout - Supersketches | 07-May-25 → 27-Dec-26 | In Progress 59% | float — EK05BPI030 PK000MD31I — Eval Bids & Issue Recmd MD301 | 07-May-25 → 11-May-25 | Complete 100% | float — EK000MU33B — Develop/Issue Load Sht & Design Data ERW - MU330 | 07-May-25 → 20-May-25 | Complete 100% | float — EK000MC31D — Technical Evaluation - MC310 | 07-May-25 → 24-May-25 | Complete 100% | float — EK000MC32D — Technical Evaluation - MC311 | 07-May-25 → 24-May-25 | Complete 100% | float — EK020MC31D — MC312 - (120,121-C) - Technical Evaluation | 07-May-25 → 24-May-25 | Complete 100% | float — PK000MB33H — MB333 - Receive Quotes 101-B | 07-May-25 → 08-Jun-25 | Complete 100% | float — EK000MU61D — Technical Evaluation - MU611 | 07-May-25 → 20-Jun-25 | Complete 100% | float — EK000MU61D PK000PIA1C — Bulk Piping A/G & U/G - Tech Evaluation | 07-May-25 → 21-Jun-25 | Complete 100% | float — PK000PIA1C PK000PIA1D — Bulk Piping A/G & U/G - Eval Bids/Issue Recmd | 07-May-25 → 01-Jul-25 | Complete 100% | float — PK000PIA1D PK000PTA0A — Engineered Pipe Supports - Inquiry REQ/RFQ | 07-May-25 → 04-Jun-25 | Complete 100% | float — EK000MU21B — Develop/Issue Load Sht & Design Data ERW - MU221 | 08-May-25 → 10-May-25 | Complete 100% | float — EK000MU22B — Develop/Issue Load Sht & Design Data ERW - MU222 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000MU29B — Develop/Issue Load Sht & Design Data ERW - MU292 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000YA005 — Process Release | 08-May-25 | Complete EK000YA811 — (EP-12) Issue Process Release | 08-May-25 | Complete EK000MD51E — Prepare & Issue Purchase ERW - MD501 | 09-May-25 → 11-May-25 | Complete 100% | float — EK000MJ37F — Develop & Issue Inquiry for ERW - MJ340 | 09-May-25 → 05-Jun-25 | Complete 100% | float — PK000MJ32M — Requote/Bid Condition/Final Tab - MJ302 | 09-May-25 → 16-Jul-25 | Complete 100% | float — PK000MJ32M PK000MJ31M — Requote/Bid Condition/Final Tab - MJ301 | 09-May-25 → 25-Jul-25 | Complete 100% | float — PK000MJ31M EK000MJ35F — Update/Issue Formal Inquiry for ERW - MJ305 | 10-May-25 → 24-May-25 | Complete 100% | float — PK000MU30I — Eval Bids & Issue Recmd MU300 | 10-May-25 → 29-Oct-25 | Complete 100% | float — PK000MU30I PK000MD47G — Issue MD406 RFQ | 13-May-25 → 13-May-25 | Complete 100% | float — EK000MBP3E — Prepare & Issue Purchase ERW 101-B Pressure Part | 13-May-25 → 16-May-25 | Complete 100% | float — PK000MBP3I — Eval Bids & Issue Recmd 101-B Pressure Parts | 13-May-25 → 18-May-25 | Complete 100% | float — EK000I220A — Issue Preliminary ERW Pkg - MOV Valves | 13-May-25 → 31-May-25 | Complete 100% | float — EK000MD45F — Update/Issue Formal Inquiry for ERW - MD405 | 13-May-25 → 31-May-25 | Complete 100% | float — PK000MB63I — Eval Bids & Issue Recmd MB630 | 13-May-25 → 11-Jul-25 | Complete 100% | float — PK000MB63I EK000I354A — ITCC - Engr ERW Issued | 13-May-25 → 23-Jul-25 | Complete 100% | float — EK000I354A EK000MU30D — Technical Evaluation - MU300 | 13-May-25 → 27-Sep-25 | Complete 100% | float — EK000MU30D EK000MD46F — Update/Issue Formal Inquiry for ERW - MD411 | 14-May-25 → 31-May-25 | Complete 100% | float — EK000MB62F — Prepare & Issue Purchase ERW - MB621 | 14-May-25 → 05-Jun-25 | Complete 100% | float — PK000MD33M — Final Tab/Recmd - MD303 | 14-May-25 → 23-Jul-25 | Complete 100% | float — PK000MD33M PK000ML33G — Issue ML330 RFQ | 14-May-25 → 15-May-25 | Complete 100% | float — PK000MD47H — Receive Quotes MD406 | 14-May-25 → 06-Jun-25 | Complete 100% | float — PK000I115E — Eval Bids / Issue Recmd - Annubars | 15-May-25 → 31-Jul-25 | Complete 100% | float — PK000I115E PK000PIA4B — Product Line Piping - Receive Bids | 16-May-25 → 06-Jun-25 | Complete 100% | float — PK000ML33H — Receive Quotes ML330 | 16-May-25 → 10-Jul-25 | Complete 100% | float — PK000ML33H PK000I116E — Eval Bids / Issue Recmd - Wedge Flow Meters | 16-May-25 → 31-Jul-25 | Complete 100% | float — PK000I116E EK000MB045 — Catalyst Vac data sheets | 20-May-25 → 28-May-25 | Complete 100% | float — EK000CV065 — Review Perimeter Wall Design - IFC (by OCI) | 20-May-25 → 14-Jun-25 | Complete 100% | float — PK000MU33I — Eval Bids & Issue Recmd MU330 | 20-May-25 → 09-Sep-25 | Complete 100% | float — PK000MU33I EK000MJ75F — Develop & Issue Inquiry for ERW - MJ750 | 21-May-25 → 28-May-25 | Complete 100% | float — PK000I110E — Eval Bids / Issue Recmd - Orific Plates | 21-May-25 → 31-Jul-25 | Complete 100% | float — PK000I110E PK000I121E — Eval Bids / Issue Recmd - Vortex Meters | 21-May-25 → 31-Jul-25 | Complete 100% | float — PK000I121E PK000I122E — Eval Bids / Issue Recmd - Coriolis Meters | 21-May-25 → 31-Jul-25 | Complete 100% | float — PK000I122E PK000I124E — Eval Bids / Issue Recmd - Rotameters | 21-May-25 → 31-Jul-25 | Complete 100% | float — PK000I124E PK000I616E — Eval Bids / Issue Recmd - Steam Drum Lvl Gauges | 21-May-25 → 31-Jul-25 | Complete 100% | float — PK000I616E PK000I621E — Eval Bids / Issue Recmd - Temperature Elements | 21-May-25 → 31-Jul-25 | Complete 100% | float — PK000I621E PK000I611E — Eval Bids / Issue Recmd - Pressure Gauges | 22-May-25 → 31-Jul-25 | Complete 100% | float — PK000I611E PK000I617E — Eval Bids / Issue Recmd - Magnetic Lvl Gauges | 22-May-25 → 31-Jul-25 | Complete 100% | float — PK000I617E EK000YA806 — (EP-07) Issue Project Plan | 24-May-25 | Complete PK000I131E — Eval Bids / Issue Recmd - Transmitters | 24-May-25 → 31-May-25 | Complete 100% | float — PK000I210E — 000 Control Valves - Eval Bids / Issue Recmd | 24-May-25 → 31-May-25 | Complete 100% | float — PK000MJ75G — Issue MJ750 RFQ | 27-May-25 → 28-May-25 | Complete 100% | float — EK000MBG10 — General & Administrative | 28-May-25 → 27-Dec-26 | In Progress 57% | float — EK000MBG10 EK000I110D — Technical Evaluation - Orific Plates | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I115D — Technical Evaluation - Annubars | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I116D — Technical Evaluation - Wedge Flow Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I121D — Technical Evaluation - Vortex Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I122D — Technical Evaluation - Coriolis Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I124D — Technical Evaluation - Rotameters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I611D — Technical Evaluation - Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I612D — Technical Evaluation - Differential Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I616D — Technical Evaluation - Steam Drum Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I617D — Technical Evaluation - Magnetic Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000MJ33F — Develop & Issue Inquiry for ERW - MJ303 | 28-May-25 → 18-Jun-25 | Complete 100% | float — EK000MJ36F — Update/Issue Formal Inquiry for ERW - MJ306 | 28-May-25 → 19-Jun-25 | Complete 100% | float — EK000I127D — Magnetic Flow Meters - Technical Evaluation | 28-May-25 → 26-Jun-25 | Complete 100% | float — EK000MB33D — MB333 - Technical Evaluation 101-B | 28-May-25 → 01-Jul-25 | Complete 100% | float — PK000I612E — Eval Bids / Issue Recmd - Differential Pressure Gauges | 28-May-25 → 31-Jul-25 | Complete 100% | float — PK000I612E EK000YA801 — (EP-02) Issue 30 day Look Ahead Schedule | 28-May-25 | Complete PK000MJ75H — Receive Quotes MJ750 | 28-May-25 → 29-May-25 | Complete 100% | float — EK000MJ75D — Technical Evaluation - MJ750 | 29-May-25 → 30-May-25 | Complete 100% | float — PK000MJ75I — Eval Bids & Issue Recmd MJ750 | 29-May-25 → 30-May-25 | Complete 100% | float — PK000MJ37G — Issue MJ340 RFQ | 31-May-25 → 11-Jun-25 | Complete 100% | float — EK000ML43F — Develop & Issue Inquiry for ERW - ML430 | 31-May-25 → 06-Jun-25 | Complete 100% | float — PK000MJ37Q — Prepare & Issue Prelim. RFQ - MJ307 to Proc. | 31-May-25 → 12-Jun-25 | Complete 100% | float — EK000MB69F — Prepare & IssuePurchase ERW - MB691 | 03-Jun-25 → 17-Jun-25 | Complete 100% | float — PK000I230B — Issue RFQ - On/Off Valves | 04-Jun-25 → 06-Jun-25 | Complete 100% | float — PK000PTA0B — Engineered Pipe Supports - Receive Bids | 04-Jun-25 → 25-Jun-25 | Complete 100% | float — EK000MU33D — Technical Evaluation - MU330 | 04-Jun-25 → 01-Jul-25 | Complete 100% | float — EK000QM025 — Training - Management System | 05-Jun-25 → 05-Jun-25 | Complete 100% | float — PK000I220B — Issue RFQ - MOV's | 05-Jun-25 → 06-Jun-25 | Complete 100% | float — EK000I230A — Issue Preliminary ERW Pkg - On/Off Valves | 05-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000PS040 — Incorporate Comments / Issue Baseline Schedule | 05-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000MU22F — Develop & Issue Inquiry for ERW - MU222 | 05-Jun-25 → 26-Jun-25 | Complete 100% | float — EK000MB65F — Develop & Issue Purchase ERW - MB622 | 06-Jun-25 → 17-Jun-25 | Complete 100% | float — PK000I221B — 000 Everest Control Valves - Issue RFQ | 06-Jun-25 → 06-Jun-25 | Complete 100% | float — PK000I221C — 000 Everest Control Valves - Receive Quotes | 06-Jun-25 → 25-Jun-25 | Complete 100% | float — PK000I230C — Receive Quotes -On/Off Valves | 07-Jun-25 → 02-Jul-25 | Complete 100% | float — PK000I220C — Receive Quotes - MOV's | 07-Jun-25 → 02-Jul-25 | Complete 100% | float — PK000PIA4C — Product Line Piping - Tech Evaluation | 07-Jun-25 → 04-Jul-25 | Complete 100% | float — PK000MB33I — MB333 - Eval Bids & Issue Recmd 101-B | 07-Jun-25 → 25-Jul-25 | Complete 100% | float — PK000MB33I PK000MD47I — Eval Bids & Issue Recmd MD406 | 07-Jun-25 → 19-Sep-25 | Complete 100% | float — PK000MD47I EK000I112D — Technical Evaluation - Venturis | 10-Jun-25 → 14-Jun-25 | Complete 100% | float — PK000MJ73G — Issue MJ730 RFQ | 10-Jun-25 → 17-Jun-25 | Complete 100% | float — EK000PS030 — Schedule Risk Analysis | 10-Jun-25 → 20-Jun-25 | Complete 100% | float — EK000MB66F — Prepare & IssuePurchase ERW - MB660 | 10-Jun-25 → 21-Jun-25 | Complete 100% | float — EK000MU34B — Develop/Issue Load Sht & Design Data ERW - Chlorination Unit | 11-Jun-25 → 15-Jun-25 | Complete 100% | float — PK000MJ37F — Issue MJ307 RFQ | 12-Jun-25 → 21-Jun-25 | Complete 100% | float — PK000MJ37H — Receive Quotes MJ340 | 12-Jun-25 → 18-Jul-25 | Complete 100% | float — EK000MB68F — Prepare & Issue Purchase ERW - MB692 | 13-Jun-25 → 26-Jun-25 | Complete 100% | float — PK000MD21G — Issue MD201 RFQ | 17-Jun-25 → 20-Jun-25 | Complete 100% | float — EK000MB21F — Prepare & Issue Purchase ERW - MB212 | 17-Jun-25 → 25-Jun-25 | Complete 100% | float — EK000MB42F — Prepare & Issue Purchase ERW - MB420 | 17-Jun-25 → 26-Jun-25 | Complete 100% | float — PK000ML43G — Issue ML430 RFQ | 18-Jun-25 → 22-Jun-25 | Complete 100% | float — PK000MB69G — Issue MB691 RFQ | 18-Jun-25 → 25-Jun-25 | Complete 100% | float — PK000MJ73H — Receive Quotes MJ730 | 18-Jun-25 → 06-Aug-25 | Complete 100% | float — PK000MJ73H PK000MJ33G — Issue MJ303 RFQ | 19-Jun-25 → 21-Jun-25 | Complete 100% | float — EK000FP055 — FP Overall Firewater P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK000FP055 EK010FP020 — FP Firewater Pump P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK010FP020 EK010FP060 — FP Deluge P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK010FP060 EK000MB34F — Prepare & Issue Purchase ERW - MB340 | 20-Jun-25 → 21-Jun-25 | Complete 100% | float — PK000MB65G — Issue MB622 RFQ | 20-Jun-25 → 25-Jun-25 | Complete 100% | float — EK010SY050 — 010 Twr & FW Tanks P&IDs - ICA Issue Milestone | 20-Jun-25 | Complete EK030SY050 — 030 Utility Plant P&IDs - ICA Issue Milestone | 20-Jun-25 | Complete EK050SY050 — 050 Dock/Storage P&IDs - ICA Issue Milestone | 20-Jun-25 | Complete PK000PSA8D — 000 Relief Valves - Eval Bids / Issue Recmd | 20-Jun-25 → 26-Sep-25 | Complete 100% | float — PK000PSA8D PK000ML43H — Receive Quotes ML430 | 21-Jun-25 → 10-Jul-25 | Complete 100% | float — PK000MJ37D — Receive Quotes MJ307 | 21-Jun-25 → 19-Jul-25 | Complete 100% | float — PK000MU41I — Eval Bids & Issue Recmd MU410 | 21-Jun-25 → 24-Jul-25 | Complete 100% | float — EK030SY135 — 030 Utility Plant CV & FE Process Data | 21-Jun-25 → 07-Sep-25 | Complete 100% | float — EK030SY135 PK000MC21M — Requote/Bid Condition/Final Tab - MC210 | 21-Jun-25 → 27-Sep-25 | Complete 100% | float — PK000MC21M PK000MC23M — Requote/Bid Condition/Final Tab - MC230 | 21-Jun-25 → 27-Sep-25 | Complete 100% | float — PK000MC23M PK000MJ33H — Receive Quotes MJ303 | 22-Jun-25 → 29-Aug-25 | Complete 100% | float — PK000MJ33H PK000MB68G — Issue MB692 RFQ | 24-Jun-25 → 26-Jun-25 | Complete 100% | float — PK000PIA1E — Bulk Piping A/G & U/G - Reconfirm Pricing | 24-Jun-25 → 01-Jul-25 | Complete 100% | float — PK000MD21H — Receive Quotes for MD201 | 24-Jun-25 → 11-Jul-25 | Complete 100% | float — EK050SY060 — 050 Dock/Storage P&ID's - IPL Issue Development | 25-Jun-25 → 11-Oct-25 | Complete 100% | float — EK050SY060 EK010SY060 — 010 CW Twr & FW Tanks P&ID's - IPL Issue Development | 25-Jun-25 → 31-Oct-25 | Complete 100% | float — EK010SY060 EK030SY060 — 030 Utility Plant P&ID's - IPL Issue Development | 25-Jun-25 → 19-Nov-25 | Complete 100% | float — EK030SY060 PK000MB66G — Issue MB660 RFQ | 25-Jun-25 → 25-Jun-25 | Complete 100% | float — EK000I221D — 000 Everest Control Valves - Technical Evaluation | 25-Jun-25 → 10-Jul-25 | Complete 100% | float — PK000MB66H — Receive Quotes for MB660 | 25-Jun-25 → 27-Jul-25 | Complete 100% | float — PK000PTA0C — Engineered Pipe Supports - Eval Bids/Issue Recmd | 25-Jun-25 → 08-Aug-25 | Complete 100% | float — PK000PTA0C EK000YA809 — (EP-10) Locate Utility Tie-Ins | 26-Jun-25 | Complete EK000MU21F — Develop & Issue Inquiry for ERW - MU221 | 26-Jun-25 → 03-Jul-25 | Complete 100% | float — PK000MB65H — Receive Quotes for MB622 | 26-Jun-25 → 18-Jul-25 | Complete 100% | float — PK000MB21G — Issue MB212 RFQ | 26-Jun-25 → 22-Jul-25 | Complete 100% | float — PK000MB69H — Receive Quotes for MB691 | 26-Jun-25 → 22-Jul-25 | Complete 100% | float — PK000MB68H — Receive Quotes for MB692 | 27-Jun-25 → 26-Jul-25 | Complete 100% | float — PK000I127E — Magnetic Flow Meters - Eval Bids / Issue Recmd | 27-Jun-25 → 31-Jul-25 | Complete 100% | float — EK000MD33E — Prepare & Issue Purchase ERW - MD303 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — EK000MD41E — Prepare & Issue Purchase ERW - MD401 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — PK000MB42G — Issue MB420 RFQ | 02-Jul-25 → 05-Jul-25 | Complete 100% | float — EK000MB64F — Prepare & Issue Purchase ERW - MB640 | 02-Jul-25 → 11-Jul-25 | Complete 100% | float — PK000MU22G — Issue MU222 RFQ | 02-Jul-25 → 02-Jul-25 | Complete 100% | float — PK000I220E — Eval Bids / Issue Recmd - MOV's | 02-Jul-25 → 27-Aug-25 | Complete 100% | float — PK000I220E PK000I230E — Eval Bids / Issue Recmd - On/Off Valves | 02-Jul-25 → 28-Aug-25 | Complete 100% | float — PK000I230E PK000MB34G — Issue MB340 RFQ | 03-Jul-25 → 03-Jul-25 | Complete 100% | float — EK03FPI000 — 03F Preliminary Drawings for Supersketch U-2002 | 03-Jul-25 → 04-Jul-25 | Complete 100% | float — PK000MU21G — Issue MU221 RFQ | 03-Jul-25 → 05-Jul-25 | Complete 100% | float — PK000MU22H — Receive Quotes MU222 | 03-Jul-25 → 22-Jul-25 | Complete 100% | float — PK000MB34H — Receive Quotes for MB340 | 03-Jul-25 → 24-Jul-25 | Complete 100% | float — PK000PIA4D — Product Line Piping - Eval Bids/Issue Recmd | 05-Jul-25 → 18-Jul-25 | Complete 100% | float — PK000MB42H — Receive Quotes for MB420 | 05-Jul-25 → 20-Sep-25 | Complete 100% | float — PK000MB42H PK000MJ34X — Eval Bids & Issue Recmd MJ304 | 06-Jul-25 → 09-Sep-25 | Complete 100% | float — PK000MJ34X PK000MU21H — Receive Quotes MU221 | 08-Jul-25 → 25-Jul-25 | Complete 100% | float — PK000MB64G — Issue MB640 RFQ | 09-Jul-25 → 11-Jul-25 | Complete 100% | float — PK000I221E — 000 Everest Control Valves - Eval Bids / Issue Recmd | 10-Jul-25 → 31-Jul-25 | Complete 100% | float — EK000ML33D — Technical Evaluation - ML330 | 10-Jul-25 → 23-Aug-25 | Complete 100% | float — EK000ML33D EK000ML43D — Technical Evaluation - ML430 | 10-Jul-25 → 06-Sep-25 | Complete 100% | float — EK000ML43D PK000I618E — Eval Bids / Issue Recmd - Temperature Gauges | 11-Jul-25 → 31-Jul-25 | Complete 100% | float — PK000MB64H — Receive Quotes for MB640 | 12-Jul-25 → 09-Aug-25 | Complete 100% | float — EK03API000 — 03A Preliminary Drawings for Supersketch L-2003 | 13-Jul-25 → 13-Jul-25 | Complete 100% | float — PK020MC31E — MC312 - (120,121-C) - Eval Bids & Issue Recmd | 13-Jul-25 → 19-Aug-25 | Complete 100% | float — PK000MC32I — Eval Bids & Issue Recmd MC311 | 13-Jul-25 → 14-Oct-25 | Complete 100% | float — PK000MC32I PK000MC31I — Eval Bids & Issue Recmd MC310 | 13-Jul-25 → 20-Dec-25 | Complete 100% | float — PK000MC31I EK03API030 — 03A Conceptual Layout - Supersketches | 15-Jul-25 → 22-Jul-25 | Complete 100% | float — PK000MD21I — Eval Bids & Issue Recmd MD201 | 15-Jul-25 → 17-Aug-25 | Complete 100% | float — PK000I623E — Eval Bids / Issue Recmd - Multi-Point Thermocouples | 16-Jul-25 → 31-Jul-25 | Complete 100% | float — EK000I220D — Technical Evaluation - MOV's | 16-Jul-25 → 23-Jul-25 | Complete 100% | float — EK000MD21D — Technical Evaluation - MD201 | 16-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000I230D — Technical Evaluation - On/Off Valves | 17-Jul-25 → 24-Jul-25 | Complete 100% | float — PK000I444B — Issue RFQ - Analyzer Shelter | 19-Jul-25 → 25-Jul-25 | Complete 100% | float — EK000MB65D — Technical Evaluation - MB622 | 19-Jul-25 → 02-Aug-25 | Complete 100% | float — PK000MJ37E — Technical Evaluation - MJ307 | 19-Jul-25 → 06-Dec-25 | Complete 100% | float — PK000MJ37E EK01UPICWA — 01U Plant Layout Model - Cooling Water | 20-Jul-25 → 23-Aug-25 | Complete 100% | float — EK000I618D — Technical Evaluation - Temperature Gauges | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I621D — Technical Evaluation - Temperature Elements | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I623D — Technical Evaluation - Multi-Point Thermocouples | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — PK000MB33J — MB333 - Final Negotiate/Interim Award 101-B | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I352A — SIS - Engr ERW Issued | 22-Jul-25 → 02-Aug-25 | Complete 100% | float — EK000MB69D — Technical Evaluation - MB691 | 22-Jul-25 → 07-Aug-25 | Complete 100% | float — PK000MB21H — Receive Quotes for MB212 | 22-Jul-25 → 28-Aug-25 | Complete 100% | float — EK000MU22D — Technical Evaluation - MU222 | 22-Jul-25 → 06-Sep-25 | Complete 100% | float — EK000MU22D PK000MU41J — Final Negotiate/Interim Award - MU410 | 24-Jul-25 → 24-Jul-25 | Complete 100% | float — PK000I354B — ITCC - Inquiry REQ/RFQ | 24-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000MB34I — Eval Bids & Issue Recmd MB340 | 24-Jul-25 → 14-Aug-25 | Complete 100% | float — EK000MJ37D — Technical Evaluation - MJ340 | 24-Jul-25 → 28-Aug-25 | Complete 100% | float — PK000MU41P — Issue Formal P.O. for MU410 | 24-Jul-25 → 05-Sep-25 | Complete 100% | float — PK000MU41P EK000MJ39D — Technical Evaluation - MJ391 | 25-Jul-25 → 21-Dec-25 | Complete 100% | float — EK000MJ39D EK000MJ31X — Technical Evaluation - MJ301 | 25-Jul-25 → 10-Aug-25 | Complete 100% | float — PK000MJ32X — Technical Evaluation - MJ302 | 25-Jul-25 → 10-Aug-25 | Complete 100% | float — PK000I444C — Receive Quotes - Analyzer Shelter | 25-Jul-25 → 13-Sep-25 | Complete 100% | float — PK000I444C PK000MU61J — Final Negotiate/Interim Award - MU611 | 26-Jul-25 → 29-Jul-25 | Complete 100% | float — PK000MB33K — MB333 - Fab/PO Promise 101-B Riser Transition 101-B | 29-Jul-25 → 27-Dec-26 | In Progress 52% | float — PK000MB33K PK000I112E — Eval Bids / Issue Recmd - Venturis | 29-Jul-25 → 31-Jul-25 | Complete 100% | float — EK000MU11L — 05B MU311 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU25L — 02G MU225 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU32L — 01D MU322 Define Chemical Treatment Requirements | 29-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MB68D — Technical Evaluation - MB692 | 29-Jul-25 → 30-Aug-25 | Complete 100% | float — PK000MU61P — Issue Formal P.O. for MU611 | 29-Jul-25 → 03-Sep-25 | Complete 100% | float — EK01BPI000 — 01B Preliminary Drawings for Supersketch J-2001,2003,2004,2007 | 30-Jul-25 → 30-Jul-25 | Complete 100% | float — EK01DPI000 — 01D Preliminary Drawings for Supersketch J-2202 | 30-Jul-25 → 30-Jul-25 | Complete 100% | float — PK000MD33J — Final Negotiate/Interim Award - MD303 | 30-Jul-25 → 09-Aug-25 | Complete 100% | float — EK000MU31L — Define Chemical Treatment Requirements - MU310 | 30-Jul-25 → 10-Aug-25 | Complete 100% | float — PK000MU35J — Final Negotiate/Interim Award - MU350 | 30-Jul-25 → 10-Aug-25 | Complete 100% | float — EK000MB66D — Technical Evaluation - MB660 | 30-Jul-25 → 13-Aug-25 | Complete 100% | float — EK000MB34D — Technical Evaluation - MB340 | 30-Jul-25 → 13-Aug-25 | Complete 100% | float — EK010SY135 — 010 CW Twr & FW Tanks CV & FE Process Data | 30-Jul-25 → 17-Aug-25 | Complete 100% | float — EK000ML51D — Technical Evaluation - ML512 | 30-Jul-25 → 19-Aug-25 | Complete 100% | float — PK000MBP3J — Final Negotiate/Interim Award - Pressure Parts | 30-Jul-25 → 30-Aug-25 | Complete 100% | float — EK000MU21D — Technical Evaluation - MU221 | 30-Jul-25 → 14-Sep-25 | Complete 100% | float — EK000MU21D PK000I110G — Final Negotiation / Interim Award - Orific Plates | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I112G — Final Negotiation / Interim Award - Venturis | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I115G — Final Negotiation / Interim Award - Annubars | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I121G — Final Negotiation / Interim Award - Vortex Meters | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I122G — Final Negotiation / Interim Award - Coriolis Meters | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I124G — Final Negotiation / Interim Award - Rotameters | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I127G — Final Negotiation / Interim Award - Magnetic Flow Meters | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I612G — Final Negotiation / Interim Award - Differential Pressure Gauges | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I616G — Final Negotiation / Interim Award - Steam Drum Lvl Gauges | 31-Jul-25 → 01-Aug-25 | Complete 100% | float — PK000I116G — Final Negotiation / Interim Award - Wedge Flow Meters | 31-Jul-25 → 06-Aug-25 | Complete 100% | float — PK000I611G — Final Negotiation / Interim Award - Pressure Gauges | 31-Jul-25 → 06-Aug-25 | Complete 100% | float — PK000I617G — Final Negotiation / Interim Award - Magnetic Lvl Gauges | 31-Jul-25 → 06-Aug-25 | Complete 100% | float — PK000I621G — Final Negotiation / Interim Award - Temperature Elements | 31-Jul-25 → 06-Aug-25 | Complete 100% | float — PK000I623G — Final Negotiation / Interim Award - Multi-Point Thermocouples | 31-Jul-25 → 06-Aug-25 | Complete 100% | float — PK000I221G — Final Negotiation / Interim Award - Everest Control Valves | 31-Jul-25 → 14-Aug-25 | Complete 100% | float — EK03DPI030 — 03D Conceptual Layout - Supersketches | 01-Aug-25 → 07-Aug-25 | Complete 100% | float — EK01DPI030 — 01D Conceptual Layout - Supersketches | 01-Aug-25 → 15-Aug-25 | Complete 100% | float — PK000I131G — Final Negotiation / Interim Award - Transmitters | 01-Aug-25 → 06-Aug-25 | Complete 100% | float — PK000MBP4J — Final Negotiate/Interim Award - Cast Material | 01-Aug-25 → 09-Aug-25 | Complete 100% | float — EK000MU35E — Prepare & Issue Purchase ERW - MU350 | 01-Aug-25 → 13-Aug-25 | Complete 100% | float — EK050SY135 — 050 Dock/Storage CV & FE Process Data | 01-Aug-25 → 15-Aug-25 | Complete 100% | float — PK000I354C — ITCC - Receive Bids | 01-Aug-25 → 28-Aug-25 | Complete 100% | float — EK020FP490 — FP OSBL Fire Protection Eqmt. Location Plans - ICA | 01-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000I115K — Issue Formal Purchase Agreement - Annubars | 01-Aug-25 → 31-Oct-25 | Complete 100% | float — PK000I115K PK000I121K — Issue Formal Purchase Agreement - Vortex Meters | 01-Aug-25 → 31-Oct-25 | Complete 100% | float — PK000I121K PK000I122K — Issue Formal Purchase Agreement - Coriolis Meters | 01-Aug-25 → 31-Oct-25 | Complete 100% | float — PK000I122K PK000I124K — Issue Formal Purchase Agreement - Rotameters | 01-Aug-25 → 31-Oct-25 | Complete 100% | float — PK000I124K PK000I127K — Magnetic Flow Meters - Issue Formal Purchase Agreement | 01-Aug-25 → 31-Oct-25 | Complete 100% | float — PK000I127K PK000I110K — Issue Formal Purchase Agreement. - Orific Plates | 01-Aug-25 → 14-Nov-25 | Complete 100% | float — PK000I110K PK000I112K — Issue Formal Purchase Agreement - Venturis | 01-Aug-25 → 14-Nov-25 | Complete 100% | float — PK000I112K PK000I616K — Issue Formal Purchase Agreement. - Steam Drum Lvl Gauges | 01-Aug-25 → 30-Dec-25 | Complete 100% | float — PK000I616K PK000I612K — Issue Formal Purchase Agreement - Differential Pressure Gauges | 01-Aug-25 → 06-Feb-26 | Complete 100% | float — PK000I612K PK000I352B — SIS - Inquiry REQ/RFQ | 02-Aug-25 → 07-Aug-25 | Complete 100% | float — EK000YA810 — (EP-11) Issue Level 3 CPM Schedule | 03-Aug-25 | Complete PK000MB61J — Final Negotiate/Interim Award - MB610 | 05-Aug-25 → 09-Aug-25 | Complete 100% | float — PK000MB62J — Final Negotiate/Interim Award - MB621 | 05-Aug-25 → 09-Aug-25 | Complete 100% | float — PK000MB63J — Final Negotiate/Interim Award - MB630 | 05-Aug-25 → 09-Aug-25 | Complete 100% | float — PK000MB81J — Final Negotiate/Interim Award - MB810 | 05-Aug-25 → 09-Aug-25 | Complete 100% | float — EK000QM005 — Training - Object Engineering | 06-Aug-25 → 13-Aug-25 | Complete 100% | float — EK000I444A — Develop & Issue Inquiry ERW - Analyzer Shelter | 06-Aug-25 → 17-Aug-25 | Complete 100% | float — EK000MJ73D — Technical Evaluation - MJ730 | 06-Aug-25 → 16-Sep-25 | Complete 100% | float — EK000MJ73D PK000MJ73I — Eval Bids & Issue Recmd MJ730 | 06-Aug-25 → 19-Oct-25 | Complete 100% | float — PK000MJ73I PK000MB69I — Eval Bids & Issue Recmd MB691 | 06-Aug-25 → 29-Oct-25 | Complete 100% | float — PK000MB69I PK000I131K — Issue Formal Purchase Agreement - Transmitters | 06-Aug-25 → 02-Dec-25 | Complete 100% | float — PK000I131K PK000I621K — Issue Formal Purchase Agreement - Temperature Elements | 06-Aug-25 → 30-Dec-25 | Complete 100% | float — PK000I621K PK000I623K — Issue Formal Purchase Agreement - Multi-Point Thermocouples | 06-Aug-25 → 30-Dec-25 | Complete 100% | float — PK000I623K PK000I617K — Issue Formal Purchase Agreement - Magnetic Lvl Gauges | 06-Aug-25 → 20-Jan-26 | Complete 100% | float — PK000I617K PK000I611K — Issue Formal Purchase Agreement - Pressure Gauges | 06-Aug-25 → 06-Feb-26 | Complete 100% | float — PK000I611K PK000I116K — Issue Formal Purchase Agreement - Wedge Flow Meters | 06-Aug-25 → 07-Feb-26 | Complete 100% | float — PK000I116K PK000I352C — SIS - Receive Bids | 07-Aug-25 → 21-Aug-25 | Complete 100% | float — PK000PTA0D — Engineered Pipe Supports - Interim Award | 08-Aug-25 → 14-Aug-25 | Complete 100% | float — EK000CV165 — Issue ISBL Rough Grade Design Pkg. | 09-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000CV165 PK000MBP1K — MB221 - Fab/PO Promise 101-B Radiant Steel Panels | 09-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MBP1K PK000MBP1Q — MB221 - Fab/PO Promise 101-B Radiant Coil/Harps | 09-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MBP1Q PK000MBP1R — MB221 - Fab/PO Promise 101-B Convection Modules | 09-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MBP1R PK000MBP1S — MB221 - Fabr/PO Promise 101-B Radiant Ducting | 09-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MBP1S PK000MD31K — MD301 - Fabricate/PO Promise 103-D | 09-Aug-25 → 17-Feb-27 | In Progress 46% | float 55.0d PK000MD31K PK000MD33K — MD303 - Fabricate/PO Promise 105-D | 09-Aug-25 → 20-Mar-27 | In Progress 44% | float 50.0d PK000MD33K PK000MJ21K — MJ202 - Fabricate/PO Promise 102/3/5-J | 09-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MJ21K PK000I210G — Final Negotiation / Interim Award - Control Valves | 09-Aug-25 → 09-Aug-25 | Complete 100% | float — PK000MB41J — Final Negotiate/Interim Award - MB410 | 09-Aug-25 → 09-Aug-25 | Complete 100% | float — PK000MD31J — Final Negotiate/Interim Award - MD301 | 09-Aug-25 → 09-Aug-25 | Complete 100% | float — PK000MJ21J — Final Negotiate/Interim Award - MJ202 | 09-Aug-25 → 09-Aug-25 | Complete 100% | float — PK000MJ75J — Final Negotiate/Interim Award - MJ750 | 09-Aug-25 → 12-Aug-25 | Complete 100% | float — PK000PR20B — PR201 KAAP Catalyst - Issue RFQ | 09-Aug-25 → 12-Aug-25 | Complete 100% | float — PK000MD34J — Final Negotiate/Interim Award - MD304 | 09-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000MD42J — Final Negotiate/Interim Award - MD402 | 09-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000MD44J — Final Negotiate/Interim Award - MD404 | 09-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000MD45J — Final Negotiate/Interim Award - MD405 | 09-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000MD46J — Final Negotiate/Interim Award - MD411 | 09-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000MD22J — Final Negotiate/Interim Award - MD202 | 09-Aug-25 → 17-Aug-25 | Complete 100% | float — PK000MD32J — Final Negotiate/Interim Award - MD302 | 09-Aug-25 → 17-Aug-25 | Complete 100% | float — PK000MD33P — Issue Formal P.O. for MD303 | 09-Aug-25 → 19-Aug-25 | Complete 100% | float — PK000MD41J — Final Negotiate/Interim Award - MD401 | 09-Aug-25 → 23-Aug-25 | Complete 100% | float — PK000MD43J — Final Negotiate/Interim Award - MD403 | 09-Aug-25 → 23-Aug-25 | Complete 100% | float — PK000MD51J — Final Negotiate/Interim Award - MD501 | 09-Aug-25 → 27-Aug-25 | Complete 100% | float — PK000MJ21N — Recv. Planning V. Data MJ202 | 09-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000MJ22J — Final Negotiate/Interim Award - MJ201 | 09-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000MJ75N — Recv. Planning V. Data MJ750 | 09-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000ML31J — Final Negotiate/Interim Award - ML313 | 09-Aug-25 → 31-Aug-25 | Complete 100% | float — PK000MD21J — Final Negotiate/Interim Award - MD201 | 09-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MB63P — Issue Formal P.O. for MB630 | 09-Aug-25 → 09-Sep-25 | Complete 100% | float — PK000MD31N — Recv. Planning V. Data MD301 | 09-Aug-25 → 09-Sep-25 | Complete 100% | float — PK000MB41P — Issue Formal P.O. for MB410 | 09-Aug-25 → 10-Sep-25 | Complete 100% | float — PK000ML31N — Recv. Planning V. Data ML313 | 09-Aug-25 → 12-Sep-25 | Complete 100% | float — PK000PIA4E — Product Line Piping - Final Negotiation/Interim Award | 09-Aug-25 → 13-Sep-25 | Complete 100% | float — PK000MD41N — Recv. Planning V. Data MD401 | 09-Aug-25 → 17-Sep-25 | Complete 100% | float — PK000MD41N PK000MJ21P — Issue Formal P.O. for MJ202 | 09-Aug-25 → 19-Sep-25 | Complete 100% | float — PK000MJ21P PK000MBP1P — Issue Formal P.O. for 101-B Shop Fab | 09-Aug-25 → 20-Sep-25 | Complete 100% | float — PK000MBP1P PK000MBP4P — Issue Formal P.O. for 101-B Cast Material | 09-Aug-25 → 20-Sep-25 | Complete 100% | float — PK000MBP4P PK000MB81P — Issue Formal P.O. for MB810 | 09-Aug-25 → 21-Sep-25 | Complete 100% | float — PK000MB81P PK000MU35P — Issue Formal P.O. for MU350 | 09-Aug-25 → 23-Sep-25 | Complete 100% | float — PK000MU35P PK000MD33N — Recv. Planning V. Data MD303 | 09-Aug-25 → 25-Sep-25 | Complete 100% | float — PK000MD33N PK000MB61P — Issue Formal P.O. for MB610 | 09-Aug-25 → 30-Sep-25 | Complete 100% | float — PK000MB61P PK000IC35G — DCS - Interim Award | 09-Aug-25 → 12-Oct-25 | Complete 100% | float — PK000IC35G PK000MD43N — Recv. Planning V. Data MD403 | 09-Aug-25 → 14-Oct-25 | Complete 100% | float — PK000MD43N EK000MB64D — Technical Evaluation - MB640 | 09-Aug-25 → 17-Oct-25 | Complete 100% | float — EK000MB64D PK000MJ32J — Final Negotiate/Interim Award - MJ302 | 09-Aug-25 → 20-Nov-25 | Complete 100% | float — PK000MJ32J PK000MJ31J — Final Negotiate/Interim Award - MJ301 | 09-Aug-25 → 21-Nov-25 | Complete 100% | float — PK000MJ31J PK000MB62P — Issue Formal P.O. for MB621 | 09-Aug-25 → 09-Dec-25 | Complete 100% | float — PK000MB62P PK000I210K — 000 Control Valves - Issue Formal Purchase Agreement | 09-Aug-25 → 03-Feb-26 | Complete 100% | float — PK000I210K PK000PIA1G — Bulk Piping A/G & U/G - Fab/Exworks (CS, SS, U/G) | 09-Aug-25 → 31-Mar-26 | Complete 100% | float — PK000PIA1G PK000MU35K — MU350 - Fabricate/PO Promise 101-U DEAERATOR | 09-Aug-25 → 23-Apr-26 | Complete 100% | float — PK000MU35K EK000EB015 — Notice to Proceed (Eng. & Procurement Only) | 10-Aug-25 | Complete EK030SY150 — 030 Relief Valve Calculations - Utility Plant | 10-Aug-25 → 26-Sep-25 | Complete 100% | float — EK030SY150 PK000MB62K — MB621 - Fabricate/PO Promise 101-B ID & FD Fans | 12-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MB62K PK000MB81K — MB810 - Fabricate/PO Promise 102-B | 12-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MB81K EK000I221A — 000 Everest Control Valves - Issue Inquiry Req | 12-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000MJ75P — Issue Formal P.O. for MJ750 | 12-Aug-25 → 23-Aug-25 | Complete 100% | float — EK000MJ21E — Prepare & Issue Purchase ERW - MJ202 | 12-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000PR20C — PR201 KAAP Catalyst - Receive Quotes | 12-Aug-25 → 17-Sep-25 | Complete 100% | float — PK000MU35N — Recv. Planning V. Data MU350 | 12-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MU35N EK05API030 — 05A Conceptual Layout - Supersketches | 12-Aug-25 → 28-Sep-25 | Complete 100% | float — EK05API030 EK000IC350 — DCS - Develop Design Basis | 12-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000IC350 PK000IC35K — DCS - Formal Award | 12-Aug-25 → 17-Oct-25 | Complete 100% | float — PK000IC35K PK000MB66I — Eval Bids & Issue Recmd MB660 | 12-Aug-25 → 20-Jan-26 | Complete 100% | float — PK000MB66I PK000MB41K — MB410 - Fabricate/PO Promise 101-B Cast Tube Supports | 12-Aug-25 → 27-Feb-26 | Complete 100% | float — PK000MB41K PK000MB61K — MB610 - Fabricate/PO Promise 101-B Burners | 12-Aug-25 → 01-Apr-26 | Complete 100% | float — PK000MB61K PK000MB63K — MB630 - Fabricate/PO Promise 101-B Air Preheater | 12-Aug-25 → 14-Apr-26 | Complete 100% | float — PK000MB63K PK000MD32K — MD302 - Fabricate/PO Promise 104-D1/2 | 13-Aug-25 → 10-Jan-27 | In Progress 49% | float 85.0d PK000MD32K PK000MJ75K — MJ750 - Fabricate/PO Promise SURFACE CONDENSORS | 13-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MJ75K EK000MU61E — Prepare & Issue Purchase ERW - MU611 | 13-Aug-25 → 16-Aug-25 | Complete 100% | float — PK000MD41P — Issue Formal P.O. for MD401 | 13-Aug-25 → 20-Aug-25 | Complete 100% | float — PK000MB34J — Final Negotiate/Interim Award - MB340 | 13-Aug-25 → 14-Aug-25 | Complete 100% | float — EK010SY150 — 010 Relief Valve Calculations - CW Twr & FW Tanks | 14-Aug-25 → 26-Sep-25 | Complete 100% | float — EK010SY150 PK000MB34K — MB340 - Fabricate/PO Promise 101-B Finning | 14-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000MB34K PK000PTA0G — Engineered Pipe Supports - Fab / Exworks | 14-Aug-25 → 27-Dec-26 | In Progress 51% | float — PK000PTA0G PK000MB34P — Issue Formal P.O. for MB340 | 14-Aug-25 → 10-Sep-25 | Complete 100% | float — PK000PTA0E — Engineered Pipe Supports - Formal Award | 14-Aug-25 → 30-Dec-25 | Complete 100% | float — PK000PTA0E PK000PTA0F — Engineered Pipe Supports - Planning V. Data | 14-Aug-25 → 24-Jan-26 | Complete 100% | float — PK000PTA0F PK000I221K — 000 Everest Control Valves - Issue Formal Purchase Agreement | 14-Aug-25 → 03-Feb-26 | Complete 100% | float — PK000I221K EK01BPI030 — 01B Conceptual Layout - Supersketches | 15-Aug-25 → 31-Aug-25 | Complete 100% | float — PK000MD22A — MD202 - Fabricate/PO Promise TOWERS 104-E | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD22A PK000MD22K — MD202 - Fabricate/PO Promise TOWERS 103/105-E | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD22K PK000MD22T — MD202 - Fabricate/PO Promise TOWERS 150-E | 16-Aug-25 → 28-Feb-27 | In Progress 45% | float 100.0d PK000MD22T PK000MD34K — MD304 - Fabricate/PO Promise 106-D, 109-DA/B | 16-Aug-25 → 29-Jan-27 | In Progress 47% | float 200.0d PK000MD34K PK000MD34Z — MD304 - Fabricate/PO Promise 108-DA/B | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD34Z PK000MD42K — MD402 - Fabricate/PO Promise 102-F1, 102-F2 | 16-Aug-25 → 21-Mar-27 | In Progress 43% | float 130.0d PK000MD42K PK000MD42N — MD402 - Fabricate/PO Promise 104-F, 144-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD42N PK000MD44K — MD404 - Fabricate/PO Promise 109-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD44K PK000MD44L — MD404 - Fabricate/PO Promise 107-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD44L PK000MD44T — MD404 - Fabricate/PO Promise 132-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD44T PK000MD45A — MD405 - Fabricate/PO Promise ISBL DRUMS - 115-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD45A PK000MD45K — MD405 - Fabricate/PO Promise ISBL DRUMS - 156-F & 157-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD45K PK000MD46K — MD411 - Fabricate/PO Promise OSBL DRUMS - 2203-F & 2204-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD46K PK000MD46T — MD411 - Fabricate/PO Promise OSBL DRUMS - 2006-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD46T PK000MD4Q — MD405 - Fabricate/PO Promise ISBL DRUMS - 118-F | 16-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD4Q PK000MD42P — Issue Formal P.O. for MD402 | 16-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MD44P — Issue Formal P.O. for MD404 | 16-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MD45P — Issue Formal P.O. for MD405 | 16-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MD46P — Issue Formal P.O. for MD411 | 16-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MD32P — Issue Formal P.O. for MD302 | 16-Aug-25 → 07-Sep-25 | Complete 100% | float — PK03FMD03 — 03F MD411 2006-F Boiler Blowdown Drum - Prod. V. Data | 16-Aug-25 → 13-Sep-25 | Complete 100% | float — PK000MD34P — Issue Formal P.O. for MD304 | 16-Aug-25 → 18-Sep-25 | Complete 100% | float — PK000MD32N — Recv. Planning V. Data MD302 | 16-Aug-25 → 02-Oct-25 | Complete 100% | float — PK000MD32N PK000MD34N — Recv. Planning V. Data MD304 | 16-Aug-25 → 12-Nov-25 | Complete 100% | float — PK000MD34N PK020MC31G — MC312 - (120,121-C) - Final Negotiate/Interim Award | 19-Aug-25 → 21-Aug-25 | Complete 100% | float — PK000MBP3M — Requote/Bid Condition/Final Tab - Pressure Parts | 19-Aug-25 → 28-Aug-25 | Complete 100% | float — PK000ML51I — Eval Bids & Issue Recmd ML512 | 19-Aug-25 → 06-Sep-25 | Complete 100% | float — PK000ML33I — Eval Bids & Issue Recmd ML330 | 19-Aug-25 → 13-Sep-25 | Complete 100% | float — EK000MJ75E — Prepare & Issue Purchase ERW - MJ750 | 19-Aug-25 → 28-Sep-25 | Complete 100% | float — EK000MJ75E EK050SY150 — 050 Relief Valve Calculations - Dock/Storage | 20-Aug-25 → 25-Sep-25 | Complete 100% | float — PK000PIA1F — Bulk Piping A/G & U/G - Formal Award | 20-Aug-25 → 03-Sep-25 | Complete 100% | float — PK020MC31C — MC312 - Fabricate/PO Promise 121-C | 21-Aug-25 → 28-Feb-27 | In Progress 44% | float 90.0d PK020MC31C PK020MC31K — MC312 - Fabricate/PO Promise 120-C | 21-Aug-25 → 28-Feb-27 | In Progress 44% | float 90.0d PK020MC31K EK000PE070 — Kick-off meeting at MEC | 22-Aug-25 → 23-Aug-25 | Complete 100% | float — PK020MC31H — MC312 - (120,121-C) - Issue Formal P.O. | 22-Aug-25 → 19-Sep-25 | Complete 100% | float — EK03UPIFWA — 03U Plant Layout Model - Firewater | 22-Aug-25 → 05-Oct-25 | Complete 100% | float — EK03UPIFWA EK01UPIFWA — 01U Plant Layout Model - Firewater | 22-Aug-25 → 08-Oct-25 | Complete 100% | float — EK01UPIFWA PK000MJ35P — Issue Formal P.O. for MJ305 | 22-Aug-25 → 04-Feb-26 | Complete 100% | float — PK000MJ35P PK000MJ36P — Issue Formal P.O. for MJ306 | 22-Aug-25 → 04-Feb-26 | Complete 100% | float — PK000MJ36P PK000MD41K — MD401 - Fabricate/PO Promise 101-F | 23-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MD41K PK000MD43K — MD403 - Fabricate/PO Promise 106-F | 23-Aug-25 → 11-Mar-27 | In Progress 43% | float 135.0d PK000MD43K PK000MJ35K — MJ305 - Fabricate/PO Promise ISBL ANSI/API PUMPS | 23-Aug-25 → 27-Dec-26 | In Progress 50% | float — PK000MJ35K ZZ2070 — MJ305 - Fabricate/PO Promise OSBL ANSI/API PUMPS | 23-Aug-25 → 27-Dec-26 | In Progress 50% | float — ZZ2070 PK000MD43P — Issue Formal P.O. for MD403 | 23-Aug-25 → 07-Sep-25 | Complete 100% | float — PK000ML43I — Eval Bids & Issue Recmd ML430 | 23-Aug-25 → 12-Sep-25 | Complete 100% | float — PK000MJ35N — Recv. Planning V. Data MJ305 | 23-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MJ36N — Recv. Planning V. Data MJ306 | 23-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MD51P — Issue Formal P.O. for MD501 | 26-Aug-25 → 06-Sep-25 | Complete 100% | float — EK01PIBSA — 01U Plant Layout Model - Benfield Sewer | 26-Aug-25 → 05-Oct-25 | Complete 100% | float — EK01PIBSA EK01UPISSA — 01U Plant Layout Model - Sanitary Sewer | 26-Aug-25 → 05-Oct-25 | Complete 100% | float — EK01UPISSA EK000MD21E — Prepare & Issue Purchase ERW - MD201 | 27-Aug-25 → 29-Aug-25 | Complete 100% | float — PK000MB51J — Final Negotiate/Interim Award - MB511 | 27-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MD22P — Issue Formal P.O. for MD202 | 27-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MB65I — Eval Bids & Issue Recmd MB622 | 27-Aug-25 → 20-Nov-25 | Complete 100% | float — PK000MB65I PK000MD51K — MD501 - Fabricate/PO Promise 107-D | 27-Aug-25 → 27-Dec-26 | In Progress 49% | float — PK000MD51K PK000I220G — Final Negotiation / Interim Award - MOV's | 27-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MD51N — Recv. Planning V. Data MD501 | 27-Aug-25 → 01-Nov-25 | Complete 100% | float — PK000MD51N PK000MBP3P — Issue Formal P.O. for 101-B Pressure Parts | 28-Aug-25 → 16-Oct-25 | Complete 100% | float — PK000MBP3P PK000MU31G — Issue MU310 RFQ | 28-Aug-25 → 30-Aug-25 | Complete 100% | float — PK000I230G — Final Negotiation / Interim Award - On/Off Valves | 28-Aug-25 → 02-Sep-25 | Complete 100% | float — PK000MJ37I — Eval Bids & Issue Recmd MJ340 | 28-Aug-25 → 19-Oct-25 | Complete 100% | float — PK000MJ37I PK000MBP3T — MB311 - Shop Recv - 101-B Radiant Fittings | 28-Aug-25 → 03-Mar-26 | Complete 100% | float — PK000MBP3T EK000MB21D — Technical Evaluation - MB212 | 29-Aug-25 → 01-Nov-25 | Complete 100% | float — EK000MB21D PK000MJ22K — MJ201 - Fabricate/PO Promise 101-J | 30-Aug-25 → 10-Jan-27 | In Progress 48% | float 86.0d PK000MJ22K PK000ML31K — ML313 - Fabricate/PO Promise 160-L | 30-Aug-25 → 27-Dec-26 | In Progress 49% | float — PK000ML31K PK000MD31P — Issue Formal P.O. for MD301 | 30-Aug-25 → 12-Sep-25 | Complete 100% | float — PK000ML31P — Issue Formal P.O. for ML313 | 30-Aug-25 → 24-Sep-25 | Complete 100% | float — PK000MJ22P — Issue Formal P.O. for MJ201 | 30-Aug-25 → 15-Oct-25 | Complete 100% | float — PK000MJ22P EK000MJ33D — Technical Evaluation - MJ303 | 30-Aug-25 → 19-Dec-25 | Complete 100% | float — EK000MJ33D PK000MB68I — Eval Bids & Issue Recmd MB692 | 30-Aug-25 → 27-Feb-26 | Complete 100% | float — PK000MB68I PK000MU21N — Recv. Planning V. Data MU221 | 01-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MBP3R — MB311 - Fab/Exworks 101-B Crossover Tube & Pipe | 02-Sep-25 → 27-Dec-26 | In Progress 49% | float — PK000MBP3R PK000MBP3S — MB311 - Fab/Exworks 101-B Crossover Fittings | 02-Sep-25 → 27-Dec-26 | In Progress 49% | float — PK000MBP3S EK010PI011 — Plot Plan - Overall Site (Drwg 0101) Client ICA Approval | 02-Sep-25 → 14-Sep-25 | Complete 100% | float — PK000MU31H — Receive Quotes MU310 | 02-Sep-25 → 23-Sep-25 | Complete 100% | float — PK000ML42N — Recv. Planning V. Data ML420 | 02-Sep-25 → 26-Sep-25 | Complete 100% | float — PK000MJ32N — Recv. Planning V. Data MJ302 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ34N — Recv. Planning V. Data MJ304 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ37N — Recv. Planning V. Data MJ340 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ39N — Recv. Planning V. Data MJ391 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ73N — Recv. Planning V. Data MJ730 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MU22N — Recv. Planning V. Data MU222 | 02-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MB51P — Issue Formal P.O. for MB511 | 02-Sep-25 → 06-Dec-25 | Complete 100% | float — PK000MB51P PK000MBP3K — MB311 - Fab/Exworks 101-B Radiant Tube & Pipe | 02-Sep-25 → 31-Mar-26 | Complete 100% | float — PK000MBP3K EK000MB095 — 101-B Ducting Detail Drawings - IFF | 02-Sep-25 → 05-Apr-26 | Complete 100% | float — EK000MB095 PK000MBP3O — MB311 - Fab/Exworks 101-B Convection Tube & Pipe | 02-Sep-25 → 15-Apr-26 | Complete 100% | float — PK000MBP3O PK000MBP3Q — MB311 - Fab/Exworks 101-B Convection Fittings | 02-Sep-25 → 15-Apr-26 | Complete 100% | float — PK000MBP3Q EK000MD055 — Pre-qualification trip to vendors shop (105-D) | 03-Sep-25 → 05-Sep-25 | Complete 100% | float — EK000MU41E — Prepare & Issue Purchase ERW - MU410 | 03-Sep-25 → 05-Sep-25 | Complete 100% | float — PK000MD21P — Issue Formal P.O. for MD201 | 03-Sep-25 → 18-Sep-25 | Complete 100% | float — PK000MU61N — Recv. Planning V. Data MU611 | 03-Sep-25 → 26-Sep-25 | Complete 100% | float — PK000MB51K — MB511 - Fabricate/PO Promise 101-B Insulation | 03-Sep-25 → 30-Dec-26 | In Progress 48% | float 204.0d PK000MB51K PK01DMUV04 — 01D MU611 2101-U - Piping Prod. V. Data | 03-Sep-25 → 03-Mar-26 | Complete 100% | float — PK01DMUV04 PK01DMUV05 — 01D MU611 2101-U - Civil Prod. V. Data | 03-Sep-25 → 03-Mar-26 | Complete 100% | float — PK01DMUV05 PK01DMUV06 — 01D MU611 2101-U - E&I Prod. V. Data | 03-Sep-25 → 03-Mar-26 | Complete 100% | float — PK01DMUV06 PK000MB33P — MB333 - Issue Formal P.O. 101-B | 04-Sep-25 → 06-Sep-25 | Complete 100% | float — PK000MC61J — Final Negotiate/Interim Award - MC610 | 05-Sep-25 → 09-Sep-25 | Complete 100% | float — PK000MJ22N — Recv. Planning V. Data MJ201 | 05-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MU41K — MU410 - Fabricate/PO Promise 2002-U PKG BOILER | 06-Sep-25 → 27-Dec-26 | In Progress 48% | float — PK000MU41K PK000MU22I — Eval Bids & Issue Recmd MU222 | 06-Sep-25 → 19-Sep-25 | Complete 100% | float — PK000MJ31N — Recv. Planning V. Data MJ301 | 06-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000ML51J — Final Negotiate/Interim Award - ML512 | 09-Sep-25 → 11-Sep-25 | Complete 100% | float — EK030PI011 — Plot Plan - Utility Plant Client ICA Approval | 09-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000MJ34J — Final Negotiate/Interim Award - MJ304 | 09-Sep-25 → 14-Oct-25 | Complete 100% | float — PK000MU33J — Final Negotiate/Interim Award - MU330 | 09-Sep-25 → 29-Oct-25 | Complete 100% | float — PK000MU33J PK000MU61K — MU611 - Fabricate/PO Promise 2101-U, 2101-UJA Thru UJG CW TWR & Fans | 09-Sep-25 → 14-Apr-26 | Complete 100% | float — PK000MU61K PK000MU61T — MU611 - Fabricate/PO Promise 2101-UJA Thru UJGM CW Motors | 09-Sep-25 → 14-Apr-26 | Complete 100% | float — PK000MU61T PK000MC61K — MC610 - Fabricate/PO Promise DBL PIPE EXCH 188-CA | 10-Sep-25 → 27-Dec-26 | In Progress 48% | float — PK000MC61K PK000MC61P — Issue Formal P.O. for MC610 | 10-Sep-25 → 12-Oct-25 | Complete 100% | float — PK000MC61N — Recv. Planning V. Data MC610 | 10-Sep-25 → 03-Dec-25 | Complete 100% | float — PK000MC61N PK000MC61L — MC610 - Fabricate/PO Promise DBL PIPE EXCH 161-C | 10-Sep-25 → 09-Apr-26 | Complete 100% | float — PK000MC61L EK000CV137 — Issue OSBL Rough Grade Design Pkg. | 11-Sep-25 → 26-Nov-25 | Complete 100% | float — EK000CV137 PK000MBP4K — MB312 - Fab/PO Promise 101-B Radiant Cast Fittings | 11-Sep-25 → 27-Dec-26 | In Progress 48% | float — PK000MBP4K PK000MBP4Q — MB312 - Fab/PO Promise 101-B Radiant Cast Stringer Grids | 11-Sep-25 → 27-Dec-26 | In Progress 48% | float — PK000MBP4Q PK000MBP4R — MB312 - Fab/PO Promise 101-B Radiant Cast Tube/Riser/Manifold | 11-Sep-25 → 27-Dec-26 | In Progress 48% | float — PK000MBP4R PK000ML51K — ML512 - Fabricate/PO Promise 2102-L LOADING ARM | 11-Sep-25 → 27-Dec-26 | In Progress 48% | float — PK000ML51K PK000MBP4M — Requote/Bid Condition/Final Tab - Cast Material | 11-Sep-25 → 16-Sep-25 | Complete 100% | float — EK000ML51E — Prepare & Issue Purchase ERW - ML512 | 11-Sep-25 → 25-Sep-25 | Complete 100% | float — PK000ML51N — Recv. Planning V. Data ML512 | 11-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000ML51P — Issue Formal P.O. for ML512 | 11-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000ML43J — Final Negotiate/Interim Award - ML430 | 12-Sep-25 → 14-Oct-25 | Complete 100% | float — PK000MB71G — Issue MB710 RFQ | 13-Sep-25 → 17-Sep-25 | Complete 100% | float — PK000ML33J — Final Negotiate/Interim Award - ML330 | 13-Sep-25 → 20-Sep-25 | Complete 100% | float — EK000MJ36E — Prepare & Issue Purchase ERW - MJ306 | 13-Sep-25 → 25-Sep-25 | Complete 100% | float — EK000MJ35E — Prepare & Issue Purchase ERW - MJ305 | 13-Sep-25 → 25-Sep-25 | Complete 100% | float — PK000PIA4F — Product Line Piping - Formal Award | 13-Sep-25 → 02-Oct-25 | Complete 100% | float — EK000MJ22E — Prepare & Issue Purchase ERW - MJ201 | 13-Sep-25 → 13-Nov-25 | Complete 100% | float — EK000MJ22E PK03EMU100 — 03E Recv. Planning V. Data - Utility Equip. | 16-Sep-25 → 16-Sep-25 | Complete 100% | float — EK050PI012 — Plot Plan - Dock/Storage Issue IPL | 16-Sep-25 → 26-Oct-25 | Complete 100% | float — EK050PI012 EK000I444D — Technical Evaluation - Analyzer Shelter | 16-Sep-25 → 11-Dec-25 | Complete 100% | float — EK000I444D PK000MD21K — MD201 - Fabricate/PO Promise 101-E | 17-Sep-25 → 01-Jan-27 | In Progress 46% | float 93.0d PK000MD21K PK000MD21M — MD201 - Fabricate/PO Promise 102-E | 17-Sep-25 → 05-Mar-27 | In Progress 41% | float 62.0d PK000MD21M PK03BMJ154 — 03B Recv. Planning V. Data - Pumps 2401-J, 2401-JA | 17-Sep-25 → 17-Sep-25 | Complete 100% | float — PK03CMJ154 — 03C Recv. Planning V. Data - Pumps 2205-J/JA, 2206-J/JA | 17-Sep-25 → 17-Sep-25 | Complete 100% | float — PK03DMJ154 — 03D Recv. Planning V. Data - Pumps 2202-J/JA | 17-Sep-25 → 17-Sep-25 | Complete 100% | float — PK05AMJ154 — 05A Recv. Planning V. Data - Pumps 2106/7-J | 17-Sep-25 → 17-Sep-25 | Complete 100% | float — PK000MU21I — Eval Bids & Issue Recmd MU221 | 17-Sep-25 → 19-Sep-25 | Complete 100% | float — EK000ML33E — Prepare & Issue Purchase ERW - ML330 | 17-Sep-25 → 25-Sep-25 | Complete 100% | float — EK03UPIOSA — 03U Plant Layout Model - Outfall Sewer | 17-Sep-25 → 26-Sep-25 | Complete 100% | float — PK000MU41N — Recv. Planning V. Data MU410 | 17-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000I220K — Issue Formal Purchase Agreement. - MOV's | 17-Sep-25 → 13-Dec-25 | Complete 100% | float — PK000I220K PK000I230K — Issue Formal Purchase Agreement. - On/Off Valves | 17-Sep-25 → 13-Dec-25 | Complete 100% | float — PK000I230K EK000FP012 — FP Electrical Area Classification OSBL - ICA | 17-Sep-25 → 10-Oct-25 | Complete 100% | float — PK000MB71H — Receive Quotes for MB710 | 17-Sep-25 → 14-Oct-25 | Complete 100% | float — EK020PR20D — PR201 KAAP Catalyst - Technical Evaluation | 17-Sep-25 → 01-Nov-25 | Complete 100% | float — EK020PR20D PK000MBP4Z — MB312 - Shop Recv. 101-B Radiant Cast Fittings | 17-Sep-25 → 03-Mar-26 | Complete 100% | float — PK000MBP4Z EK000MC61E — Prepare & Issue Purchase ERW - MC610 | 18-Sep-25 → 25-Sep-25 | Complete 100% | float — PK000MU21J — Final Negotiate/Interim Award - MU221 | 19-Sep-25 → 04-Nov-25 | Complete 100% | float — PK000MU21J PK000MU22J — Final Negotiate/Interim Award - MU222 | 19-Sep-25 → 04-Nov-25 | Complete 100% | float — PK000MU22J EK000MJ32E — Prepare & Issue Purchase ERW - MJ302 | 20-Sep-25 → 13-Nov-25 | Complete 100% | float — EK000MJ32E PK000ML33K — ML330 - Fabricate/Po Promise 2101-L | 20-Sep-25 → 27-Dec-26 | In Progress 47% | float — PK000ML33K PK000MD47J — Final Negotiate/Interim Award - MD406 | 20-Sep-25 → 25-Sep-25 | Complete 100% | float — PK000ML33N — Recv. Planning V. Data ML330 | 20-Sep-25 → 27-Sep-25 | Complete 100% | float — EK03UPIASA — 03U Plant Layout Model - Acid Sewer | 20-Sep-25 → 08-Oct-25 | Complete 100% | float — EK03UPICSA — 03U Plant Layout Model - Caustic Sewer | 20-Sep-25 → 08-Oct-25 | Complete 100% | float — PK000ML33P — Issue Formal P.O. for ML330 | 20-Sep-25 → 31-Oct-25 | Complete 100% | float — PK000ML33P PK000ML43N — Recv. Planning V. Data ML430 | 20-Sep-25 → 01-Nov-25 | Complete 100% | float — PK000ML43N EK000MJ34E — Prepare & Issue Final Data Shts - MJ304 | 21-Sep-25 → 08-Nov-25 | Complete 100% | float — EK000MJ34E EK000MU33E — Prepare & Issue Purchase ERW - MU330 | 21-Sep-25 → 26-Sep-25 | Complete 100% | float — EK020MC31C — MC312 - (120,121-C) - Prepare & Issue Purchase ERW | 23-Sep-25 → 27-Sep-25 | Complete 100% | float — EK03CPI030 — 03C Conceptual Layout - Supersketches | 23-Sep-25 → 27-Sep-25 | Complete 100% | float — PK020MC31F — MC312 - (120,121-C) - Planning V. Data (Setting Plans) | 23-Sep-25 → 08-Oct-25 | Complete 100% | float — EK010I1240 — Rotameters - D/S,Sizing,Tech Eval | 23-Sep-25 → 15-Nov-25 | Complete 100% | float — EK010I1240 EK030I1100 — 030 Orific Plates - D/S Utility Plant | 24-Sep-25 → 05-Nov-25 | Complete 100% | float — EK030I1100 EK030IC210 — 030 Control Valves - D/S, Sizing,Tech Eval | 24-Sep-25 → 21-Dec-25 | Complete 100% | float — EK030IC210 EK000MU31D — Technical Evaluation - MU310 | 24-Sep-25 → 30-Sep-25 | Complete 100% | float — PK000MD47P — Issue Formal P.O. for MD406 | 24-Sep-25 → 03-Oct-25 | Complete 100% | float — EK010IC242 — MOV Valves - D/S,Sizing,Tech Eval | 25-Sep-25 → 15-Nov-25 | Complete 100% | float — EK010IC242 EK050SY185 — 050 SP Item Data Sheets - Dock/Storage | 25-Sep-25 → 24-Dec-25 | Complete 100% | float — EK050SY185 EK01JPI030 — 01J Conceptual Layout - Supersketches | 25-Sep-25 → 03-Oct-25 | Complete 100% | float — EK010SY185 — 010 SP Item Data Sheets - CW Twr & FW Tanks | 25-Sep-25 → 24-Dec-25 | Complete 100% | float — EK010SY185 PK000PSA8E — 000 Relief Valves - Final Negotiation / Interim Award | 26-Sep-25 → 27-Sep-25 | Complete 100% | float — EK01UPIPWA — 01U Plant Layout Model - Potable Water | 26-Sep-25 → 05-Oct-25 | Complete 100% | float — PK000MU33P — Issue Formal P.O. for MU330 | 26-Sep-25 → 20-Feb-26 | Complete 100% | float — PK000MU33P EK030SY185 — 030 SP Item Data Sheets - Utiliy Plant | 27-Sep-25 → 24-Dec-25 | Complete 100% | float — EK030SY185 EK04API030 — 04A Conceptual Layout - Supersketches | 27-Sep-25 → 27-Dec-26 | In Progress 46% | float — EK04API030 PK000PSA8G — 000 Relief Valves - Fabricate/Exworks | 27-Sep-25 → 30-Dec-26 | In Progress 46% | float 257.0d PK000PSA8G PK01BMJ154 — 01B Recv. Planning V. Data - Pumps (2001,4,7,2203,4) | 27-Sep-25 → 27-Sep-25 | Complete 100% | float — PK000PSA8F — 000 Relief Valves - Issue Formal Blanket P.O. | 27-Sep-25 → 20-Dec-25 | Complete 100% | float — PK000PSA8F EK01UPIPAA — 01U Plant Layout Model - Plant Air | 30-Sep-25 → 30-Sep-25 | Complete 100% | float — EK01UPIWWA — 01U Plant Layout Model - Waste Water | 30-Sep-25 → 05-Oct-25 | Complete 100% | float — EK000MC23E — Prepare & Issue Purchase ERW - MC230 | 30-Sep-25 → 15-Oct-25 | Complete 100% | float — EK000I352D — SIS - Tech Evaluation | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000I352D EK000MC21E — Prepare & Issue Purchase ERW - MC210 | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000MC21E PK000MD47K — MD406 - Fabricate/PO Promise ISBL DRUMS | 01-Oct-25 → 27-Dec-26 | In Progress 45% | float — PK000MD47K PK000MU33K — MU330 - Fabricate/PO Promise 2001-U | 01-Oct-25 → 27-Dec-26 | In Progress 45% | float — PK000MU33K PK000PIA1K — Bulk Piping A/G - Fab/Exworks (CROME) | 01-Oct-25 → 27-Dec-26 | In Progress 45% | float — PK000PIA1K PK000PIA4G — Product Line Piping - Fab/Exworks +/- 5700 Mts. | 01-Oct-25 → 27-Dec-26 | In Progress 45% | float — PK000PIA4G PK01HMJ135 — 01H Recv. Planning V.Data - Emerg Pwr Generator | 01-Oct-25 → 01-Oct-25 | Complete 100% | float — PK05AML100 — 05A Recv. Planning V. Data - Special Equip. | 01-Oct-25 → 01-Oct-25 | Complete 100% | float — PK05BML100 — 05B Recv. Planning V. Data - Special Equip. 2102-L | 01-Oct-25 → 01-Oct-25 | Complete 100% | float — EK000MU30E — Prepare & Issue Purchase ERW - MU300 | 01-Oct-25 → 14-Oct-25 | Complete 100% | float — EK01API030 — 01A Conceptual Layout - Supersketches | 01-Oct-25 → 08-Oct-25 | Complete 100% | float — PK000MC21J — Final Negotiate/Interim Award - MC210 | 01-Oct-25 → 09-Oct-25 | Complete 100% | float — PK000MC23J — Final Negotiate/Interim Award - MC230 | 01-Oct-25 → 09-Oct-25 | Complete 100% | float — EK000ML42E — Prepare & Issue Purchase ERW - ML420 | 01-Oct-25 → 10-Oct-25 | Complete 100% | float — EK000MJ37E — Prepare & Issue Purchase ERW - MJ340 | 01-Oct-25 → 16-Oct-25 | Complete 100% | float — PK000MB42J — Final Negotiate/Interim Award - MB420 | 01-Oct-25 → 07-Nov-25 | Complete 100% | float — PK000PR20E — PR201 KAAP Catalyst - Eval Bids & Issue Recmd | 02-Oct-25 → 17-Oct-25 | Complete 100% | float — EK03BPI030 — 03B Conceptual Layout - Supersketches | 03-Oct-25 → 07-Oct-25 | Complete 100% | float — PK000I352E — SIS - Eval Bids/Issue Recmd | 03-Oct-25 → 28-Dec-25 | Complete 100% | float — PK000I352E EK010I1100 — 010 Orific Plates - D/S,Sizing,Tech Eval | 04-Oct-25 → 24-Oct-25 | Complete 100% | float — EK010I1150 — Annubars - D/S,Sizing,Tech Eval | 04-Oct-25 → 02-Nov-25 | Complete 100% | float — EK010I1210 — Vortex Meters - D/S,Sizing,Tech Eval | 04-Oct-25 → 02-Nov-25 | Complete 100% | float — EK050I1100 — 050 Orific Plates - D/S Dock/Storage Area | 04-Oct-25 → 05-Nov-25 | Complete 100% | float — EK010IC210 — 010 Control Valves - D/S,Sizing,Tech Eval | 04-Oct-25 → 21-Dec-25 | Complete 100% | float — EK010IC210 EK000MU31E — Prepare & Issue Purchase ERW - MU310 | 04-Oct-25 → 08-Oct-25 | Complete 100% | float — EK000IC351 — DCS - Develop Purchase T-Req | 05-Oct-25 → 07-Nov-25 | Complete 100% | float — EK010SY155 — 010 Issue Requisition - PSA08 Relief Valves - CW Twr & FW Tanks | 05-Oct-25 → 19-Nov-25 | Complete 100% | float — EK010SY155 EK030SY155 — 030 Issue Requisition - PSA08 Relief Valves - Utility PLant | 05-Oct-25 → 19-Nov-25 | Complete 100% | float — EK030SY155 EK050SY155 — 050 Issue Requisition - PSA08 Relief Valves - Dock/Storage | 05-Oct-25 → 19-Nov-25 | Complete 100% | float — EK050SY155 PK000IC350 — DCS - Vendor Update Pricing / Quote | 07-Oct-25 → 11-Oct-25 | Complete 100% | float — EK000PR600 — MD305 Merc. Removal Bed - Develop & Issue Load Sheets for ERW | 08-Oct-25 → 09-Oct-25 | Complete 100% | float — EK000MJ31E — Prepare & Issue Purchase ERW - MJ301 | 08-Oct-25 → 13-Nov-25 | Complete 100% | float — PK000MJ33N — Recv. Planning V. Data MJ303 | 08-Oct-25 → 26-Dec-25 | Complete 100% | float — PK000MJ33N PK000MU31I — Eval Bids & Issue Recmd MU310 | 08-Oct-25 → 04-Jan-26 | Complete 100% | float — PK000MU31I EK000ML31E — Prepare & Issue Purchase ERW - ML313 | 08-Oct-25 → 09-Jan-26 | Complete 100% | float — EK000ML31E PK000ML42J — Final Negotiate/Interim Award - ML420 | 09-Oct-25 → 12-Oct-25 | Complete 100% | float — PK000MC21K — MC210 - Fabricate/PO Promise 110/115/124/128/130/133/134/160/167/173/174-C | 09-Oct-25 → 27-Dec-26 | In Progress 44% | float — PK000MC21K PK000MC21N — MC210 - Fabricate/PO Promise 127-C | 09-Oct-25 → 27-Dec-26 | In Progress 44% | float — PK000MC21N PK000MC23A — MC230 - Fabricate/PO Promise 106-C & 109-C | 09-Oct-25 → 27-Dec-26 | In Progress 44% | float — PK000MC23A PK000MC23K — MC230 - Fabricate/PO Promise 105/107/172/183-C | 09-Oct-25 → 27-Dec-26 | In Progress 44% | float — PK000MC23K PK000MC23N — MC230 - Fabricate/PO Promise 111/114-C | 09-Oct-25 → 27-Dec-26 | In Progress 44% | float — PK000MC23N PK000MC23P — Issue Formal P.O. for MC230 | 09-Oct-25 → 09-Nov-25 | Complete 100% | float — PK000MC21P — Issue Formal P.O. for MC210 | 09-Oct-25 → 04-Dec-25 | Complete 100% | float — PK000MC21P EK020ELEG2 — Cathodic Protection - Subcontract Consultant ERW Package | 09-Oct-25 → 01-Mar-26 | Complete 100% | float — EK020ELEG2 EK000MC32E — Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4) | 10-Oct-25 → 15-Nov-25 | Complete 100% | float — EK000MD103 — MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW | 10-Oct-25 → 26-Nov-25 | Complete 100% | float — EK000MD103 EK000PR610 — MD305 Merc. Removal Bed - Analytical Design | 10-Oct-25 → 26-Nov-25 | Complete 100% | float — EK000PR610 EK000YA813 — (EP-14) Issue Plot Plans for Client Approval | 11-Oct-25 | Complete EK04ASY170 — 04A OSBL P&IDs IPL & Line List Issue Milestone | 11-Oct-25 | Complete EK050SY090 — 050 Dock/Storage P&IDs IPL Issue Milestone | 11-Oct-25 | Complete EK05ASY170 — 05A OSBL P&IDs IPL & Line List Issue Milestone | 11-Oct-25 | Complete EK05BSY170 — 05B OSBL P&IDs IPL & Line List Issue Milestone | 11-Oct-25 | Complete EK050PI011 — Plot Plan - Dock/Storage Client ICA Approval | 11-Oct-25 → 26-Oct-25 | Complete 100% | float — PK000ML42P — Issue Formal P.O. for ML420 | 11-Oct-25 → 30-Oct-25 | Complete 100% | float — PK000ML42K — ML420 - Fabricate/PO Promise CARTRIDGE FILTERS | 11-Oct-25 → 28-Mar-26 | Complete 100% | float — PK000ML42K PK000MC32J — Final Negotiate/Interim Award - MC311 | 14-Oct-25 → 16-Oct-25 | Complete 100% | float — PK000ML43P — Issue Formal P.O. for ML430 | 14-Oct-25 → 06-Nov-25 | Complete 100% | float — PK000ML43K — ML430 - Fabricate/PO Promise 110-L BENFIELD MIXER | 14-Oct-25 → 11-Mar-26 | Complete 100% | float — PK000ML43K PK000MJ34K — MJ304 - Fabricate/PO Promise MP BFW PUMPS | 15-Oct-25 → 16-Jan-27 | In Progress 42% | float 186.0d PK000MJ34K EK000I354D — ITCC - Tech Evaluation | 15-Oct-25 → 12-Dec-25 | Complete 100% | float — EK000I354D EK000MB42D — Technical Evaluation - MB420 | 16-Oct-25 → 30-Oct-25 | Complete 100% | float — PK000MC32K — MC311 - Fabricate/PO Promise KBR S&T EXCH | 16-Oct-25 → 16-Jan-27 | In Progress 42% | float 76.0d PK000MC32K PK000MC32P — Issue Formal P.O. for MC311 | 16-Oct-25 → 13-Dec-25 | Complete 100% | float — PK000MC32P PK000IC35J — DCS - Planning V. Data | 17-Oct-25 → 27-Dec-26 | In Progress 43% | float — PK000IC35J PK000MB64I — Eval Bids & Issue Recmd MB640 | 18-Oct-25 → 11-Nov-25 | Complete 100% | float — PK000MJ73J — Final Negotiate/Interim Award - MJ730 | 18-Oct-25 → 11-Nov-25 | Complete 100% | float — PK000MJ37J — Final Negotiate/Interim Award - MJ340 | 18-Oct-25 → 13-Dec-25 | Complete 100% | float — PK000MJ37J PK000MB71I — Eval Bids & Issue Recmd MB710 | 18-Oct-25 → 31-Dec-25 | Complete 100% | float — PK000MB71I PK000IC35H — DCS - Fabricate Hardware | 21-Oct-25 → 27-Dec-26 | In Progress 43% | float — PK000IC35H PK000MU30J — Final Negotiate/Interim Award - MU300 | 25-Oct-25 → 29-Oct-25 | Complete 100% | float — PK000MJ34P — Issue Formal P.O. for MJ304 | 30-Oct-25 → 22-Nov-25 | Complete 100% | float — PK010I1240 — Rotameters - Fabricate/Exworks | 30-Oct-25 → 27-Dec-26 | In Progress 42% | float — PK010I1240 PK000MB42I — Eval Bids & Issue Recmd MB420 | 30-Oct-25 → 31-Oct-25 | Complete 100% | float — PK000MB69J — Final Negotiate/Interim Award - MB691 | 30-Oct-25 → 02-Nov-25 | Complete 100% | float — PK000MU32G — 01D MU322 Issue RFQ | 30-Oct-25 → 11-Nov-25 | Complete 100% | float — PK000MU33N — 03E MU330 2001-U - Piping Conceptual V. Data | 30-Oct-25 → 02-Feb-26 | Complete 100% | float — PK000MU33N PK010I1150 — Annubars - Fabricate/Exworks | 31-Oct-25 → 30-Dec-26 | In Progress 41% | float 509.0d PK010I1150 EK010SY090 — 010 CW Twr & FW Tanks P&IDs IPL Issue Milestone | 31-Oct-25 | Complete EK01ASY170 — 01A OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01BSY170 — 01B OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01CSY170 — 01C OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01DSY170 — 01D OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01ESY170 — 01E OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01FSY170 — 01F OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01HSY170 — 01H OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01JSY170 — 01J OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01YSY170 — 01Y OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK010FP031 — FP Firewater Pump P&IDs - Development & Issue IFD | 01-Nov-25 → 27-Dec-26 | In Progress 41% | float — EK010FP031 EK000ML43E — Prepare & Issue Purchase ERW - ML430 | 01-Nov-25 → 07-Nov-25 | Complete 100% | float — PK01FMU100 — 01F Recv. Planning V. Data - Utility Equip. 2603-K, 2607-K | 01-Nov-25 → 15-Nov-25 | Complete 100% | float — PK000MB69K — MB691 - Fabricate/PO Promise 101-B | 04-Nov-25 → 27-Dec-26 | In Progress 41% | float — PK000MB69K PK000MU21K — MU221 - Fabricate/PO Promise LIFT STATION | 04-Nov-25 → 27-Dec-26 | In Progress 41% | float — PK000MU21K PK000MU22K — MU222 - Fabricate/PO Promise 2401-U | 04-Nov-25 → 27-Dec-26 | In Progress 41% | float — PK000MU22K PK000MB69P — Issue Formal P.O. for MB691 | 04-Nov-25 → 04-Nov-25 | Complete 100% | float — EK000MJ37R — Develop & Issue Load Sheets for ERW - MJ307 | 04-Nov-25 → 08-Nov-25 | Complete 100% | float — EK000MJ38R — Develop & Issue Load Sheets for ERW - MJ308 | 04-Nov-25 → 08-Nov-25 | Complete 100% | float — PK000PR20F — PR201 KAAP Catalyst - Final Negotiate/Interim Award | 04-Nov-25 → 09-Dec-25 | Complete 100% | float — PK000MU21P — Issue Formal P.O. for MU221 | 04-Nov-25 → 11-Dec-25 | Complete 100% | float — PK000MU22P — Issue Formal P.O. for MU222 | 04-Nov-25 → 11-Dec-25 | Complete 100% | float — PK000MB21I — Eval Bids & Issue Recmd MB212 | 05-Nov-25 → 06-Nov-25 | Complete 100% | float — EK000MU21E — Prepare & Issue Purchase ERW - MU221 | 05-Nov-25 → 22-Nov-25 | Complete 100% | float — EK000MU22E — Prepare & Issue Purchase ERW - MU222 | 05-Nov-25 → 22-Nov-25 | Complete 100% | float — EK000MU29F — Develop & Issue Inquiry for ERW - MU292 | 05-Nov-25 → 23-Nov-25 | Complete 100% | float — PK000MJ32P — Issue Formal P.O. for MJ302 | 05-Nov-25 → 27-Nov-25 | Complete 100% | float — PK000MB21J — Final Negotiate/Interim Award - MB212 | 06-Nov-25 → 07-Nov-25 | Complete 100% | float — PK000MB21P — Issue Formal P.O. for MB212 | 07-Nov-25 → 21-Nov-25 | Complete 100% | float — PK000MB42K — MB420 - Fabricate/PO Promise 101-B Cast Peep Sites | 07-Nov-25 → 29-Jan-26 | Complete 100% | float — PK000MB42K EK03FPI030 — 03F Conceptual Layout - Supersketches (Need Dwgs) | 07-Nov-25 → 01-Feb-26 | Complete 100% | float — EK03FPI030 PK000MB21K — MB212 - Fabricate/PO Promise Equip. 101-B Siding | 07-Nov-25 → 03-Mar-26 | Complete 100% | float — PK000MB21K PK000MB42P — Issue Formal P.O. for MB420 | 08-Nov-25 → 21-Nov-25 | Complete 100% | float — PK000MJ73P — Issue Formal P.O. for MJ730 | 11-Nov-25 → 11-Nov-25 | Complete 100% | float — EK000MJ37S — Develop & Issue Design Data for ERW - MJ307 | 11-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000MJ38S — Develop & Issue Design Data for ERW - MJ308 | 11-Nov-25 → 15-Nov-25 | Complete 100% | float — EK05BEL175 — Client Review of MCC Oneline Diagrams | 11-Nov-25 → 22-Nov-25 | Complete 100% | float — PK000MU32H — 01D MU322 Receive Quotes | 11-Nov-25 → 23-Dec-25 | Complete 100% | float — PK000MU32H PK000MB64J — Final Negotiate/Interim Award - MB640 | 11-Nov-25 → 06-Jan-26 | Complete 100% | float — PK000MB64J EK000IC352 — DCS - Final Tech Evaluation for Purchase | 13-Nov-25 → 15-Nov-25 | Complete 100% | float — EK05BEL155 — Client Review of Switchgear Oneline Diagrams | 14-Nov-25 → 22-Nov-25 | Complete 100% | float — PK000IC351 — DCS - Vendor Provides Software & Workstations | 14-Nov-25 → 29-Nov-25 | Complete 100% | float — EK000MJ37T — Update/Issue Formal Inquiry for ERW - MJ307 | 18-Nov-25 → 26-Nov-25 | Complete 100% | float — EK000MJ73E — Prepare & Issue Purchase ERW - MJ730 | 19-Nov-25 → 05-Dec-25 | Complete 100% | float — EK000FA005 — Issue First Invoice to EBIC | 19-Nov-25 | Complete PK000MU30K — MU300 - Fabricate/PO Promise 2102-U | 19-Nov-25 → 27-Dec-26 | In Progress 39% | float — PK000MU30K EK030SY090 — 030 Utility Plant P&IDs IPL Issue Milestone | 19-Nov-25 | Complete EK03ASY170 — 03A OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03BSY170 — 03B OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03CSY170 — 03C OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03DSY170 — 03D OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03ESY170 — 03E OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03FSY170 — 03F OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03YSY170 — 03Y OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete PK000MU30N — Recv. Planning V. Data MU300 - EDR Unit | 19-Nov-25 → 10-Jan-26 | Complete 100% | float — PK000MU30N PK000MU30P — Issue Formal P.O. for MU300 | 19-Nov-25 → 16-Jan-26 | Complete 100% | float — PK000MU30P PK000MJ31K — MJ301 - Fabricate/ PO Promise 104-J | 20-Nov-25 → 31-Jan-27 | In Progress 35% | float 168.0d PK000MJ31K PK000MJ32K — MJ302 - Fabricate/PO Promise 107-JA/JB/JC | 20-Nov-25 → 17-Jan-27 | In Progress 37% | float 175.0d PK000MJ32K PK000MU11G — 05B MU311 Issue RFQ | 20-Nov-25 → 26-Nov-25 | Complete 100% | float — PK000MJ31P — Issue Formal P.O. for MJ301 | 20-Nov-25 → 27-Nov-25 | Complete 100% | float — PK000MB65J — Final Negotiate/Interim Award - MB622 | 20-Nov-25 → 06-Jan-26 | Complete 100% | float — PK000MB65J EK000E001A — Sub Stations - Issue ERW | 22-Nov-25 → 31-Dec-25 | Complete 100% | float — EK000E001A EK000MD102 — MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur. | 26-Nov-25 → 05-Dec-25 | Complete 100% | float — PK000MU29G — Issue MU292 RFQ | 26-Nov-25 → 06-Dec-25 | Complete 100% | float — PK000ML50Y — Requote - ML500 | 26-Nov-25 → 10-Dec-25 | Complete 100% | float — PK000MU11H — 05B MU311 Receive Quotes | 26-Nov-25 → 03-Jan-26 | Complete 100% | float — PK000MU11H EK010PI012 — Plot Plan - Overall Site (Drwg 0101) Issue IPL | 28-Nov-25 → 20-Dec-25 | Complete 100% | float — EK030PI012 — Plot Plan - Utility Plant Issue IPL | 28-Nov-25 → 20-Dec-25 | Complete 100% | float — PK000MD104 — MD305 Merc. Removal Bed - Issue RFQ | 05-Dec-25 → 10-Dec-25 | Complete 100% | float — PK000MU29H — Receive Quotes MU292 | 05-Dec-25 → 20-Jan-26 | Complete 100% | float — PK000MU29H PK000MJ37B — Eval Bids & Issue Recmd MJ307 | 06-Dec-25 → 21-Dec-25 | Complete 100% | float — PK000PR20G — PR201 KAAP Catalyst - Issue Formal P.O. | 09-Dec-25 → 09-Dec-25 | Complete 100% | float — PK000ML52G — Issue ML501 RFQ | 09-Dec-25 → 31-Dec-25 | Complete 100% | float — PK000PR20H — PR201 KAAP Catalyst - Fabricate/Exworks | 10-Dec-25 → 03-Nov-27 | In Progress 19% | float 26.0d PK000PR20H PK000ML90G — Issue ML900 RFQ | 10-Dec-25 → 16-Dec-25 | Complete 100% | float — EK000ML50Z — Technical Evaluation - ML500 | 10-Dec-25 → 31-Dec-25 | Complete 100% | float — PK000MD106 — MD305 Merc. Removal Bed - Receive Quotes | 11-Dec-25 → 10-Jan-26 | Complete 100% | float — PK000MJ37K — MJ340 - Fabricate/PO Promise METERING PUMPS | 13-Dec-25 → 27-Dec-26 | In Progress 35% | float — PK000MJ37K PK000MJ37P — Issue Formal P.O. for MJ340 | 13-Dec-25 → 20-Jan-26 | Complete 100% | float — PK000MJ37P PK000I354E — ITCC - Eval Bids/Issue Recmd | 16-Dec-25 → 28-Dec-25 | Complete 100% | float — PK000ML90H — Receive Quotes ML900 | 16-Dec-25 → 20-Jan-26 | Complete 100% | float — PK000I444E — Eval Bids / Issue Recmd - Analyzer Shelter | 17-Dec-25 → 20-Dec-25 | Complete 100% | float — EK03EPI030 — 03E Conceptual Layout - Supersketches | 17-Dec-25 → 31-Mar-26 | Complete 100% | float — EK03EPI030 EK000E002A — Transformer - Issue ERW | 18-Dec-25 → 30-Dec-25 | Complete 100% | float — PK000MJ33I — Eval Bids & Issue Recmd MJ303 | 19-Dec-25 → 24-Dec-25 | Complete 100% | float — EK000MJ33E — Prepare & Issue Purchase ERW - MJ303 | 19-Dec-25 → 27-Dec-25 | Complete 100% | float — PK000MC31J — Final Negotiate/Interim Award - MC310 | 20-Dec-25 → 03-Jan-26 | Complete 100% | float — PK000I352G — SIS - Interim Award | 20-Dec-25 → 20-Jan-26 | Complete 100% | float — PK000I354G — ITCC - Interim Award | 20-Dec-25 → 20-Jan-26 | Complete 100% | float — PK000MJ37M — Final Negotiate/Interim Award - MJ307 | 20-Dec-25 → 20-Jan-26 | Complete 100% | float — PK000MJ39I — Eval Bids & Issue Recmd MJ391/MJ392 | 20-Dec-25 → 14-Mar-26 | Complete 100% | float — PK000MJ39I PK000PSA8C — 000 Relief Valves - Technical Evaluation | 23-Dec-25 → 27-Dec-25 | Complete 100% | float — EK010PI013 — Plot Plan - Overall Site (Drwg 0101) Issue IPL | 23-Dec-25 → 23-Jan-26 | Complete 100% | float — EK000MU32D — 01D MU322 Technical Evaluation | 23-Dec-25 → 31-Jan-26 | Complete 100% | float — EK000MU32D PK000MU32I — 01D MU322 Eval Bids & Issue Recmd | 23-Dec-25 → 01-Apr-26 | Complete 100% | float — PK000MU32I PK000MJ33J — Final Negotiate/Interim Award - MJ303 | 24-Dec-25 → 03-Jan-26 | Complete 100% | float — PK000MJ73K — MJ730 - Fabricate/PO Promise EMERG PWR GENERATOR | 25-Dec-25 → 28-Feb-27 | In Progress 28% | float 70.0d PK000MJ73K EK010IC213 — 010 Control Valves - Purchase ERW | 25-Dec-25 → 27-Dec-26 | In Progress 33% | float — EK010IC213 PK01DMJ154 — 01D Recv. Planning V. Data - Pumps 2210-J | 26-Dec-25 → 26-Dec-25 | Complete 100% | float — PK03DMJV02 — 03D MJ305 2002-J/JA - Civil Prod. V. Data | 27-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03DMJV02 PK000I444G — Final Negotiation / Interim Award - Shelters/ Analyzers | 28-Dec-25 → 17-Feb-26 | Complete 100% | float — PK000I444G EK000ELEJ1 — Lighting, Installation Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000ELEK1 — A/G Power & Control, Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK05BELED0 — Substation Building Layout | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — PK000EL000 — OSBL Motors & Drivers - Prod. V. Data (Information Only) | 30-Dec-25 → 30-Dec-26 | In Progress 32% | float — PK000EL000 PK03DMJV01 — 03D MJ305 2002-J/JA - Piping Prod. V. Data | 30-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03DMJV01 PK03DMJV03 — 03D MJ305 2002-J/JA - E&I Prod. V. Data | 30-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03DMJV03 PK000MU25G — 02G MU225 Issue RFQ | 30-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000GE025 — First Check Estimate | 30-Dec-25 → 27-Feb-26 | Complete 100% | float — EK000GE025 PK01BMJV03 — 01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK01BMJV03 PK01HMJV01 — 01H MJ730 2303-J - Civil Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK01HMJV01 PK01HMJV02 — 01H MJ730 2303-J - E&I Prod. V. Data | 31-Dec-25 → 30-Dec-26 | In Progress 31% | float 511.0d PK01HMJV02 PK03BMUV03 — 03B MU222,MJ305 2401-J/JA - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03BMUV03 PK03CMJV03 — 03C MJ305 2205-J/JA,2206-J/JA - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03CMJV03 PK03EMUV01 — 03E MU330 2001-U - Piping Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03EMUV01 PK03EMUV02 — 03E MU330 2001-U - Civil Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03EMUV02 PK03EMUV03 — 03E MU330 2001-U - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03EMUV03 PK03FMUV03 — 03F MU222 2401-U - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03FMUV03 PK03FMUV04 — 03F MU410 2002-U - Piping Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03FMUV04 PK03FMUV05 — 03F MU410 2002-U - Civil Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03FMUV05 PK03FMUV06 — 03F MU410 2002-U - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK03FMUV06 PK05AMLV01 — 05A ML330 2101-L - Piping Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK05AMLV01 PK05AMLV02 — 05A ML330 2101-L - Civil Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK05AMLV02 PK05AMLV03 — 05A ML330 2101-L - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK05AMLV03 PK05BMLV03 — 05B ML512 2102-L - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK05BMLV03 PK01EMUV01 — 01E MU221 Warehouse / Maintenance Area - Piping Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK01EMUV02 — 01E MU221 Warehouse / Maintenance Area - Civil Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK01EMUV03 — 01E MU221 Warehouse / Maintenance Area - E&I Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK03CMD06 — 03C MD411 2203-F 50% Caustic Storage Tank - Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK03CMD07 — 03C MD411 2204-F 98% Sulfuric Acid Drum - Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK000E002B — Transformer - Inquiry REQ/RFQ | 31-Dec-25 → 16-Jan-26 | Complete 100% | float — PK03CMJV01 — 03C MJ305 2205-J/JA,2206-J/JA - Piping Prod. V. Data | 31-Dec-25 → 03-Mar-26 | Complete 100% | float — PK03CMJV01 PK05AMJV01 — 05A MJ305 2106-J,2107-J - Piping Prod. V. Data | 31-Dec-25 → 03-Mar-26 | Complete 100% | float — PK05AMJV01 PK03FMUV01 — 03F MU222 2401-U - Piping Prod. V. Data | 31-Dec-25 → 05-Mar-26 | Complete 100% | float — PK03FMUV01 PK03FMUV02 — 03F MU222 2401-U - Civil Prod. V. Data | 31-Dec-25 → 05-Mar-26 | Complete 100% | float — PK03FMUV02 PK03BMUV01 — 03B MU222 2401-J/JA - Piping Prod. V. Data | 31-Dec-25 → 08-Mar-26 | Complete 100% | float — PK03BMUV01 PK03BMUV02 — 03B MU222 2401-J/JA - Civil Prod. V. Data | 31-Dec-25 → 08-Mar-26 | Complete 100% | float — PK03BMUV02 EK010I1105 — 010 Orific Plates - Purchase ERW | 31-Dec-25 → 11-Mar-26 | Complete 100% | float — EK010I1105 EK030I1105 — 030 Orific Plates - Purchase ERW Utility Plant | 31-Dec-25 → 11-Mar-26 | Complete 100% | float — EK030I1105 EK050I1105 — 050 Orific Plates - Purchase ERW Dock/Storage Area | 31-Dec-25 → 11-Mar-26 | Complete 100% | float — EK050I1105 PK05AMJV02 — 05A MJ305 2106-J,2107-J - Civil Prod. V. Data | 31-Dec-25 → 20-Mar-26 | Complete 100% | float — PK05AMJV02 PK01BMJV02 — 01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Civil Prod. V. Data | 31-Dec-25 → 21-Mar-26 | Complete 100% | float — PK01BMJV02 PK03CMJV02 — 03C MJ305 2205-J/JA,2206-J/JA - Civil Prod. V. Data | 31-Dec-25 → 21-Mar-26 | Complete 100% | float — PK03CMJV02 PK05AMJV03 — 05A MJ305 2106-J,2107-J - E&I Prod. V. Data | 31-Dec-25 → 21-Mar-26 | Complete 100% | float — PK05AMJV03 PK05BMLV01 — 05B ML512 2102-L - Piping Prod. V. Data | 31-Dec-25 → 21-Mar-26 | Complete 100% | float — PK05BMLV01 PK05BMLV02 — 05B ML512 2102-L - Civil Prod. V. Data | 31-Dec-25 → 21-Mar-26 | Complete 100% | float — PK05BMLV02 PK01BMJV01 — 01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Piping Prod. V. Data | 31-Dec-25 → 31-Mar-26 | Complete 100% | float — PK01BMJV01 PK000E001B — Sub Stations - Inquiry REQ/RFQ | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK000MB71J — Final Negotiate/Interim Award - MB710 | 31-Dec-25 → 06-Jan-26 | Complete 100% | float — PK000MU25H — 02G MU225 Receive Quotes | 31-Dec-25 → 29-Jan-26 | Complete 100% | float — PK000E001C — Sub Stations - Receive Bids | 31-Dec-25 → 19-Feb-26 | Complete 100% | float — PK000E001C EK030IC213 — 030 Control Valves - Purchase ERW | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK030IC213 EK01AIC300 — 01A In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK01AIC300 EK01BIC300 — 01B In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK01BIC300 EK01CIC300 — 01C In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK01CIC300 EK01DIC300 — 01D In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK01DIC300 EK01YIC300 — 01Y In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK01YIC300 EK03AIC300 — 03A In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03AIC300 EK03BIC300 — 03B In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03BIC300 EK03DIC300 — 03D In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03DIC300 EK03EIC300 — 03E In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03EIC300 EK03FIC300 — 03F In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03FIC300 EK03YIC300 — 03Y In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03YIC300 EK05AIC300 — 05A In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK05AIC300 EK05BIC300 — 05B In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK05BIC300 PK000MJ38Q — Prepare & Issue Prelim. RFQ - MJ308 to Proc. | 01-Jan-26 → 13-Jan-26 | Complete 100% | float — EK050PI013 — Plot Plan - Dock/Storage Issue IPL | 01-Jan-26 → 23-Jan-26 | Complete 100% | float — EK01JIC300 — 01J In Line Instrument Approved Vendor Data | 01-Jan-26 → 15-Apr-26 | Complete 100% | float — EK01JIC300 EK03CIC300 — 03C In Line Instrument Approved Vendor Data | 01-Jan-26 → 15-Apr-26 | Complete 100% | float — EK03CIC300 EK04AIC300 — 04A In Line Instrument Approved Vendor Data | 01-Jan-26 → 15-Apr-26 | Complete 100% | float — EK04AIC300 PK000MC31K — MC310 - Fabricate/PO Promise 101-C & 102-C (Heavy Lift) | 03-Jan-26 → 30-Jun-27 | In Progress 20% | float 8.0d PK000MC31K PK000MJ33K — MJ303 - Fabricate/PO Promise CW PUMPS | 03-Jan-26 → 28-Feb-27 | In Progress 26% | float 27.0d PK000MJ33K EK000MU11D — 05B MU311 Technical Evaluation | 03-Jan-26 → 01-Feb-26 | Complete 100% | float — PK000MJ33P — Issue Formal P.O. for MJ303 | 03-Jan-26 → 03-Feb-26 | Complete 100% | float — EK000MC31E — Prepare & Issue Purchase ERW - MC310 | 03-Jan-26 → 12-Feb-26 | Complete 100% | float — EK000MC31E PK000MC31P — Issue Formal P.O. for MC310 | 03-Jan-26 → 19-Feb-26 | Complete 100% | float — PK000MC31P PK01DMJV01 — 01D MJ303 2202-JA/JB/JC - Civil Prod. V. Data | 03-Jan-26 → 07-Mar-26 | Complete 100% | float — PK01DMJV01 PK01DMJV02 — 01D MJ303 2202-JA/JB/JC - Piping Prod. V. Data | 03-Jan-26 → 07-Mar-26 | Complete 100% | float — PK01DMJV02 PK000ML90I — Eval Bids & Issue Recmd ML900 | 03-Jan-26 → 01-Apr-26 | Complete 100% | float — PK000ML90I PK01DMJV03 — 01D MJ303 2202-JA/JB/JC - E&I Prod. V. Data | 04-Jan-26 → 27-Dec-26 | In Progress 31% | float — PK01DMJV03 PK000MB64K — MB640 - Fabricate/PO Promise 101-B Springs & Hangers | 06-Jan-26 → 27-Dec-26 | In Progress 30% | float — PK000MB64K PK000MB71K — MB710 - Fabricate/PO Promise 2202-B/BL Storage Flare & Flame FRT Gen. | 06-Jan-26 → 27-Dec-26 | In Progress 30% | float — PK000MB71K PK000MB64P — Issue Formal P.O. for MB640 | 06-Jan-26 → 20-Jan-26 | Complete 100% | float — PK000MB71P — Issue Formal P.O. for MB710 | 06-Jan-26 → 21-Jan-26 | Complete 100% | float — PK000ML52I — Eval Bids & Issue Recmd ML501 | 06-Jan-26 → 01-Feb-26 | Complete 100% | float — PK000MB65K — MB622 - Fab/PO Promise 101-B Penthouse Circ Fans | 07-Jan-26 → 27-Dec-26 | In Progress 30% | float — PK000MB65K PK000MB65P — Issue Formal P.O. for MB622 | 07-Jan-26 → 20-Jan-26 | Complete 100% | float — PK000MU31J — Final Negotiate/Interim Award - MU310 | 07-Jan-26 → 14-Jan-26 | Complete 100% | float — PK01BMU100 — 01B Recv. Planning V. Data - 2007-L (No Req.) | 10-Jan-26 → 10-Jan-26 | Complete 100% | float — PK000MJ38F — Issue MJ308 RFQ | 13-Jan-26 → 17-Jan-26 | Complete 100% | float — EK000MD104 — MD305 Merc. Removal Bed - Technical Evaluation | 13-Jan-26 → 29-Jan-26 | Complete 100% | float — PK000MU31K — MU310 - Fabricate/PO Promise Injection System & Chlorination Unit | 14-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK000MU31K PK01DMUV01 — 01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L-Piping Prod. V. Data | 14-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK01DMUV01 PK01DMUV03 — 01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L- E&I Prod. V. Data | 14-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK01DMUV03 PK000MU31P — Issue Formal P.O. for MU310 | 14-Jan-26 → 14-Jan-26 | Complete 100% | float — PK01DMUV02 — 01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L - Civil Prod. V. Data | 14-Jan-26 → 31-Mar-26 | Complete 100% | float — PK01DMUV02 PK03FMUV07 — 03F MU310 2001-L - Piping Prod. V. Data | 15-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK03FMUV07 PK03FMUV08 — 03F MU310 2001-L - Civil Prod. V. Data | 15-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK03FMUV08 PK03FMUV09 — 03F MU310 2001-L - E&I Prod. V. Data | 15-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK03FMUV09 EK000IC353 — DCS - Software Programming by KBR | 15-Jan-26 → 27-Dec-26 | In Progress 29% | float — EK000IC353 PK01CMUV01 — 01C MU300 2102-U - Piping Prod. V. Data | 16-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK01CMUV01 PK01CMUV02 — 01C MU300 2102-U - Civil Prod. V. Data | 16-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK01CMUV02 PK01CMUV03 — 01C MU300 2102-U - E&I Prod. V. Data | 16-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK01CMUV03 PK000ML52J — Final Negotiate/Interim Award - ML501 | 16-Jan-26 → 31-Jan-26 | Complete 100% | float — PK000ML50J — Final Negotiate/Interim Award - ML500 | 16-Jan-26 → 01-Feb-26 | Complete 100% | float — PK000E002C — Transformer - Receive Bids | 16-Jan-26 → 04-Mar-26 | Complete 100% | float — PK000E002C EK000CV045 — Prepare Foundation Design Criteria | 16-Jan-26 → 14-Mar-26 | Complete 100% | float — EK000CV045 EK000MJ37C — Prepare & Issue Purchase ERW - MJ307 | 17-Jan-26 → 20-Jan-26 | Complete 100% | float — PK000MJ37U — MJ307 - Fabricate/PO Promise ISBL ANSI/API PUMPS | 20-Jan-26 → 20-Jan-27 | In Progress 26% | float 192.0d PK000MJ37U PK05AMJV04 — 05A MJ307 2100-JA/JB - Piping Prod. V. Data | 20-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK05AMJV04 PK05AMJV05 — 05A MJ307 2100-JA/JB - Civil Prod. V. Data | 20-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK05AMJV05 PK05AMJV06 — 05A MJ307 2100-JA/JB - E&I Prod. V. Data | 20-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK05AMJV06 PK000MJ37T — Recv. Planning V. Data MJ307 | 20-Jan-26 → 23-Jan-26 | Complete 100% | float — PK000MB66J — Final Negotiate/Interim Award - MB660 | 20-Jan-26 → 24-Jan-26 | Complete 100% | float — PK000MJ37R — Issue Formal P.O. for MJ307 | 20-Jan-26 → 31-Jan-26 | Complete 100% | float — PK000I352K — SIS - Formal Award | 20-Jan-26 → 10-Feb-26 | Complete 100% | float — PK000I354K — ITCC - Formal Award | 20-Jan-26 → 10-Feb-26 | Complete 100% | float — PK000MJ38D — Receive Quotes MJ308 | 20-Jan-26 → 10-Feb-26 | Complete 100% | float — EK000MU29D — Technical Evaluation - MU292 | 20-Jan-26 → 03-Mar-26 | Complete 100% | float — EK000MU29D PK000MB66K — MB660 - Fabricate/PO Promise 101-B Dampers & Air Doors | 24-Jan-26 → 27-Dec-26 | In Progress 27% | float — PK000MB66K PK000MB66P — Issue Formal P.O. for MB660 | 24-Jan-26 → 24-Jan-26 | Complete 100% | float — PK000PS00A — 000 SP Items - Issue RFQ | 24-Jan-26 → 29-Jan-26 | Complete 100% | float — PK000PTA0H — Engineered Pipe Supports - Production V. Data | 24-Jan-26 → 29-Jan-26 | Complete 100% | float — PK000MU11I — 05B MU311 Eval Bids & Issue Recmd | 24-Jan-26 → 31-Jan-26 | Complete 100% | float — EK010I1241 — Rotameters - Purchase ERW | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EK010I1241 EK050PI014 — Plot Plan - Dock/Storage Issue IFC | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EK050PI014 PK01BMF02 — 01B MF302 2001-FA/FB Water Tank - Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF02 PK01BMF03 — 01B MF302 2001-FA/FB Water Tank - Piping Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF03 PK01BMF04 — 01B MF302 2001-FA/FB Water Tank - Civil Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF04 PK01BMF05 — 01B MF302 2001-FA/FB Water Tank - E&I Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF05 PK03DMF01 — 03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK03DMF01 EK000SY095 — 010 P&ID's - Tech Review | 28-Jan-26 → 29-Jan-26 | Complete 100% | float — PK01BMF01 — 01B MF302 2001-FA/FB Water Tank - Fdn. V. Data (Subcontract) | 28-Jan-26 → 21-Feb-26 | Complete 100% | float — EK000I3540 — ITCC - Develop Final Design Basis | 28-Jan-26 → 04-Mar-26 | Complete 100% | float — EK000I3520 — SIS - Develop Final Design Basis | 28-Jan-26 → 12-Mar-26 | Complete 100% | float — EK000I3520 PK03DMF00 — 03D MF302 2002-F Demineralized Water Tank - Fdn. V. Data (Subcontract) | 28-Jan-26 → 18-Mar-26 | Complete 100% | float — PK03DMF00 EK010PI014 — Plot Plan - Overall Site (Drwg 0101) Issue IFC | 28-Jan-26 → 29-Mar-26 | Complete 100% | float — EK010PI014 EK010IC252 — MOV Valves - Purchase ERW | 28-Jan-26 → 15-Apr-26 | Complete 100% | float — EK010IC252 EK000MU25D — 02G MU225 Technical Evaluation | 28-Jan-26 → 21-Feb-26 | Complete 100% | float — PK000I1220 — Coriolis Meters - Fabricate/Exworks | 29-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK000I1220 EK01YPI050 — 01Y Model Comment Resolution Approval | 29-Jan-26 → 31-Jan-26 | Complete 100% | float — PK000MD107 — MD305 Merc. Removal Bed - Eval Bids & Issue Recmd | 29-Jan-26 → 31-Jan-26 | Complete 100% | float — EK000MD105 — MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW | 29-Jan-26 → 01-Feb-26 | Complete 100% | float — PK000PS00B — 000 SP Items - Receive Quotes | 29-Jan-26 → 11-Feb-26 | Complete 100% | float — PK000ML50N — Recv. Planning V. Data ML500 | 29-Jan-26 → 24-Feb-26 | Complete 100% | float — PK000ML50P — Issue Formal P.O. for ML500 | 29-Jan-26 → 26-Mar-26 | Complete 100% | float — PK000ML50P PK000MB42S — MB420 - Marshaling 101-B Cast Peep Sites | 30-Jan-26 → 27-Dec-26 | In Progress 25% | float — PK000MB42S PK03AMLV01 — 03A ML500 2003-L - Piping Prod. V. Data | 31-Jan-26 → 27-Dec-26 | In Progress 25% | float — PK03AMLV01 PK03AMLV02 — 03A ML500 2003-L - Civil Prod. V. Data | 31-Jan-26 → 27-Dec-26 | In Progress 25% | float — PK03AMLV02 PK03AMLV03 — 03A ML500 2003-L - E&I Prod. V. Data | 31-Jan-26 → 27-Dec-26 | In Progress 25% | float — PK03AMLV03 PK000MD108 — MD305 Merc. Removal Bed - Final Negotiate/Interim Award | 31-Jan-26 → 03-Feb-26 | Complete 100% | float — PK000MU11J — 05B MU311 Final Negotiate/Interim Award | 31-Jan-26 → 13-Feb-26 | Complete 100% | float — EK010E008A — 540-SB Admin. Area Pwr Supply - ERW Package | 01-Feb-26 → 14-Feb-26 | Complete 100% | float — PK000I221H — 000 Everest Control Valves - Fabricate/Exworks | 03-Feb-26 → 30-Dec-26 | In Progress 24% | float 504.0d PK000I221H PK000MD110 — MD305 Merc. Removal Bed - Fabricate/PO Promise | 03-Feb-26 → 28-Feb-27 | In Progress 21% | float 157.0d PK000MD110 EK01DPI021 — 01D Model Review Comment Resolution | 03-Feb-26 → 07-Feb-26 | Complete 100% | float — EK00012210 — 000 Everest Control Valves - D/S,Sizing,Tech Eval | 03-Feb-26 → 05-Mar-26 | Complete 100% | float — PK000MD109 — MD305 Merc. Removal Bed - Issue Formal P.O. | 03-Feb-26 → 11-Mar-26 | Complete 100% | float — PK000ML52P — Issue Formal P.O. for ML501 | 03-Feb-26 → 26-Mar-26 | Complete 100% | float — PK000ML52P PK000ML50K — ML500 - Fabricate/PO Promise 2003-L PAI/IA | 04-Feb-26 → 10-Feb-27 | In Progress 21% | float 78.0d PK000ML50K PK000MJ36K — MJ305 - Fabricate/PO Promise OSBL PUMPS | 04-Feb-26 → 10-Jan-27 | In Progress 23% | float 60.0d PK000MJ36K PK000MBP3U — MB311 - Shop Recv - 101-B Convection Tube & Pipe | 07-Feb-26 → 22-Apr-26 | Complete 100% | float — PK000MBP3U EK000YA822 — (EP-22) Issue for Planning (IPL) >90% OSBL P&ID's | 09-Feb-26 | Complete EK000YA824 — (EP-23) Issue For Planning (IPL) >90% ISBL P&ID's | 09-Feb-26 | Complete PK000I352H — SIS - Fabricate Hardware | 10-Feb-26 → 27-Dec-26 | In Progress 23% | float — PK000I352H EK01BPI050 — 01B Model Comment Resolution Approval | 10-Feb-26 → 14-Feb-26 | Complete 100% | float — PK000MJ38E — Technical Evaluation - MJ308 | 10-Feb-26 → 27-Mar-26 | Complete 100% | float — PK000MJ38E PK05AMF05 — 05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract) | 11-Feb-26 → 27-Dec-26 | In Progress 23% | float — PK05AMF05 EK000MU11E — 05B MU311 Prepare & Issue Purchase ERW | 11-Feb-26 → 13-Feb-26 | Complete 100% | float — EK01EIC120 — 01E Instrument Detail Model / Review | 11-Feb-26 → 01-Mar-26 | Complete 100% | float — PK000MF32D — 05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF33 — 05A MF312 2105-F - Piping Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF34 — 05A MF312 2105-F - Civil Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF35 — 05A MF312 2105-F - E&I Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK000PS00D — 000 SP Items - Eval Bids / Issue Recmd | 11-Feb-26 → 18-Feb-26 | Complete 100% | float — EK000PS00C — 000 SP Items - Technical Evaluation | 11-Feb-26 → 01-Mar-26 | Complete 100% | float — EK01DPI050 — 01D Model Comment Resolution Approval | 12-Feb-26 → 13-Feb-26 | Complete 100% | float — PK000I1100 — 020 Orific Plates - Fabricate/Exworks | 13-Feb-26 → 27-Dec-26 | In Progress 22% | float — PK000I1100 PK000MU11K — 05B MU311 - Fabricate/PO Promise HYDROCHLORIC ACID STORAGE | 13-Feb-26 → 27-Dec-26 | In Progress 22% | float — PK000MU11K PK000MU11P — 05B MU311 Issue Formal P.O. | 13-Feb-26 → 13-Feb-26 | Complete 100% | float — PK000MU11N — 05B MU311 Recv. Planning V. Data | 13-Feb-26 → 28-Feb-26 | Complete 100% | float — PK000I444K — Issue Formal Purchase Order - Shelters/ Analyzers | 17-Feb-26 → 17-Feb-26 | Complete 100% | float — PK010E008B — 540-SB Admin. Area Pwr Supply - Inquiry REQ/RFQ | 17-Feb-26 → 20-Feb-26 | Complete 100% | float — PK000MJ71G — Issue MJ731 RFQ | 17-Feb-26 → 10-Mar-26 | Complete 100% | float — EK000I444B — Develop Final Design Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000I444M — Develop Final Deign Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000E004A — UPS System - Issue ERW | 17-Feb-26 → 28-Mar-26 | Complete 100% | float — EK000E004A EK03DPI050 — 03D Model Comment Resolution Approval | 18-Feb-26 → 06-Mar-26 | Complete 100% | float — EK000E001D — Sub Stations - Tech Evaluation | 19-Feb-26 → 27-Dec-26 | In Progress 21% | float — EK000E001D PK000PS00E — 000 SP Items - Final Negotiation / Interim Award | 19-Feb-26 → 27-Dec-26 | In Progress 21% | float — PK000PS00E PK010E008C — 540-SB Admin. Area Pwr Supply - Receive Bids | 20-Feb-26 → 03-Apr-26 | Complete 100% | float — PK010E008C PK000MU25I — 02G MU225 Eval Bids & Issue Recmd | 21-Feb-26 → 18-Mar-26 | Complete 100% | float — EK000CS027 — Turnover System Definition for OSBL | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000CS027 EK000I444F — Planning V. Data - Shelters/ Analyzers | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000I444F PK000I352J — SIS - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I352J PK000I354J — ITCC - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I354J PK05AMLV04 — 05A ML501 2103-L - Piping Prod. V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK05AMLV04 PK05AMLV05 — 05A ML501 2103-L - Civil Prod. V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK05AMLV05 PK05AMLV06 — 05A ML501 2103-L - E&I Prod. V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK05AMLV06 EK000MJ38T — Update/Issue Formal Inquiry for ERW - MJ308 | 25-Feb-26 → 03-Mar-26 | Complete 100% | float — EK000ML50E — Prepare & Issue Purchase ERW - ML500 | 25-Feb-26 → 08-Mar-26 | Complete 100% | float — EK000YA831 — (EP-26) Complete Hazard Review Meeting on >90% ISBL P&ID's | 25-Feb-26 | Complete EK000MJ39E — Prepare & Issue Purchase ERW - MJ391 | 27-Feb-26 → 09-Apr-26 | Complete 100% | float — EK000MJ39E PK000MB68J — Final Negotiate/Interim Award - MB692 | 27-Feb-26 → 03-Mar-26 | Complete 100% | float — EK000I3541 — ITCC - Develop Purchase T-Req | 27-Feb-26 → 05-Mar-26 | Complete 100% | float — PK000MB68K — MB692 - Fabricate/PO Promise 101-B Cat Vacuum Equip. | 03-Mar-26 → 27-Dec-26 | In Progress 17% | float — PK000MB68K PK000MB68P — Issue Formal P.O. for MB692 | 03-Mar-26 → 06-Mar-26 | Complete 100% | float — PK000MU29I — Eval Bids & Issue Recmd MU292 | 03-Mar-26 → 19-Mar-26 | Complete 100% | float — EK030I131A — Develop / Issue Purchase ERW -Transmitter OSBL | 04-Mar-26 → 27-Dec-26 | In Progress 17% | float — EK030I131A EK000E002D — Transformer - Tech Evaluation | 04-Mar-26 → 27-Dec-26 | In Progress 17% | float — EK000E002D PK000E002E — Transformer - Eval Bids/Issue Recmd | 04-Mar-26 → 27-Dec-26 | In Progress 17% | float — PK000E002E PK000MB21F — Marshaling of Equip. 101-B Siding for MB212 | 04-Mar-26 → 27-Dec-26 | In Progress 17% | float — PK000MB21F EK000YA826 — (EP-27) Begin Issuing Area Line Installation Details (IDF Files) | 04-Mar-26 | Complete EK03CPI050 — 03C Model Comment Resolution Approval | 05-Mar-26 → 07-Mar-26 | Complete 100% | float — PK000I3540 — ITCC - Vendor Update Pricing / Quote | 06-Mar-26 → 29-Mar-26 | Complete 100% | float — EK000I221F — 000 Everest Control Valves - Purchase ERW | 11-Mar-26 → 27-Dec-26 | In Progress 15% | float — EK000I221F EK010I1211 — Vortex Meters - Purchase ERW | 11-Mar-26 → 27-Dec-26 | In Progress 15% | float — EK010I1211 PK000MJ71H — Receive Quotes MJ731 | 11-Mar-26 → 05-Apr-26 | Complete 100% | float — PK000ML43S — ML430 - Marshaling 110-L BENFIELD MIXER | 11-Mar-26 → 27-Dec-26 | In Progress 15% | float — PK000ML43S PK05BMU06 — 05B MU311 2109-LA/LB, 2110-L - Piping Prod. V. Data | 14-Mar-26 → 27-Dec-26 | In Progress 14% | float — PK05BMU06 PK05BMU07 — 05B MU311 2109-LA/LB, 2110-L - Civil Prod. V. Data | 14-Mar-26 → 27-Dec-26 | In Progress 14% | float — PK05BMU07 PK000MJ39J — Final Negotiate/Interim Award - MJ391/MJ392 | 14-Mar-26 → 17-Mar-26 | Complete 100% | float — PK03BMU100 — 03B Recv. Planning V. Data - Utility Equip. 2401-J/JA | 15-Mar-26 → 31-Mar-26 | Complete 100% | float — PK000MJ39P — Issue Formal P.O. for MJ391/MJ392 | 17-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK000MJ39P EK050PI006 — Site Data Needed - Loading Area (SPDC) | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — EK050PI006 PK000MJ39K — Fabricate/Exworks FIREWATER PUMPS | 18-Mar-26 → 10-Jan-27 | In Progress 12% | float 60.0d PK000MJ39K PK01BMJV04 — 01B MJ391 2204-J/JA - Piping Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK01BMJV04 PK01BMJV05 — 01B MJ391 2204-J/JA - Civil Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK01BMJV05 PK01BMJV06 — 01B MJ391 2204-J/JA - E&I Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK01BMJV06 PK05AMJV07 — 05A MJ392 2105-JA/JB - Piping Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK05AMJV07 PK05AMJV08 — 05A MJ392 2105-JA/JB - Civil Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK05AMJV08 PK05AMJV09 — 05A MJ392 2105-JA/JB - E&I Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK05AMJV09 PK000MU25J — 02G MU225 Final Negotiate/Interim Award | 19-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK000MU25J PK000MU29K — MU292 - Fabricate/PO Promise 2404-L | 19-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK000MU29K PK03BMUV04 — 03B MU292 2404-L - Piping Prod. V. Data | 19-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK03BMUV04 PK03BMUV05 — 03B MU292 2404-L - Civil Prod. V. Data | 19-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK03BMUV05 PK03BMUV06 — 03B MU292 2404-L - E&I Prod. V. Data | 19-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK03BMUV06 PK000MU29J — Final Negotiate/Interim Award - MU292 | 19-Mar-26 → 19-Mar-26 | Complete 100% | float — PK000MU29P — Issue Formal P.O. for MU292 | 19-Mar-26 → 31-Mar-26 | Complete 100% | float — PK000MU29N — Recv. Planning V. Data MU292 | 19-Mar-26 → 09-Apr-26 | Complete 100% | float — EK030I616A — Develop / Issue Purchase ERW - Steam Drum Lvl Gauges - OSBL | 22-Mar-26 → 27-Dec-26 | In Progress 12% | float — EK030I616A EK03CIC120 — 03C Instrument Detail Model / Review | 22-Mar-26 → 18-Apr-26 | Complete 100% | float — EK000MU29E — Prepare & Issue Purchase ERW - MU292 | 24-Mar-26 → 27-Mar-26 | Complete 100% | float — PK000MU32J — 01D MU322 Final Negotiate/Interim Award | 24-Mar-26 → 31-Mar-26 | Complete 100% | float — PK020IC210 — 020 Control Valves - Fabricate/Exworks | 27-Mar-26 → 27-Dec-26 | In Progress 10% | float — PK020IC210 PK000E004B — UPS System - Inquiry REQ/RFQ | 27-Mar-26 → 08-Apr-26 | Complete 100% | float — PK000MJ38B — Eval Bids & Issue Recmd MJ308 | 27-Mar-26 → 23-Apr-26 | Complete 100% | float — PK010IC210 — 010 Control Valves - Fabricate/Exworks | 28-Mar-26 → 27-Dec-26 | In Progress 10% | float — PK010IC210 PK030IC210 — 030 Control Valves - Fabricate/Exworks | 28-Mar-26 → 27-Dec-26 | In Progress 10% | float — PK030IC210 EK020FP460 — FP Electrical Area Classification OSBL - IFC | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — EK020FP460 PK01DMUV07 — 01D MU322 2210-L,2211-L - Piping Prod. V. Data | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — PK01DMUV07 PK01DMUV09 — 01D MU322 2210-L,2211-L - E&I Prod. V. Data | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — PK01DMUV09 EK000MU32E — 01D MU322 Prepare & Issue Purchase ERW | 31-Mar-26 → 31-Mar-26 | Complete 100% | float — PK000MBP3Z — MB311 - Shop Recv - 101-B Radiant Tube & Pipe | 31-Mar-26 → 31-Mar-26 | Complete 100% | float — PK01DMUV08 — 01D MU322 2210-L,2211-L - Civil Prod. V. Data | 31-Mar-26 → 01-Apr-26 | Complete 100% | float — PK000ML90J — Final Negotiate/Interim Award - ML900 | 31-Mar-26 → 02-Apr-26 | Complete 100% | float — EK000I3521 — SIS - Develop Purchase T-Req | 31-Mar-26 → 03-Apr-26 | Complete 100% | float — PK000MU32P — 01D MU322 Issue Formal P.O. | 31-Mar-26 → 22-Apr-26 | Complete 100% | float — EK000MU25E — 02G MU225 Prepare & Issue Purchase ERW | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EK000MU25E EK010I1151 — Annubars - Purchase ERW | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EK010I1151 EK030I623A — Develop / Issue Purchase ERW -Multi-Point Thermocouples - OSBL | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EK030I623A PK000ML42S — ML420 - Marshaling CARTRIDGE FILTERS | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK000ML42S PK05AMB46 — 05A MB710 2202-B/BL - Piping Prod. V. Data | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK05AMB46 PK05AMB47 — 05A MB710 2202-B/BL - Civil Prod. V. Data | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK05AMB47 PK05AMB48 — 05A MB710 2202-B/BL - E&I Prod. V. Data | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK05AMB48 EK000I3542 — ITCC - Final Tech Evaluation for Purchase | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK000I444C — Develop / Issue T-Req - Shelters/ Analyzers | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK01YIC120 — 01Y Instrument Detail Model / Review | 01-Apr-26 → 10-Apr-26 | Complete 100% | float — PK000PIA1H — Bulk Piping A/G & U/G - Transport / Delivery (First CS,SS,U/G) | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK000PIA1H PK000MB61L — Marshaling of 101-B Burners MB610 | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK000MB61L PK000MU32K — 01D MU322 - Fabricate/PO Promise COOLING WTR FILTER & CLARIFIER | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK000MU32K PK000ML90K — ML900 - Fabricate/PO Promise Evap. Pond Spray Nzl. | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK000ML90K PK01AMLV01 — 01A ML900 2408-LA,LB,LC,LD - Piping Prod. V. Data | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK01AMLV01 PK01AMLV02 — 01A ML900 2408-LA,LB,LC,LD - Civil Prod. V. Data | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK01AMLV02 PK01AMLV03 — 01A ML900 2408-LA,LB,LC,LD - E&I Prod. V. Data | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK01AMLV03 PK000ML90P — Issue Formal P.O. for ML900 | 02-Apr-26 → 15-Apr-26 | Complete 100% | float — PK000MBP3X — MB311 - Shop Recv - 101-B Convection Fittings | 02-Apr-26 → 15-Apr-26 | Complete 100% | float — EK010E008D — 540-SB Admin. Area Pwr Supply - Tech Evaluation | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — EK010E008D EK05BEL160 — Switchgear One line Diagrams - IFD | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — EK05BEL160 EK05BEL180 — MCC One line Diagrams - IFD | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — EK05BEL180 PK000E00C — UPS System - Receive Bids | 07-Apr-26 → 27-Dec-26 | In Progress 6% | float — PK000E00C EK030I621A — Develop / Issue Purchase ERW - Temperature Elements - OSBL | 08-Apr-26 → 27-Dec-26 | In Progress 6% | float — EK030I621A EK01API050 — 01A Model Comment Resolution Approval | 08-Apr-26 → 17-Apr-26 | Complete 100% | float — PK000MC61F — MC610 - Marshaling DBL PIPE EXCH 161-C | 10-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MC61F PK000I444D — Vendor Update Pricing - Shelters/ Analyzers | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000I444D PK000MB83S — MB630 - Marshaling 101-B Air Preheater | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MB83S PK000MU61S — MU611 - Marshaling 2101-U, 2101-UJA Thru UJG CW TWR & Fans | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MU61S PK000MU61U — MU611 - Marshaling 2101-UJA Thru UJGM CW Motors | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MU61U PK000I3521 — SIS - Vendor Provides Software & Workstations | 16-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000I3521 PK010I1210 — Vortex Meters - Fabricate/Exworks | 16-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK010I1210 EK000I3523 — SIS - Software Programming by KBR | 18-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK000I3523 EK030I611A — Develop / Issue Purchase ERW - Pressure Gauges - OSBL | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK030I611A EK05AIC120 — 05A Instrument Detail Model / Review | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK05AIC120 PK000I3520 — SIS - Vendor Update Pricing / Quote | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000I3520 PK010I1100 — 010 Orific Plates - Fabricate/Exworks | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK010I1100 EK000MJ38C — Prepare & Issue Purchase ERW - MJ308 | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK000MJ38C PK000MJ38M — Final Negotiate/Interim Award - MJ308 | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MJ38M PK000MJ38R — Issue Formal P.O. for MJ308 | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MJ38R PK000MJ38T — Recv. Planning V. Data MJ308 | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MJ38T PK000MJ38U — MJ308 - Fabricate/PO Promisse ISBL ANSI/API PUMPS | 23-Apr-26 → 10-Jan-27 | In Progress 5% | float 198.0d PK000MJ38U PK01AMJV01 — 01A MJ308 2408-JA/JB - Piping Prod. V. Data | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK01AMJV01 PK01AMJV02 — 01A MJ308 2408-JA/JB - Civil Prod. V. Data | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK01AMJV02 PK01AMJV03 — 01A MJ308 2408-JA/JB - E&I Prod. V. Data | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK01AMJV03 PK000MU35S — MU350 - Marshaling 101-U DEAERATOR | 24-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK000MU35S EK000CV146 — Receive Site Survey Data Areas 04 & 05 | 27-Dec-26 | Not Started EK000E004D — UPS System - Tech Evaluation | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000ELEG0 — Electrical Heat Tracing - ERW Package | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP060 — FP Overall Firewater P&IDs - Development & Issue IFD | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP065 — FP Overall Firewater P&IDs - Development & Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000GE030 — Production Check Estimate | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I3522 — SIS - Final Tech Evaluation for Purchase | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I352M — SIS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I354M — ITCC - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444E — Final Tech Evaluation - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444G — Review / Approve V. Data - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000YA832 — (EP-32) Issue OSBL (Units01/03) found./UG pipe work package | 27-Dec-26 | Not Started EK000YA833 — (EP-33) Issue > 90% ISBL Civil Foundations | 27-Dec-26 | Not Started EK000YA839 — (EP-35) Issue >90% OSBL P&ID's For Construction (IFC) | 27-Dec-26 | Not Started EK000YA841 — (EP-29) Issue OSBL Plot Plan for Construction (IFC) | 27-Dec-26 | Not Started EK000YA848 — (EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC) | 27-Dec-26 | Not Started EK000YA888 — (TLA-02) Second TLA Payment | 27-Dec-26 | Not Started EK010FP040 — FP Firewater Pump P&IDs - Development & Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01AIC120 — 01A Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01API144 — 01A OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01BIC120 — 01B Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01BPI144 — 01B OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01CIC120 — 01C Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01CPI143 — 01C OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01DIC120 — 01D Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01DPI144 — 01D OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01HIC120 — 01H Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01JIC120 — 01J Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01JPI050 — 01J Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01JPI143 — 01J Op's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK01YPI143 — 01Y OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK020ELEG5 — Cathodic Protection - Design & Specs Package (By Consultant) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03AIC120 — 03A Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03API050 — 03A Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03API143 — 03A OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03BIC120 — 03B Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03BPI050 — 03B Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03BPI143 — 03B OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03CPI143 — 03C OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03DIC120 — 03D Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03DPI145 — 03D OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03EIC120 — 03E Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03EPI050 — 03E Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03EPI144 — 03E OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03FIC120 — 03F Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03FPI050 — 03F Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03FPI144 — 03F OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03YIC120 — 03Y Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03YPI050 — 03Y Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03YPI144 — 03Y OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK04AIC120 — 04A Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK05API050 — 05A Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK05API144 — 05A OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK05BPI035 — 05B Plot Plan | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI021 — 03Y Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK0003525 — SIS - Ship to DCS Shop/ Setup | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK0003526 — SIS - Integrated FAT | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001E — Sub Stations - Eval Bids/Issue Recmd | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001G — Sub Stations - Interim Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001J — Sub Stations - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001K — Sub Stations - Formal Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001M — Sub Stations - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002G — Transformer - Interim Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002J — Transformer - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002K — Transformer - Formal Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002M — Transformer - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004E — UPS System - Eval Bids/Issue Recmd | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004G — UPS System - Interim Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004J — UPS System - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004K — UPS System - Formal Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004M — UPS System - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I1103 — 020 Orific Plates - Transport & Deliver | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I1161 — 020 Wedge Flow Meters - Fabricate/Exworks | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I1162 — 020 Wedge Flow Meters - Transport & Deliver | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I1221 — Coriolis Meters - Transport & Deliver | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I1270 — Fabricate/Exworks Magnetic Flow Meters | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I1271 — Transport & Deliver Magnetic Flow Meters | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I3522 — SIS - FAT Test | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I3523 — SIS - Cleanup / Changes | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I3542 — ITCC - Software Programming by Vendor | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I3543 — ITCC - FAT Test | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I3544 — ITCC - Cleanup / Changes | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I354P — ITCC - Ship to DCS Shop/ Setup | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I354Q — ITCC - Integrated FAT | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I444H — Fabricate - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I611H — Fabricate / Exworks - Pressure Gauges - ISBL | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I616H — Fabricate / Exworks - Steam Drum Lvl Gauges | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I616N — Transport & Deliver - Steam Drum Lvl Gauges | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000I617H — Fabricate / Exworks - Magnetic Lvl Gauges | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000IC352 — DCS - FAT Test | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000IC353 — DCS - Cleanup / Changes | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000IC355 — DCS - ITCC / SIS / DCS - Integrated FAT | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000IC35M — DCS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB21O — Transport & Deliver of Equip. 101-B Siding | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB33O — MB333 - Transport/Customes Equip. 101-B | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB33S — MB333 - Marshaling Riser Transition 101-B | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB34Z — Shop Recv.- 101-B Finned Convection Tubes & Pipe | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB41Z — Shop Recv. - 101-B Cast Tube Supports | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB42O — MB420 - Transport to Vendor 101-B Cast Peep Sites | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB61O — Transport & Deliver 101-B Burners | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB63O — MB630 - Transport/Customes 101-B Air Preheater | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB64O — MB640 - Transport/Customes 101-B Springs & Hangers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB64S — MB640 - Marshaling 101-B Springs & Hangers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB65O — MB622 - Transport/Customes 101-B Penthouse Circ Fans | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB65S — MB622 - Marshaling 101-B Penthouse Circ Fans | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB66O — MB660 - Transport/Customes 101-B Dampers & Air Doors | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB66S — MB660 - Marshaling 101-B Dampers & Air Doors | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB68O — MB692 - Transport/Customes 101-B Cat Vacuum Equip. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB68S — MB692 - Marshaling 101-B Cat Vacuum Equip. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB69O — MB691 - Transport/Customes of Equip. 101-B | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB69S — MB691 - Marshaling 101-B for MB691 | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB81O — MB810 - Transport & Deliver of Equip. 101-B | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MB81S — MB810 - Marshaling 102-B | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP1C — MB221 - Marshaling 101-B Convection Modules | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP1M — MB221 - Transport/Customes 101-B Radiant Steel Panels | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP1T — MB221 - Fab/PO Promise 101-B Crossover Pipe | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP1U — MB221 - Transport/Customes 101-B Radiant Harps | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP1V — MB221 - Transport/Customes 101-B Convection Modules | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP1X — MB221 - Transport/Customes 101-B Radiant Ducting | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP1Y — MB221 - Transport/Customes 101-B Crossover | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP2C — MB221 - Marshaling 101-B Crossover | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP3C — MB221 - Marshaling 101-B Radiant Ducting | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP3V — MB311 - Shop Recv - 101-B Crossover Tube & Pipe | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP3W — MB311 - Shop Recv - 101-B Crossover Fittings | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP4C — MB221 - Marshaling 101-B Radiant Coil/Harps | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP4O — MB312 - Transport/Customes 101-B Radiant Cast Stringer Grids | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP4S — MB312 - Transport/Customes 101-B Radiant Cast Tube/Riser/Manifold | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP4T — MB312 - Shop Recv. 101-B Radiant Cast Stringer Grids | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP4U — MB312 - Shop Recv. 101-B Radiant Cast Tube/Riser/Manifold | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MBP5C — MB221 - Marshaling 101-B Radiant Steel Panels | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC21O — MC210 - Transport/Customes 110/115/124/128/130/133/134/160/167/173/174-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC21R — MC210 - Marshaling 127-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC21S — MC210 - Marshaling 110/115/124/128/130/133/134/160/167/173/174-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC21T — MC210 - Transport/Customes 127-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC23B — MC230 - Marshaling 106-C & 109-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC23C — MC230 - Transport/Customes 106-C & 109-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC23O — MC230 - Transport/Customes 105/172/183-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC23R — MC230 - Marshaling 111/114-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC23S — MC230 - Marshaling 105/172/183-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC23T — MC230 - Transport/Customes 114-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC61O — MC610 - Transport/Customes DBL PIPE EXCH 188-CA | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC61Q — MC610 - Transport/Customes DBL PIPE EXCH 161-C | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MC61S — MC610 - Marshaling DBL PIPE EXCH 188-CA | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD22B — MD202 - Marshaling TOWERS 104-E | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD22C — MD202 - Transport/Customes TOWERS 104-E | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD22O — MD202 - Transport/Customes TOWERS 103/105-E | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD22S — MD202 - Marshaling TOWERS 103/105-E | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD42A — MD402 -Marshaling 144-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD42B — MD402 - Transport/Customes 144-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD42R — MD402 - Transport/Customes 104-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD42T — MD402 -Marshaling 104-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD44M — MD404 - Marshaling 107-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD44N — MD404 - Transport/Customes 107-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD44O — MD404 - Transport/Customes 109-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD44S — MD404 - Marshaling 109-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD45B — MD405 - Marshaling ISBL DRUMS - 115-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD45C — MD405 - Transport/Customes ISBL DRUMS - 115-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD45O — MD405 - Transport/Customes ISBL DRUMS - 156-F & 157-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD45S — MD405 - Marshaling ISBL DRUMS - 156-F & 157-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD45T — MD405 - Transport/Customes ISBL DRUMS - 118-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD46O — MD411 - Transport/Customes OSBL DRUMS - 2203-F & 2204-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD46S — MD411 - Marshaling OSBL DRUMS - 2203-F & 2204-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD46U — MD411 - Marshaling OSBL DRUMS - 2006-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD46V — MD411 - Transport/Customes OSBL DRUMS - 2006-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD47O — MD406 - Transport/DCustomes ISBL DRUMS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD47S — MD406 - Marshaling ISBL DRUMS 103-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD51O — MD501 - Transport/Customes 107-D | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MD51S — MD501 - Marshaling 107-D | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MDR — MD405 - Marshaling ISBL DRUMS - 118-F | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ21O — MJ202 - Transport/Customes 102/3/5-J | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ21S — MJ202 - Marshaling 102/3/5-J | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ37O — MJ340 - Transport/Customes METERING PUMPS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ37S — MJ340 - Marshaling METERING PUMPS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ71I — Eval Bids & Issue Recmd MJ731 | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ71J — Final Negotiate/Interim Award - MJ731 | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ71P — Issue Formal P.O. for MJ731 | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ75O — MJ750 - Transport/Customes SURFACE CONDENSORS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MJ75S — MJ750 - Marshaling SURFACE CONDENSORS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000ML33O — ML330 - Transport/Customes 2101-L | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000ML33S — ML330 - Marshaling 2101-L | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000ML42O — ML420 - Transpor/Customes CARTRIDGE FILTERS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000ML43O — ML430 - Transport/Customes 110-L BENFIELD MIXER | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000ML51O — ML512 - Transport/Customs 2102-L LOADING ARM | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000ML51S — ML512 - Marshaling 2102-L LOADING ARM | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU11S — 05B MU311 - Marshaling HYDROCHLORIC ACID STORAGE | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU21O — MU221 - Transport/Customs LIFT STATION | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU21S — MU221 - Marshaling LIFT STATION | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU22O — MU222 - Transport/Customes .2401-U | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU22S — MU222 - Marshaling 2401-U | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU25K — MU225 - 02G Fabricate/PO Promise LIFT STATION | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU25P — 02G MU225 Issue Formal P.O. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU311 — 05B MU311 Transport/Customes BULK CHEM. STORAGE TANKS | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU35O — MU350 - Transport/Customes 101-U DEAERATOR | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU41O — MU410 - Transport/Customes 2002-U PKG BOILER | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU41S — MU410 - Marshaling 2002-U PKG BOILER | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000MU61O — MU611 - Transport/Customes 2101-U, 2101-UJA Thru UJG CW TWR & Fans | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000PIA1J — Bulk Piping A/G & U/G - Receive at Site FIRST (CS,SS,U/G) | 27-Dec-26 | Not Started PK000PIA1L — Bulk Piping A/G - Transport / Delivery (CROME) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000PIA1M — Bulk Piping A/G - Receive at Site (CHROME) | 27-Dec-26 | Not Started PK000PIA4H — Product Line Piping - Transport / Delivery to Insulation Shop | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000PIA4I — Product Line Piping - Insulation Fab/Exworks | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000PIA4J — Product Line Piping - Receive at Site | 27-Dec-26 | Not Started PK000PIA4K — Product Line Piping - Transport / Delivery | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000PIA4L — Product Line Piping - Fab/Exworks Remaining +/- 1500 Mts. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000PS00F — 000 SP Items - Issue Formal Blanket P.O. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008F — 540-SG Admin. Area Pwr Supply - Eval Bids/Issue Recmd | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008G — 540-SG Admin. Area Pwr Supply - Interim Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008H — 540-SG Admin. Area Pwr Supply - Formal Award | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008J — 540-SG Admin. Area Pwr Supply - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008L — 540-SG Admin. Area Pwr Supply - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010I1103 — 010 Orific Plates - Transport & Deliver | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010I1105 — 010 Orific Plates - Recv on Site | 27-Dec-26 | Not Started PK01DMU61Z — 01D Recv. at Site - 2101-U, 2101-UJA Thru UJG CW TWR & Fans | 27-Dec-26 | Not Started PK01FMU21Z — 01E Recv. at Site - 2402-L Lift Station | 27-Dec-26 | Not Started PK01GMU21Z — 01E Recv. at Site - Lift Station | 27-Dec-26 | Not Started PK020I131H — Fabricate / Exworks - Transmitters -Press. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK020IC214 — 020 Control Valves - Transport & Deliver | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK02FMU11Z — 05B MU311 Recv. at Site - 2109-LA HYDROCHLORIC ACID STORAGE TANK A | 27-Dec-26 | Not Started PK02GMU11Z — 05B MU311 Recv. at Site - 2109-LB HYDROCHLORIC ACID STORAGE TANK B | 27-Dec-26 | Not Started PK02LMU11Z — 05B MU311 Recv. at Site - 2110-L SODIUM HYDROCHLORITE STORAGE | 27-Dec-26 | Not Started PK030I1100 — Orific Plates - Fabricate/Exworks | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK030IC214 — 030 Control Valves - Transport & Delivery | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK030IC220 — 030 Control Valves - Recv on Site | 27-Dec-26 | Not Started PK03BMU22Z — 03B Recv. at Site - 2401-U Sanitary Treatment Pkg | 27-Dec-26 | Not Started PK03CMD46Z — 03C Recv. at Site - 2203-F & 2204-F Caustic Tank/ Acid Drum | 27-Dec-26 | Not Started PK03FMD46Z — 03F Recv. at Site - 2006-F Boiler Blowdown Drum | 27-Dec-26 | Not Started PK03FMU11Z — 05B MU311 Recv. at Site - 2109-L HYDROCHLORIC ACID STORAGE | 27-Dec-26 | Not Started PK03FMU41Z — 03F Recv. at Site - 2002-U Package Boiler | 27-Dec-26 | Not Started PK050I1105 — 050 Orfice Plates - Recv on Site Dock/Storage Area | 27-Dec-26 | Not Started PK05AMF25 — 05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK05AMJV10 — 05A MJ731 2108-J - Civil Prod. V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK05AMJV11 — 05A MJ731 2108-J - E&I Prod. V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK05AML33Z — 05A Recv. at Site - 2101-L Ammonia Refrigeration Pkg | 27-Dec-26 | Not Started PK05BML51Z — 05B Recv. at Site - 2102-L Loading Arm | 27-Dec-26 | Not Started ZZ1020 — 01D Recv. at Site - 2101-UJA Thru UJGM CW Motors | 27-Dec-26 | Not Started ZZ1040 — MU611 - Transport/Customes 2101-UJA Thru UJGM CW Motors | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000YA500 — Issue ISBL Paint & Insulation Work Package | 28-Dec-26 → 08-Mar-27 | Not Started 0% | float 750.0d EK000YA500 EK000ELEGP — Electrical Heat Tracing - Design & BOM by Consultant | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 91.0d EK000ELEN1 — 01,03,04 LV Wiring Diagrams - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN2 — 01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN3 — 01,03, Equipment Interconnection Diagrams - IFC | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EK020ELEG6 — Cathodic Protection - Material Supply (By Consultant) | 30-Dec-26 → 02-May-27 | Not Started 0% | float 6.0d EK020ELEG6 EK05ACV200 — 05A Redesign Piling & Ammonia Tank Foundations | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float -44.0d EK05BIC120 — 05B Instrument Model | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 110.0d PK000E001H — Sub Stations - Fab / Exworks | 30-Dec-26 → 28-Feb-27 | Not Started 0% | float 62.0d PK000E001H PK000E002H — Transformer - Fab / Exworks | 30-Dec-26 → 04-Feb-27 | Not Started 0% | float 28.0d PK000E004H — UPS System - Fab / Exworks | 30-Dec-26 → 05-Feb-27 | Not Started 0% | float 27.0d PK000I1121 — 020 Venturis - Fabricate/Exworks | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 509.0d PK000I2300 — On/Off Valves - Fabricate/Exworks | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 460.0d PK000I2300 PK000I3524 — SIS - Packing / Exworks | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 55.0d PK000I3545 — ITCC - Packing / Exworks | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 55.0d PK000I4440 — FAT Test - Shelters/ Analyzers | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 161.0d PK000I611N — Transport & Deliver - Pressure Gauges - ISBL | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 110.0d PK000I612H — Fabricate / Exworks - Differential Pressure Gauges | 30-Dec-26 → 18-Feb-27 | Not Started 0% | float 28.0d PK000I612H PK000I617N — Transport & Deliver - Magnetic Lvl Gauges | 30-Dec-26 → 13-Jan-27 | Not Started 0% | float 104.0d PK000I621H — Fabricate / Exworks - Temperature Elements | 30-Dec-26 → 13-Mar-27 | Not Started 0% | float 31.0d PK000I621H PK000I623H — Fabricate / Exworks - Multi-Point Thermocouples | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 84.0d PK000IC354 — DCS - Packing / Exworks | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 85.0d PK000IC35N — DCS - Transport (Hold for Field Request) | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 85.0d PK000IC35N PK000MB62S — MB621 - Marshaling 101-B ID & FD Fans | 30-Dec-26 → 14-Feb-27 | Not Started 0% | float 215.0d PK000MB62S PK000MB71S — MB710 - Marshaling 2202-B/BL Storage Flare & Flame FRT Gen. | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 240.0d PK000MB71S PK000MD34T — MD304 - Marshaling 108-DA/B | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 162.0d PK000MD34T PK000MD41S — MD401 - Marshaling 101-F | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 175.0d PK000MD41S PK000MD44U — MD404 - Marshaling 132-F | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 65.0d PK000MD44U PK000MJ35S — MJ305 - Marshaling ISBL ANSI/API PUMPS | 30-Dec-26 → 11-Feb-27 | Not Started 0% | float 153.0d PK000MJ35S PK000MJ71K — MJ731 - Fabricate/PO Promise EMERG PWR GENERATOR | 30-Dec-26 → 21-Feb-27 | Not Started 0% | float 70.0d PK000MJ71K PK000ML31S — ML313 - Marshaling 160-L | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 261.0d PK000ML90S — 01A ML900 - Marshaling Evap. Pond Spray Nzl. | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 103.0d PK000MU25S — 02G MU225 - Marshaling LIFT STATION | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 215.0d PK000MU25S PK000MU29S — MU292 - Marshaling 2404-L | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 195.0d PK000MU29S PK000MU30S — MU300 - Marshaling 2102-U | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 76.0d PK000MU30S PK000MU31S — MU310 - Marshaling Injection System & Chlorination Unit | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 59.0d PK000MU31S PK000MU32S — MU322 - Marshaling COOLING WTR FILTER & CLARIFIER | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 71.0d PK000MU32S PK000MU33S — MU330 - Marshaling 2001-U | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 111.0d PK000MU33S PK000PIA1N — Bulk Piping A/G - Fab/Exworks (FINAL) | 30-Dec-26 → 07-Mar-27 | Not Started 0% | float 45.0d PK000PIA1N PK000PS00G — 000 SP Items - Fabricate/Exworks | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 247.0d PK000PSA8H — 000 Relief Valves - Transport & Deliver | 30-Dec-26 → 24-Feb-27 | Not Started 0% | float 257.0d PK000PSA8H PK000PTA0J — Engineered Pipe Supports - Transport | 30-Dec-26 → 10-Feb-27 | Not Started 0% | float 58.0d PK000PTA0J PK010E008K — 540-SG Admin. Area Pwr Supply - Fab / Exworks | 30-Dec-26 → 11-Feb-27 | Not Started 0% | float 70.0d PK010E008K PK010I1211 — Vortex Meters - Transport & Deliver | 30-Dec-26 → 31-Dec-26 | Not Started 0% | float 533.0d PK010I1241 — Rotameters - Transport & Deliver | 30-Dec-26 → 14-Jan-27 | Not Started 0% | float 523.0d PK010IC214 — 010 Control Valves - Transport & Deliver | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 535.0d PK010IC220 — 010 Control Valves - Recv on Site | 30-Dec-26 | Not Started PK010IC252 — MOV Valves - Fabricate/Exworks | 30-Dec-26 → 27-Jan-27 | Not Started 0% | float 475.0d PK020I131N — Transport & Deliver - Transmitters -Press. | 30-Dec-26 → 20-Feb-27 | Not Started 0% | float 76.0d PK020I131N PK030I1103 — Orific Plates -Transport & Deliver | 30-Dec-26 → 27-Jan-27 | Not Started 0% | float 514.0d PK030I131H — Fabricate / Exworks - Transmitters - Temp. | 30-Dec-26 → 16-Jan-27 | Not Started 0% | float 71.0d PK030I611H — Fabricate / Exworks - Pressure Gauges - OSBL | 30-Dec-26 → 04-Feb-27 | Not Started 0% | float 58.0d ZZ2080 — MJ305 - Transport/Customes OSBL ANSI/API PUMPS | 30-Dec-26 → 07-Feb-27 | Not Started 0% | float 190.0d ZZ2080 ZZ2090 — MJ305 - Marshaling OSBL ANSI/API PUMPS | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 190.0d PK000I1131 — Venturis - Transport & Deliver | 31-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d PK000I221N — 000 Everest Control Valves - Transport & Deliver | 31-Dec-26 → 10-Feb-27 | Not Started 0% | float 504.0d PK000I221N PK000MB51S — MB511 - Marshaling 101-B Insulation | 31-Dec-26 → 20-Jan-27 | Not Started 0% | float 204.0d PK000ML31O — ML313 - Transport/Customs 160-L | 31-Dec-26 → 24-Jan-27 | Not Started 0% | float 365.0d PK000PS00H — 000 SP Items - Transport & Deliver | 31-Dec-26 → 10-Mar-27 | Not Started 0% | float 247.0d PK000PS00H PK010I1151 — Annubars - Transport & Deliver | 31-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d PK010I1212 — Vortex Meters - Recv on Site | 31-Dec-26 | Not Started PK000MD21S — MD201- Marshaling 101-E | 02-Jan-27 → 07-Feb-27 | Not Started 0% | float 93.0d EK000PI200 — Final Delta Piping Bulk Quanities for Purchase | 03-Jan-27 | Not Started EK000YA838 — (EP-34) Issue >90% ISBL P&ID's For Construction (IFC) | 03-Jan-27 | Not Started PK000I352N — SIS - Transport & Delivery | 13-Jan-27 → 21-Mar-27 | Not Started 0% | float 55.0d PK000I352N PK000I354N — ITCC - Transport & Delivery | 13-Jan-27 → 21-Mar-27 | Not Started 0% | float 55.0d PK000I354N PK000I4441 — Cleanup / Changes - Shelters/ Analyzers | 13-Jan-27 → 24-Jan-27 | Not Started 0% | float 161.0d PK000MD32S — MD302 - Marshaling 104-D1/2 | 13-Jan-27 → 07-Feb-27 | Not Started 0% | float 85.0d PK000MJ22S — MJ201 - Marshaling 101-J | 13-Jan-27 → 31-Jan-27 | Not Started 0% | float 86.0d PK000MJ36S — MJ305 - Marshaling OSBL PUMPS | 13-Jan-27 → 31-Jan-27 | Not Started 0% | float 60.0d PK000MJ38V — MJ308 - Marshaling ISBL ANSI/API PUMPS | 13-Jan-27 → 31-Jan-27 | Not Started 0% | float 198.0d PK000MJ39S — Marshaling FIREWATER PUMPS | 13-Jan-27 → 31-Jan-27 | Not Started 0% | float 60.0d PK000ML90O — 01A ML900 - Transport/Customes Evap. Pond Spray Nzl. | 13-Jan-27 → 21-Feb-27 | Not Started 0% | float 103.0d PK000ML90O PK010I1242 — Rotameters - Recv on Site | 14-Jan-27 | Not Started EK05BPI050 — 05B Model Comment Resolution Approval | 15-Jan-27 → 17-Jan-27 | Not Started 0% | float 75.0d PK000MC32S — MC311 - Marshaling KBR S&T EXCH | 17-Jan-27 → 06-Mar-27 | Not Started 0% | float 76.0d PK000MC32S PK000MJ34S — MJ304 - Marshaling MP BFW PUMPS | 17-Jan-27 → 06-Feb-27 | Not Started 0% | float 186.0d PK030I131N — Transport & Deliver - Transmitters - Temp. | 17-Jan-27 → 30-Jan-27 | Not Started 0% | float 91.0d PK000MJ32S — MJ302 - Marshaling 107-JA/JB/JC | 20-Jan-27 → 07-Feb-27 | Not Started 0% | float 175.0d PK000MB51O — MB511 - Transport/Customes 101-B Insulation | 21-Jan-27 → 03-Mar-27 | Not Started 0% | float 204.0d PK000MB51O PK000MJ37V — MJ307 - Marshaling ISBL ANSI/API PUMPS | 21-Jan-27 → 10-Feb-27 | Not Started 0% | float 192.0d EK000YA030 — Last PDS Planning Release | 24-Jan-27 | Not Started EK05BEL165 — Switchgear One line Diagrams - IFC | 27-Jan-27 → 30-Jan-27 | Not Started 0% | float 276.0d EK05BEL185 — MCC One line Diagrams - IFC | 27-Jan-27 → 30-Jan-27 | Not Started 0% | float 286.0d PK000I4442 — Packing / Exworks - Shelters/ Analyzers | 27-Jan-27 → 31-Jan-27 | Not Started 0% | float 161.0d PK030I1105 — Orific Plates - Recv on Site | 27-Jan-27 | Not Started PK000MD34S — MD304 - Marshaling 106-D, 109-DA/B | 30-Jan-27 → 07-Feb-27 | Not Started 0% | float 200.0d EK000YA040 — Engineering 95% Complete | 30-Jan-27 | Not Started PK000I444N — Transport & Deliver - Shelters/ Analyzers | 03-Feb-27 → 11-Apr-27 | Not Started 0% | float 161.0d PK000I444N PK000MJ22O — MJ201 - Transport/Customs 101-J | 03-Feb-27 → 07-Mar-27 | Not Started 0% | float 86.0d PK000MJ31S — MJ301 - Marshaling 104-J | 03-Feb-27 → 04-Mar-27 | Not Started 0% | float 168.0d PK000MJ36O — MJ305 - Transport/Customes OSBL PUMPS | 03-Feb-27 → 14-Mar-27 | Not Started 0% | float 60.0d PK000MJ36O PK000MJ38W — MJ308 - Transport/Customes ISBL ANSI/API PUMP | 03-Feb-27 → 14-Mar-27 | Not Started 0% | float 198.0d PK000MJ38W PK000MJ39O — Transport/Customes FIREWATER PUMPS | 03-Feb-27 → 14-Mar-27 | Not Started 0% | float 60.0d PK000MJ39O PK010IC262 — MOV Valves - Transport & Deliver | 03-Feb-27 → 21-Mar-27 | Not Started 0% | float 475.0d PK010IC262 PK010I1152 — Annubars - Recv on Site | 03-Feb-27 | Not Started PK000E002X — Transformer - Marshalling | 05-Feb-27 → 01-Apr-27 | Not Started 0% | float 28.0d PK000E002X PK030I611N — Transport & Deliver - Pressure Gauges - OSBL | 05-Feb-27 → 25-Feb-27 | Not Started 0% | float 73.0d PK000E004X — UPS System - Marshalling | 06-Feb-27 → 02-Apr-27 | Not Started 0% | float 27.0d PK000E004X PK000MJ34O — MJ304 - Transport/Customes MP BFW PUMPS | 07-Feb-27 → 20-Mar-27 | Not Started 0% | float 186.0d PK000MJ34O PK000MB71O — MB710 - Transport/Customes 2202-B/BL Storage Flare & Flame FRT Gen. | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 336.0d PK000MD21O — MD201 - Transport/Customes 101-E | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 131.0d PK000MD32O — MD302 - Transport/Customes 104-D1/2 | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 120.0d PK000MD34O — MD304 - Transport/Customes 106-D, 109-DA/B | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 280.0d PK000MD41O — MD401 - Transport/Customes 101-F | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 246.0d PK000MD44V — MD404 - Transport/Customes 132-F | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 93.0d PK000MU225 — 02G MU225 Transport/Customes LIFT STATION | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 302.0d PK000MU29O — MU292 - Transport/Customes 2404-L | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 275.0d PK000MU30O — MU300 - Transport/Customes 2102-U | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 108.0d PK000MU31O — MU310 - Transport/Customes Injection System & Chlorination Unit | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 83.0d PK000MU322 — MU322 Transport/Customes COOLING WTR FILTER & CLARIFIER | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 101.0d PK000MU33O — MU330 - Transport/Customes 2001-U | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 157.0d ZZ2100 — MD304 - Transport/Customes 108-DA/B | 08-Feb-27 → 28-Feb-27 | Not Started 0% | float 228.0d PK01GIC35L — DCS - Receive at Site | 08-Feb-27 | Not Started PK000I2330 — On/Off Valves - Transport & Deliver | 10-Feb-27 → 11-Apr-27 | Not Started 0% | float 460.0d PK000I2330 PK000MJ32O — MJ302 - Transport/Customes 107-JA/JB/JC | 10-Feb-27 → 28-Feb-27 | Not Started 0% | float 175.0d ZZ2110 — MC230 - Transport/Customes 107/111 | 10-Feb-27 → 28-Feb-27 | Not Started 0% | float 93.0d PK000I221L — 000 Everest Control Valves - Recv on Site | 10-Feb-27 | Not Started PK000PTA0K — Engineered Pipe Supports - Receive at Site | 10-Feb-27 | Not Started EK035BI145 — 05B OP's & Serv. Model Comments Resolution Approval | 11-Feb-27 → 13-Feb-27 | Not Started 0% | float 75.0d PK000MJ37W — MJ307 - Transport/Customes ISBL ANSI/API PUMP | 11-Feb-27 → 24-Mar-27 | Not Started 0% | float 192.0d PK000MJ37W PK000ML50S — ML500 - Marshaling 2003-L PAI/IA | 11-Feb-27 → 07-Mar-27 | Not Started 0% | float 78.0d PK000MJ35O — MJ305 - Transport/Customes ISBL ANSI/API PUMPS | 12-Feb-27 → 25-Mar-27 | Not Started 0% | float 153.0d PK000MJ35O PK010E008M — 540-SG Admin. Area Pwr Supply - Marshalling | 12-Feb-27 → 08-Apr-27 | Not Started 0% | float 70.0d PK010E008M PK000MB62O — MB621 - Transport/Customes of 101-B ID & FD Fans | 15-Feb-27 → 07-Mar-27 | Not Started 0% | float 301.0d PK000E001Z — Sub Stations - FAT | 17-Feb-27 → 28-Feb-27 | Not Started 0% | float 62.0d PK000MD31S — MD301 - Marshaling 103-D | 18-Feb-27 → 07-Mar-27 | Not Started 0% | float 55.0d PK000I612N — Transport & Deliver - Differential Pressure Gauges | 19-Feb-27 → 29-Apr-27 | Not Started 0% | float 28.0d PK000I612N EK000YA835 — (EP-36) Issue >90% Area Line Installation Details | 21-Feb-27 | Not Started EK000YA847 — (EP-39) Issue >90% OSBL Electrical Design Drawings | 21-Feb-27 | Not Started PK000ML90Z — 01A ML900 - Recv. at Site - Evap. Pond Spray Nzl. | 22-Feb-27 | Not Started PK000MJ71S — MJ731 - Marshaling EMERG PWR GENERATOR | 24-Feb-27 → 07-Mar-27 | Not Started 0% | float 70.0d PK000PSA8J — 000 Relief Valves - Recv on Site | 24-Feb-27 | Not Started PK03FMU32Z — MU322 Recv. at Site - COOLING WTR FILTER & CLARIFIER | 28-Feb-27 | Not Started PK030I131L — Recv at Site - Transmitters -Temp. | 01-Mar-27 | Not Started PK000MB71Z — 05A Recv. at Site - Storage Flare & Flame FRT Gen. | 01-Mar-27 | Not Started PK01BMU30Z — 01C Recv. at Site - 2102-U EDR Unit | 01-Mar-27 | Not Started PK03BMU29Z — 03B Recv. at Site - 2404-L Oil Skimmer | 01-Mar-27 | Not Started PK03EMU33Z — 03E Recv. at Site - 2001-U Demineralizer Unit | 01-Mar-27 | Not Started PK000E001N — Sub Stations - Transport | 03-Mar-27 → 11-Apr-27 | Not Started 0% | float 62.0d PK000E001N PK000md113 — MD305 Merc. Removal Bed 102-D - Marshaling | 03-Mar-27 → 07-Mar-27 | Not Started 0% | float 157.0d PK000MD22U — MD202 - Marshaling TOWERS 150-E | 03-Mar-27 → 07-Mar-27 | Not Started 0% | float 100.0d PK000MJ33S — MJ303 - Marshaling CW PUMPS | 03-Mar-27 → 19-Mar-27 | Not Started 0% | float 27.0d PK000MJ73S — MJ730 - Marshaling EMERG PWR GENERATOR | 03-Mar-27 → 07-Mar-27 | Not Started 0% | float 70.0d PK020MC31D — MC312 - Marshaling 121-C | 03-Mar-27 → 07-Mar-27 | Not Started 0% | float 90.0d PK020MC31S — MC312 - Marshaling 120-C | 03-Mar-27 → 07-Mar-27 | Not Started 0% | float 90.0d PK000MJ31O — MJ301 - Transport/Customes 104-J | 05-Mar-27 → 15-Apr-27 | Not Started 0% | float 168.0d PK000MJ31O PK000MD22N — MD201- Marshaling 102-E | 06-Mar-27 → 07-Mar-27 | Not Started 0% | float 62.0d PK000MC32O — MC311 - Transport/Customes KBR S&T EXCH | 06-Mar-27 → 27-Mar-27 | Not Started 0% | float 108.0d PK000ML50O — ML500 - Transport/Customes 2003-L PAI/IA | 08-Mar-27 → 28-Mar-27 | Not Started 0% | float 110.0d PK000MD111 — MD305 Merc. Removal Bed - Transport & Deliver | 10-Mar-27 → 02-May-27 | Not Started 0% | float 157.0d PK000MD111 PK000MD211 — MD201 - Transport/Customes 102-E | 10-Mar-27 → 18-Apr-27 | Not Started 0% | float 62.0d PK000MD211 PK000MD22V — MD202 - Transport/Customes TOWERS 150-E | 10-Mar-27 → 02-May-27 | Not Started 0% | float 100.0d PK000MD22V PK000MD31O — MD301 - Transport/Customes 103-D | 10-Mar-27 → 04-Apr-27 | Not Started 0% | float 55.0d PK000MJ71O — MJ731 - Transport/Customes EMERG PWR GENERATOR | 10-Mar-27 → 18-Apr-27 | Not Started 0% | float 70.0d PK000MJ71O PK000MJ73O — MJ730 - Transport/Customes EMERG PWR GENERATOR | 10-Mar-27 → 18-Apr-27 | Not Started 0% | float 70.0d PK000MJ73O PK000PIA1O — Bulk Piping A/G - Transport / Delivery (FINAL) | 10-Mar-27 → 11-Apr-27 | Not Started 0% | float 45.0d PK020MC31J — MC312 - Transport/Customes 121-C | 10-Mar-27 → 04-Apr-27 | Not Started 0% | float 90.0d PK020MC31L — MC312 - Transport/Customes 120-C | 10-Mar-27 → 04-Apr-27 | Not Started 0% | float 90.0d PK000PS00J — 000 SP Items - Recv on Site | 10-Mar-27 | Not Started PK000MD43S — MD403 - Marshaling 106-F | 12-Mar-27 → 25-Apr-27 | Not Started 0% | float 135.0d PK000MD43S PK000I621N — Transport & Deliver - Temperature Elements | 14-Mar-27 → 14-Apr-27 | Not Started 0% | float 39.0d PK000MJ38A — 05A Recv. at Site - 2100-JA Pumps - MJ308 | 15-Mar-27 | Not Started PK01BMJ36Z — 01B Recv. at Site - 2001-JA/JB/JC, 2004-J/JA, 2007J/JA | 15-Mar-27 | Not Started PK01BMJ39Z — Recv. at Site - Firewater Pumps | 15-Mar-27 | Not Started PK03CMJ36Z — 03C Recv. at Site - 2205-J/JA, 2206-J/JA Pumps | 15-Mar-27 | Not Started PK03DMJ36Z — 03D Recv. at Site - 2002-J/JA Demineralized Water Pumps | 15-Mar-27 | Not Started PK05AMJ36Z — 05A Recv. at Site - 2203-J/JM, 2106-J, 2107-J Pumps | 15-Mar-27 | Not Started PK030I611L — Recv at Site - Pressure Gauges - OSBL | 19-Mar-27 | Not Started PK000MJ33O — MJ303 - Transport/Customes CW PUMPS | 20-Mar-27 → 30-Apr-27 | Not Started 0% | float 27.0d PK000MJ33O PK000MD33S — MD303 - Marshaling 105-D | 21-Mar-27 → 11-Apr-27 | Not Started 0% | float 50.0d PK010IC272 — MOV Valves - Recv on Site | 22-Mar-27 | Not Started PK01GI352L — SIS - Receive at Site | 22-Mar-27 | Not Started PK01GI354L — ITCC - Receive at Site | 22-Mar-27 | Not Started PK000MD42S — MD402 -Marshaling 102-F1, 102-F2 | 24-Mar-27 → 28-Mar-27 | Not Started 0% | float 130.0d PK05AMJ37A — 05A Recv. at Site - 2100-JA Pumps - MJ307 | 24-Mar-27 | Not Started PK03AML50Z — 03A Recv. at Site - 2003-L PAI/IA Compressor Pkg | 29-Mar-27 | Not Started PK000MD42O — MD402 - Transport/Customes 102-F1, 102-F2 | 31-Mar-27 → 09-May-27 | Not Started 0% | float 130.0d PK000MD42O PK000E002N — Transformer - Transport | 02-Apr-27 → 13-May-27 | Not Started 0% | float 28.0d PK000E002N PK000E004N — UPS System - Transport | 03-Apr-27 → 14-May-27 | Not Started 0% | float 27.0d PK000E004N PK010E008N — 540-SG Admin. Area Pwr Supply - Transport | 09-Apr-27 → 20-May-27 | Not Started 0% | float 70.0d PK010E008N PK000I444L — Recv at Site - Shelters/ Analyzers | 12-Apr-27 | Not Started PK000I9000 — Receive Instruments at Site | 12-Apr-27 | Not Started PK000PIA1P — Bulk Piping A/G - Receive at Site (FINAL) | 12-Apr-27 | Not Started PK01HE001L — Sub Stations - Receive at Site | 12-Apr-27 | Not Started PK000MD33O — MD303 - Transport/Customes 105-D | 14-Apr-27 → 09-May-27 | Not Started 0% | float 50.0d PK000MJ71Z — 05A Recv. at Site - 2108-J Emerg Power Generator | 19-Apr-27 | Not Started PK01HMJ73Z — 01H Recv. at Site - 2303-J Emerg Power Generator | 19-Apr-27 | Not Started PK000MD43O — MD403 - Transport/Customs 106-F | 28-Apr-27 → 23-May-27 | Not Started 0% | float 135.0d PK01BMJ33Z — 01B Recv. at Site - 2007-J/JA Cooling Wtr Makeup Pumps | 30-Apr-27 | Not Started PK01DMJ33Z — 01D Recv. at Site - Equip. 2202-JA/B/C | 30-Apr-27 | Not Started EK000YA889 — (TLA-03) Complete > TLA Payments | 03-May-27 | Not Started PK01HE002L — Transformer - Receive at Site | 13-May-27 | Not Started PK000E004L — UPS System - Receive at Site | 14-May-27 | Not Started PK010E008P — 540-SG Admin. Area Pwr Supply - Receive at Site | 20-May-27 | Not Started PK000MC31S — MC310 - Marshaling 101-C & 102-C (Heavy Lift) | 01-Jul-27 → 01-Jul-27 | Not Started 0% | float 8.0d PK000MC31O — MC310 - Transport/Customes 101-C & 102-C (Heavy Lift) | 02-Jul-27 → 29-Jul-27 | Not Started 0% | float 8.0d PK000PR20J — PR201 KAAP Catalyst - Transport & Deliver | 04-Nov-27 → 12-Jan-28 | Not Started 0% | float 26.0d PK000PR20J