PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in MS Project Milestones × clear
Code
Activity
Start
Finish
Flt
%
PMU4-MS-001
Notice to Proceed (NTP)
02-Mar-25
02-Mar-25
0.0d
100%
PMU4-MS-100
First Concrete Pour
30-Nov-25
30-Nov-25
0.0d
100%
PMU4-MS-002
All Foundations Complete
30-Apr-26
30-Apr-26
0.0d
0%
PMU4-MS-003
Steel Topped Out
30-Jun-26
30-Jun-26
0.0d
0%
PMU4-MS-200
Steam Turbine Set
31-Jul-26
31-Jul-26
0.0d
0%
PMU4-MS-999
Commercial Operation Date (COD)
29-Apr-27
29-Apr-27
0.0d
0%
24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr Data Date
PMU4-MS-001 — Notice to Proceed (NTP) | 02-Mar-25 | Complete PMU4-MS-100 — First Concrete Pour | 30-Nov-25 | Complete PMU4-MS-002 — All Foundations Complete | 30-Apr-26 | Not Started PMU4-MS-003 — Steel Topped Out | 30-Jun-26 | Not Started PMU4-MS-200 — Steam Turbine Set | 31-Jul-26 | Not Started PMU4-MS-999 — Commercial Operation Date (COD) | 29-Apr-27 | Not Started