PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in EN.EL Electrical × clear
Code
Activity
Start
Finish
Flt
%
EN-EL-300
Substation Single Line Diagram
23-Mar-25
12-May-25
10.0d
100%
EN-EL-310
Cable Schedule & Routing
04-May-25
23-Jul-25
10.0d
100%
24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul Data Date
EN-EL-300 — Substation Single Line Diagram | 23-Mar-25 → 12-May-25 | Complete 100% | float 10.0d EN-EL-300 EN-EL-310 — Cable Schedule & Routing | 04-May-25 → 23-Jul-25 | Complete 100% | float 10.0d EN-EL-310