Projects
PMU4-CC

Plant Mitchell Unit 4 Combined Cycle

Data Date: 24-Apr-26
Plan: 03-Mar-25 – 30-Apr-27
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in CN.IC Instrumentation × clear
Code
Activity
Start
Finish
Flt
%
CN-IC-1520
DCS Cabinet Install
20-Sep-26
30-Oct-26
5.0d
0%
CN-IC-1500
Field Instrument Install
11-Oct-26
30-Dec-26
0.0d
0%
CN-IC-1510
Instrument Tubing
15-Nov-26
04-Jan-27
5.0d
0%
CN-IC-1530
Loop Checks
03-Jan-27
04-Mar-27
0.0d
0%
31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
CN-IC-1520 — DCS Cabinet Install | 20-Sep-26 → 30-Oct-26 | Not Started 0% | float 5.0d CN-IC-1520 CN-IC-1500 — Field Instrument Install | 11-Oct-26 → 30-Dec-26 | Not Started 0% | float 0.0d CN-IC-1500 CN-IC-1510 — Instrument Tubing | 15-Nov-26 → 04-Jan-27 | Not Started 0% | float 5.0d CN-IC-1510 CN-IC-1530 — Loop Checks | 03-Jan-27 → 04-Mar-27 | Not Started 0% | float 0.0d CN-IC-1530