Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in CN.PN Painting/Insulation × clear
Code
Activity
Start
Finish
Flt
%
CN-PN-1620
Tank Insulation
15-Nov-26
15-Dec-26
15.0d
0%
CN-PN-1600
Pipe Insulation
22-Nov-26
21-Jan-27
5.0d
0%
CN-PN-1610
Equipment Painting
06-Dec-26
15-Jan-27
10.0d
0%
Nov 2026 Dec 2026 Jan 2027 Data Date
CN-PN-1620 — Tank Insulation | 15-Nov-26 → 15-Dec-26 | Not Started 0% | float 15.0d CN-PN-1620 CN-PN-1600 — Pipe Insulation | 22-Nov-26 → 21-Jan-27 | Not Started 0% | float 5.0d CN-PN-1600 CN-PN-1610 — Equipment Painting | 06-Dec-26 → 15-Jan-27 | Not Started 0% | float 10.0d CN-PN-1610