PMU4-CC
Plant Mitchell Unit 4 Combined Cycle
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 14
activities
in CM Commissioning & Startup
× clear
Code
Activity
Start
Finish
Flt
%
CM-PR-1700
Mechanical Completion Walkdowns
03-Jan-27
12-Feb-27
0.0d
0%
CM-PR-1730
Electrical Testing & Energization
10-Jan-27
14-Feb-27
0.0d
0%
CM-PR-1710
Hydrostatic Testing
17-Jan-27
16-Feb-27
0.0d
0%
CM-PR-1720
Cleaning & Flushing
31-Jan-27
25-Feb-27
0.0d
0%
CM-CM-1800
Auxiliary Systems Commissioning
07-Feb-27
19-Mar-27
0.0d
0%
CM-CM-1810
BOP Systems Commissioning
21-Feb-27
28-Mar-27
0.0d
0%
CM-CM-1820
First Fire of Gas Turbine
28-Feb-27
28-Feb-27
0.0d
0%
CM-CM-1830
HRSG Steam Blow
07-Mar-27
06-Apr-27
0.0d
0%
CM-CM-1840
Steam Turbine Roll & Sync
21-Mar-27
15-Apr-27
0.0d
0%
CM-CM-1850
Combined Cycle Operation
28-Mar-27
02-May-27
0.0d
0%
CM-PT-1900
Performance Test Run #1
11-Apr-27
01-May-27
0.0d
0%
CM-PT-1910
Performance Test Run #2
18-Apr-27
08-May-27
0.0d
0%
CM-PT-1930
Punch List Closure
18-Apr-27
18-May-27
5.0d
0%
CM-PT-1920
Reliability Run (72hr)
25-Apr-27
05-May-27
0.0d
0%