PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in EN.ME Mechanical × clear
Code
Activity
Start
Finish
Flt
%
EN-ME-200
Steam Turbine Foundation Spec
16-Mar-25
25-Apr-25
10.0d
100%
EN-ME-210
HRSG Mechanical Design
13-Apr-25
12-Jul-25
10.0d
100%
EN-ME-230
Piping Isometrics — U/G
27-Apr-25
26-Jun-25
10.0d
100%
EN-ME-220
Piping Isometrics — A/G
11-May-25
29-Aug-25
10.0d
100%
24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug Data Date
EN-ME-200 — Steam Turbine Foundation Spec | 16-Mar-25 → 25-Apr-25 | Complete 100% | float 10.0d EN-ME-200 EN-ME-210 — HRSG Mechanical Design | 13-Apr-25 → 12-Jul-25 | Complete 100% | float 10.0d EN-ME-210 EN-ME-230 — Piping Isometrics — U/G | 27-Apr-25 → 26-Jun-25 | Complete 100% | float 10.0d EN-ME-230 EN-ME-220 — Piping Isometrics — A/G | 11-May-25 → 29-Aug-25 | Complete 100% | float 10.0d EN-ME-220