PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 12 activities in PR Procurement × clear
Code
Activity
Start
Finish
Flt
%
PR-EQ-500
Award Steam Turbine PO
01-Jun-25
11-Jun-25
0.0d
100%
PR-EQ-520
Award HRSG PO
15-Jun-25
25-Jun-25
5.0d
100%
PR-EQ-540
Award Generator PO
06-Jul-25
16-Jul-25
15.0d
100%
PR-EQ-505
Manufacture Steam Turbine
13-Jul-25
20-Mar-26
0.0d
100%
PR-EQ-525
Manufacture HRSG
27-Jul-25
24-Mar-26
5.0d
100%
PR-BM-600
Procure Structural Steel
03-Aug-25
22-Oct-25
10.0d
100%
PR-EB-710
Procure Switchgear
10-Aug-25
07-Jan-26
0.0d
100%
PR-EQ-545
Manufacture Generator
17-Aug-25
25-Mar-26
15.0d
100%
PR-BM-610
Procure Piping Bulk Materials
31-Aug-25
09-Dec-25
5.0d
100%
PR-EB-700
Procure Cable & Conduit
14-Sep-25
13-Dec-25
5.0d
100%
PR-EQ-510
Ship & Receive Steam Turbine
31-May-26
10-Jul-26
0.0d
0%
PR-EQ-530
Ship & Receive HRSG
12-Jul-26
11-Aug-26
5.0d
0%
Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Data Date
PR-EQ-500 — Award Steam Turbine PO | 01-Jun-25 → 11-Jun-25 | Complete 100% | float 0.0d PR-EQ-500 PR-EQ-520 — Award HRSG PO | 15-Jun-25 → 25-Jun-25 | Complete 100% | float 5.0d PR-EQ-520 PR-EQ-540 — Award Generator PO | 06-Jul-25 → 16-Jul-25 | Complete 100% | float 15.0d PR-EQ-540 PR-EQ-505 — Manufacture Steam Turbine | 13-Jul-25 → 20-Mar-26 | Complete 100% | float 0.0d PR-EQ-505 PR-EQ-525 — Manufacture HRSG | 27-Jul-25 → 24-Mar-26 | Complete 100% | float 5.0d PR-EQ-525 PR-BM-600 — Procure Structural Steel | 03-Aug-25 → 22-Oct-25 | Complete 100% | float 10.0d PR-BM-600 PR-EB-710 — Procure Switchgear | 10-Aug-25 → 07-Jan-26 | Complete 100% | float 0.0d PR-EB-710 PR-EQ-545 — Manufacture Generator | 17-Aug-25 → 25-Mar-26 | Complete 100% | float 15.0d PR-EQ-545 PR-BM-610 — Procure Piping Bulk Materials | 31-Aug-25 → 09-Dec-25 | Complete 100% | float 5.0d PR-BM-610 PR-EB-700 — Procure Cable & Conduit | 14-Sep-25 → 13-Dec-25 | Complete 100% | float 5.0d PR-EB-700 PR-EQ-510 — Ship & Receive Steam Turbine | 31-May-26 → 10-Jul-26 | Not Started 0% | float 0.0d PR-EQ-510 PR-EQ-530 — Ship & Receive HRSG | 12-Jul-26 → 11-Aug-26 | Not Started 0% | float 5.0d PR-EQ-530