PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in PR.EQ Major Equipment × clear
Code
Activity
Start
Finish
Flt
%
PR-EQ-500
Award Steam Turbine PO
01-Jun-25
11-Jun-25
0.0d
100%
PR-EQ-520
Award HRSG PO
15-Jun-25
25-Jun-25
5.0d
100%
PR-EQ-540
Award Generator PO
06-Jul-25
16-Jul-25
15.0d
100%
PR-EQ-505
Manufacture Steam Turbine
13-Jul-25
20-Mar-26
0.0d
100%
PR-EQ-525
Manufacture HRSG
27-Jul-25
24-Mar-26
5.0d
100%
PR-EQ-545
Manufacture Generator
17-Aug-25
25-Mar-26
15.0d
100%
PR-EQ-510
Ship & Receive Steam Turbine
31-May-26
10-Jul-26
0.0d
0%
PR-EQ-530
Ship & Receive HRSG
12-Jul-26
11-Aug-26
5.0d
0%
Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Data Date
PR-EQ-500 — Award Steam Turbine PO | 01-Jun-25 → 11-Jun-25 | Complete 100% | float 0.0d PR-EQ-520 — Award HRSG PO | 15-Jun-25 → 25-Jun-25 | Complete 100% | float 5.0d PR-EQ-540 — Award Generator PO | 06-Jul-25 → 16-Jul-25 | Complete 100% | float 15.0d PR-EQ-505 — Manufacture Steam Turbine | 13-Jul-25 → 20-Mar-26 | Complete 100% | float 0.0d PR-EQ-505 PR-EQ-525 — Manufacture HRSG | 27-Jul-25 → 24-Mar-26 | Complete 100% | float 5.0d PR-EQ-525 PR-EQ-545 — Manufacture Generator | 17-Aug-25 → 25-Mar-26 | Complete 100% | float 15.0d PR-EQ-545 PR-EQ-510 — Ship & Receive Steam Turbine | 31-May-26 → 10-Jul-26 | Not Started 0% | float 0.0d PR-EQ-510 PR-EQ-530 — Ship & Receive HRSG | 12-Jul-26 → 11-Aug-26 | Not Started 0% | float 5.0d