Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CM.PR Pre-Commissioning × clear
Code
Activity
Start
Finish
Flt
%
CM-PR-1700
Mechanical Completion Walkdowns
03-Jan-27
12-Feb-27
0.0d
0%
CM-PR-1730
Electrical Testing & Energization
10-Jan-27
14-Feb-27
0.0d
0%
CM-PR-1710
Hydrostatic Testing
17-Jan-27
16-Feb-27
0.0d
0%
CM-PR-1720
Cleaning & Flushing
31-Jan-27
25-Feb-27
0.0d
0%
28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb Data Date
CM-PR-1700 — Mechanical Completion Walkdowns | 03-Jan-27 → 12-Feb-27 | Not Started 0% | float 0.0d CM-PR-1700 CM-PR-1730 — Electrical Testing & Energization | 10-Jan-27 → 14-Feb-27 | Not Started 0% | float 0.0d CM-PR-1730 CM-PR-1710 — Hydrostatic Testing | 17-Jan-27 → 16-Feb-27 | Not Started 0% | float 0.0d CM-PR-1710 CM-PR-1720 — Cleaning & Flushing | 31-Jan-27 → 25-Feb-27 | Not Started 0% | float 0.0d CM-PR-1720