Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in CM.CM Commissioning × clear
Code
Activity
Start
Finish
Flt
%
CM-CM-1800
Auxiliary Systems Commissioning
07-Feb-27
19-Mar-27
0.0d
0%
CM-CM-1810
BOP Systems Commissioning
21-Feb-27
28-Mar-27
0.0d
0%
CM-CM-1820
First Fire of Gas Turbine
28-Feb-27
28-Feb-27
0.0d
0%
CM-CM-1830
HRSG Steam Blow
07-Mar-27
06-Apr-27
0.0d
0%
CM-CM-1840
Steam Turbine Roll & Sync
21-Mar-27
15-Apr-27
0.0d
0%
CM-CM-1850
Combined Cycle Operation
28-Mar-27
02-May-27
0.0d
0%
01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr 03-May 10-May 17-May 24-May 31-May Data Date
CM-CM-1800 — Auxiliary Systems Commissioning | 07-Feb-27 → 19-Mar-27 | Not Started 0% | float 0.0d CM-CM-1800 CM-CM-1810 — BOP Systems Commissioning | 21-Feb-27 → 28-Mar-27 | Not Started 0% | float 0.0d CM-CM-1810 CM-CM-1820 — First Fire of Gas Turbine | 28-Feb-27 | Not Started CM-CM-1830 — HRSG Steam Blow | 07-Mar-27 → 06-Apr-27 | Not Started 0% | float 0.0d CM-CM-1830 CM-CM-1840 — Steam Turbine Roll & Sync | 21-Mar-27 → 15-Apr-27 | Not Started 0% | float 0.0d CM-CM-1840 CM-CM-1850 — Combined Cycle Operation | 28-Mar-27 → 02-May-27 | Not Started 0% | float 0.0d CM-CM-1850