Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in CN.PN Painting/Insulation × clear
Code
Activity
Start
Finish
Flt
%
CN-PN-1620
Tank Insulation
15-Nov-26
15-Dec-26
15.0d
0%
CN-PN-1600
Pipe Insulation
22-Nov-26
21-Jan-27
5.0d
0%
CN-PN-1610
Equipment Painting
06-Dec-26
15-Jan-27
10.0d
0%
26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
CN-PN-1620 — Tank Insulation | 15-Nov-26 → 15-Dec-26 | Not Started 0% | float 15.0d CN-PN-1620 CN-PN-1600 — Pipe Insulation | 22-Nov-26 → 21-Jan-27 | Not Started 0% | float 5.0d CN-PN-1600 CN-PN-1610 — Equipment Painting | 06-Dec-26 → 15-Jan-27 | Not Started 0% | float 10.0d CN-PN-1610