EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 1500
of 4648
(capped — pick a WBS subtree, or
show all)
activities
Code
Activity
Start
Finish
Flt
%
PK000I354H
ITCC - Fabricate Hardware
11-Feb-25
27-Dec-26
—
64%
EK05BPI030
05B Conceptual Layout - Supersketches
07-May-25
27-Dec-26
—
59%
EK000MBG10
General & Administrative
28-May-25
27-Dec-26
—
57%
EM03EPI120
03E Plant Layout Model
14-Jun-25
27-Dec-26
—
56%
EM03API120
03A Plant Layout Model
22-Jul-25
27-Dec-26
—
53%
EM03YPI120
03Y Plant Layout Model
22-Jul-25
27-Dec-26
—
53%
PK000MB33K
MB333 - Fab/PO Promise 101-B Riser Transition 101-B
29-Jul-25
27-Dec-26
—
52%
PK000MBP1K
MB221 - Fab/PO Promise 101-B Radiant Steel Panels
09-Aug-25
27-Dec-26
—
51%
PK000MBP1Q
MB221 - Fab/PO Promise 101-B Radiant Coil/Harps
09-Aug-25
27-Dec-26
—
51%
PK000MBP1R
MB221 - Fab/PO Promise 101-B Convection Modules
09-Aug-25
27-Dec-26
—
51%
PK000MBP1S
MB221 - Fabr/PO Promise 101-B Radiant Ducting
09-Aug-25
27-Dec-26
—
51%
PK000MD31K
MD301 - Fabricate/PO Promise 103-D
09-Aug-25
17-Feb-27
55.0d
46%
PK000MD33K
MD303 - Fabricate/PO Promise 105-D
09-Aug-25
20-Mar-27
50.0d
44%
PK000MJ21K
MJ202 - Fabricate/PO Promise 102/3/5-J
09-Aug-25
27-Dec-26
—
51%
PK000MB62K
MB621 - Fabricate/PO Promise 101-B ID & FD Fans
12-Aug-25
27-Dec-26
—
51%
PK000MB81K
MB810 - Fabricate/PO Promise 102-B
12-Aug-25
27-Dec-26
—
51%
PK000MD32K
MD302 - Fabricate/PO Promise 104-D1/2
13-Aug-25
10-Jan-27
85.0d
49%
PK000MJ75K
MJ750 - Fabricate/PO Promise SURFACE CONDENSORS
13-Aug-25
27-Dec-26
—
51%
PK000MB34K
MB340 - Fabricate/PO Promise 101-B Finning
14-Aug-25
27-Dec-26
—
51%
PK000PTA0G
Engineered Pipe Supports - Fab / Exworks
14-Aug-25
27-Dec-26
—
51%
EK020IC210
020 Control Valves - D/S,Sizing,Tech Eval
15-Aug-25
27-Dec-26
—
51%
PK000MD22A
MD202 - Fabricate/PO Promise TOWERS 104-E
16-Aug-25
27-Dec-26
—
50%
PK000MD22K
MD202 - Fabricate/PO Promise TOWERS 103/105-E
16-Aug-25
27-Dec-26
—
50%
PK000MD22T
MD202 - Fabricate/PO Promise TOWERS 150-E
16-Aug-25
28-Feb-27
100.0d
45%
PK000MD34K
MD304 - Fabricate/PO Promise 106-D, 109-DA/B
16-Aug-25
29-Jan-27
200.0d
47%
PK000MD34Z
MD304 - Fabricate/PO Promise 108-DA/B
16-Aug-25
27-Dec-26
—
50%
PK000MD42K
MD402 - Fabricate/PO Promise 102-F1, 102-F2
16-Aug-25
21-Mar-27
130.0d
43%
PK000MD42N
MD402 - Fabricate/PO Promise 104-F, 144-F
16-Aug-25
27-Dec-26
—
50%
PK000MD44K
MD404 - Fabricate/PO Promise 109-F
16-Aug-25
27-Dec-26
—
50%
PK000MD44L
MD404 - Fabricate/PO Promise 107-F
16-Aug-25
27-Dec-26
—
50%
PK000MD44T
MD404 - Fabricate/PO Promise 132-F
16-Aug-25
27-Dec-26
—
50%
PK000MD45A
MD405 - Fabricate/PO Promise ISBL DRUMS - 115-F
16-Aug-25
27-Dec-26
—
50%
PK000MD45K
MD405 - Fabricate/PO Promise ISBL DRUMS - 156-F & 157-F
16-Aug-25
27-Dec-26
—
50%
PK000MD46K
MD411 - Fabricate/PO Promise OSBL DRUMS - 2203-F & 2204-F
16-Aug-25
27-Dec-26
—
50%
PK000MD46T
MD411 - Fabricate/PO Promise OSBL DRUMS - 2006-F
16-Aug-25
27-Dec-26
—
50%
PK000MD4Q
MD405 - Fabricate/PO Promise ISBL DRUMS - 118-F
16-Aug-25
27-Dec-26
—
50%
PK020MC31C
MC312 - Fabricate/PO Promise 121-C
21-Aug-25
28-Feb-27
90.0d
44%
PK020MC31K
MC312 - Fabricate/PO Promise 120-C
21-Aug-25
28-Feb-27
90.0d
44%
PK000MD41K
MD401 - Fabricate/PO Promise 101-F
23-Aug-25
27-Dec-26
—
50%
PK000MD43K
MD403 - Fabricate/PO Promise 106-F
23-Aug-25
11-Mar-27
135.0d
43%
PK000MJ35K
MJ305 - Fabricate/PO Promise ISBL ANSI/API PUMPS
23-Aug-25
27-Dec-26
—
50%
ZZ2070
MJ305 - Fabricate/PO Promise OSBL ANSI/API PUMPS
23-Aug-25
27-Dec-26
—
50%
EM01CPI120
01C Plant Layout Model
24-Aug-25
27-Dec-26
—
50%
PK000MD51K
MD501 - Fabricate/PO Promise 107-D
27-Aug-25
27-Dec-26
—
49%
PK000MJ22K
MJ201 - Fabricate/PO Promise 101-J
30-Aug-25
10-Jan-27
86.0d
48%
PK000ML31K
ML313 - Fabricate/PO Promise 160-L
30-Aug-25
27-Dec-26
—
49%
PK000MBP3R
MB311 - Fab/Exworks 101-B Crossover Tube & Pipe
02-Sep-25
27-Dec-26
—
49%
PK000MBP3S
MB311 - Fab/Exworks 101-B Crossover Fittings
02-Sep-25
27-Dec-26
—
49%
PK000MB51K
MB511 - Fabricate/PO Promise 101-B Insulation
03-Sep-25
30-Dec-26
204.0d
48%
PK000MU41K
MU410 - Fabricate/PO Promise 2002-U PKG BOILER
06-Sep-25
27-Dec-26
—
48%
PK02HMD21
02H MD301 103-D Secondary Reformer - Prod. V. Data
09-Sep-25
27-Dec-26
—
48%
PK000MC61K
MC610 - Fabricate/PO Promise DBL PIPE EXCH 188-CA
10-Sep-25
27-Dec-26
—
48%
PK000MBP4K
MB312 - Fab/PO Promise 101-B Radiant Cast Fittings
11-Sep-25
27-Dec-26
—
48%
PK000MBP4Q
MB312 - Fab/PO Promise 101-B Radiant Cast Stringer Grids
11-Sep-25
27-Dec-26
—
48%
PK000MBP4R
MB312 - Fab/PO Promise 101-B Radiant Cast Tube/Riser/Manifold
11-Sep-25
27-Dec-26
—
48%
PK000ML51K
ML512 - Fabricate/PO Promise 2102-L LOADING ARM
11-Sep-25
27-Dec-26
—
48%
EM020ELEL2
02 U/G Electrical Routing Plans - IFC
16-Sep-25
27-Dec-26
—
47%
EK000FP036
FP ISBL Firewater P&IDs - Development & Issue IFC
17-Sep-25
27-Dec-26
—
47%
PK000MD21K
MD201 - Fabricate/PO Promise 101-E
17-Sep-25
01-Jan-27
93.0d
46%
PK000MD21M
MD201 - Fabricate/PO Promise 102-E
17-Sep-25
05-Mar-27
62.0d
41%
PK02EMD02
02E MD304 106-D Methanator - Prod. V. Data
18-Sep-25
27-Dec-26
—
47%
PK000ML33K
ML330 - Fabricate/Po Promise 2101-L
20-Sep-25
27-Dec-26
—
47%
EM020ELEH2
02 Develop & Issue Earthing / Grounding Dwgs - IFC
24-Sep-25
27-Dec-26
—
46%
EK04API030
04A Conceptual Layout - Supersketches
27-Sep-25
27-Dec-26
—
46%
PK000PSA8G
000 Relief Valves - Fabricate/Exworks
27-Sep-25
30-Dec-26
257.0d
46%
PK000MD47K
MD406 - Fabricate/PO Promise ISBL DRUMS
01-Oct-25
27-Dec-26
—
45%
PK000MU33K
MU330 - Fabricate/PO Promise 2001-U
01-Oct-25
27-Dec-26
—
45%
PK000PIA1K
Bulk Piping A/G - Fab/Exworks (CROME)
01-Oct-25
27-Dec-26
—
45%
PK000PIA4G
Product Line Piping - Fab/Exworks +/- 5700 Mts.
01-Oct-25
27-Dec-26
—
45%
PK000MC21K
MC210 - Fabricate/PO Promise 110/115/124/128/130/133/134/160/167/173/174-C
09-Oct-25
27-Dec-26
—
44%
PK000MC21N
MC210 - Fabricate/PO Promise 127-C
09-Oct-25
27-Dec-26
—
44%
PK000MC23A
MC230 - Fabricate/PO Promise 106-C & 109-C
09-Oct-25
27-Dec-26
—
44%
PK000MC23K
MC230 - Fabricate/PO Promise 105/107/172/183-C
09-Oct-25
27-Dec-26
—
44%
PK000MC23N
MC230 - Fabricate/PO Promise 111/114-C
09-Oct-25
27-Dec-26
—
44%
PK02AMC14
02A MC210 160-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
PK02AMC15
02A MC210 160-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
PK02AMC16
02A MC210 160-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
PK02LMC21
02E MC230 114-C, 172-C & 183-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
PK02LMC22
02E MC230 114-C, 172-C & 183-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
PK02LMC23
02E MC230 114-C, 172-C & 183-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1430
02C MC210 128-C, 134-C, 167-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1440
02C MC210 128-C, 134-C, 167-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1490
02D MC210 127-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1500
02D MC210 127-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1510
02E MC210 115-C, 130-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1520
02E MC210 115-C, 130-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1530
02E MC210 115-C, 130-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1540
02G MC210 133-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1550
02G MC210 133-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1560
02G MC210 133-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1590
02J MC210 173-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1600
02J MC210 173-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1610
02K MC210 174-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1620
02K MC210 174-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1630
02K MC210 174-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1670
02L MC210 110-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1680
02L MC210 110-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1690
02L MC210 110-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1700
02M MC210 124-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1710
02M MC210 124-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1720
02M MC210 124-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1760
02L MC230 105-C, 106-C, 107-C, 109-C & 111-C - Piping Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1770
02L MC230 105-C, 106-C, 107-C, 109-C & 111-C - Civil Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
ZZ1780
02L MC230 105-C, 106-C, 107-C, 109-C & 111-C - E&I Prod. V. Data
10-Oct-25
27-Dec-26
—
44%
PK000MJ34K
MJ304 - Fabricate/PO Promise MP BFW PUMPS
15-Oct-25
16-Jan-27
186.0d
42%
PK000MC32K
MC311 - Fabricate/PO Promise KBR S&T EXCH
16-Oct-25
16-Jan-27
76.0d
42%
PK000IC35J
DCS - Planning V. Data
17-Oct-25
27-Dec-26
—
43%
PK000IC35H
DCS - Fabricate Hardware
21-Oct-25
27-Dec-26
—
43%
PK010I1240
Rotameters - Fabricate/Exworks
30-Oct-25
27-Dec-26
—
42%
PK010I1150
Annubars - Fabricate/Exworks
31-Oct-25
30-Dec-26
509.0d
41%
EK010FP031
FP Firewater Pump P&IDs - Development & Issue IFD
01-Nov-25
27-Dec-26
—
41%
ZZ1850
02J MC311 103-C1/C2 - Piping Prod. V. Data
02-Nov-25
27-Dec-26
—
41%
ZZ1870
02J MC311 103-C1/C2 - E&I Prod. V. Data
02-Nov-25
27-Dec-26
—
41%
ZZ1930
02M MC311 123-C1/C2A/C2B - E&I Prod. V. Data
02-Nov-25
27-Dec-26
—
41%
PK000MB69K
MB691 - Fabricate/PO Promise 101-B
04-Nov-25
27-Dec-26
—
41%
PK000MU21K
MU221 - Fabricate/PO Promise LIFT STATION
04-Nov-25
27-Dec-26
—
41%
PK000MU22K
MU222 - Fabricate/PO Promise 2401-U
04-Nov-25
27-Dec-26
—
41%
CO000K0106
Mobilize Temporary Facilities (& Punchlist & Perm. Power)
09-Nov-25
27-Dec-26
—
40%
PK02KMD11
02K MD202 150-E Process Condensate Stripper - Prod. V. Data
13-Nov-25
27-Dec-26
—
40%
EM02FCV160
02F Design & Model Major Eq. Fdns
13-Nov-25
27-Dec-26
—
40%
PK000MU30K
MU300 - Fabricate/PO Promise 2102-U
19-Nov-25
27-Dec-26
—
39%
PK000MJ31K
MJ301 - Fabricate/ PO Promise 104-J
20-Nov-25
31-Jan-27
168.0d
35%
PK000MJ32K
MJ302 - Fabricate/PO Promise 107-JA/JB/JC
20-Nov-25
17-Jan-27
175.0d
37%
PK02FMJV01
02F MJ301 104-J/JA - Piping Prod. V. Data
20-Nov-25
27-Dec-26
—
39%
PK02FMJV02
02F MJ301 104-J/JA - Civil Prod. V. Data
20-Nov-25
27-Dec-26
—
39%
PK02FMJV03
02F MJ301 104-J/JA - E&I Prod. V. Data
21-Nov-25
22-Jan-27
517.0d
36%
PK000PR20H
PR201 KAAP Catalyst - Fabricate/Exworks
10-Dec-25
03-Nov-27
26.0d
19%
EK020EL126
Electrical Load List - Revised IFD w/Outstanding Equip. Data
13-Dec-25
27-Dec-26
—
35%
PK000MJ37K
MJ340 - Fabricate/PO Promise METERING PUMPS
13-Dec-25
27-Dec-26
—
35%
CO000C0150
Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
WO010K0110
010 Site Prep - Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
EK020EL000
ISBL Motor & Drivers - Prod. V. Data (information only)
16-Dec-25
22-Jan-27
—
32%
EK000I2305
On/Off Valves - Purchase ERW
18-Dec-25
27-Dec-26
—
34%
PK000MJ73K
MJ730 - Fabricate/PO Promise EMERG PWR GENERATOR
25-Dec-25
28-Feb-27
70.0d
28%
EK010IC213
010 Control Valves - Purchase ERW
25-Dec-25
27-Dec-26
—
33%
PK03DMJV02
03D MJ305 2002-J/JA - Civil Prod. V. Data
27-Dec-25
27-Dec-26
—
32%
EK020ELEE0
Tie-in List - IFC
28-Dec-25
27-Dec-26
—
32%
EM03BCV110
03B Design & Model Sumps
30-Dec-25
27-Dec-26
—
32%
PK000EL000
OSBL Motors & Drivers - Prod. V. Data (Information Only)
30-Dec-25
30-Dec-26
—
32%
PK03DMJV01
03D MJ305 2002-J/JA - Piping Prod. V. Data
30-Dec-25
27-Dec-26
—
32%
PK03DMJV03
03D MJ305 2002-J/JA - E&I Prod. V. Data
30-Dec-25
27-Dec-26
—
32%
EM02ACV122
02A Update Model Struct Steel & Issue Dwgs - IFC
31-Dec-25
27-Dec-26
—
32%
PK01BMJV03
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK01HMJV01
01H MJ730 2303-J - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK01HMJV02
01H MJ730 2303-J - E&I Prod. V. Data
31-Dec-25
30-Dec-26
511.0d
31%
PK02BMLV03
02B ML313 160-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02CMJV04
02C MJ202 103-J/105-J - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02CMJV05
02C MJ202 103-J/105-J - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02CMJV08
02C MJ305 112-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02DMD01
02D MD403 106-F Ammonia Separator - Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02DMJV03
02D MJ305 120-J/JA, 124-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02GMJV03
02G MJ202 102/3/5-J - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02GMJV06
02G MJ201 101-J - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02GMJV07
02G MJ201 101-J - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02GMJV08
02G MJ201 101-J - E&I Prod. V. Data
31-Dec-25
30-Dec-26
535.0d
31%
PK02GMJV11
02G MJ305 113-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02KMJV03
02K MJ305 111-J,115-J - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02LMJV01
02L MJ302 107-J - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02LMJV02
02L MJ302 107-J - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02LMJV03
02L MJ302 107-J - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK02LMJV06
02L MJ305 116-J/JA,121-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03BMUV03
03B MU222,MJ305 2401-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03CMJV03
03C MJ305 2205-J/JA,2206-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV01
03E MU330 2001-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV02
03E MU330 2001-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV03
03E MU330 2001-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV03
03F MU222 2401-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV04
03F MU410 2002-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV05
03F MU410 2002-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV06
03F MU410 2002-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV01
05A ML330 2101-L - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV02
05A ML330 2101-L - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV03
05A ML330 2101-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05BMLV03
05B ML512 2102-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
EK030IC213
030 Control Valves - Purchase ERW
01-Jan-26
27-Dec-26
—
31%
EM02NCV164
02N Update Model Major Eq. Fdns & Issue Dwgs-IFC
01-Jan-26
27-Dec-26
—
31%
EK01AIC300
01A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01BIC300
01B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01CIC300
01C In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01DIC300
01D In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK01YIC300
01Y In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02CIC300
02C In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02EIC300
02E In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02FIC300
02F In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02GIC300
02G In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02HIC300
02H In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02JIC300
02J In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02KIC300
02K In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02LIC300
02L In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02MIC300
02M In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02NIC300
02N In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK02QIC300
02Q In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03AIC300
03A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03BIC300
03B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03DIC300
03D In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03EIC300
03E In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03FIC300
03F In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK03YIC300
03Y In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK05AIC300
05A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EK05BIC300
05B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
—
31%
EM02ECV122
02E Update Model Struct Steel & Issue Dwgs - IFC
02-Jan-26
27-Dec-26
—
31%
EM02ECV164
02E Update Model Major Eq. Fdns & Issue Dwgs-IFC
02-Jan-26
27-Dec-26
—
31%
EM05ACV160
05A Design & Model Major Eq. Fdns
03-Jan-26
27-Dec-26
—
31%
PK000MC31K
MC310 - Fabricate/PO Promise 101-C & 102-C (Heavy Lift)
03-Jan-26
30-Jun-27
8.0d
20%
PK000MJ33K
MJ303 - Fabricate/PO Promise CW PUMPS
03-Jan-26
28-Feb-27
27.0d
26%
PK01DMJV03
01D MJ303 2202-JA/JB/JC - E&I Prod. V. Data
04-Jan-26
27-Dec-26
—
31%
ZZ1790
02H MC310 101,102-C - Piping Prod. V. Data
04-Jan-26
27-Dec-26
—
31%
ZZ1800
02H MC310 101,102-C - Civil Prod. V. Data
04-Jan-26
27-Dec-26
—
31%
ZZ1810
02H MC310 101,102-C - E&I Prod. V. Data
04-Jan-26
27-Dec-26
—
31%
PO000MF010
Field Erected Tanks Subcontract - Purchasing & Fabrication
04-Jan-26
27-Dec-26
—
31%
PK000MB64K
MB640 - Fabricate/PO Promise 101-B Springs & Hangers
06-Jan-26
27-Dec-26
—
30%
PK000MB71K
MB710 - Fabricate/PO Promise 2202-B/BL Storage Flare & Flame FRT Gen.
06-Jan-26
27-Dec-26
—
30%
PK02HMB38
02H MB622 101-B - Piping Prod. V. Data
06-Jan-26
27-Dec-26
—
30%
PK02HMB39
02H MB622 101-B - Civil Prod. V. Data
06-Jan-26
27-Dec-26
—
30%
PK02HMB40
02H MB622 101-B - E&I Prod. V. Data
06-Jan-26
27-Dec-26
—
30%
PK000MB65K
MB622 - Fab/PO Promise 101-B Penthouse Circ Fans
07-Jan-26
27-Dec-26
—
30%
EM03FCV160
03F Design & Model Major Eq. Fdns
07-Jan-26
27-Dec-26
—
30%
EK020ELEC2
Short Circuit, Load Flow Motor starting
10-Jan-26
27-Dec-26
—
30%
EM000MCG10
GEN and ADMINISTRATIVE
13-Jan-26
27-Dec-26
—
29%
PK000MU31K
MU310 - Fabricate/PO Promise Injection System & Chlorination Unit
14-Jan-26
27-Dec-26
—
29%
PK01DMUV01
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L-Piping Prod. V. Data
14-Jan-26
27-Dec-26
—
29%
PK01DMUV03
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L- E&I Prod. V. Data
14-Jan-26
27-Dec-26
—
29%
PK02LMLV07
02L MU310 109-L - Piping Prod. V. Data
14-Jan-26
27-Dec-26
—
29%
PK02FMUV01
02F MU310 106-L,108-L - Piping Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK02FMUV02
02F MU310 106-L,107-L,108-L - Civil Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK02FMUV03
02F MU310 106-L,107-L,108-L - E&I Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK02LMLV08
02L MU310 109-L - Civil Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK02LMLV09
02L MU310 109-L - E&I Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03FMUV07
03F MU310 2001-L - Piping Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03FMUV08
03F MU310 2001-L - Civil Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03FMUV09
03F MU310 2001-L - E&I Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
EK000IC353
DCS - Software Programming by KBR
15-Jan-26
27-Dec-26
—
29%
EM02JPI134
02J Detail Model Development
15-Jan-26
27-Dec-26
—
29%
EM02QPI134
02Q Detail Model Development
16-Jan-26
27-Dec-26
—
28%
PK01CMUV01
01C MU300 2102-U - Piping Prod. V. Data
16-Jan-26
27-Dec-26
—
28%
PK01CMUV02
01C MU300 2102-U - Civil Prod. V. Data
16-Jan-26
27-Dec-26
—
28%
PK01CMUV03
01C MU300 2102-U - E&I Prod. V. Data
16-Jan-26
27-Dec-26
—
28%
EK020IC213
020 Control Valves - Purchase ERW
17-Jan-26
27-Dec-26
—
28%
PK000MJ37U
MJ307 - Fabricate/PO Promise ISBL ANSI/API PUMPS
20-Jan-26
20-Jan-27
192.0d
26%
PK05AMJV04
05A MJ307 2100-JA/JB - Piping Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV05
05A MJ307 2100-JA/JB - Civil Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV06
05A MJ307 2100-JA/JB - E&I Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK000MB66K
MB660 - Fabricate/PO Promise 101-B Dampers & Air Doors
24-Jan-26
27-Dec-26
—
27%
EK010I1241
Rotameters - Purchase ERW
28-Jan-26
27-Dec-26
—
26%
EK050PI014
Plot Plan - Dock/Storage Issue IFC
28-Jan-26
27-Dec-26
—
26%
EM01API200
01A Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM01CPI200
01C Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM02GPI200
02G Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM02YPI134
02Y Detail Model Development
28-Jan-26
27-Dec-26
—
26%
EM03API200
03A Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM03BPI200
03B Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM03EPI200
03E Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM05API200
05A Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
PK01BMF02
01B MF302 2001-FA/FB Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK01BMF03
01B MF302 2001-FA/FB Water Tank - Piping Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK01BMF04
01B MF302 2001-FA/FB Water Tank - Civil Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK01BMF05
01B MF302 2001-FA/FB Water Tank - E&I Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
PK02AMJV01
02A MJ340 130-J/JA,131-J/JA - Piping Prod. V. Data
28-Jan-26
27-Dec-26
—
26%
PK02AMJV02
02A MJ340 130-J/JA,131-J/JA - Civil Prod. V. Data
28-Jan-26
27-Dec-26
—
26%
PK02AMJV03
02A MJ340 130-J/JA,131-J/JA - E&I Prod. V. Data
28-Jan-26
27-Dec-26
—
26%
PK03DMF01
03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
—
26%
EM02EPI134
02E Detail Model Development
29-Jan-26
27-Dec-26
—
26%
EM02MPI134
02M Detail Model Development
29-Jan-26
27-Dec-26
—
26%
EM02ACV164
02A Update Model Major Eq. Fdns & Issue Dwgs-IFC
29-Jan-26
27-Dec-26
—
26%
PK000I1220
Coriolis Meters - Fabricate/Exworks
29-Jan-26
27-Dec-26
—
26%
XE000OW301
05B SPDC TO Provide Required Eng. Data
29-Jan-26
27-Dec-26
—
26%
PK000MB42S
MB420 - Marshaling 101-B Cast Peep Sites
30-Jan-26
27-Dec-26
—
25%
PK03AMLV01
03A ML500 2003-L - Piping Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK03AMLV02
03A ML500 2003-L - Civil Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK03AMLV03
03A ML500 2003-L - E&I Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK000I221H
000 Everest Control Valves - Fabricate/Exworks
03-Feb-26
30-Dec-26
504.0d
24%
PK000MD110
MD305 Merc. Removal Bed - Fabricate/PO Promise
03-Feb-26
28-Feb-27
157.0d
21%
PK02MMD12
02M MD305 102-D Mercury Guard - Prod. V. Data
03-Feb-26
27-Dec-26
—
24%
PK000ML50K
ML500 - Fabricate/PO Promise 2003-L PAI/IA
04-Feb-26
10-Feb-27
78.0d
21%
PK000MJ36K
MJ305 - Fabricate/PO Promise OSBL PUMPS
04-Feb-26
10-Jan-27
60.0d
23%
EM02LPI134
02L Detail Model Development
06-Feb-26
27-Dec-26
—
24%
PK000I352H
SIS - Fabricate Hardware
10-Feb-26
27-Dec-26
—
23%
EK02EIC120
02E Instrument Detail Model / Review
11-Feb-26
27-Dec-26
—
23%
EK02HIC120
02H Instrument Detail Model / Review
11-Feb-26
27-Dec-26
—
23%
EK02JIC120
02J Instrument Detail Model / Review
11-Feb-26
27-Dec-26
—
23%
EK02KIC120
02K Instrument Detail Model / Review
11-Feb-26
27-Dec-26
—
23%
EK02LIC120
02L Instrument Detail Model / Review
11-Feb-26
27-Dec-26
—
23%
EK02MIC120
02M Instrument Detail Model / Review
11-Feb-26
27-Dec-26
—
23%
EK02QIC120
02Q Instrument Detail Model / Review
11-Feb-26
27-Dec-26
—
23%
EM01CCV160
01C Design & Model Major Eq. Fdns (Excluding EDR)
11-Feb-26
27-Dec-26
—
23%
PK02KMF04
02K MF301 114-F Benfield Solution Storage Tank - Fdn. V. Data (Subcontract)
11-Feb-26
27-Dec-26
—
23%
PK02KMF05
02K MF301 114-F Benfield Solution Storage Tank - Prod. V. Data (Subcontract)
11-Feb-26
27-Dec-26
—
23%
PK05AMF05
05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract)
11-Feb-26
27-Dec-26
—
23%
PK000I1100
020 Orific Plates - Fabricate/Exworks
13-Feb-26
27-Dec-26
—
22%
PK000MU11K
05B MU311 - Fabricate/PO Promise HYDROCHLORIC ACID STORAGE
13-Feb-26
27-Dec-26
—
22%
EM02UPICWG
02U U/G Plan Dwgs Issue IFC
14-Feb-26
27-Dec-26
—
22%
EK000E001D
Sub Stations - Tech Evaluation
19-Feb-26
27-Dec-26
—
21%
PK000PS00E
000 SP Items - Final Negotiation / Interim Award
19-Feb-26
27-Dec-26
—
21%
EM02CPI134
02C Detail Model Development
20-Feb-26
27-Dec-26
—
20%
EM01BCV226
01B Issue Fdn IFC- 2001-FA/FB (Water Storage Tanks)
24-Feb-26
27-Dec-26
—
19%
EK000CS027
Turnover System Definition for OSBL
25-Feb-26
27-Dec-26
—
19%
EK000I444F
Planning V. Data - Shelters/ Analyzers
25-Feb-26
27-Dec-26
—
19%
EM03ECV110
03E Design & Model Containment Area
25-Feb-26
27-Dec-26
—
19%
PK000I352J
SIS - Planning V. Data
25-Feb-26
27-Dec-26
—
19%
PK000I354J
ITCC - Planning V. Data
25-Feb-26
27-Dec-26
—
19%
PK02GMLV02
02G ML425 101-L - Civil Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK02GMLV03
02G ML425 101-L - E&I Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV04
05A ML501 2103-L - Piping Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV05
05A ML501 2103-L - Civil Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV06
05A ML501 2103-L - E&I Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
EM20ELEK2
02 Develop & Issue Cable Ladder Plans - IFC
03-Mar-26
27-Dec-26
—
17%
PK000MB68K
MB692 - Fabricate/PO Promise 101-B Cat Vacuum Equip.
03-Mar-26
27-Dec-26
—
17%
EK020I131A
Develop / Issue Purchase ERW -Transmitter ISBL
04-Mar-26
27-Dec-26
—
17%
EK030I131A
Develop / Issue Purchase ERW -Transmitter OSBL
04-Mar-26
27-Dec-26
—
17%
EM02FPI134
02F Detail Model Development
04-Mar-26
27-Dec-26
—
17%
EK000E002D
Transformer - Tech Evaluation
04-Mar-26
27-Dec-26
—
17%
PK000E002E
Transformer - Eval Bids/Issue Recmd
04-Mar-26
27-Dec-26
—
17%
PK000MB21F
Marshaling of Equip. 101-B Siding for MB212
04-Mar-26
27-Dec-26
—
17%
EM02HPI134
02H Detail Model Development
07-Mar-26
27-Dec-26
—
16%
EK000I221F
000 Everest Control Valves - Purchase ERW
11-Mar-26
27-Dec-26
—
15%
EK010I1211
Vortex Meters - Purchase ERW
11-Mar-26
27-Dec-26
—
15%
EK02CIC120
02C Instrument Detail Model / Review
11-Mar-26
27-Dec-26
—
15%
EM02YCV122
02Y Update Model Struct Steel & Issue Dwgs - IFC
11-Mar-26
27-Dec-26
—
15%
PK000ML43S
ML430 - Marshaling 110-L BENFIELD MIXER
11-Mar-26
27-Dec-26
—
15%
EM02DMD229
02D Vessel Steel Release IFC (MD403, MD404, 106/7/9-F)
12-Mar-26
27-Dec-26
—
15%
EM02EMD229
02E Vessel Steel Release IFC
12-Mar-26
27-Dec-26
—
15%
EM02HMD229
02H Vessel Steel Release IFC (MD301, MD405, MD501)
12-Mar-26
27-Dec-26
—
15%
EM02JMD229
02J Vessel Steel Release IFC (MD302,MD304)
12-Mar-26
27-Dec-26
—
15%
EM02LMD229
02L Vessel Steel Release IFC (MD201, MD402, MD404, MD406)
12-Mar-26
27-Dec-26
—
15%
EM02MMD229
02M Vessel Steel Release IFC (MD303, MD402)
12-Mar-26
27-Dec-26
—
15%
EM02QMD229
02Q Vessel Steel Release IFC (MD401)
12-Mar-26
27-Dec-26
—
15%
EK000I617A
Develop / Issue Purchase ERW - Magnetic Lvl Gauges
13-Mar-26
27-Dec-26
—
15%
EM02AMD229
02A Vessel Steel Release IFC
13-Mar-26
27-Dec-26
—
15%
EM02KMD229
02K Vessel Steel Release IFC (MD202, MD405)
13-Mar-26
27-Dec-26
—
15%
PK05BMU06
05B MU311 2109-LA/LB, 2110-L - Piping Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
PK05BMU07
05B MU311 2109-LA/LB, 2110-L - Civil Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
PK000MJ39P
Issue Formal P.O. for MJ391/MJ392
17-Mar-26
27-Dec-26
—
13%
EK050PI006
Site Data Needed - Loading Area (SPDC)
18-Mar-26
27-Dec-26
—
13%
PK000MJ39K
Fabricate/Exworks FIREWATER PUMPS
18-Mar-26
10-Jan-27
60.0d
12%
PK01BMJV04
01B MJ391 2204-J/JA - Piping Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK01BMJV05
01B MJ391 2204-J/JA - Civil Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK01BMJV06
01B MJ391 2204-J/JA - E&I Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK02EMD03
02E MD304 109-DA Molecular Sieve Dryer - Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK02EMD04
02E MD304 109-DB Molecular Sieve Dryer - Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV07
05A MJ392 2105-JA/JB - Piping Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV08
05A MJ392 2105-JA/JB - Civil Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV09
05A MJ392 2105-JA/JB - E&I Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK000MU25J
02G MU225 Final Negotiate/Interim Award
19-Mar-26
27-Dec-26
—
13%
PK000MU29K
MU292 - Fabricate/PO Promise 2404-L
19-Mar-26
27-Dec-26
—
13%
PK03BMUV04
03B MU292 2404-L - Piping Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
PK03BMUV05
03B MU292 2404-L - Civil Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
PK03BMUV06
03B MU292 2404-L - E&I Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
EM01YPI138
01Y Design / Issue Pipe Supports IFC
20-Mar-26
27-Dec-26
—
12%
EM02LCV164
02L Update Model Major Eq. Fdns & Issue Dwgs-IFC
20-Mar-26
27-Dec-26
—
12%
EM02MCV164
02M Update Model Major Eq. Fdns & Issue Dwgs-IFC
20-Mar-26
27-Dec-26
—
12%
CO02HC0140
02H Form Pour Strip Fnds - Structure
21-Mar-26
27-Dec-26
—
12%
EM03CPI138
03C Design / Issue Pipe Supports IFC
21-Mar-26
27-Dec-26
—
12%
WO020C0100
020 Concrete & Excavation
21-Mar-26
23-Mar-27
215.0d
9%
EK000I616A
Develop / Issue Purchase ERW - Steam Drum Lvl Gauges - ISBL
22-Mar-26
27-Dec-26
—
12%
EK030I616A
Develop / Issue Purchase ERW - Steam Drum Lvl Gauges - OSBL
22-Mar-26
27-Dec-26
—
12%
EM02API134
02A Detail Model Development
22-Mar-26
27-Dec-26
—
12%
CK01UU4150
01U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
164.0d
10%
CK02UU4150
02U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
164.0d
10%
CK03UU4150
03U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
164.0d
10%
CK05UU4150
05U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
318.0d
10%
CO000CK110
Set-Up KBR Pipe Fab Shop
24-Mar-26
27-Dec-26
—
11%
XE000OW300
04A SPDC TO Provide Required Eng. Data
24-Mar-26
27-Dec-26
—
11%
EM02YCV133
02Y Update Model Structural Fdns & Issue Dwgs - IFC
25-Mar-26
27-Dec-26
—
11%
EM03CMD229
03C Vessel Steel Release IFC (MD411 2203-F, 2204-F)
26-Mar-26
27-Dec-26
—
11%
EM03FMD229
03F Vessel Steel Release IFC (MD411, 2006-F)
26-Mar-26
27-Dec-26
—
11%
PK020IC210
020 Control Valves - Fabricate/Exworks
27-Mar-26
27-Dec-26
—
10%
WO010C0100
010 Concrete & Excavation
27-Mar-26
04-May-27
149.0d
7%
PK010IC210
010 Control Valves - Fabricate/Exworks
28-Mar-26
27-Dec-26
—
10%
PK030IC210
030 Control Valves - Fabricate/Exworks
28-Mar-26
27-Dec-26
—
10%
CO02JC0150
02J Form, Pour, Strip Fnd - 104-D2 (Low Temp Shift Converter)
30-Mar-26
27-Dec-26
—
9%
CO02JC0160
02J Form, Pour, Strip Fnd - 104-D1 (High Temp Shift Converter)
30-Mar-26
27-Dec-26
—
9%
CO01DC0150
01D Form, Pour, Strip Fnd - 2101-U (Cooling Tower)
31-Mar-26
27-Dec-26
—
9%
EK020FP460
FP Electrical Area Classification OSBL - IFC
31-Mar-26
27-Dec-26
—
9%
EM000ELEH2
01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC
31-Mar-26
27-Dec-26
—
9%
EM02HCV164
02H Update Model Major Eq. Fdns & Issue Dwgs-IFC
31-Mar-26
27-Dec-26
—
9%
PK01DMUV07
01D MU322 2210-L,2211-L - Piping Prod. V. Data
31-Mar-26
27-Dec-26
—
9%
PK01DMUV09
01D MU322 2210-L,2211-L - E&I Prod. V. Data
31-Mar-26
27-Dec-26
—
9%
CO02JC0110
02J Form, Pour, Strip Fnds - Major Fnds Gen'l
01-Apr-26
27-Dec-26
—
9%
EK000I1122
020 Venturis - Purchase ERW
01-Apr-26
27-Dec-26
—
9%
EK000I623A
Develop / Issue Purchase ERW -Multi-Point Thermocouples - ISBL
01-Apr-26
27-Dec-26
—
9%
EK000MU25E
02G MU225 Prepare & Issue Purchase ERW
01-Apr-26
27-Dec-26
—
9%
EK010I1151
Annubars - Purchase ERW
01-Apr-26
27-Dec-26
—
9%
EK02AIC120
02A Instrument Detail Model / Review
01-Apr-26
27-Dec-26
—
9%
EK030I623A
Develop / Issue Purchase ERW -Multi-Point Thermocouples - OSBL
01-Apr-26
27-Dec-26
—
9%
EM010IC123
UNIT 01 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
—
9%
EM01BMD229
01B Vessel Steel Release IFC
01-Apr-26
27-Dec-26
—
9%
EM020IC124
UNIT 02 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
—
9%
EM020IC128
Instrument Wiring Diagrams - IFC
01-Apr-26
27-Dec-26
—
9%
EM030IC125
UNIT 03 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
—
9%
EM050IC130
05B Instr. Location Plans - IFC
01-Apr-26
16-Jan-27
166.0d
8%
PK000ML42S
ML420 - Marshaling CARTRIDGE FILTERS
01-Apr-26
27-Dec-26
—
9%
PK02HMB50
02H MB692 101-BL2 - Piping Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK02HMB51
02H MB692 101-BL2 - Civil Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK02HMB52
02H MB692 101-BL2 - E&I Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK05AMB46
05A MB710 2202-B/BL - Piping Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK05AMB47
05A MB710 2202-B/BL - Civil Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK05AMB48
05A MB710 2202-B/BL - E&I Prod. V. Data
01-Apr-26
27-Dec-26
—
9%
PK000PIA1H
Bulk Piping A/G & U/G - Transport / Delivery (First CS,SS,U/G)
01-Apr-26
27-Dec-26
—
9%
PK000MB61L
Marshaling of 101-B Burners MB610
02-Apr-26
27-Dec-26
—
8%
PK000MU32K
01D MU322 - Fabricate/PO Promise COOLING WTR FILTER & CLARIFIER
02-Apr-26
27-Dec-26
—
8%
PK000ML90K
ML900 - Fabricate/PO Promise Evap. Pond Spray Nzl.
02-Apr-26
27-Dec-26
—
8%
PK01AMLV01
01A ML900 2408-LA,LB,LC,LD - Piping Prod. V. Data
02-Apr-26
27-Dec-26
—
8%
PK01AMLV02
01A ML900 2408-LA,LB,LC,LD - Civil Prod. V. Data
02-Apr-26
27-Dec-26
—
8%
PK01AMLV03
01A ML900 2408-LA,LB,LC,LD - E&I Prod. V. Data
02-Apr-26
27-Dec-26
—
8%
CO01GA0115
01G Erect Control Building (Columns & Parapet Only)
03-Apr-26
27-Dec-26
—
8%
CO02LC0150
02L Form, Pour, Strip Fnd - 101-E (CO2 Absorber)
03-Apr-26
27-Dec-26
—
8%
CO02MC0110
02M Form, Pour, Strip Fnds - Major Fnds Gen'l
03-Apr-26
27-Dec-26
—
8%
CO02MC0140
02M Form Pour Strip Fnds - Structure
03-Apr-26
27-Dec-26
—
8%
EK010E008D
540-SB Admin. Area Pwr Supply - Tech Evaluation
03-Apr-26
27-Dec-26
—
8%
EM01YCV122
01Y Update Model S/S Piperack & Issue Dwgs - IFC
03-Apr-26
27-Dec-26
—
8%
CO02KC0150
02K Form, Pour, Strip Fnd - 114-F (Benfield Solution Tank)
04-Apr-26
27-Dec-26
—
7%
EK020EL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK020EL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK05BEL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK05BEL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EM01UPICWG
01U U/G Plan Dwgs Issue IFC
04-Apr-26
27-Dec-26
—
7%
CO03DC0110
03D Form, Pour, Strip Fnds - 2002-F (Demin Water Tank)
06-Apr-26
27-Dec-26
—
7%
WO030C0100
030 Concrete & Excavation
06-Apr-26
19-Mar-27
229.0d
5%
PK000E00C
UPS System - Receive Bids
07-Apr-26
27-Dec-26
—
6%
EK000I621A
Develop / Issue Purchase ERW - Temperature Elements - ISBL
08-Apr-26
27-Dec-26
—
6%
EK030I621A
Develop / Issue Purchase ERW - Temperature Elements - OSBL
08-Apr-26
27-Dec-26
—
6%
CO02BC0110
02B Form, Pour, Strip Fnds - Major Fnds
09-Apr-26
27-Dec-26
—
6%
PK000MC61F
MC610 - Marshaling DBL PIPE EXCH 161-C
10-Apr-26
27-Dec-26
—
5%
EM03CCV126
03C Conceptual Misc. Steel Design/ Model
11-Apr-26
27-Dec-26
—
5%
EM02CCV128
02C Update Model Structural Fdns & Issue Dwgs - IFC
11-Apr-26
27-Dec-26
—
5%
EM02ECV128
02E Update Model Structural Fdns & Issue Dwgs - IFC
14-Apr-26
27-Dec-26
—
5%
CO010K0120
010 Construct Perimeter Roads
15-Apr-26
28-Dec-26
—
5%
CO02AC0110
02A Form, Pour, Strip Fnds - Major Fnds
15-Apr-26
09-Mar-27
189.0d
5%
EM02DCV126
02D Conceptual Misc. Steel Design/ Model
15-Apr-26
27-Dec-26
—
5%
EM02DCV164
02D Update Model Major Eq. Fdns & Issue Dwgs-IFC
15-Apr-26
27-Dec-26
—
5%
EM02UPI200
02U Issue U/G Material Final Release
15-Apr-26
27-Dec-26
—
5%
EM05UPI191
05U U/G Plan Dwgs IFC
15-Apr-26
27-Dec-26
—
5%
PK000I444D
Vendor Update Pricing - Shelters/ Analyzers
15-Apr-26
27-Dec-26
—
5%
PK000MB83S
MB630 - Marshaling 101-B Air Preheater
15-Apr-26
27-Dec-26
—
5%
EM02DCV166
02D Conceptual Misc. Foundations Design/ Model
15-Apr-26
27-Dec-26
—
5%
PK000MU61S
MU611 - Marshaling 2101-U, 2101-UJA Thru UJG CW TWR & Fans
15-Apr-26
27-Dec-26
—
5%
PK000MU61U
MU611 - Marshaling 2101-UJA Thru UJGM CW Motors
15-Apr-26
27-Dec-26
—
5%
PK000I3521
SIS - Vendor Provides Software & Workstations
16-Apr-26
27-Dec-26
—
5%
PK010I1210
Vortex Meters - Fabricate/Exworks
16-Apr-26
27-Dec-26
—
5%
EM02DCV128
02D Update Model Structural Fdns & Issue Dwgs - IFC
16-Apr-26
27-Dec-26
—
5%
EM02NPI143
02N OP's & Service Model Review Comment Resolution
16-Apr-26
27-Dec-26
—
5%
EM03CCV166
03C Conceptual Misc. Foundations Design/ Model
16-Apr-26
27-Dec-26
—
5%
EM03YCV120
03Y Design & Model Major Structural Steel
17-Apr-26
27-Dec-26
—
5%
EM01UPI200
01U Issue U/G Material Final Release 90%
17-Apr-26
27-Dec-26
—
5%
EK000I3523
SIS - Software Programming by KBR
18-Apr-26
27-Dec-26
—
5%
EM020ELEK2
02 Develop & Issue Power Plans - IFC
18-Apr-26
27-Dec-26
—
5%
EK000I611A
Develop / Issue Purchase ERW - Pressure Gauges - ISBL
19-Apr-26
27-Dec-26
—
5%
CO01BC0160
01B Form, Pour, Strip Fnd - 2001-FB (Water Storage Tank)
20-Apr-26
27-Dec-26
—
5%
CO02HC0150
02H Form, Pour, Strip Fnd - 103-D (Secondary Reformer)
21-Apr-26
27-Dec-26
—
5%
CO03CC0110
03C Form, Pour, Strip Fnds - Major Fnds
21-Apr-26
27-Dec-26
—
5%
EM02GPI021
02G Model Review Comment Resolution
21-Apr-26
27-Dec-26
—
5%
EM03UPI200
03U Issue U/G Material Final Release (90%)
21-Apr-26
27-Dec-26
—
5%
EM05BEL120
05B Electrical Conceptual Layouts
21-Apr-26
27-Dec-26
—
5%
EK02FIC120
02F Instrument Detail Model / Review
22-Apr-26
27-Dec-26
—
5%
EK030I611A
Develop / Issue Purchase ERW - Pressure Gauges - OSBL
22-Apr-26
27-Dec-26
—
5%
EK05ACV100
05A Soils Investigation - Golder Review & Report
22-Apr-26
27-Dec-26
—
5%
EK05AIC120
05A Instrument Detail Model / Review
22-Apr-26
27-Dec-26
—
5%
EM02JCV126
02J Misc. Steel Design/ Model
22-Apr-26
27-Dec-26
—
5%
EM03UPI190
03U U/G Plan Dwgs Issue IFC
22-Apr-26
27-Dec-26
—
5%
EM03UPIASG
03U Iso Issue IFC - Other HDPE (AS & NA)
22-Apr-26
27-Dec-26
—
5%
EM03UPIOSG
03U Iso Issue IFC - Metalic Piping (OS)
22-Apr-26
27-Dec-26
—
5%
PK000I3520
SIS - Vendor Update Pricing / Quote
22-Apr-26
27-Dec-26
—
5%
PK010I1100
010 Orific Plates - Fabricate/Exworks
22-Apr-26
27-Dec-26
—
5%
EK02GIC120
02G Instrument Detail Model / Review
23-Apr-26
27-Dec-26
—
5%
EK000MJ38C
Prepare & Issue Purchase ERW - MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38M
Final Negotiate/Interim Award - MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38R
Issue Formal P.O. for MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38T
Recv. Planning V. Data MJ308
23-Apr-26
27-Dec-26
—
5%
PK000MJ38U
MJ308 - Fabricate/PO Promisse ISBL ANSI/API PUMPS
23-Apr-26
10-Jan-27
198.0d
5%
PK01AMJV01
01A MJ308 2408-JA/JB - Piping Prod. V. Data
23-Apr-26
27-Dec-26
—
5%
PK01AMJV02
01A MJ308 2408-JA/JB - Civil Prod. V. Data
23-Apr-26
27-Dec-26
—
5%
PK01AMJV03
01A MJ308 2408-JA/JB - E&I Prod. V. Data
23-Apr-26
27-Dec-26
—
5%
EM03CPI141
03C Detail OP's & Services Model Review Mtg
24-Apr-26
27-Dec-26
—
5%
EM02DPI141
02D Detail OP's & Services Model Review Mtg
24-Apr-26
27-Dec-26
—
5%
PK000MU35S
MU350 - Marshaling 101-U DEAERATOR
24-Apr-26
27-Dec-26
—
5%
WK000U4100
000 U/G Pipe Spool Fabrication
10-Aug-26
07-Dec-26
—
0%
CO000M0110
Mobilize Field Fab Tank Contractor
27-Dec-26
27-Dec-26
—
0%
CO01BC0110
01B Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
—
0%
CO01BC0150
01B Form, Pour, Strip Fnd - 2001-FA (Water Storage Tank)
27-Dec-26
27-Dec-26
—
0%
CO01DC0140
01D Form Pour Strip Fnds - Sleepers
27-Dec-26
27-Dec-26
—
0%
CO01YC0140
01Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
—
0%
CO02CC0160
02C Form, Pour, Strip Fnd - 103-JTC
27-Dec-26
27-Dec-26
—
0%
CO02CM0140
02C Set - 103-JTC Surface Condenser
27-Dec-26
27-Dec-26
—
0%
CO02EC0110
02E Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
—
0%
CO02EC0140
02E Form Pour Strip Fnds - Structure
27-Dec-26
27-Dec-26
—
0%
CO02GC0160
02G Form, Pour, Strip Fnd - 102-J Fd Gas Compr. & Aux.
27-Dec-26
27-Dec-26
—
0%
CO02HC0110
02H Form, Pour, Strip Fnds - 101B (Primary Reformer)
27-Dec-26
27-Dec-26
—
0%
CO02HC0160
02H Form, Pour, Strip Fnd - 156-F (Steam Blowdown Drum)
27-Dec-26
27-Dec-26
—
0%
CO02HM0140
02H Set - 156-F Steam Blowdown Drum
27-Dec-26
27-Dec-26
—
0%
CO02LC0160
02L Form, Pour, Strip Fnd - 102-E (CO2 Stripper)
27-Dec-26
27-Dec-26
—
0%
CO02MC0150
02M Form, Pour, Strip Fnd - 105-D (Ammonia Synthesis Converter)
27-Dec-26
27-Dec-26
—
0%
CO02NC0110
02N Form, Pour, Strip Fnds - Major Fnds
27-Dec-26
27-Dec-26
—
0%
CO02YC0140
02Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
—
0%
CO03CM0110
03C Set Static Equipment - 2203/4-F Caustic, Sulfuric Acid Tanks
27-Dec-26
27-Dec-26
—
0%
CO03DC0150
03D Form, Pour, Strip Fnd - 2002J/JA (Fresh Cooling Water Pumps)
27-Dec-26
27-Dec-26
—
0%
CO03FC0110
03F Form, Pour, Strip Fnds - Package Boiler
27-Dec-26
27-Dec-26
—
0%
CO05AC0170
05A Install Test Piles
27-Dec-26
27-Dec-26
—
0%
CO05AMF200
05A Final Tank Design Loads Submitted by DSD
27-Dec-26
27-Dec-26
—
0%
EK000CV146
Receive Site Survey Data Areas 04 & 05
27-Dec-26
27-Dec-26
—
0%
EK000E004D
UPS System - Tech Evaluation
27-Dec-26
27-Dec-26
—
0%
EK000ELEG0
Electrical Heat Tracing - ERW Package
27-Dec-26
27-Dec-26
—
0%
EK000FP034
FP ISBL Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
—
0%
EK000FP060
FP Overall Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
—
0%
EK000FP065
FP Overall Firewater P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
—
0%
EK000GE030
Production Check Estimate
27-Dec-26
27-Dec-26
—
0%
EK000I3522
SIS - Final Tech Evaluation for Purchase
27-Dec-26
27-Dec-26
—
0%
EK000I352M
SIS - Review / Approve V. Data
27-Dec-26
27-Dec-26
—
0%
EK000I354M
ITCC - Review / Approve V. Data
27-Dec-26
27-Dec-26
—
0%
EK000I444E
Final Tech Evaluation - Shelters/ Analyzers
27-Dec-26
27-Dec-26
—
0%
EK000I444G
Review / Approve V. Data - Shelters/ Analyzers
27-Dec-26
27-Dec-26
—
0%
EK000I612A
Develop / Issue Purchase ERW - Differential Pressure Gauges
27-Dec-26
27-Dec-26
—
0%
EK000MF32D
05A MF312 2105-F Water Tank - Fdn Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EK000YA828
(EP-30) Vendor Acceptance of Commitment for Electrical 20 MVA Transformers
27-Dec-26
27-Dec-26
—
0%
EK000YA829
(EP-31) Vendor Acceptance of Commitment for Substation
27-Dec-26
27-Dec-26
—
0%
EK000YA832
(EP-32) Issue OSBL (Units01/03) found./UG pipe work package
27-Dec-26
27-Dec-26
—
0%
EK000YA833
(EP-33) Issue > 90% ISBL Civil Foundations
27-Dec-26
27-Dec-26
—
0%
EK000YA836
(PC-07) Issue 101-B -Primary Reformer Erection Drawings
27-Dec-26
27-Dec-26
—
0%
EK000YA839
(EP-35) Issue >90% OSBL P&ID's For Construction (IFC)
27-Dec-26
27-Dec-26
—
0%
EK000YA841
(EP-29) Issue OSBL Plot Plan for Construction (IFC)
27-Dec-26
27-Dec-26
—
0%
EK000YA848
(EP-37) Issue >90% ISBL Instrument Location Plans/Wire Lists for Construction (IFC)
27-Dec-26
27-Dec-26
—
0%
EK000YA858
(EP-38) Deliver Syn Gas Compressor, 103-J, and Ammonia Refrig Compressor, 105-J, to site
27-Dec-26
27-Dec-26
—
0%
EK000YA888
(TLA-02) Second TLA Payment
27-Dec-26
27-Dec-26
—
0%
EK010FP040
FP Firewater Pump P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
—
0%
EK01AIC120
01A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01API144
01A OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01BIC120
01B Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01BPI144
01B OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01CIC120
01C Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01CPI143
01C OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01DIC120
01D Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01DPI144
01D OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01HIC120
01H Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01JIC120
01J Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK01JPI050
01J Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01JPI143
01J Op's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK01YPI143
01Y OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK020EL121
Overall One line Diagrams - IFD
27-Dec-26
27-Dec-26
—
0%
EK020EL210
Production Check Estimate - Electrical
27-Dec-26
27-Dec-26
—
0%
EK020ELEC3
Protective Device Coordination
27-Dec-26
27-Dec-26
—
0%
EK020ELEG5
Cathodic Protection - Design & Specs Package (By Consultant)
27-Dec-26
27-Dec-26
—
0%
EK020ELEM1
Cable & Raceway Schedule - IFC
27-Dec-26
27-Dec-26
—
0%
EK020ELG70
Construction & Operation Interfac.
27-Dec-26
27-Dec-26
—
0%
EK020IC133
Field Bus J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
—
0%
EK02API144
02A OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02CPI144
02C OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02DPI143
02D OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02EPI143
02E OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02FPI143
02F OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02GPI050
02G Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02HPI144
02H OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02JPI144
02J OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02KPI143
02K OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02LPI143
02L OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02MPI143
02M OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02NPI144
02N OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK02YPI144
02Y OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03AIC120
03A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03API050
03A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03API143
03A OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03BIC120
03B Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03BPI050
03B Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03BPI143
03B OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03CPI143
03C OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03DIC120
03D Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03DPI145
03D OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03EIC120
03E Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03EPI050
03E Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03EPI144
03E OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03FIC120
03F Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03FPI050
03F Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03FPI144
03F OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03YIC120
03Y Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK03YPI050
03Y Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK03YPI144
03Y OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK04AIC120
04A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
—
0%
EK05ACV110
05A Update Model & Issue Fnd Dwgs-IFC (Ammonia Tanks)
27-Dec-26
27-Dec-26
—
0%
EK05AMD100
05A Review & Select Ammonia Tank Design
27-Dec-26
27-Dec-26
—
0%
EK05API050
05A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK05API144
05A OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK05BPI035
05B Plot Plan
27-Dec-26
27-Dec-26
—
0%
EK100ELEK2
01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A
27-Dec-26
27-Dec-26
—
0%
EK200ELEK2
01H Develop & Issue Cable Ladder Plans - IFC
27-Dec-26
27-Dec-26
—
0%
EK2QPI144
02Q OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EM000ELEJ2
01,03,05 Develop & Issue Lighting Plans - IFC
27-Dec-26
27-Dec-26
—
0%
EM000ELEK2
01,03,04,05 Develop & Issue Power Plans - IFC
27-Dec-26
27-Dec-26
—
0%
EM000ELEL2
01,03,04,05 Electrical Routing Plans
27-Dec-26
27-Dec-26
—
0%
EM000ELEM2
Dev/Issue Elect Cable/Raceway Sched IFC
27-Dec-26
27-Dec-26
—
0%
EM01API132
01A Planning Release
27-Dec-26
27-Dec-26
—
0%
EM01API134
01A Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM01API135
01A A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM01API136
01A IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM01API138
01A Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM01API141
01A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM01API143
01A OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM01ASY172
01A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM01ASY272
01A P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM01BCV123
01B Update Model S/S Sleepers & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01BCV126
01B Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM01BCV127
01B Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01BCV133
01B Update Model S/S Sleeper Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01BCV164
01B Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM01BCV166
01B Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM01BCV167
01B Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01BPI134
01B Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM01BPI135
01B A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM01BPI136
01B IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM01BPI138
01B Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM01BPI141
01B Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM01BPI143
01B OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM01BSY172
01B P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM01BSY272
01B P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM01CCV164
01C Update Model Major Eq. Fdns & Issue Dwgs-IFC (Excluding EDR)
27-Dec-26
27-Dec-26
—
0%
EM01CCV180
01C Design & Model Major Eq. Fdns (Including EDR)
27-Dec-26
27-Dec-26
—
0%
EM01CCV190
01C Update Model Major Eq. Fdns & Issue Dwgs-IFC (Including EDR)
27-Dec-26
27-Dec-26
—
0%
EM01CPI132
01C Planning Release
27-Dec-26
27-Dec-26
—
0%
EM01CPI134
01C Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM01CPI135
01C A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM01CPI136
01C IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM01CPI138
01C Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM01CPI141
01C Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM01CPI142
01C OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM01CSY172
01C P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM01CSY272
01C P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM01DCV122
01D Update Model S/S Sleepers & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01DCV126
01D Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM01DCV127
01D Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01DCV133
01D Update Model S/S Sleeper Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01DCV166
01D Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM01DCV167
01D Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01DPI134
01D Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM01DPI135
01D A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM01DPI136
01D IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM01DPI138
01D Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM01DPI141
01D Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM01DPI143
01D OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM01DSY172
01D P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM01DSY272
01D P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM01HCV125
01H Design & Model Substation Fdns
27-Dec-26
27-Dec-26
—
0%
EM01HCV126
01H Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM01HCV127
01H Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01HCV128
01H Update Model Substation Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01HCV160
01H Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
—
0%
EM01HCV164
01H Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM01HCV166
01H Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM01HCV167
01H Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01JCV122
01J Update Model Metering Enclosure & Issue Dwgs (Concrete Wall) - IFC
27-Dec-26
27-Dec-26
—
0%
EM01JCV133
01J Update Model Metering Enclosure Fdns & Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM01JPI130
01J Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM01JPI132
01J Planning Release
27-Dec-26
27-Dec-26
—
0%
EM01JPI133
01J IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM01JPI134
01J Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM01JPI135
01J A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM01JPI136
01J IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM01JPI138
01J Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM01JPI140
01J Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM01JPI141
01J Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM01JPI142
01J OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM01JSY272
01J P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM01YCV133
01Y Update Model Piperack Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM01YPI135
01Y A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM01YPI136
01Y IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM01YPI141
01Y Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM01YPI142
01Y OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM01YSY272
01Y P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM020ELEJ2
02 Develop & Issue Lighting Plans - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC127
Instrument Installation Details (10%) - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC129
Instrument Loop Diagrams - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC132
Traditional J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC134
DCS Marshalling Report - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC135
SIS Termination Report - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC136
ITCC Termination Report - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC137
Miscellaneous Wiring Report - IFC
27-Dec-26
27-Dec-26
—
0%
EM02ACV126
02A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02ACV127
02A Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02ACV166
02A Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02ACV167
02A Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02API135
02A A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02API136
02A IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02API138
02A Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02API142
02A Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02API143
02A OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02ASY172
02A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02ASY272
02A P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02CCV122
02C Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02CCV126
02C Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02CCV127
02C Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02CCV164
02C Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM02CCV166
02C Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02CCV167
02C Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02CPI135
02C A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02CPI136
02C IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02CPI138
02C Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02CPI141
02C Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02CPI143
02C OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02CSY172
02C P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02CSY272
02C P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02DCV122
02D Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02DCV127
02D Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02DCV167
02D Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02DPI135
02D A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02DPI136
02D IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02DPI138
02D Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02DPI142
02D OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02DSY272
02D P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02ECV126
02E Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02ECV127
02E Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02ECV166
02E Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02ECV167
02E Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02EPI135
02E A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02EPI136
02E IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02EPI138
02E Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02EPI141
02E Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02EPI142
02E OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02ESY172
02E P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02ESY272
02E P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02FCV126
02F Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02FCV127
02F Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02FCV164
02F Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM02FCV166
02F Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02FCV167
02F Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02FPI135
02F A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02FPI136
02F IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02FPI138
02F Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02FPI141
02F Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02FPI142
02F OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02FSY172
02F P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02FSY272
02F P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02GCV164
02G Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM02GPI132
02G Planning Release
27-Dec-26
27-Dec-26
—
0%
EM02GPI133
02G IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM02GPI134
02G Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM02GPI141
02G Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02GSY172
02G P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02HCV122
02H Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02HCV126
02H Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02HCV127
02H Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02HCV128
02H Update Model Structural Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02HCV166
02H Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02HCV167
02H Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02HPI135
02H A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02HPI136
02H IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02HPI138
02H Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02HPI141
02H Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02HPI143
02H OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02HSY172
02H P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02HSY272
02H P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02JCV122
02J Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02JCV127
02J Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02JCV166
02J Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02JCV167
02J Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02JPI135
02J A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02JPI136
02J IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02JPI138
02J Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02JPI141
02J Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02JPI143
02J OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02JSY172
02J P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02JSY272
02J P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02KCV126
02K Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02KCV164
02K Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM02KCV166
02K Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02KPI134
02K Plant Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM02KPI135
02K A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02KPI136
02K IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02KPI138
02K Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02KPI141
02K Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02KPI142
02K OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02KSY172
02K P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02KSY272
02K P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02LCV122
02L Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02LCV126
02L Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02LCV127
02L Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02LCV128
02L Update Model Structural Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02LCV166
02L Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02LCV167
02L Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02LPI135
02L A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02LPI136
02L IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02LPI138
02L Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02LPI141
02L Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02LPI142
02L OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02LSY172
02L P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02LSY272
02L P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02MCV122
02M Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02MCV126
02M Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02MCV127
02M Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02MCV128
02M Update Model Structural Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02MCV166
02M Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM02MCV167
02M Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM02MPI135
02M A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02MPI136
02M IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02MPI138
02M Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02MPI141
02M Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02MPI142
02M OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02MSY172
02M P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02MSY272
02M P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02NPI135
02N A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02NPI136
02N IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02NPI138
02N Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02NSY272
02N P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02PSY272
02P P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02QPI135
02Q A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02QPI136
02Q IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02QPI138
02Q Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02QPI142
02Q Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02QPI143
02Q OP's & Service Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02QSY172
02Q P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02QSY272
02Q P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM02YCV123
02Y Struct Steel Issue Dwgs - IFC Silencer Area
27-Dec-26
27-Dec-26
—
0%
EM02YPI135
02Y A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02YPI136
02Y IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02YPI138
02Y Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02YPI142
02Y Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02YPI143
02Y OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02YSY172
02Y P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM02YSY272
02Y P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM03ACV126
03A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03ACV127
03A Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03ACV160
03A Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
—
0%
EM03ACV164
03A Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM03ACV166
03A Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03ACV167
03A Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03API130
03A Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03API132
03A Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03API133
03A IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03API134
03A Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03API135
03A A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03API136
03A IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03API138
03A Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03API140
03A Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03API141
03A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03API142
03A OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03ASY172
03A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM03ASY272
03A P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM03BCV112
03B Update Model Sumps & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM03BCV126
03B Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03BCV127
03B Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03BCV166
03B Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03BCV167
03B Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03BMD228
03B Clips Release IFC
27-Dec-26
27-Dec-26
—
0%
EM03BMD229
03B Vessel Steel Release IFC
27-Dec-26
27-Dec-26
—
0%
EM03BPI130
03B Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03BPI132
03B Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03BPI133
03B IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03BPI134
03B Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03BPI135
03B A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03BPI136
03B IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03BPI138
03B Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03BPI140
03B Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03BPI141
03B Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03BPI142
03B OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03BSY172
03B P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM03BSY272
03B P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM03CCV127
03C Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03CCV167
03C Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03CPI135
03C A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03CPI136
03C IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03CPI142
03C OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03CSY272
03C P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM03DCV126
03D Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03DCV127
03D Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03DCV164
03D Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM03DCV166
03D Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03DCV167
03D Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03DPI134
03D Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03DPI135
03D A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03DPI136
03D IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03DPI138
03D Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03DPI141
03D Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03DPI143
03D OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM03DSY172
03D P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM03DSY272
03D P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM03ECV112
03E Update Model Containment Area & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM03ECV126
03E Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03ECV127
03E Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03ECV160
03E Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
—
0%
EM03ECV164
03E Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM03ECV166
03E Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03ECV167
03E Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03EPI123
03E Plant Layout Nozzle Release
27-Dec-26
27-Dec-26
—
0%
EM03EPI130
03E Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03EPI132
03E Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03EPI133
03E IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03EPI134
03E Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03EPI135
03E A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03EPI136
03E IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03EPI138
03E Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03EPI141
03E Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03EPI142
03E Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03EPI143
03E OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03ESY172
03E P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM03ESY272
03E P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM03FCV126
03F Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03FCV127
03F Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03FCV164
03F Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
—
0%
EM03FCV166
03F Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM03FCV167
03F Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03FPI130
03F Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03FPI132
03F Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03FPI133
03F IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03FPI134
03F Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03FPI135
03F A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03FPI136
03F IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03FPI138
03F Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03FPI141
03F Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03FPI142
03F Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03FPI143
03F OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03FPI200
03F Equipment Location Plans
27-Dec-26
27-Dec-26
—
0%
EM03FSY172
03F P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM03FSY272
03F P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM03YCV122
03Y Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03YCV133
03Y Update Model Piperack Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM03YPI021
03Y Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03YPI130
03Y Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03YPI132
03Y Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03YPI133
03Y IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03YPI134
03Y Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03YPI135
03Y A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03YPI136
03Y IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03YPI138
03Y Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03YPI141
03Y Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03YPI143
03Y OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM03YSY172
03Y P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM03YSY272
03Y P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
—
0%
EM04API120
04A Plant Layout Model
27-Dec-26
27-Dec-26
—
0%
EM04API134
04A Plant Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM04API138
04A Design / Issue Pipe & Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM04API200
04A Issue U/G Material Final Release
27-Dec-26
27-Dec-26
—
0%
EM05ACV126
05A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM05ACV166
05A Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM05AMD228
05A Clips Release IFC
27-Dec-26
27-Dec-26
—
0%
EM05AMD229
05A Vessel Steel Release IFC
27-Dec-26
27-Dec-26
—
0%
EM05API130
05A Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM05API132
05A Planning Release
27-Dec-26
27-Dec-26
—
0%
EM05API133
05A IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM05API134
05A Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM05API136
05A IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM05API140
05A Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM05API142
05A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM05API143
05A OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM05BPI120
05B Plant Layout Model
27-Dec-26
27-Dec-26
—
0%
EM05BPI130
05B Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM05BSY172
05B P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EM05UPI200
05U Issue U/G Material Final Release
27-Dec-26
27-Dec-26
—
0%
EM5ASY172
05A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
—
0%
EMO2YCV124
02Y Structl Fdns Issue Dwgs - IFC Silencer Area
27-Dec-26
27-Dec-26
—
0%
PK0003525
SIS - Ship to DCS Shop/ Setup
27-Dec-26
27-Dec-26
—
0%
PK0003526
SIS - Integrated FAT
27-Dec-26
27-Dec-26
—
0%
PK000E001E
Sub Stations - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
—
0%
PK000E001G
Sub Stations - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK000E001J
Sub Stations - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E001K
Sub Stations - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK000E001M
Sub Stations - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E002G
Transformer - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK000E002J
Transformer - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E002K
Transformer - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK000E002M
Transformer - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E004E
UPS System - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
—
0%
PK000E004G
UPS System - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK000E004J
UPS System - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK000E004K
UPS System - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK000E004M
UPS System - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK000I1103
020 Orific Plates - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK000I1105
020 Orific Plates - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK000I1161
020 Wedge Flow Meters - Fabricate/Exworks
27-Dec-26
27-Dec-26
—
0%
PK000I1162
020 Wedge Flow Meters - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK000I1163
020 Wedge Flow Meters - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK000I1221
Coriolis Meters - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK000I1222
Coriolis Meters - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK000I1270
Fabricate/Exworks Magnetic Flow Meters
27-Dec-26
27-Dec-26
—
0%
PK000I1271
Transport & Deliver Magnetic Flow Meters
27-Dec-26
27-Dec-26
—
0%
PK000I1272
Recv on Site Magnetic Flow Meters
27-Dec-26
27-Dec-26
—
0%
PK000I3522
SIS - FAT Test
27-Dec-26
27-Dec-26
—
0%
PK000I3523
SIS - Cleanup / Changes
27-Dec-26
27-Dec-26
—
0%
PK000I3542
ITCC - Software Programming by Vendor
27-Dec-26
27-Dec-26
—
0%
PK000I3543
ITCC - FAT Test
27-Dec-26
27-Dec-26
—
0%
PK000I3544
ITCC - Cleanup / Changes
27-Dec-26
27-Dec-26
—
0%
PK000I354P
ITCC - Ship to DCS Shop/ Setup
27-Dec-26
27-Dec-26
—
0%
PK000I354Q
ITCC - Integrated FAT
27-Dec-26
27-Dec-26
—
0%
PK000I444H
Fabricate - Shelters/ Analyzers
27-Dec-26
27-Dec-26
—
0%
PK000I611H
Fabricate / Exworks - Pressure Gauges - ISBL
27-Dec-26
27-Dec-26
—
0%
PK000I616H
Fabricate / Exworks - Steam Drum Lvl Gauges
27-Dec-26
27-Dec-26
—
0%
PK000I616L
Recv at Site - Steam Drum Lvl Gauges
27-Dec-26
27-Dec-26
—
0%
PK000I616N
Transport & Deliver - Steam Drum Lvl Gauges
27-Dec-26
27-Dec-26
—
0%
PK000I617H
Fabricate / Exworks - Magnetic Lvl Gauges
27-Dec-26
27-Dec-26
—
0%
PK000IC352
DCS - FAT Test
27-Dec-26
27-Dec-26
—
0%
PK000IC353
DCS - Cleanup / Changes
27-Dec-26
27-Dec-26
—
0%
PK000IC355
DCS - ITCC / SIS / DCS - Integrated FAT
27-Dec-26
27-Dec-26
—
0%
PK000IC35M
DCS - Review / Approve V. Data
27-Dec-26
27-Dec-26
—
0%
PK000MB21O
Transport & Deliver of Equip. 101-B Siding
27-Dec-26
27-Dec-26
—
0%
PK000MB33O
MB333 - Transport/Customes Equip. 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB33S
MB333 - Marshaling Riser Transition 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB33Z
02H Recv. at Site - 101-B Riser Transition
27-Dec-26
27-Dec-26
—
0%
PK000MB34Z
Shop Recv.- 101-B Finned Convection Tubes & Pipe
27-Dec-26
27-Dec-26
—
0%
PK000MB41Z
Shop Recv. - 101-B Cast Tube Supports
27-Dec-26
27-Dec-26
—
0%
PK000MB42O
MB420 - Transport to Vendor 101-B Cast Peep Sites
27-Dec-26
27-Dec-26
—
0%
PK000MB61O
Transport & Deliver 101-B Burners
27-Dec-26
27-Dec-26
—
0%
PK000MB63O
MB630 - Transport/Customes 101-B Air Preheater
27-Dec-26
27-Dec-26
—
0%
PK000MB64O
MB640 - Transport/Customes 101-B Springs & Hangers
27-Dec-26
27-Dec-26
—
0%
PK000MB64S
MB640 - Marshaling 101-B Springs & Hangers
27-Dec-26
27-Dec-26
—
0%
PK000MB65O
MB622 - Transport/Customes 101-B Penthouse Circ Fans
27-Dec-26
27-Dec-26
—
0%
PK000MB65S
MB622 - Marshaling 101-B Penthouse Circ Fans
27-Dec-26
27-Dec-26
—
0%
PK000MB66O
MB660 - Transport/Customes 101-B Dampers & Air Doors
27-Dec-26
27-Dec-26
—
0%
PK000MB66S
MB660 - Marshaling 101-B Dampers & Air Doors
27-Dec-26
27-Dec-26
—
0%
PK000MB68O
MB692 - Transport/Customes 101-B Cat Vacuum Equip.
27-Dec-26
27-Dec-26
—
0%
PK000MB68S
MB692 - Marshaling 101-B Cat Vacuum Equip.
27-Dec-26
27-Dec-26
—
0%
PK000MB69O
MB691 - Transport/Customes of Equip. 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB69S
MB691 - Marshaling 101-B for MB691
27-Dec-26
27-Dec-26
—
0%
PK000MB81O
MB810 - Transport & Deliver of Equip. 101-B
27-Dec-26
27-Dec-26
—
0%
PK000MB81S
MB810 - Marshaling 102-B
27-Dec-26
27-Dec-26
—
0%
PK000MBP1C
MB221 - Marshaling 101-B Convection Modules
27-Dec-26
27-Dec-26
—
0%
PK000MBP1M
MB221 - Transport/Customes 101-B Radiant Steel Panels
27-Dec-26
27-Dec-26
—
0%
PK000MBP1T
MB221 - Fab/PO Promise 101-B Crossover Pipe
27-Dec-26
27-Dec-26
—
0%
PK000MBP1U
MB221 - Transport/Customes 101-B Radiant Harps
27-Dec-26
27-Dec-26
—
0%
PK000MBP1V
MB221 - Transport/Customes 101-B Convection Modules
27-Dec-26
27-Dec-26
—
0%
PK000MBP1X
MB221 - Transport/Customes 101-B Radiant Ducting
27-Dec-26
27-Dec-26
—
0%
PK000MBP1Y
MB221 - Transport/Customes 101-B Crossover
27-Dec-26
27-Dec-26
—
0%
PK000MBP2C
MB221 - Marshaling 101-B Crossover
27-Dec-26
27-Dec-26
—
0%
PK000MBP3C
MB221 - Marshaling 101-B Radiant Ducting
27-Dec-26
27-Dec-26
—
0%
PK000MBP3V
MB311 - Shop Recv - 101-B Crossover Tube & Pipe
27-Dec-26
27-Dec-26
—
0%
PK000MBP3W
MB311 - Shop Recv - 101-B Crossover Fittings
27-Dec-26
27-Dec-26
—
0%
PK000MBP4C
MB221 - Marshaling 101-B Radiant Coil/Harps
27-Dec-26
27-Dec-26
—
0%
PK000MBP4O
MB312 - Transport/Customes 101-B Radiant Cast Stringer Grids
27-Dec-26
27-Dec-26
—
0%
PK000MBP4S
MB312 - Transport/Customes 101-B Radiant Cast Tube/Riser/Manifold
27-Dec-26
27-Dec-26
—
0%
PK000MBP4T
MB312 - Shop Recv. 101-B Radiant Cast Stringer Grids
27-Dec-26
27-Dec-26
—
0%
PK000MBP4U
MB312 - Shop Recv. 101-B Radiant Cast Tube/Riser/Manifold
27-Dec-26
27-Dec-26
—
0%
PK000MBP5C
MB221 - Marshaling 101-B Radiant Steel Panels
27-Dec-26
27-Dec-26
—
0%
PK000MC21O
MC210 - Transport/Customes 110/115/124/128/130/133/134/160/167/173/174-C
27-Dec-26
27-Dec-26
—
0%
PK000MC21R
MC210 - Marshaling 127-C
27-Dec-26
27-Dec-26
—
0%
PK000MC21S
MC210 - Marshaling 110/115/124/128/130/133/134/160/167/173/174-C
27-Dec-26
27-Dec-26
—
0%
PK000MC21T
MC210 - Transport/Customes 127-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23B
MC230 - Marshaling 106-C & 109-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23C
MC230 - Transport/Customes 106-C & 109-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23O
MC230 - Transport/Customes 105/172/183-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23R
MC230 - Marshaling 111/114-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23S
MC230 - Marshaling 105/172/183-C
27-Dec-26
27-Dec-26
—
0%
PK000MC23T
MC230 - Transport/Customes 114-C
27-Dec-26
27-Dec-26
—
0%
PK000MC61O
MC610 - Transport/Customes DBL PIPE EXCH 188-CA
27-Dec-26
27-Dec-26
—
0%
PK000MC61Q
MC610 - Transport/Customes DBL PIPE EXCH 161-C
27-Dec-26
27-Dec-26
—
0%
PK000MC61S
MC610 - Marshaling DBL PIPE EXCH 188-CA
27-Dec-26
27-Dec-26
—
0%
PK000MD22B
MD202 - Marshaling TOWERS 104-E
27-Dec-26
27-Dec-26
—
0%
PK000MD22C
MD202 - Transport/Customes TOWERS 104-E
27-Dec-26
27-Dec-26
—
0%
PK000MD22O
MD202 - Transport/Customes TOWERS 103/105-E
27-Dec-26
27-Dec-26
—
0%
PK000MD22S
MD202 - Marshaling TOWERS 103/105-E
27-Dec-26
27-Dec-26
—
0%
PK000MD42A
MD402 -Marshaling 144-F
27-Dec-26
27-Dec-26
—
0%
PK000MD42B
MD402 - Transport/Customes 144-F
27-Dec-26
27-Dec-26
—
0%
PK000MD42R
MD402 - Transport/Customes 104-F
27-Dec-26
27-Dec-26
—
0%
PK000MD42T
MD402 -Marshaling 104-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44M
MD404 - Marshaling 107-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44N
MD404 - Transport/Customes 107-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44O
MD404 - Transport/Customes 109-F
27-Dec-26
27-Dec-26
—
0%
PK000MD44Q
02D Recv. at Site - 107-F Ammonia Letdown Drum
27-Dec-26
27-Dec-26
—
0%
PK000MD44S
MD404 - Marshaling 109-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45B
MD405 - Marshaling ISBL DRUMS - 115-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45C
MD405 - Transport/Customes ISBL DRUMS - 115-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45O
MD405 - Transport/Customes ISBL DRUMS - 156-F & 157-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45S
MD405 - Marshaling ISBL DRUMS - 156-F & 157-F
27-Dec-26
27-Dec-26
—
0%
PK000MD45T
MD405 - Transport/Customes ISBL DRUMS - 118-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46O
MD411 - Transport/Customes OSBL DRUMS - 2203-F & 2204-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46S
MD411 - Marshaling OSBL DRUMS - 2203-F & 2204-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46U
MD411 - Marshaling OSBL DRUMS - 2006-F
27-Dec-26
27-Dec-26
—
0%
PK000MD46V
MD411 - Transport/Customes OSBL DRUMS - 2006-F
27-Dec-26
27-Dec-26
—
0%
PK000MD47O
MD406 - Transport/DCustomes ISBL DRUMS
27-Dec-26
27-Dec-26
—
0%
PK000MD47S
MD406 - Marshaling ISBL DRUMS 103-F
27-Dec-26
27-Dec-26
—
0%
PK000MD51O
MD501 - Transport/Customes 107-D
27-Dec-26
27-Dec-26
—
0%
PK000MD51S
MD501 - Marshaling 107-D
27-Dec-26
27-Dec-26
—
0%
PK000MDR
MD405 - Marshaling ISBL DRUMS - 118-F
27-Dec-26
27-Dec-26
—
0%
PK000MJ21O
MJ202 - Transport/Customes 102/3/5-J
27-Dec-26
27-Dec-26
—
0%
PK000MJ21S
MJ202 - Marshaling 102/3/5-J
27-Dec-26
27-Dec-26
—
0%
PK000MJ37O
MJ340 - Transport/Customes METERING PUMPS
27-Dec-26
27-Dec-26
—
0%
PK000MJ37S
MJ340 - Marshaling METERING PUMPS
27-Dec-26
27-Dec-26
—
0%
PK000MJ71I
Eval Bids & Issue Recmd MJ731
27-Dec-26
27-Dec-26
—
0%
PK000MJ71J
Final Negotiate/Interim Award - MJ731
27-Dec-26
27-Dec-26
—
0%
PK000MJ71P
Issue Formal P.O. for MJ731
27-Dec-26
27-Dec-26
—
0%
PK000MJ75O
MJ750 - Transport/Customes SURFACE CONDENSORS
27-Dec-26
27-Dec-26
—
0%
PK000MJ75S
MJ750 - Marshaling SURFACE CONDENSORS
27-Dec-26
27-Dec-26
—
0%
PK000ML33O
ML330 - Transport/Customes 2101-L
27-Dec-26
27-Dec-26
—
0%
PK000ML33S
ML330 - Marshaling 2101-L
27-Dec-26
27-Dec-26
—
0%
PK000ML42O
ML420 - Transpor/Customes CARTRIDGE FILTERS
27-Dec-26
27-Dec-26
—
0%
PK000ML43O
ML430 - Transport/Customes 110-L BENFIELD MIXER
27-Dec-26
27-Dec-26
—
0%
PK000ML51O
ML512 - Transport/Customs 2102-L LOADING ARM
27-Dec-26
27-Dec-26
—
0%
PK000ML51S
ML512 - Marshaling 2102-L LOADING ARM
27-Dec-26
27-Dec-26
—
0%
PK000MU11S
05B MU311 - Marshaling HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
—
0%
PK000MU21O
MU221 - Transport/Customs LIFT STATION
27-Dec-26
27-Dec-26
—
0%
PK000MU21S
MU221 - Marshaling LIFT STATION
27-Dec-26
27-Dec-26
—
0%
PK000MU22O
MU222 - Transport/Customes .2401-U
27-Dec-26
27-Dec-26
—
0%
PK000MU22S
MU222 - Marshaling 2401-U
27-Dec-26
27-Dec-26
—
0%
PK000MU25K
MU225 - 02G Fabricate/PO Promise LIFT STATION
27-Dec-26
27-Dec-26
—
0%
PK000MU25P
02G MU225 Issue Formal P.O.
27-Dec-26
27-Dec-26
—
0%
PK000MU311
05B MU311 Transport/Customes BULK CHEM. STORAGE TANKS
27-Dec-26
27-Dec-26
—
0%
PK000MU35O
MU350 - Transport/Customes 101-U DEAERATOR
27-Dec-26
27-Dec-26
—
0%
PK000MU41O
MU410 - Transport/Customes 2002-U PKG BOILER
27-Dec-26
27-Dec-26
—
0%
PK000MU41S
MU410 - Marshaling 2002-U PKG BOILER
27-Dec-26
27-Dec-26
—
0%
PK000MU61O
MU611 - Transport/Customes 2101-U, 2101-UJA Thru UJG CW TWR & Fans
27-Dec-26
27-Dec-26
—
0%
PK000PIA1J
Bulk Piping A/G & U/G - Receive at Site FIRST (CS,SS,U/G)
27-Dec-26
27-Dec-26
—
0%
PK000PIA1L
Bulk Piping A/G - Transport / Delivery (CROME)
27-Dec-26
27-Dec-26
—
0%
PK000PIA1M
Bulk Piping A/G - Receive at Site (CHROME)
27-Dec-26
27-Dec-26
—
0%
PK000PIA4H
Product Line Piping - Transport / Delivery to Insulation Shop
27-Dec-26
27-Dec-26
—
0%
PK000PIA4I
Product Line Piping - Insulation Fab/Exworks
27-Dec-26
27-Dec-26
—
0%
PK000PIA4J
Product Line Piping - Receive at Site
27-Dec-26
27-Dec-26
—
0%
PK000PIA4K
Product Line Piping - Transport / Delivery
27-Dec-26
27-Dec-26
—
0%
PK000PIA4L
Product Line Piping - Fab/Exworks Remaining +/- 1500 Mts.
27-Dec-26
27-Dec-26
—
0%
PK000PS00F
000 SP Items - Issue Formal Blanket P.O.
27-Dec-26
27-Dec-26
—
0%
PK010E008F
540-SG Admin. Area Pwr Supply - Eval Bids/Issue Recmd
27-Dec-26
27-Dec-26
—
0%
PK010E008G
540-SG Admin. Area Pwr Supply - Interim Award
27-Dec-26
27-Dec-26
—
0%
PK010E008H
540-SG Admin. Area Pwr Supply - Formal Award
27-Dec-26
27-Dec-26
—
0%
PK010E008J
540-SG Admin. Area Pwr Supply - Planning V. Data
27-Dec-26
27-Dec-26
—
0%
PK010E008L
540-SG Admin. Area Pwr Supply - Production V. Data
27-Dec-26
27-Dec-26
—
0%
PK010I1103
010 Orific Plates - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK010I1105
010 Orific Plates - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK01DMU61Z
01D Recv. at Site - 2101-U, 2101-UJA Thru UJG CW TWR & Fans
27-Dec-26
27-Dec-26
—
0%
PK01FMU21Z
01E Recv. at Site - 2402-L Lift Station
27-Dec-26
27-Dec-26
—
0%
PK01GMU21Z
01E Recv. at Site - Lift Station
27-Dec-26
27-Dec-26
—
0%
PK020I131H
Fabricate / Exworks - Transmitters -Press.
27-Dec-26
27-Dec-26
—
0%
PK020IC214
020 Control Valves - Transport & Deliver
27-Dec-26
27-Dec-26
—
0%
PK020IC220
020 Control Valves - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK02AMC21Z
02A Recv. at Site - 160-C Ammonia Distl Column Reboiler
27-Dec-26
27-Dec-26
—
0%
PK02AMC61Z
02A Recv. at Site - 161-C Aqua Ammonia Interchanger
27-Dec-26
27-Dec-26
—
0%
PK02AMD22D
02A Recv. at Site - 104-E Tower
27-Dec-26
27-Dec-26
—
0%
PK02AMD22Z
02A Recv. at Site - 103-E, 105-E Towers
27-Dec-26
27-Dec-26
—
0%
PK02AMJ37Z
02A Recv. at Site - 130-J/JA, 131-J/JA Metering Pumps
27-Dec-26
27-Dec-26
—
0%
PK02CMC21Z
02C Recv. at Site - 128-C, 134-C, 167-C Exchangers
27-Dec-26
27-Dec-26
—
0%
PK02CMJ21Z
02C Recv. at Site - 103-J & 105-J
27-Dec-26
27-Dec-26
—
0%
PK02CMJ75Z
02C Recv. at Site - 103-JTC Surface Condenser
27-Dec-26
27-Dec-26
—
0%
PK02DMC21Z
02D Recv. at Site - 127-C Refrigerant Condenser
27-Dec-26
27-Dec-26
—
0%
PK02DMD44Z
02D Recv. at Site - 109-F Refrigerant Receiver
27-Dec-26
27-Dec-26
—
0%
PK02EMC21Z
02E Recv. at Site - 115-C & 130-C Exchangers
27-Dec-26
27-Dec-26
—
0%
PK02EMC23S
02E Recv. at Site - 114-C Exchangers
27-Dec-26
27-Dec-26
—
0%
PK02EMC23Z
02E Recv. at Site - 172-C, 183-C Exchangers
27-Dec-26
27-Dec-26
—
0%
PK02EMD42Z
02E Recv. at Site - 104-F Syn Gas Compr Suction Drum
27-Dec-26
27-Dec-26
—
0%
PK02EMD45Z
02E Recv. at Site - 157-F Mole Sieve Regen HP Cond Drum
27-Dec-26
27-Dec-26
—
0%
PK02FMU11Z
05B MU311 Recv. at Site - 2109-LA HYDROCHLORIC ACID STORAGE TANK A
27-Dec-26
27-Dec-26
—
0%
PK02GMC21Z
02G Recv. at Site - 133-C Fd Gas Compr. Kickback Cooler
27-Dec-26
27-Dec-26
—
0%
PK02GMJ21Z
02G Recv. at Site - 102-J/JL Fd Gas Compr. & Aux.
27-Dec-26
27-Dec-26
—
0%
PK02GMJ75Z
02G Recv. at Site - 101-JTC Surface Condenser
27-Dec-26
27-Dec-26
—
0%
PK02GMLV04
02G MU225 2104-L - Piping Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK02GMLV05
02G MU225 2104-L - Civil Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK02GMLV06
02G MU225 2104-L - E&I Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK02GMU11Z
05B MU311 Recv. at Site - 2109-LB HYDROCHLORIC ACID STORAGE TANK B
27-Dec-26
27-Dec-26
—
0%
PK02HMB21Z
02H Recv. at Site - 101-B Siding
27-Dec-26
27-Dec-26
—
0%
PK02HMB42Z
02H Recv. at Vendor - 101-B Cast Peep Sites
27-Dec-26
27-Dec-26
—
0%
PK02HMB61Z
02H Recv. at Site - 101-B Burners
27-Dec-26
27-Dec-26
—
0%
PK02HMB63Z
02H Recv. at Site - 101-B Air Preheater
27-Dec-26
27-Dec-26
—
0%
PK02HMB64Z
02H Recv. at Site - 101-B Springs & Hangers
27-Dec-26
27-Dec-26
—
0%
PK02HMB65Z
02H Recv. at Site - 101-B Penthouse Circ Fans
27-Dec-26
27-Dec-26
—
0%
PK02HMB66Z
02H Recv. at Site - 101-B Dampers & Air Doors
27-Dec-26
27-Dec-26
—
0%
PK02HMB68Z
02H Recv. at Site - 101-B Cat Vacuum Equip
27-Dec-26
27-Dec-26
—
0%
PK02HMB69Z
02H Recv. at Site - 101-B Expansion Joints
27-Dec-26
27-Dec-26
—
0%
PK02HMBP1K
02H Recv. at Site - 101-B Radiant Steel Panels
27-Dec-26
27-Dec-26
—
0%
PK02HMBP1Q
02H Recv. at Site - 101-B Radiant Harps
27-Dec-26
27-Dec-26
—
0%
PK02HMBP1R
02H Recv. at Site - 101-B Convection Modules
27-Dec-26
27-Dec-26
—
0%
PK02HMBP1S
02H Recv. at Site - 101-B Radiant Ducting
27-Dec-26
27-Dec-26
—
0%
PK02HMBP1T
02H Recv. at Site - 101-B Crossover
27-Dec-26
27-Dec-26
—
0%
PK02HMD45Z
02H Recv. at Site - 156-F Steam Blowdown Drum
27-Dec-26
27-Dec-26
—
0%
PK02HMD51Z
02H Recv. at Site - 107-D Primary Reformer Tranfer Line
27-Dec-26
27-Dec-26
—
0%
PK02JMC21Z
02J Recv. at Site - 173-C Startup Cooler
27-Dec-26
27-Dec-26
—
0%
PK02KMC21Z
02K Recv. at Site - 174-C Stripped Condensate Cooler
27-Dec-26
27-Dec-26
—
0%
PK02KMC61Z
02K Recv. at Site - 188-CA/ CB/ CC Exchangers
27-Dec-26
27-Dec-26
—
0%
PK02KMD45A
02K Recv. at Site - Equip. 115-F
27-Dec-26
27-Dec-26
—
0%
PK02KMD45Z
02K Recv. at Site - Equip. 118-F
27-Dec-26
27-Dec-26
—
0%
PK02KML42Z
02K Recv. at Site - 115-L Benfeild Sump Filter
27-Dec-26
27-Dec-26
—
0%
PK02KML43Z
02K Recv. at Site - 110-L Benfeild Mixer
27-Dec-26
27-Dec-26
—
0%
PK02LMC21Z
02L Recv. at Site - 110-C Lean Solution Cooler
27-Dec-26
27-Dec-26
—
0%
PK02LMC23A
02L Recv. at Site - 106-C & 109-C Exchangers
27-Dec-26
27-Dec-26
—
0%
PK02LMC23Z
02L Recv. at Site - 105-C Exchanger
27-Dec-26
27-Dec-26
—
0%
PK02LMD47Z
02L Recv. at Site - 103-F CO2 Stripper Cond KO Drum
27-Dec-26
27-Dec-26
—
0%
PK02LML42Z
02L Recv. at Site - 104-L Benfeild Solution Filter
27-Dec-26
27-Dec-26
—
0%
PK02LMU11Z
05B MU311 Recv. at Site - 2110-L SODIUM HYDROCHLORITE STORAGE
27-Dec-26
27-Dec-26
—
0%
PK02MMB81Z
02M Recv. at Site - 102-B Startup Heater
27-Dec-26
27-Dec-26
—
0%
PK02MMC21Z
02M Recv. at Site - 124-C Ammonia Convr. Effluent Cooler
27-Dec-26
27-Dec-26
—
0%
PK02MMD42Z
02M Recv. at Site - 144-F Feed Gas KO Drum
27-Dec-26
27-Dec-26
—
0%
PK02PMU35Z
02P Recv. at Site - 101-U Deaerator
27-Dec-26
27-Dec-26
—
0%
PK030I1100
Orific Plates - Fabricate/Exworks
27-Dec-26
27-Dec-26
—
0%
PK030IC214
030 Control Valves - Transport & Delivery
27-Dec-26
27-Dec-26
—
0%
PK030IC220
030 Control Valves - Recv on Site
27-Dec-26
27-Dec-26
—
0%
PK03BMU22Z
03B Recv. at Site - 2401-U Sanitary Treatment Pkg
27-Dec-26
27-Dec-26
—
0%
PK03CMD46Z
03C Recv. at Site - 2203-F & 2204-F Caustic Tank/ Acid Drum
27-Dec-26
27-Dec-26
—
0%
PK03FMD46Z
03F Recv. at Site - 2006-F Boiler Blowdown Drum
27-Dec-26
27-Dec-26
—
0%
PK03FMU11Z
05B MU311 Recv. at Site - 2109-L HYDROCHLORIC ACID STORAGE
27-Dec-26
27-Dec-26
—
0%
PK03FMU41Z
03F Recv. at Site - 2002-U Package Boiler
27-Dec-26
27-Dec-26
—
0%
PK050I1105
050 Orfice Plates - Recv on Site Dock/Storage Area
27-Dec-26
27-Dec-26
—
0%
PK05AMF25
05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract)
27-Dec-26
27-Dec-26
—
0%
PK05AMJV10
05A MJ731 2108-J - Civil Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK05AMJV11
05A MJ731 2108-J - E&I Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK05AML33Z
05A Recv. at Site - 2101-L Ammonia Refrigeration Pkg
27-Dec-26
27-Dec-26
—
0%
PK05BML51Z
05B Recv. at Site - 2102-L Loading Arm
27-Dec-26
27-Dec-26
—
0%
PO000P0015
Purch/Fab/Delv - Temporary Testing Materials
27-Dec-26
27-Dec-26
—
0%
PO000P0020
Receive at Site - Temporary Testing Materials
27-Dec-26
27-Dec-26
—
0%
PO000V1000
Purch/Fab/Delv - Painting Materials
27-Dec-26
27-Dec-26
—
0%
PO000V1005
Receive at Site - Painting Materials
27-Dec-26
27-Dec-26
—
0%
PO020EL155
020 Issue E&I Cable/Bulks/JB Reqn (OCI)
27-Dec-26
27-Dec-26
—
0%
XE000OW305
(EBIC) Permit - Free Zone Status (SIDC)
27-Dec-26
27-Dec-26
—
0%
XE000OW310
(EBIC) Arrange For Solid Waste Collection/Disposal
27-Dec-26
27-Dec-26
—
0%
XE000OW325
(EBIC) Tie-In Construction Elec Power Supply
27-Dec-26
27-Dec-26
—
0%
XE000OW373
(EBIC) Permit - Free Zone Status (SPDC)
27-Dec-26
27-Dec-26
—
0%
XE05AOW340
(EBIC) Clear & Level Site For Ammonia Storage
27-Dec-26
27-Dec-26
—
0%
ZZ1020
01D Recv. at Site - 2101-UJA Thru UJGM CW Motors
27-Dec-26
27-Dec-26
—
0%
ZZ1040
MU611 - Transport/Customes 2101-UJA Thru UJGM CW Motors
27-Dec-26
27-Dec-26
—
0%
CK000P0110
000 Pipe Fabrication
28-Dec-26
31-May-27
49.0d
0%
CK000U4110
Start Pipe Fab
28-Dec-26
28-Dec-26
—
0%
CK01AP0110
01A A/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK01BU4110
01B U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK01CU4110
01C U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK01DP0110
01D A/G Pipe Spool Fabrication
28-Dec-26
22-Mar-27
104.0d
0%
CK01DU4110
01D U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK01EU4120
01E/F/G U/G Pipe Spool Fabrication (to Blg Stub Outs)
28-Dec-26
28-Dec-26
—
0%
CK01YP0110
01Y A/G Pipe Spool Fabrication
28-Dec-26
29-Jan-27
117.0d
0%
CK02AU4110
02A U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02BP0110
02B A/G Pipe Spool Fabrication
28-Dec-26
24-May-27
55.0d
0%
CK02BU4110
02B U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02CU4110
02C U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02DP0110
02D A/G Pipe Spool Fabrication
28-Dec-26
30-Apr-27
75.0d
0%
CK02DU4110
02D U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02EP0110
02E A/G Pipe Spool Fabrication
28-Dec-26
25-Feb-27
130.0d
0%
CK02EU4110
02E U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02FP0110
02F A/G Pipe Spool Fabrication
28-Dec-26
20-Apr-27
84.0d
0%
CK02FU4110
02F U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02GU4110
02G U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02HU4110
02H U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02JU4110
02J U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02KU4110
02K U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02LU4110
02L U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02MU4110
02M U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK02NP0110
02N A/G Pipe Spool Fabrication
28-Dec-26
27-Mar-27
104.0d
0%
CK02PP0110
02P A/G Pipe Spool Fabrication
28-Dec-26
21-Apr-27
83.0d
0%
CK02UU4110
02U U/G Pipe Spool Fabrication (CW & Misc Headers)
28-Dec-26
28-Dec-26
—
0%
CK02YP0110
02Y A/G Pipe Spool Fabrication
28-Dec-26
29-Jan-27
27.0d
0%
CK03AU4110
03A U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK03BU4110
03B U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK03CP0110
03C A/G Pipe Spool Fabrication
28-Dec-26
17-Feb-27
137.0d
0%
CK03CU4110
03C U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK03DU4110
03D U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK03EU4110
03E U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK03FU4110
03F U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CK03YP0110
03Y A/G Pipe Spool Fabrication
28-Dec-26
06-Feb-27
80.0d
0%
CK05AU4110
05A U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
—
0%
CO01AC0120
01A Form, Pour, Strip Fnds - Misc Fnds & Sumps...
28-Dec-26
09-Jan-27
247.0d
0%
CO01BC0120
01B Form, Pour, Strip Fnds - Misc Fnds
28-Dec-26
06-Jan-27
210.0d
0%
CO01BC0140
01B Form Pour Strip Fnds - Sleepers to Evap Pond
28-Dec-26
27-Jan-27
148.0d
0%
CO01BM0130
01B Tank Erection 2001-FA (Water Storage Tank)
28-Dec-26
21-Apr-27
9.0d
0%
CO01BM0140
01B Tank Erection 2001-FB (Water Storage Tank)
28-Dec-26
25-Mar-27
32.0d
0%
CO01DM0130
01D Erect 2101-U Cooling Tower
28-Dec-26
04-May-27
61.0d
0%
CO01GA0110
01G Erect Control Building (Continuation w/ Design Rev)
28-Dec-26
24-Jun-27
-14.0d
0%
CO01HC0110
01H Form, Pour, Strip Piers - Substation Building
28-Dec-26
06-Feb-27
112.0d
0%
CO01YU3110
01Y U/G Earthing Installation - Pipe Rack
28-Dec-26
06-Feb-27
134.0d
0%
CO02AU4120
02A U/G Piping Installation
28-Dec-26
29-Jan-27
222.0d
0%
CO02BU4120
02B U/G Piping Installation
28-Dec-26
29-Jan-27
219.0d
0%
CO02CC0110
02C Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
26-Jan-27
165.0d
0%
CO02CC0150
02C Form, Pour, Strip Fnd - 103/105-J & Table Tops
28-Dec-26
28-Dec-26
—
0%
CO02CM0110
02C Set Static Equipment - 128/167-C
28-Dec-26
28-Dec-26
—
0%
CO02CU4120
02C U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02DC0110
02D Form, Pour, Strip Fnds - Major Fnds
28-Dec-26
09-Jan-27
252.0d
0%
CO02DU4120
02D U/G Piping Installation
28-Dec-26
29-Jan-27
248.0d
0%
CO02EU4120
02E U/G Piping Installation
28-Dec-26
29-Jan-27
227.0d
0%
CO02FC0110
02F Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
234.0d
0%
CO02FU4120
02F U/G Piping Installation
28-Dec-26
29-Jan-27
234.0d
0%
CO02GC0150
02G Form, Pour, Strip Fnd - 101-J/JT & 2ea. Table Tops
28-Dec-26
01-Feb-27
134.0d
0%
CO02GM0140
02G Set/Install - 102-J Fd Gas Compr. & Aux.
28-Dec-26
22-Apr-27
188.0d
0%
CO02HU4120
02H U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02JU4120
02J U/G Piping Installation
28-Dec-26
29-Jan-27
211.0d
0%
CO02KC0110
02K Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
192.0d
0%
CO02KM0130
02K Tank Erection 114-F (Benfield Solution Tank)
28-Dec-26
08-Jan-27
97.0d
0%
CO02KU4120
02K U/G Piping Installation
28-Dec-26
29-Jan-27
214.0d
0%
CO02LC0110
02L Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
123.0d
0%
CO02LC0140
02L Form Pour Strip Fnds - 02L Structure
28-Dec-26
29-Jan-27
45.0d
0%
CO02MU4120
02M U/G Piping Installation
28-Dec-26
29-Jan-27
239.0d
0%
CO02UP0130
02U LB Pipe Erection (CW & Misc Headers)
28-Dec-26
29-Jan-27
71.0d
0%
CO02UV1110
02U Paint Fabricated Pipe Spools (CW & Misc Headers)
28-Dec-26
28-Dec-26
—
0%
CO02YU3110
02Y U/G Earthing Installation
28-Dec-26
29-Jan-27
100.0d
0%
CO03AC0110
03A Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
16-Jan-27
155.0d
0%
CO03BC0110
03B Form, Pour, Strip Fnds - Major Fnds (N/A)
28-Dec-26
28-Dec-26
—
0%
CO03BC0140
03B Form, Pour, Strip Fnds - 2401-A Wastewater Sump
28-Dec-26
30-Dec-26
266.0d
0%
CO03DM0145
03D Tank Erection 2002-F (Demin Water Tank)
28-Dec-26
12-Jan-27
105.0d
0%
CO03DU4120
03D U/G Piping Installation
28-Dec-26
05-Jan-27
199.0d
0%
CO03EC0110
03E Form, Pour, Strip Fnds - 2001-U Water Treatment
28-Dec-26
20-Feb-27
126.0d
0%
CO03FM0110
03F Erect 2002-U Package Boiler
28-Dec-26
13-Mar-27
159.0d
0%
CO03YC0110
03Y Form, Pour, Strip Fnds - Sleeper Fnds
28-Dec-26
01-Jan-27
98.0d
0%
CO03YC0120
03Y Form, Pour, Strip Fnds - Pipe Rack Fnds
28-Dec-26
28-Dec-26
—
0%
CO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
CO05AC0175
05A Test Piles (Load Test)
28-Dec-26
09-Jan-27
-51.0d
0%
EK000YA500
Issue ISBL Paint & Insulation Work Package
28-Dec-26
08-Mar-27
750.0d
0%
EK000YA845
(PC-08) Complete >10% - ISBL -Unit 02 - Pipe Spool Fabrication,>2 Inch Diameter
28-Dec-26
28-Dec-26
—
0%
P002YS0010
02Y Recv at Site - Structural Steel (First Shipment)
28-Dec-26
28-Dec-26
—
0%
PO000E0000
Purch/Fab/Deliver - A/G Electrical Bulks (First)
28-Dec-26
10-Apr-27
20.0d
0%
PO000V2000
Purch/Fab/Delv - Insulation Materials
28-Dec-26
15-May-27
98.0d
0%
PO01BS0130
01B Fab & Ship Miscellaneous Steel
28-Dec-26
26-Feb-27
86.0d
0%
PO01DS0120
01D Fab & Ship Structural Steel
28-Dec-26
19-Feb-27
94.0d
0%
PO01DS0130
01D Fab & Ship Miscellaneous Steel
28-Dec-26
19-Feb-27
94.0d
0%
PO01EA0135
01E Guard House Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
200.0d
0%
PO01FA0135
01F Mosque Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
143.0d
0%
PO01HS0130
01H Fab & Ship Miscellaneous Steel
28-Dec-26
09-Apr-27
51.0d
0%
PO01YS0120
01Y Fab & Ship Structural Steel
28-Dec-26
29-Jan-27
39.0d
0%
PO02AS0120
02A Fab & Ship Structural Steel
28-Dec-26
09-Apr-27
103.0d
0%
PO02AS0130
02A Fab & Ship Miscellaneous Steel
28-Dec-26
09-Apr-27
115.0d
0%
PO02CS0130
02C Fab & Ship Miscellaneous Steel
28-Dec-26
26-Mar-27
83.0d
0%
PO02DS0120
02D Fab & Ship Structural Steel
28-Dec-26
02-Apr-27
93.0d
0%
PO02DS0130
02D Fab & Ship Miscellaneous Steel
28-Dec-26
02-Apr-27
105.0d
0%
PO02ES0120
02E Fab & Ship Structural Steel
28-Dec-26
16-Apr-27
127.0d
0%
PO02ES0130
02E Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
67.0d
0%
PO02FS0130
02F Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
133.0d
0%
PO02HS0120
02H Fab & Ship Structural Steel
28-Dec-26
26-Mar-27
92.0d
0%
PO02HS0130
02H Fab & Ship Miscellaneous Steel
28-Dec-26
26-Mar-27
78.0d
0%
PO02JS0120
02J Fab & Ship Structural Steel
28-Dec-26
16-Apr-27
98.0d
0%
PO02JS0130
02J Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
110.0d
0%
PO02LS0120
02L Fab & Ship Structural Steel
28-Dec-26
05-Mar-27
-15.0d
0%
PO02LS0130
02L Fab & Ship Miscellaneous Steel
28-Dec-26
05-Mar-27
93.0d
0%
PO02MS0120
02M Fab & Ship Structural Steel
28-Dec-26
19-Mar-27
123.0d
0%
PO02MS0130
02M Fab & Ship Miscellaneous Steel
28-Dec-26
19-Mar-27
147.0d
0%
PO02NMS100
02N Fab & Ship Miscellaneous Steel
28-Dec-26
30-Apr-27
67.0d
0%
PO02QMS100
02Q Fab & Ship Miscellaneous Steel
28-Dec-26
23-Apr-27
121.0d
0%
PO02YS0120
02Y Fab & Ship Structural Steel
28-Dec-26
05-Mar-27
-22.0d
0%
PO03AS0130
03A Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
56.0d
0%
PO03BS0130
03B Fab & Ship Miscellaneous Steel
28-Dec-26
09-Apr-27
169.0d
0%
PO03CS0130
03C Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
87.0d
0%
PO03DS0130
03D Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
98.0d
0%
PO03ES0130
03E Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
58.0d
0%
PO03YS0120
03Y Fab & Ship Structural Steel
28-Dec-26
29-Jan-27
39.0d
0%
WK000P0100
000 A/G Pipe Spool Fabrication
28-Dec-26
31-May-27
49.0d
0%
WO010A0100
010 Buildings
28-Dec-26
24-Jun-27
94.0d
0%
WO010M0100
010 Major Equipment
28-Dec-26
01-Sep-27
54.0d
0%
WO010U3100
010 Install U/G Electrical
28-Dec-26
27-Mar-27
170.0d
0%
WO020M0100
020 Major Equipment
28-Dec-26
16-Aug-27
156.0d
0%
WO020U3100
020 Install U/G Electrical
28-Dec-26
12-Mar-27
265.0d
0%
WO020U4100
020 U/G Piping Installation
28-Dec-26
26-Feb-27
224.0d
0%
WO030M0100
030 Major Equipment
28-Dec-26
26-Apr-27
192.0d
0%
WO030U4100
030 U/G Piping Installation
28-Dec-26
26-Feb-27
229.0d
0%
WO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
WO050C0110
050 Concrete Paving
28-Dec-26
28-Dec-26
0.0d
0%
WT010M0100
010 Tank Erection
28-Dec-26
21-Apr-27
9.0d
0%
WT020M0100
020 Tank Erection
28-Dec-26
08-Jan-27
97.0d
0%
WT030M0100
030 Tank Erection
28-Dec-26
12-Jan-27
105.0d
0%
EK000YA843
(PC-18) Complete >90% Bldg No. 2604-K Workshop / Warehouse Erection
28-Dec-26
28-Dec-26
750.0d
0%
SC01JT0120
01J RFSU
28-Dec-26
28-Dec-26
441.0d
0%
XE000OW335
(EBIC) Permit - Land Easement (SIDC Assistance)
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW340
(EBIC) Permit - Tanks (SIDC)
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW345
(EBIC) Purchase Chemicals For Operation
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW355
(EBIC) Tie-In Municipal Water To Site
28-Dec-26
28-Dec-26
353.0d
0%
XE000OW370
(EBIC) Permit - Tanks (SPDC)
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW375
(EBIC) Tie-In Site Electrical Power Supply
28-Dec-26
28-Dec-26
297.0d
0%
XE000OW405
(EBIC) Tie-In Port Elec Power Supply To Substation
28-Dec-26
28-Dec-26
750.0d
0%
EK000CS040
Issue Operation & Maintenance Manuals for Review
30-Dec-26
21-Mar-27
215.0d
0%
EK000ELEGP
Electrical Heat Tracing - Design & BOM by Consultant
30-Dec-26
30-Jan-27
91.0d
0%
EK000ELEN1
01,03,04 LV Wiring Diagrams - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN2
01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN3
01,03, Equipment Interconnection Diagrams - IFC
30-Dec-26
30-Jan-27
511.0d
0%
EK020EL130
Overall One line Diagrams - IFC
30-Dec-26
01-Jan-27
82.0d
0%
EK020EL165
Switchgear One line Diagrams - IFC
30-Dec-26
29-Jan-27
231.0d
0%
EK020EL185
MCC One line Diagrams - IFC
30-Dec-26
30-Jan-27
231.0d
0%
EK020ELEG6
Cathodic Protection - Material Supply (By Consultant)
30-Dec-26
02-May-27
6.0d
0%
EK020ELEN1
02 LV Wiring Diagrams - IFC
30-Dec-26
16-Jan-27
296.0d
0%
EK020ELEN2
02 MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC
30-Dec-26
26-Feb-27
306.0d
0%
EK020ELEN3
02 Equipment Interconnection Diagrams - IFC
30-Dec-26
30-Jan-27
511.0d
0%
EK020IC131
Instrument Loop Diagrams FF - IFC
30-Dec-26
03-Jan-27
530.0d
0%
EK05ACV200
05A Redesign Piling & Ammonia Tank Foundations
30-Dec-26
10-Jan-27
-44.0d
0%
EK05BIC120
05B Instrument Model
30-Dec-26
30-Dec-26
110.0d
0%
EM000ELEN3
01,03 Equipment Interconnection Diagrams
30-Dec-26
30-Jan-27
511.0d
0%
EM020ELEN1
02 LV WIRING DIAGRAMS & CTL SCHEMATICS
30-Dec-26
29-Jan-27
512.0d
0%
EM020ELEN2
02 MV WIRING DIAGRAMS & CTL SCHEMATICS
30-Dec-26
29-Jan-27
512.0d
0%
EM020ELEN3
02 Equipment Interconnection Diagrams
30-Dec-26
30-Jan-27
511.0d
0%
EM02GPI143
02G OP's & Serv. Model Review Comments Resolution
30-Dec-26
03-Jan-27
88.0d
0%
EM02KCV127
02K Model Misc. Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
100.0d
0%
EM02KCV167
02K Update Model Misc Fdns & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
207.0d
0%
EM05ACV122
05A Update Model PR Struct Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
21.0d
0%
EM05ACV127
05A Model Misc. Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
25.0d
0%
EM05ACV164
05A Update Model Major Eq. Fdns & Issue Dwgs-IFC
30-Dec-26
27-Jan-27
-14.0d
0%
EM05API135
05A A/G Piping Iso's - Issue IFC
30-Dec-26
03-Jan-27
90.0d
0%
EM05API138
05A Design / Issue Pipe Supports IFC
30-Dec-26
03-Jan-27
162.0d
0%
EM05BCV122
05B Design / Model / IFC - Sleeper Steel & FDN's
30-Dec-26
24-Jan-27
71.0d
0%
EM05BCV133
05B Design / Model / IFC - S/S at Jetty
30-Dec-26
24-Jan-27
71.0d
0%
EM05BPI141
05B Model Review Comment Resolution
30-Dec-26
10-Jan-27
75.0d
0%
PK000E001H
Sub Stations - Fab / Exworks
30-Dec-26
28-Feb-27
62.0d
0%
PK000E002H
Transformer - Fab / Exworks
30-Dec-26
04-Feb-27
28.0d
0%
PK000E004H
UPS System - Fab / Exworks
30-Dec-26
05-Feb-27
27.0d
0%
PK000I1121
020 Venturis - Fabricate/Exworks
30-Dec-26
30-Dec-26
509.0d
0%
PK000I2300
On/Off Valves - Fabricate/Exworks
30-Dec-26
07-Feb-27
460.0d
0%
PK000I3524
SIS - Packing / Exworks
30-Dec-26
10-Jan-27
55.0d
0%
PK000I3545
ITCC - Packing / Exworks
30-Dec-26
10-Jan-27
55.0d
0%
PK000I4440
FAT Test - Shelters/ Analyzers
30-Dec-26
10-Jan-27
161.0d
0%
PK000I611N
Transport & Deliver - Pressure Gauges - ISBL
30-Dec-26
03-Jan-27
110.0d
0%
PK000I612H
Fabricate / Exworks - Differential Pressure Gauges
30-Dec-26
18-Feb-27
28.0d
0%
PK000I617N
Transport & Deliver - Magnetic Lvl Gauges
30-Dec-26
13-Jan-27
104.0d
0%
PK000I621H
Fabricate / Exworks - Temperature Elements
30-Dec-26
13-Mar-27
31.0d
0%
PK000I623H
Fabricate / Exworks - Multi-Point Thermocouples
30-Dec-26
30-Dec-26
84.0d
0%
PK000IC354
DCS - Packing / Exworks
30-Dec-26
30-Dec-26
85.0d
0%
PK000IC35N
DCS - Transport (Hold for Field Request)
30-Dec-26
07-Feb-27
85.0d
0%
PK000MB62S
MB621 - Marshaling 101-B ID & FD Fans
30-Dec-26
14-Feb-27
215.0d
0%
PK000MB71S
MB710 - Marshaling 2202-B/BL Storage Flare & Flame FRT Gen.
30-Dec-26
07-Feb-27
240.0d
0%
PK000MD34T
MD304 - Marshaling 108-DA/B
30-Dec-26
07-Feb-27
162.0d
0%
PK000MD41S
MD401 - Marshaling 101-F
30-Dec-26
07-Feb-27
175.0d
0%
PK000MD44U
MD404 - Marshaling 132-F
30-Dec-26
07-Feb-27
65.0d
0%
PK000MJ35S
MJ305 - Marshaling ISBL ANSI/API PUMPS
30-Dec-26
11-Feb-27
153.0d
0%
PK000MJ71K
MJ731 - Fabricate/PO Promise EMERG PWR GENERATOR
30-Dec-26
21-Feb-27
70.0d
0%
PK000ML31S
ML313 - Marshaling 160-L
30-Dec-26
30-Dec-26
261.0d
0%
PK000ML90S
01A ML900 - Marshaling Evap. Pond Spray Nzl.
30-Dec-26
10-Jan-27
103.0d
0%
PK000MU25S
02G MU225 - Marshaling LIFT STATION
30-Dec-26
07-Feb-27
215.0d
0%
PK000MU29S
MU292 - Marshaling 2404-L
30-Dec-26
07-Feb-27
195.0d
0%
PK000MU30S
MU300 - Marshaling 2102-U
30-Dec-26
07-Feb-27
76.0d
0%
PK000MU31S
MU310 - Marshaling Injection System & Chlorination Unit
30-Dec-26
07-Feb-27
59.0d
0%
PK000MU32S
MU322 - Marshaling COOLING WTR FILTER & CLARIFIER
30-Dec-26
07-Feb-27
71.0d
0%
PK000MU33S
MU330 - Marshaling 2001-U
30-Dec-26
07-Feb-27
111.0d
0%
PK000PIA1N
Bulk Piping A/G - Fab/Exworks (FINAL)
30-Dec-26
07-Mar-27
45.0d
0%
PK000PS00G
000 SP Items - Fabricate/Exworks
30-Dec-26
30-Dec-26
247.0d
0%
PK000PSA8H
000 Relief Valves - Transport & Deliver
30-Dec-26
24-Feb-27
257.0d
0%
PK000PTA0J
Engineered Pipe Supports - Transport
30-Dec-26
10-Feb-27
58.0d
0%
PK010E008K
540-SG Admin. Area Pwr Supply - Fab / Exworks
30-Dec-26
11-Feb-27
70.0d
0%
PK010I1211
Vortex Meters - Transport & Deliver
30-Dec-26
31-Dec-26
533.0d
0%
PK010I1241
Rotameters - Transport & Deliver
30-Dec-26
14-Jan-27
523.0d
0%
PK010IC214
010 Control Valves - Transport & Deliver
30-Dec-26
30-Dec-26
535.0d
0%
PK010IC220
010 Control Valves - Recv on Site
30-Dec-26
30-Dec-26
—
0%
PK010IC252
MOV Valves - Fabricate/Exworks
30-Dec-26
27-Jan-27
475.0d
0%
PK020I131N
Transport & Deliver - Transmitters -Press.
30-Dec-26
20-Feb-27
76.0d
0%
PK030I1103
Orific Plates -Transport & Deliver
30-Dec-26
27-Jan-27
514.0d
0%
PK030I131H
Fabricate / Exworks - Transmitters - Temp.
30-Dec-26
16-Jan-27
71.0d
0%
PK030I611H
Fabricate / Exworks - Pressure Gauges - OSBL
30-Dec-26
04-Feb-27
58.0d
0%
ZZ2080
MJ305 - Transport/Customes OSBL ANSI/API PUMPS
30-Dec-26
07-Feb-27
190.0d
0%
ZZ2090
MJ305 - Marshaling OSBL ANSI/API PUMPS
30-Dec-26
30-Dec-26
190.0d
0%
CK01BP0110
01B A/G Pipe Spool Fabrication
31-Dec-26
23-Mar-27
101.0d
0%
CO01AV1110
01A Paint Fabricated Pipe Spools
31-Dec-26
02-Jan-27
253.0d
0%
PK000I1131
Venturis - Transport & Deliver
31-Dec-26
03-Feb-27
509.0d
0%
PK000I221N
000 Everest Control Valves - Transport & Deliver
31-Dec-26
10-Feb-27
504.0d
0%
PK000MB51S
MB511 - Marshaling 101-B Insulation
31-Dec-26
20-Jan-27
204.0d
0%
PK000ML31O
ML313 - Transport/Customs 160-L
31-Dec-26
24-Jan-27
365.0d
0%
PK000PS00H
000 SP Items - Transport & Deliver
31-Dec-26
10-Mar-27
247.0d
0%
PK010I1151
Annubars - Transport & Deliver
31-Dec-26
03-Feb-27
509.0d
0%
WO010V1100
010 Paint
31-Dec-26
05-Oct-27
131.0d
0%
PK010I1212
Vortex Meters - Recv on Site
31-Dec-26
31-Dec-26
615.0d
0%
EM05ACV133
05A Update Model Structural Piperack Fdns & Issue Dwgs - IFC
01-Jan-27
10-Jan-27
121.0d
0%
XE000OW230
(EBIC) Permit - Operating Permit (SPDC)
01-Jan-27
01-Jan-27
746.0d
0%
XE000OW374
(EBIC) Permit - Operating Permit (SIDC)
01-Jan-27
01-Jan-27
746.0d
0%
EM5ASY272
05A P&IDs & Line List Issue - IFC
01-Jan-27
01-Jan-27
164.0d
0%
EM5BSY272
05B P&IDs & Line List Issue - IFC
01-Jan-27
01-Jan-27
267.0d
0%
CO02HM0200
02H Start Primary Reformer Erection (101-B)
02-Jan-27
02-Jan-27
108.0d
0%
CO02HM0210
02H Erect Radiant Section Shell (101-B)
02-Jan-27
02-Apr-27
108.0d
0%
CO02LU4120
02L U/G Piping Installation
02-Jan-27
29-Jan-27
123.0d
0%
PK000MD21S
MD201- Marshaling 101-E
02-Jan-27
07-Feb-27
93.0d
0%
PO03FS0130
03F Fab & Ship Miscellaneous Steel
02-Jan-27
09-Apr-27
88.0d
0%
EK01EA0140
01E Guard House Design Drawings - Approval
03-Jan-27
16-Jan-27
175.0d
0%
EK01FA0140
01F Mosque Design Drawings - Approval
03-Jan-27
16-Jan-27
119.0d
0%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
—
0%
EK000YA838
(EP-34) Issue >90% ISBL P&ID's For Construction (IFC)
03-Jan-27
03-Jan-27
—
0%
EK02GPI144
02G OP's & Serv. Model Comments Resolution Approval
03-Jan-27
03-Jan-27
—
0%
EM02GCV122
02G Update Model Struct Steel & Issue Dwgs - IFC
03-Jan-27
03-Jan-27
—
0%
EM02GCV126
02G Conceptual Misc. Steel Design/ Model
03-Jan-27
03-Jan-27
—
0%
EM02GCV127
02G Model Misc. Steel & Issue Dwgs - IFC
03-Jan-27
03-Jan-27
—
0%
EM02GCV128
02G Update Model Structural Fdns & Issue Dwgs - IFC
03-Jan-27
03-Jan-27
—
0%
EM02GCV166
02G Conceptual Misc. Foundations Design/ Model
03-Jan-27
03-Jan-27
—
0%
EM02GCV167
02G Update Model Misc Fdns & Issue Dwgs - IFC
03-Jan-27
03-Jan-27
—
0%
EM02GPI135
02G A/G Piping Iso's - Issue IFC
03-Jan-27
03-Jan-27
—
0%
EM02GPI136
02G IDP - Detail Design
03-Jan-27
03-Jan-27
—
0%
EM02GPI138
02G Design / Issue Pipe Supports IFC
03-Jan-27
03-Jan-27
—
0%
EM02GSY272
02G P&IDs & Line List Issue - IFC
03-Jan-27
03-Jan-27
—
0%
PK000I611L
Recv at Site - Pressure Gauges - ISBL
04-Jan-27
04-Jan-27
134.0d
0%
PO01CS0130
01C Fab & Ship Miscellaneous Steel
04-Jan-27
09-Apr-27
106.0d
0%
PO02GS0130
02G Fab & Ship Miscellaneous Steel
04-Jan-27
26-Mar-27
107.0d
0%
CO01UP0150
01U LB Pipe Erection (Firewater Piping)
05-Jan-27
06-Feb-27
212.0d
0%
WO010U4100
010 U/G Piping Installation
05-Jan-27
26-Mar-27
171.0d
0%
CO02GU4120
02G U/G Piping Installation
06-Jan-27
26-Feb-27
159.0d
0%
CO03DC0120
03D Form, Pour, Strip Fnds - Misc Fnds
06-Jan-27
19-Jan-27
199.0d
0%
EM000IC100
Instrument Index - IFC
06-Jan-27
06-Jan-27
530.0d
0%
CK02QP0110
02Q A/G Pipe Spool Fabrication
11-Jan-27
13-Apr-27
90.0d
0%
EK05ACV210
05A COSMO Design Approval (Assuming No Change)
11-Jan-27
16-Jan-27
-51.0d
0%
CO02CM0125
02C Set - 103/105-J Compressors
12-Jan-27
16-Jan-27
167.0d
0%
CO02YS0110
02Y Erect Structural Steel - Pipe Rack
12-Jan-27
14-Jun-27
-35.0d
0%
WO020S0100
020 Erect Steel
12-Jan-27
07-Oct-27
69.0d
0%
CO02HU3110
02H U/G Earthing Installation
13-Jan-27
12-Feb-27
162.0d
0%
CO03YV1110
03Y Paint Fabricated Pipe Spools
13-Jan-27
13-Feb-27
154.0d
0%
EM05BPI133
05B IDP - Plant Layout
13-Jan-27
14-Jan-27
75.0d
0%
PK000I352N
SIS - Transport & Delivery
13-Jan-27
21-Mar-27
55.0d
0%
PK000I354N
ITCC - Transport & Delivery
13-Jan-27
21-Mar-27
55.0d
0%
PK000I4441
Cleanup / Changes - Shelters/ Analyzers
13-Jan-27
24-Jan-27
161.0d
0%
PK000MD32S
MD302 - Marshaling 104-D1/2
13-Jan-27
07-Feb-27
85.0d
0%
PK000MJ22S
MJ201 - Marshaling 101-J
13-Jan-27
31-Jan-27
86.0d
0%
PK000MJ36S
MJ305 - Marshaling OSBL PUMPS
13-Jan-27
31-Jan-27
60.0d
0%
PK000MJ38V
MJ308 - Marshaling ISBL ANSI/API PUMPS
13-Jan-27
31-Jan-27
198.0d
0%
PK000MJ39S
Marshaling FIREWATER PUMPS
13-Jan-27
31-Jan-27
60.0d
0%
PK000ML90O
01A ML900 - Transport/Customes Evap. Pond Spray Nzl.
13-Jan-27
21-Feb-27
103.0d
0%
WO030V1100
030 Paint
13-Jan-27
23-Aug-27
153.0d
0%
CO02CU3110
02C U/G Earthing Installation
14-Jan-27
12-Feb-27
168.0d
0%
PK000I617L
Recv at Site - Magnetic Lvl Gauges
14-Jan-27
14-Jan-27
125.0d
0%
PK010I1242
Rotameters - Recv on Site
14-Jan-27
14-Jan-27
—
0%
CO03DU3110
03D U/G Earthing Installation
15-Jan-27
19-Jan-27
199.0d
0%
EK05BPI050
05B Model Comment Resolution Approval
15-Jan-27
17-Jan-27
75.0d
0%
EM05ACV167
05A Update Model Misc Fdns & Issue Dwgs - IFC
15-Jan-27
24-Jan-27
111.0d
0%
WO030U3100
030 Install U/G Electrical
15-Jan-27
12-Mar-27
229.0d
0%
PO05AS0120
05A Fab & Ship Structural Steel
15-Jan-27
04-Jun-27
23.0d
0%
PO05AS0130
05A Fab & Ship Miscellaneous Steel
15-Jan-27
04-Jun-27
27.0d
0%
CO02HC0120
02H Form, Pour, Strip Fnds - Misc Fnds
16-Jan-27
05-Feb-27
174.0d
0%
CO02LU3110
02L U/G Earthing Installation
16-Jan-27
12-Feb-27
129.0d
0%
CO02UP0150
02U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO03UP0150
03U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
PK000MC32S
MC311 - Marshaling KBR S&T EXCH
17-Jan-27
06-Mar-27
76.0d
0%
PK000MJ34S
MJ304 - Marshaling MP BFW PUMPS
17-Jan-27
06-Feb-27
186.0d
0%
PK030I131N
Transport & Deliver - Transmitters - Temp.
17-Jan-27
30-Jan-27
91.0d
0%
CO02CM0130
02C Install - 103/105-J Compressors & Aux. Equip.
18-Jan-27
13-May-27
167.0d
0%
CO05AC0185
05A Procure Material & Mob Piling Contractor
18-Jan-27
30-Jan-27
-51.0d
0%
CO02AU3110
02A U/G Earthing Installation
20-Jan-27
05-Feb-27
228.0d
0%
CO02CV1110
02C Paint Fabricated Pipe Spools
20-Jan-27
27-Feb-27
245.0d
0%
EM05BCV167
05B Design / Model / IFC - Equip. Fdn's.
20-Jan-27
20-Jan-27
221.0d
0%
EM05BPI132
05B Planning Release
20-Jan-27
24-Jan-27
75.0d
0%
EM05BPI200
05B Equipment Location Plans
20-Jan-27
24-Jan-27
221.0d
0%
PK000MJ32S
MJ302 - Marshaling 107-JA/JB/JC
20-Jan-27
07-Feb-27
175.0d
0%
WO020V1100
020 Paint
20-Jan-27
14-Feb-28
23.0d
0%