Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 12 activities in PR Procurement × clear
Code
Activity
Start
Finish
Flt
%
PR-EQ-500
Award Steam Turbine PO
01-Jun-25
11-Jun-25
0.0d
100%
PR-EQ-520
Award HRSG PO
15-Jun-25
25-Jun-25
5.0d
100%
PR-EQ-540
Award Generator PO
06-Jul-25
16-Jul-25
15.0d
100%
PR-EQ-505
Manufacture Steam Turbine
13-Jul-25
20-Mar-26
0.0d
100%
PR-EQ-525
Manufacture HRSG
27-Jul-25
24-Mar-26
5.0d
100%
PR-BM-600
Procure Structural Steel
03-Aug-25
22-Oct-25
10.0d
100%
PR-EB-710
Procure Switchgear
10-Aug-25
07-Jan-26
0.0d
100%
PR-EQ-545
Manufacture Generator
17-Aug-25
25-Mar-26
15.0d
100%
PR-BM-610
Procure Piping Bulk Materials
31-Aug-25
09-Dec-25
5.0d
100%
PR-EB-700
Procure Cable & Conduit
14-Sep-25
13-Dec-25
5.0d
100%
PR-EQ-510
Ship & Receive Steam Turbine
31-May-26
10-Jul-26
0.0d
0%
PR-EQ-530
Ship & Receive HRSG
12-Jul-26
11-Aug-26
5.0d
0%
26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug Data Date
PR-EQ-500 — Award Steam Turbine PO | 01-Jun-25 → 11-Jun-25 | Complete 100% | float 0.0d PR-EQ-500 PR-EQ-520 — Award HRSG PO | 15-Jun-25 → 25-Jun-25 | Complete 100% | float 5.0d PR-EQ-520 PR-EQ-540 — Award Generator PO | 06-Jul-25 → 16-Jul-25 | Complete 100% | float 15.0d PR-EQ-540 PR-EQ-505 — Manufacture Steam Turbine | 13-Jul-25 → 20-Mar-26 | Complete 100% | float 0.0d PR-EQ-505 PR-EQ-525 — Manufacture HRSG | 27-Jul-25 → 24-Mar-26 | Complete 100% | float 5.0d PR-EQ-525 PR-BM-600 — Procure Structural Steel | 03-Aug-25 → 22-Oct-25 | Complete 100% | float 10.0d PR-BM-600 PR-EB-710 — Procure Switchgear | 10-Aug-25 → 07-Jan-26 | Complete 100% | float 0.0d PR-EB-710 PR-EQ-545 — Manufacture Generator | 17-Aug-25 → 25-Mar-26 | Complete 100% | float 15.0d PR-EQ-545 PR-BM-610 — Procure Piping Bulk Materials | 31-Aug-25 → 09-Dec-25 | Complete 100% | float 5.0d PR-BM-610 PR-EB-700 — Procure Cable & Conduit | 14-Sep-25 → 13-Dec-25 | Complete 100% | float 5.0d PR-EB-700 PR-EQ-510 — Ship & Receive Steam Turbine | 31-May-26 → 10-Jul-26 | Not Started 0% | float 0.0d PR-EQ-510 PR-EQ-530 — Ship & Receive HRSG | 12-Jul-26 → 11-Aug-26 | Not Started 0% | float 5.0d PR-EQ-530