PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CN.IC Instrumentation × clear
Code
Activity
Start
Finish
Flt
%
CN-IC-1520
DCS Cabinet Install
20-Sep-26
30-Oct-26
5.0d
0%
CN-IC-1500
Field Instrument Install
11-Oct-26
30-Dec-26
0.0d
0%
CN-IC-1510
Instrument Tubing
15-Nov-26
04-Jan-27
5.0d
0%
CN-IC-1530
Loop Checks
03-Jan-27
04-Mar-27
0.0d
0%
Q3 2026 Q4 2026 Q1 2027 Data Date
CN-IC-1520 — DCS Cabinet Install | 20-Sep-26 → 30-Oct-26 | Not Started 0% | float 5.0d CN-IC-1520 CN-IC-1500 — Field Instrument Install | 11-Oct-26 → 30-Dec-26 | Not Started 0% | float 0.0d CN-IC-1500 CN-IC-1510 — Instrument Tubing | 15-Nov-26 → 04-Jan-27 | Not Started 0% | float 5.0d CN-IC-1510 CN-IC-1530 — Loop Checks | 03-Jan-27 → 04-Mar-27 | Not Started 0% | float 0.0d CN-IC-1530