Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 14 activities in CM Commissioning & Startup × clear
Code
Activity
Start
Finish
Flt
%
CM-PR-1700
Mechanical Completion Walkdowns
03-Jan-27
12-Feb-27
0.0d
0%
CM-PR-1730
Electrical Testing & Energization
10-Jan-27
14-Feb-27
0.0d
0%
CM-PR-1710
Hydrostatic Testing
17-Jan-27
16-Feb-27
0.0d
0%
CM-PR-1720
Cleaning & Flushing
31-Jan-27
25-Feb-27
0.0d
0%
CM-CM-1800
Auxiliary Systems Commissioning
07-Feb-27
19-Mar-27
0.0d
0%
CM-CM-1810
BOP Systems Commissioning
21-Feb-27
28-Mar-27
0.0d
0%
CM-CM-1820
First Fire of Gas Turbine
28-Feb-27
28-Feb-27
0.0d
0%
CM-CM-1830
HRSG Steam Blow
07-Mar-27
06-Apr-27
0.0d
0%
CM-CM-1840
Steam Turbine Roll & Sync
21-Mar-27
15-Apr-27
0.0d
0%
CM-CM-1850
Combined Cycle Operation
28-Mar-27
02-May-27
0.0d
0%
CM-PT-1900
Performance Test Run #1
11-Apr-27
01-May-27
0.0d
0%
CM-PT-1910
Performance Test Run #2
18-Apr-27
08-May-27
0.0d
0%
CM-PT-1930
Punch List Closure
18-Apr-27
18-May-27
5.0d
0%
CM-PT-1920
Reliability Run (72hr)
25-Apr-27
05-May-27
0.0d
0%
28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May Data Date
CM-PR-1700 — Mechanical Completion Walkdowns | 03-Jan-27 → 12-Feb-27 | Not Started 0% | float 0.0d CM-PR-1700 CM-PR-1730 — Electrical Testing & Energization | 10-Jan-27 → 14-Feb-27 | Not Started 0% | float 0.0d CM-PR-1730 CM-PR-1710 — Hydrostatic Testing | 17-Jan-27 → 16-Feb-27 | Not Started 0% | float 0.0d CM-PR-1710 CM-PR-1720 — Cleaning & Flushing | 31-Jan-27 → 25-Feb-27 | Not Started 0% | float 0.0d CM-PR-1720 CM-CM-1800 — Auxiliary Systems Commissioning | 07-Feb-27 → 19-Mar-27 | Not Started 0% | float 0.0d CM-CM-1800 CM-CM-1810 — BOP Systems Commissioning | 21-Feb-27 → 28-Mar-27 | Not Started 0% | float 0.0d CM-CM-1810 CM-CM-1820 — First Fire of Gas Turbine | 28-Feb-27 | Not Started CM-CM-1830 — HRSG Steam Blow | 07-Mar-27 → 06-Apr-27 | Not Started 0% | float 0.0d CM-CM-1830 CM-CM-1840 — Steam Turbine Roll & Sync | 21-Mar-27 → 15-Apr-27 | Not Started 0% | float 0.0d CM-CM-1840 CM-CM-1850 — Combined Cycle Operation | 28-Mar-27 → 02-May-27 | Not Started 0% | float 0.0d CM-CM-1850 CM-PT-1900 — Performance Test Run #1 | 11-Apr-27 → 01-May-27 | Not Started 0% | float 0.0d CM-PT-1900 CM-PT-1910 — Performance Test Run #2 | 18-Apr-27 → 08-May-27 | Not Started 0% | float 0.0d CM-PT-1910 CM-PT-1930 — Punch List Closure | 18-Apr-27 → 18-May-27 | Not Started 0% | float 5.0d CM-PT-1930 CM-PT-1920 — Reliability Run (72hr) | 25-Apr-27 → 05-May-27 | Not Started 0% | float 0.0d CM-PT-1920