PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CM.PR Pre-Commissioning × clear
Code
Activity
Start
Finish
Flt
%
CM-PR-1700
Mechanical Completion Walkdowns
03-Jan-27
12-Feb-27
0.0d
0%
CM-PR-1730
Electrical Testing & Energization
10-Jan-27
14-Feb-27
0.0d
0%
CM-PR-1710
Hydrostatic Testing
17-Jan-27
16-Feb-27
0.0d
0%
CM-PR-1720
Cleaning & Flushing
31-Jan-27
25-Feb-27
0.0d
0%
Q1 2027 Data Date
CM-PR-1700 — Mechanical Completion Walkdowns | 03-Jan-27 → 12-Feb-27 | Not Started 0% | float 0.0d CM-PR-1700 CM-PR-1730 — Electrical Testing & Energization | 10-Jan-27 → 14-Feb-27 | Not Started 0% | float 0.0d CM-PR-1710 — Hydrostatic Testing | 17-Jan-27 → 16-Feb-27 | Not Started 0% | float 0.0d CM-PR-1720 — Cleaning & Flushing | 31-Jan-27 → 25-Feb-27 | Not Started 0% | float 0.0d