PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in EN.EL Electrical × clear
Code
Activity
Start
Finish
Flt
%
EN-EL-300
Substation Single Line Diagram
23-Mar-25
12-May-25
10.0d
100%
EN-EL-310
Cable Schedule & Routing
04-May-25
23-Jul-25
10.0d
100%
Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Data Date
EN-EL-300 — Substation Single Line Diagram | 23-Mar-25 → 12-May-25 | Complete 100% | float 10.0d EN-EL-300 EN-EL-310 — Cable Schedule & Routing | 04-May-25 → 23-Jul-25 | Complete 100% | float 10.0d EN-EL-310