Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in MS Project Milestones × clear
Code
Activity
Start
Finish
Flt
%
PMU4-MS-001
Notice to Proceed (NTP)
02-Mar-25
02-Mar-25
0.0d
100%
PMU4-MS-100
First Concrete Pour
30-Nov-25
30-Nov-25
0.0d
100%
PMU4-MS-002
All Foundations Complete
30-Apr-26
30-Apr-26
0.0d
0%
PMU4-MS-003
Steel Topped Out
30-Jun-26
30-Jun-26
0.0d
0%
PMU4-MS-200
Steam Turbine Set
31-Jul-26
31-Jul-26
0.0d
0%
PMU4-MS-999
Commercial Operation Date (COD)
29-Apr-27
29-Apr-27
0.0d
0%
Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 Data Date
PMU4-MS-001 — Notice to Proceed (NTP) | 02-Mar-25 | Complete PMU4-MS-100 — First Concrete Pour | 30-Nov-25 | Complete PMU4-MS-002 — All Foundations Complete | 30-Apr-26 | Not Started PMU4-MS-003 — Steel Topped Out | 30-Jun-26 | Not Started PMU4-MS-200 — Steam Turbine Set | 31-Jul-26 | Not Started PMU4-MS-999 — Commercial Operation Date (COD) | 29-Apr-27 | Not Started