PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CM.PT Performance Testing × clear
Code
Activity
Start
Finish
Flt
%
CM-PT-1900
Performance Test Run #1
11-Apr-27
01-May-27
0.0d
0%
CM-PT-1910
Performance Test Run #2
18-Apr-27
08-May-27
0.0d
0%
CM-PT-1930
Punch List Closure
18-Apr-27
18-May-27
5.0d
0%
CM-PT-1920
Reliability Run (72hr)
25-Apr-27
05-May-27
0.0d
0%
29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May Data Date
CM-PT-1900 — Performance Test Run #1 | 11-Apr-27 → 01-May-27 | Not Started 0% | float 0.0d CM-PT-1900 CM-PT-1910 — Performance Test Run #2 | 18-Apr-27 → 08-May-27 | Not Started 0% | float 0.0d CM-PT-1910 CM-PT-1930 — Punch List Closure | 18-Apr-27 → 18-May-27 | Not Started 0% | float 5.0d CM-PT-1930 CM-PT-1920 — Reliability Run (72hr) | 25-Apr-27 → 05-May-27 | Not Started 0% | float 0.0d CM-PT-1920