Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in EN.CV Civil/Structural × clear
Code
Activity
Start
Finish
Flt
%
EN-CV-100
Civil Site Plan & Grading Design
03-Mar-25
02-May-25
10.0d
100%
EN-CV-110
Foundation Design Package
31-Mar-25
19-Jun-25
10.0d
100%
24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun Data Date
EN-CV-100 — Civil Site Plan & Grading Design | 03-Mar-25 → 02-May-25 | Complete 100% | float 10.0d EN-CV-100 EN-CV-110 — Foundation Design Package | 31-Mar-25 → 19-Jun-25 | Complete 100% | float 10.0d EN-CV-110