PMU4-CC
Plant Mitchell Unit 4 Combined Cycle
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 6
activities
in MS Project Milestones
× clear
Code
Activity
Start
Finish
Flt
%
PMU4-MS-001
Notice to Proceed (NTP)
02-Mar-25
02-Mar-25
0.0d
100%
PMU4-MS-100
First Concrete Pour
30-Nov-25
30-Nov-25
0.0d
100%
PMU4-MS-002
All Foundations Complete
30-Apr-26
30-Apr-26
0.0d
0%
PMU4-MS-003
Steel Topped Out
30-Jun-26
30-Jun-26
0.0d
0%
PMU4-MS-200
Steam Turbine Set
31-Jul-26
31-Jul-26
0.0d
0%
PMU4-MS-999
Commercial Operation Date (COD)
29-Apr-27
29-Apr-27
0.0d
0%