Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in MS Project Milestones × clear
Code
Activity
Start
Finish
Flt
%
PMU4-MS-001
Notice to Proceed (NTP)
02-Mar-25
02-Mar-25
0.0d
100%
PMU4-MS-100
First Concrete Pour
30-Nov-25
30-Nov-25
0.0d
100%
PMU4-MS-002
All Foundations Complete
30-Apr-26
30-Apr-26
0.0d
0%
PMU4-MS-003
Steel Topped Out
30-Jun-26
30-Jun-26
0.0d
0%
PMU4-MS-200
Steam Turbine Set
31-Jul-26
31-Jul-26
0.0d
0%
PMU4-MS-999
Commercial Operation Date (COD)
29-Apr-27
29-Apr-27
0.0d
0%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Q2 2027 Data Date
PMU4-MS-001 — Notice to Proceed (NTP) | 02-Mar-25 | Complete PMU4-MS-100 — First Concrete Pour | 30-Nov-25 | Complete PMU4-MS-002 — All Foundations Complete | 30-Apr-26 | Not Started PMU4-MS-003 — Steel Topped Out | 30-Jun-26 | Not Started PMU4-MS-200 — Steam Turbine Set | 31-Jul-26 | Not Started PMU4-MS-999 — Commercial Operation Date (COD) | 29-Apr-27 | Not Started