Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in PR.BM Bulk Materials × clear
Code
Activity
Start
Finish
Flt
%
PR-BM-600
Procure Structural Steel
03-Aug-25
22-Oct-25
10.0d
100%
PR-BM-610
Procure Piping Bulk Materials
31-Aug-25
09-Dec-25
5.0d
100%
Q3 2025 Q4 2025 Data Date
PR-BM-600 — Procure Structural Steel | 03-Aug-25 → 22-Oct-25 | Complete 100% | float 10.0d PR-BM-600 PR-BM-610 — Procure Piping Bulk Materials | 31-Aug-25 → 09-Dec-25 | Complete 100% | float 5.0d PR-BM-610