Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 14 activities in CM Commissioning & Startup × clear
Code
Activity
Start
Finish
Flt
%
CM-PR-1700
Mechanical Completion Walkdowns
03-Jan-27
12-Feb-27
0.0d
0%
CM-PR-1730
Electrical Testing & Energization
10-Jan-27
14-Feb-27
0.0d
0%
CM-PR-1710
Hydrostatic Testing
17-Jan-27
16-Feb-27
0.0d
0%
CM-PR-1720
Cleaning & Flushing
31-Jan-27
25-Feb-27
0.0d
0%
CM-CM-1800
Auxiliary Systems Commissioning
07-Feb-27
19-Mar-27
0.0d
0%
CM-CM-1810
BOP Systems Commissioning
21-Feb-27
28-Mar-27
0.0d
0%
CM-CM-1820
First Fire of Gas Turbine
28-Feb-27
28-Feb-27
0.0d
0%
CM-CM-1830
HRSG Steam Blow
07-Mar-27
06-Apr-27
0.0d
0%
CM-CM-1840
Steam Turbine Roll & Sync
21-Mar-27
15-Apr-27
0.0d
0%
CM-CM-1850
Combined Cycle Operation
28-Mar-27
02-May-27
0.0d
0%
CM-PT-1900
Performance Test Run #1
11-Apr-27
01-May-27
0.0d
0%
CM-PT-1910
Performance Test Run #2
18-Apr-27
08-May-27
0.0d
0%
CM-PT-1930
Punch List Closure
18-Apr-27
18-May-27
5.0d
0%
CM-PT-1920
Reliability Run (72hr)
25-Apr-27
05-May-27
0.0d
0%
Jan 2027 Feb 2027 Mar 2027 Apr 2027 May 2027 Data Date
CM-PR-1700 — Mechanical Completion Walkdowns | 03-Jan-27 → 12-Feb-27 | Not Started 0% | float 0.0d CM-PR-1700 CM-PR-1730 — Electrical Testing & Energization | 10-Jan-27 → 14-Feb-27 | Not Started 0% | float 0.0d CM-PR-1730 CM-PR-1710 — Hydrostatic Testing | 17-Jan-27 → 16-Feb-27 | Not Started 0% | float 0.0d CM-PR-1710 CM-PR-1720 — Cleaning & Flushing | 31-Jan-27 → 25-Feb-27 | Not Started 0% | float 0.0d CM-PR-1720 CM-CM-1800 — Auxiliary Systems Commissioning | 07-Feb-27 → 19-Mar-27 | Not Started 0% | float 0.0d CM-CM-1800 CM-CM-1810 — BOP Systems Commissioning | 21-Feb-27 → 28-Mar-27 | Not Started 0% | float 0.0d CM-CM-1810 CM-CM-1820 — First Fire of Gas Turbine | 28-Feb-27 | Not Started CM-CM-1830 — HRSG Steam Blow | 07-Mar-27 → 06-Apr-27 | Not Started 0% | float 0.0d CM-CM-1830 CM-CM-1840 — Steam Turbine Roll & Sync | 21-Mar-27 → 15-Apr-27 | Not Started 0% | float 0.0d CM-CM-1840 CM-CM-1850 — Combined Cycle Operation | 28-Mar-27 → 02-May-27 | Not Started 0% | float 0.0d CM-CM-1850 CM-PT-1900 — Performance Test Run #1 | 11-Apr-27 → 01-May-27 | Not Started 0% | float 0.0d CM-PT-1900 CM-PT-1910 — Performance Test Run #2 | 18-Apr-27 → 08-May-27 | Not Started 0% | float 0.0d CM-PT-1910 CM-PT-1930 — Punch List Closure | 18-Apr-27 → 18-May-27 | Not Started 0% | float 5.0d CM-PT-1930 CM-PT-1920 — Reliability Run (72hr) | 25-Apr-27 → 05-May-27 | Not Started 0% | float 0.0d CM-PT-1920