PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CM.PT Performance Testing × clear
Code
Activity
Start
Finish
Flt
%
CM-PT-1900
Performance Test Run #1
11-Apr-27
01-May-27
0.0d
0%
CM-PT-1910
Performance Test Run #2
18-Apr-27
08-May-27
0.0d
0%
CM-PT-1930
Punch List Closure
18-Apr-27
18-May-27
5.0d
0%
CM-PT-1920
Reliability Run (72hr)
25-Apr-27
05-May-27
0.0d
0%
Apr 2027 May 2027 Data Date
CM-PT-1900 — Performance Test Run #1 | 11-Apr-27 → 01-May-27 | Not Started 0% | float 0.0d CM-PT-1900 CM-PT-1910 — Performance Test Run #2 | 18-Apr-27 → 08-May-27 | Not Started 0% | float 0.0d CM-PT-1910 CM-PT-1930 — Punch List Closure | 18-Apr-27 → 18-May-27 | Not Started 0% | float 5.0d CM-PT-1930 CM-PT-1920 — Reliability Run (72hr) | 25-Apr-27 → 05-May-27 | Not Started 0% | float 0.0d CM-PT-1920